You are on page 1of 48

Type of Document : Title : Panel No.

Site Acceptance Test Protection Relay Test PHT Garuda


Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Protection Relay Test


A1. Relay F871 Test

1. Technical Data Protection Relay

Device Identification Line Current Differential & Distance

Manufacture Siemens
Device Type 7SL87
Serial Number BM2303012399
Ratio CT 1600 A / 1 A
Ratio VT 150 kV / 100 V
Test Equipment CMC 356 / JA081R

2. Metering
2.1. Current Measurement test
Inject current in the relay as per the table below. Observe the reading in primary values

Inject Test
No. Expected (A) Actual (A) Remark
Phase
Scale (%) Current (A)
Injected
1 Phase L1 0.25 0 400 401 Good
2 25% Phase L2 0.25 -120 400 400 Good
3 Phase L3 0.25 120 400 402 Good
4 Phase L1 0.5 0 800 799 Good
5 50% Phase L2 0.5 -120 800 800 Good
6 Phase L3 0.5 120 800 800 Good
7 Phase L1 0.75 0 1200 1201 Good
8 75% Phase L2 0.75 -120 1200 1200 Good
9 Phase L3 0.75 120 1200 1199 Good
10 Phase L1 1 0 1600 1599 Good
11 100% Phase L2 1 -120 1600 1600 Good
12 Phase L3 1 120 1600 1599 Good

2.2 Voltage Measurement test


Inject Voltage in the relay as per the table below. Observe the reading in primary values

Inject Test
No. Expected (kV) Actual (kV) Remark
Phase
Scale (%) Voltage (V)
Injected
1 Phase L1 14.4 0 21.63 21.62 Good
2 25% Phase L2 14.4 -120 21.63 21.62 Good
3 Phase L3 14.4 120 21.63 21.62 Good
4 Phase L1 28.8 0 43.27 43.24 Good
5 50% Phase L2 28.8 -120 43.27 43.24 Good
6 Phase L3 28.8 120 43.27 43.24 Good
7 Phase L1 43.3 0 64.91 64.87 Good
8 75% Phase L2 43.3 -120 64.91 64.87 Good
9 Phase L3 43.3 120 64.91 64.87 Good
Page A1 _ 1 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

10 Phase L1 57.74 0 86.56 86.54 Good


11 100% Phase L2 57.74 -120 86.56 86.54 Good
12 Phase L3 57.74 120 86.56 86.54 Good

2.3 Export Active Power (P) Measurement test


Inject Current and Voltage in the relay as per the table below. Observe the reading in primary
values
Inject Test
Expected Actual
No. Remark
Scale Phase (MW) (MW)
Current (A) Voltage (V)
(%) Injected
1 Phase L1 0.250 14.4 0
2 25% Phase L2 0.25-120 14.4 -120 103.92 103.88 Good
3 Phase L3 0.25120 14.4 120
4 Phase L1 0.50 28.8 0
5 50% Phase L2 0.5-120 28.8 -120 207.85 207.71 Good
6 Phase L3 0.5120 28.8 120
7 Phase L1 0.750 43.3 0
8 75% Phase L2 0.75-120 43.3-120 311.77 311.57 Good
9 Phase L3 0.75120 43.3120
10 Phase L1 10 57.740
11 100% Phase L2 1-120 57.74-120 415.7 415.45 Good
12 Phase L3 1120 57.74120

2.4 Import Active Power (P) Measurement test


Inject Current and Voltage in the relay as per the table below. Observe the reading in primary
values
Inject Test
Expected Actual
No. Remark
Scale Phase (MW) (MW)
Current (A) Voltage (V)
(%) Injected
1 Phase L1 0.25180 14.4 0
2 25% Phase L2 0.2560 14.4 -120 -103.92 -103.88 Good
3 Phase L3 0.25300 14.4 120
4 Phase L1 0.5180 28.8 0
5 50% Phase L2 0.560 28.8 -120 -207.85 -207.71 Good
6 Phase L3 0.5300 28.8 120
7 Phase L1 0.75180 43.3 0
8 75% Phase L2 0.7560 43.3 -120 -311.77 -311.57 Good
9 Phase L3 0.75300 43.3 120
10 Phase L1 1180 57.740
11 100% Phase L2 1 60 57.74-120 -415.7 -415.45 Good
12 Phase L3 1300 57.74120

Page A1 _ 2 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

2.5 Export Reactive Power (Q) Measurement test


Inject Current and Voltage in the relay as per the table below. Observe the reading in primary
values

Inject Test
Expected Actual
No. Remark
Scale Phase (MVar) (MVar)
Current (A) Voltage (V)
(%) Injected
1 Phase L1 0.25-90 14.40
2 25% Phase L2 0.25-210 14.4-120 103.92 103.88 Good
3 Phase L3 0.2530 14.4120
4 Phase L1 0.5-90 28.8 0
5 50% Phase L2 0.5-210 28.8 -120 207.85 207.71 Good
6 Phase L3 0.530 28.8 120
7 Phase L1 0.75-90 43.3 0
8 75% Phase L2 0.75-210 43.3 -120 311.77 311.57 Good
9 Phase L3 0.7530 43.3 120
10 Phase L1 1-90 57.74 0
11 100% Phase L2 1-210 57.74-120 415.7 415.45 Good
12 Phase L3 130 57.74120

2.6 Import Reactive Power (Q) Measurement test


Inject Current and Voltage in the relay as per the table below. Observe the reading in primary
values

Inject Test
Expected Actual
No. Remark
Scale Phase (MVar) (MVar)
Current (A) Voltage (V)
(%) Injected
1 Phase L1 0.2590 14.40
2 25% Phase L2 0.25 -30 14.4-120 -103.92 -103.88 Good
3 Phase L3 0.25210 14.4120
4 Phase L1 0.590 28.8 0
5 50% Phase L2 0.5-30 28.8 -120 -207.85 -207.71 Good
6 Phase L3 0.5210 28.8 120
7 Phase L1 0.7590 43.3 0
8 75% Phase L2 0.75-30 43.3 -120 -311.77 -311.57 Good
9 Phase L3 0.75210 43.3 120
10 Phase L1 190 57.74 0
11 100% Phase L2 1-30 57.74-120 -415.7 -415.45 Good
12 Phase L3 1210 57.74120

Page A1 _ 3 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

3. Line Differential (87L) Parameter

Relay Setting Setting Value

Idiff 0.2 A
Idiff fast -
Directional Forward
Trip Time 0.0 s

4. Pick Up / Drop Off Test


87LPick up Test/Drop Off Test
Pickup Current Drop off Current
I Diff Setting Phase Result
Current I Diff Current I Diff

L1 0.24 A 24.4 % 0.18 A 18.9 % Good


0.2 L2 0.24 A 24.4 % 0.18 A 18.9 % Good
L3 0.24 A 24.4 % 0.18 A 18.8 % Good
*Tolerance ±5%

5. Slope Test Characteristic

No Side Injection Injection Diagram I-diff I-Rest Result


0.27 A 0.00˚ 16.00 % 20.33%
SIDE 0.27 A -120.00˚ 16.03 % 20.33%
1
0.27 A 120.00˚ 16.00 % 20.34%
1 Trip
0.1 A 180.00˚ 16.00 % 20.33%
SIDE
0.1 A 60.00˚ 16.03 % 20.34%
2
0.1 A 300.00˚ 16.00 % 20.33%

Page A1 _ 4 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

No Side Injection Injection Diagram I-diff I-Rest Result


0.29 A 0.00˚ 16.91 % 21.33%
SIDE 0.29 A -120.00˚ 16.82 % 21.33%
1
0.29 A 120.00˚ 16.77 % 21.34%
2 Trip
0.12 A 180.00˚ 16.91 % 21.33%
SIDE
0.12 A 60.00˚ 16.82 % 21.34%
2
0.12 A 300.00˚ 16.77 % 21.33%

Page A1 _ 5 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

No Side Injection Injection Diagram I-diff I-Rest Result


0.32 A 0.00˚ 17.01% 21.45%
SIDE 0.32 A -120.00˚ 17.01% 21.47%
1
0.32 A 120.00˚ 17.03% 21.45%
3 Trip
0.14 A 180.00˚ 17.01% 21.45%
SIDE
0.14 A 60.00˚ 17.02% 21.45%
2
0.14 A 300.00˚ 17.01% 21.45%

No Side Injection Injection Diagram I-diff I-Rest Result


0.34 A 0.00˚ 17.11% 21.73%
SIDE 0.34 A -120.00˚ 17.11% 21.73%
1
0.34 A 120.00˚ 17.11% 21.73%
4 Trip
0.16 A 180.00˚ 17.11% 21.73%
SIDE
0.16 A 60.00˚ 17.11% 21.73%
2
0.16 A 300.00˚ 17.11% 21.73%

Page A1 _ 6 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

No Side Injection Injection Diagram I-diff I-Rest Result


0.36 A 0.00˚ 17.99% 21.84%
SIDE 0.36 A -120.00˚ 17.99% 21.84%
1
0.36 A 120.00˚ 17.99% 21.84%
5 Trip
0.18 A 180.00˚ 17.99% 21.84%
SIDE
0.18 A 60.00˚ 17.99% 21.84%
2
0.18 A 300.00˚ 17.99% 21.84%

Page A1 _ 7 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

No Side Injection Injection Diagram I-diff I-Rest Result


0.38 A 0.00˚ 18.06% 21.91%
SIDE 0.38 A -120.00˚ 18.06% 21.91%
1
0.38 A 120.00˚ 18.06% 21.91%
6 Trip
0.2 A 180.00˚ 18.06% 21.91%
SIDE
0.2 A 60.00˚ 18.06% 21.91%
2
0.2 A 300.00˚ 18.06% 21.91%

No Side Injection Injection Diagram I-diff I-Rest Result


0.4 A 0.00˚ 18.13% 22.15%
SIDE 0.4 A -120.00˚ 18.13% 22.15%
1
0.4 A 120.00˚ 18.13% 22.15%
7 Trip
0.22 A 180.00˚ 18.13% 22.15%
SIDE
0.22 A 60.00˚ 18.13% 22.15%
2
0.22 A 300.00˚ 18.13% 22.15%

Page A1 _ 8 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

No Side Injection Injection Diagram I-diff I-Rest Result


0.42 A 0.00˚ 18.20% 22.21%
SIDE 0.42 A -120.00˚ 18.20% 22.21%
1
0.42 A 120.00˚ 18.20% 22.21%
8 Trip
0.24 A 180.00˚ 18.20% 22.21%
SIDE
0.24 A 60.00˚ 18.20% 22.21%
2
0.24 A 300.00˚ 18.20% 22.21%

Page A1 _ 9 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

No Side Injection Injection Diagram I-diff I-Rest Result


1.73 A 0.00˚ 22.28% 30.74%
SIDE 1.73 A -120.00˚ 22.28% 30.74%
1
1.73 A 120.00˚ 22.28% 30.74%
9 Trip
1.5 A 180.00˚ 22.28% 30.74%
SIDE
1.5 A 60.00˚ 22.28% 30.74%
2
1.5 A 300.00˚ 22.28% 30.74%

No Side Injection Injection Diagram I-diff I-Rest Result


2.1 A 0.00˚ 30.03% 37.22%
SIDE 2.1 A -120.00˚ 30.03% 37.22%
1
2.1 A 120.00˚ 30.03% 37.22%
10 Trip
1.8 A 180.00˚ 30.03% 37.22%
SIDE
1.8 A 60.00˚ 30.03% 37.22%
2
1.8 A 300.00˚ 30.03% 37.22%

Page A1 _ 10 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

6. Line Differential (87L) Shot Test

Injection Secondary Injection Diagram Expected Time Actual Time

IA 0.25 A <0 ᵒ

IB 0.0 A < -120 ᵒ 0.0s 26.12 ms

IC 0.0 A < 120 ᵒ

Injection Secondary Injection Diagram Expected Time Actual Time

IA 0.0 A <0 ᵒ

IB 0.25 A < -120 ᵒ 0.0s 21.59 ms

IC 0.0 A < 120 ᵒ

Injection Secondary Injection Diagram Expected Time Actual Time

IA 0.0 A <0 ᵒ

IB 0.0 A < -120 ᵒ 0.0s 22.29 ms

IC 0.25 A < 120 ᵒ

Injection Secondary Injection Diagram Expected Time Actual Time

IA 0.25 A <0 ᵒ

IB 0.25 A < -120 ᵒ 0.0s 22.30 ms

IC 0.00 A < 120 ᵒ

Page A1 _ 11 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Injection Secondary Injection Diagram Expected Time Actual Time

IA 0.0 A <0 ᵒ

IB 0.25 A < -120 ᵒ 0.0s 21.21 ms

IC 0.25 A < 120 ᵒ

Injection Secondary Injection Diagram Expected Time Actual Time

IA 0.25 A <0 ᵒ

IB 0.0 A < -120 ᵒ 0.0s 26.29 ms

IC 0.25 A < 120 ᵒ

Injection Secondary Injection Diagram Expected Time Actual Time

IA 0.25 A <0 ᵒ

IB 0.25 A < -120 ᵒ 0.0s 20.12 ms

IC 0.25 A < 120 ᵒ

*Tolerance 50 ms
**Tolerance ±5%

7. Stability Secondary Test


- Stability 25%
Stable Condition
No Side Injection Injection Diagram I-diff I-Rest
0.05 A 0.00˚ 0.004 % 20.77 %

SIDE 1 0.05 A -120.00˚ 0.008 % 20.77 %

0.05 A 120.00˚ 0.003 % 20.77 %


1
0.05 A 180.00˚ 0.007 % 20.77 %

SIDE 2 0.05 A 60.00˚ 0.008 % 20.77 %

0.05 A 300.00˚ 0.008 % 20.77 %

Page A1 _ 12 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Unstable Condition
No Side Injection Injection Diagram I-diff I-Rest
0.05 A 0.00˚ 9.940 % 20.77 %

SIDE 1 0.05 A -120.00˚ 9.936 % 20.77 %

0.05 A 120.00˚ 10.10 % 20.77 %


2
0.05 A 0.00˚ 9.940 % 20.77 %

SIDE 2 0.05 A -120.00˚ 9.935 % 20.77 %

0.05 A 120.00˚ 10.10 % 20.77 %

- Stability 50%
Stable Condition
No Side Injection Injection Diagram I-diff I-Rest
0.1 A 0.00˚ 0.113 % 21.51 %

SIDE 1 0.1 A -120.00˚ 0.076 % 21.52 %

0.1 A 120.00˚ 0.077 % 21.49 %


1
0.1 A 180.00˚ 0.112 % 21.51 %

SIDE 2 0.1 A 60.00˚ 0.076 % 21.51 %

0.1 A 300.00˚ 0.077 % 21.49 %


Unstable Condition
No Side Injection Injection Diagram I-diff I-Rest
0.1 A 0.00˚ 20.08 % 21.51 %

SIDE 1 0.1 A -120.00˚ 20.06 % 21.52 %

0.1 A 120.00˚ 20.08 % 21.49 %


2
0.1 A 0.00˚ 20.08 % 21.51 %

SIDE 2 0.1 A -120.00˚ 20.06 % 21.51 %

0.1 A 120.00˚ 20.08 % 21.49 %

- Stability 75%
Stable Condition
No Side Injection Injection Diagram I-diff I-Rest
0.15 A 0.00˚ 0.071 % 22.21 %

SIDE 1 0.15 A -120.00˚ 0.079 % 22.20 %

0.15 A 120.00˚ 0.071 % 22.21 %


1
0.15 A 180.00˚ 0.078 % 22.20 %

SIDE 2 0.15 A 60.00˚ 0.070 % 22.21 %

0.15 A 300.00˚ 0.071 % 22.20 %

Page A1 _ 13 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Unstable Condition
No Side Injection Injection Diagram I-diff I-Rest
0.15 A 0.00˚ 29.94 % 22.21 %

SIDE 1 0.15 A -120.00˚ 29.97 % 22.20 %

0.15 A 120.00˚ 29.99 % 22.21 %


2
0.15 A 0.00˚ 29.94 % 22.20 %

SIDE 2 0.15 A -120.00˚ 29.97 % 22.21 %

0.15 A 120.00˚ 29.99 % 22.20 %

- Stability 100%
Stable Condition
No Side Injection Injection Diagram I-diff I-Rest
0.2 A 0.00˚ 0.084 % 22.73 %

SIDE 1 0.2 A -120.00˚ 0.083 % 22.75 %

0.2 A 120.00˚ 0.081 % 22.73 %


1
0.2 A 180.00˚ 0.082 % 22.73 %

SIDE 2 0.2 A 60.00˚ 0.084 % 22.75 %

0.2 A 300.00˚ 0.084 % 22.73 %


Unstable Condition
No Side Injection Injection Diagram I-diff I-Rest
0.2 A 0.00˚ 39.97 % 22.73 %

SIDE 1 0.2 A -120.00˚ 39.97 % 22.75 %

0.2 A 120.00˚ 39.97 % 22.73 %


2
0.2 A 0.00˚ 39.97 % 22.73 %

SIDE 2 0.2 A -120.00˚ 39.97 % 22.75 %

0.2 A 120.00˚ 39.97 % 22.73 %

Page A1 _ 14 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

8. Function Test Line Diff

Fungsi PMT
Posisi
No Item Uji Synchrocheck TRIP RECLOSE
Switch AR FT
R S T R S T
PENGUJIAN SAAT SIGNALLING HEALTHY
1 Pengujian Diff Ph A AR ON SYNC OK v v
2 Pengujian Diff Ph B AR ON SYNC OK v v
3 Pengujian Diff Ph C AR ON SYNC OK v v
4 Pengujian Diff Ph A-B AR ON SYNC OK v v v v v v
5 Pengujian Diff Ph B-C AR ON SYNC OK v v v v v v
6 Pengujian Diff Ph C-A AR ON SYNC OK v v v v v v
7 Pengujian Diff Ph A-B-C AR ON SYNC OK v v v v v v
8 Pengujian Diff Ph A-B AR ON SYNC NOT OK v v v v
9 Pengujian Diff Ph A AR OFF SYNC OK v v v v
10 Pengujian Diff Ph B AR OFF SYNC OK v v v v
11 Pengujian Diff Ph C AR OFF SYNC OK v v v v
12 Pengujian Diff Ph A-B AR OFF SYNC OK v v v v
Pengujian permanent fault Diff ph A +
13 AR ON SYNC OK v v v
(deadtime) + Diff ph C
Pengujian evolving fault Diff ph A + Diff Ph B +
14 AR ON SYNC OK v v v v
(deadtime) + Diff ph B
Pengujian SOTF ph C (manual close via BO alat
15 AR ON SYNC OK v v v v
uji)
16 Pengujian DC loss (booting) AR ON SYNC OK No Action
17 2nd Harmonic & 5th Harmonic No Action

9. Distance Parameter

Distance (21) Parameter:

Relay Setting Distance Zone 1 Distance Zone 2 Distance Zone 3

Imin (secondary) 0.19 A 0.19 A 0.19 A


Characteristic Quad/Quad Quad/Quad Quad/Quad
R (Ph-G) & R (Ph-Ph) 17.43Ω/17.43Ω 17.43Ω/17.43Ω 17.43Ω/17.43Ω
X Reach 6.46Ω 9.69Ω 21.73Ω
Angle 74.7° 74.7° 74.7°
Directional Forward Forward Forward
Trip Time 0s 0.4s 1.4s
Kr / Kx NA NA NA
*Tolerance 50 ms
**Tolerance ±5%

Page A1 _ 15 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Characteristic Zone:

10. Zone Test


Characteristic Zone 1

Page A1 _ 16 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Characteristic Zone 2

Characteristic Zone 3

Page A1 _ 17 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Shot Test Z1 , Z2 , Z3

X/Ω

20

15

10

-5

-10 -5 0 5 10 15 20
R/Ω

Shot Test: Fault Type L1-E


|Z| Phi % % of t nom t act. Dev. VTest: Result
6.296 Ω 19.62 ° n/a 0.00 s 17.50 ms 17.50 ms 50.00 V Passed
11.59 Ω 43.23 ° n/a 400.0 ms 419.6 ms 4.9 % 50.00 V Passed
21.67 Ω 53.32 ° n/a 1.400 s 1.423 s 1.621 % 50.00 V Passed

Shot Test: Fault Type L2-E


|Z| Phi % % of t nom t act. Dev. VTest: Result
6.296 Ω 19.62 ° n/a 0.00 s 17.50 ms 17.50 ms 50.00 V Passed
11.59 Ω 43.23 ° n/a 400.0 ms 421.1 ms 5.275 % 50.00 V Passed
21.67 Ω 53.32 ° n/a 1.400 s 1.423 s 1.636 % 50.00 V Passed

Shot Test: Fault Type L3-E


|Z| Phi % % of t nom t act. Dev. VTest: Result
6.296 Ω 19.62 ° n/a 0.00 s 18.50 ms 18.50 ms 50.00 V Passed
11.59 Ω 43.23 ° n/a 400.0 ms 421.4 ms 5.35 % 50.00 V Passed
21.67 Ω 53.32 ° n/a 1.400 s 1.423 s 1.607 % 50.00 V Passed
Shot Test: Fault Type L1-L2
|Z| Phi % % of t nom t act. Dev. VTest: Result
6.296 Ω 19.62 ° n/a 0.00 s 18.20 ms 18.20 ms 50.00 V Passed
11.59 Ω 43.23 ° n/a 400.0 ms 418.9 ms 4.725 % 50.00 V Passed
21.67 Ω 53.32 ° n/a 1.400 s 1.424 s 1.736 % 50.00 V Passed

Shot Test: Fault Type L2-L3


|Z| Phi % % of t nom t act. Dev. VTest: Result
6.296 Ω 19.62 ° n/a 0.00 s 17.20 ms 17.20 ms 50.00 V Passed
11.59 Ω 43.23 ° n/a 400.0 ms 419.1 ms 4.775 % 50.00 V Passed
21.67 Ω 53.32 ° n/a 1.400 s 1.422 s 1.55 % 50.00 V Passed

Page A1 _ 18 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Shot Test: Fault Type L3-L1


|Z| Phi % % of t nom t act. Dev. VTest: Result
6.296 Ω 19.62 ° n/a 0.00 s 17.70 ms 17.70 ms 50.00 V Passed
11.59 Ω 43.23 ° n/a 400.0 ms 418.6 ms 4.65 % 50.00 V Passed
21.67 Ω 53.32 ° n/a 1.400 s 1.419 s 1.321 % 50.00 V Passed

Characteristic Distance ( Search test )


- Sudut Line ( 74.7° )
Search Test: Fault Type L1-E
Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 6.719 Ω 74.70 ° 1.773 Ω 6.481 Ω |Z| 6.697 Ω 0.324 % Passed
Z2 10.08 Ω 74.70 ° 2.660 Ω 9.721 Ω |Z| 10.05 Ω 0.324 % Passed
Z3 22.60 Ω 74.70 ° 5.964 Ω 21.80 Ω |Z| 22.53 Ω 0.324 % Passed
X/Ω

20

15

10

-5

-10 -5 0 5 10 15 20
R/Ω

Search Test: Fault Type L2-E


Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 6.719 Ω 74.70 ° 1.773 Ω 6.481 Ω |Z| 6.697 Ω 0.324 % Passed
Z2 10.08 Ω 74.70 ° 2.660 Ω 9.721 Ω |Z| 10.05 Ω 0.324 % Passed
Z3 22.60 Ω 74.70 ° 5.964 Ω 21.80 Ω |Z| 22.53 Ω 0.324 % Passed
X/Ω

20

15

10

-5

-10 -5 0 5 10 15 20
R/Ω

Page A1 _ 19 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Search Test: Fault Type L3-E


Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 6.719 Ω 74.70 ° 1.773 Ω 6.481 Ω |Z| 6.697 Ω 0.324 % Passed
Z2 10.08 Ω 74.70 ° 2.660 Ω 9.721 Ω |Z| 10.05 Ω 0.324 % Passed
Z3 22.60 Ω 74.70 ° 5.964 Ω 21.80 Ω |Z| 22.53 Ω 0.324 % Passed
X/Ω

20

15

10

-5

-10 -5 0 5 10 15 20
R/Ω

Search Test: Fault Type L1-L2


Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 6.719 Ω 74.70 ° 1.773 Ω 6.481 Ω |Z| 6.697 Ω 0.324 % Passed
Z2 10.08 Ω 74.70 ° 2.660 Ω 9.721 Ω |Z| 10.05 Ω 0.324 % Passed
Z3 22.60 Ω 74.70 ° 5.964 Ω 21.80 Ω |Z| 22.53 Ω 0.324 % Passed
X/Ω

20

15

10

-5

-10 -5 0 5 10 15 20
R/Ω

Page A1 _ 20 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Search Test: Fault Type L2-L3


Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 6.719 Ω 74.70 ° 1.773 Ω 6.481 Ω |Z| 6.697 Ω 0.324 % Passed
Z2 10.08 Ω 74.70 ° 2.660 Ω 9.721 Ω |Z| 10.05 Ω 0.324 % Passed
Z3 22.60 Ω 74.70 ° 5.964 Ω 21.80 Ω |Z| 22.53 Ω 0.324 % Passed
X/Ω

20

15

10

-5

-10 -5 0 5 10 15 20
R/Ω

Search Test: Fault Type L3-L1


Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 6.719 Ω 74.70 ° 1.773 Ω 6.481 Ω |Z| 6.697 Ω 0.324 % Passed
Z2 10.08 Ω 74.70 ° 2.660 Ω 9.721 Ω |Z| 10.05 Ω 0.324 % Passed
Z3 22.46 Ω 74.70 ° 5.925 Ω 21.66 Ω |Z| 22.53 Ω -0.324 % Passed
X/Ω

20

15

10

-5

-10 -5 0 5 10 15 20
R/Ω

Page A1 _ 21 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

- Sudut 0°

Search Test: Fault Type L1-E


Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 17,38 Ω 0,00 ° 17,38 Ω 0,00 Ω |Z| 17,47 Ω -0,4962 % Passed
X/Ω

10,0

7,5

5,0

2,5

0,0

-2,5

-5,0

-7,5

-10,0

-2,5 0,0 2,5 5,0 7,5 10,0 12,5 15,0 17,5


R/Ω

Search Test: Fault Type L2-E


Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 17,38 Ω 0,00 ° 17,38 Ω 0,00 Ω |Z| 17,47 Ω -0,4962 % Passed
X/Ω

10,0

7,5

5,0

2,5

0,0

-2,5

-5,0

-7,5

-10,0

-2,5 0,0 2,5 5,0 7,5 10,0 12,5 15,0 17,5


R/Ω

Page A1 _ 22 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Search Test: Fault Type L3-E


Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 17,38 Ω 0,00 ° 17,38 Ω 0,00 Ω |Z| 17,47 Ω -0,4962 % Passed
X/Ω

10,0

7,5

5,0

2,5

0,0

-2,5

-5,0

-7,5

-10,0

-2,5 0,0 2,5 5,0 7,5 10,0 12,5 15,0 17,5


R/Ω

Search Test: Fault Type L1-L2


Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 17,38 Ω 0,00 ° 17,38 Ω 0,00 Ω |Z| 17,47 Ω -0,4962 % Passed
X/Ω

10,0

7,5

5,0

2,5

0,0

-2,5

-5,0

-7,5

-10,0

-2,5 0,0 2,5 5,0 7,5 10,0 12,5 15,0 17,5


R/Ω

Page A1 _ 23 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Search Test: Fault Type L2-L3


Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 17,38 Ω 0,00 ° 17,38 Ω 0,00 Ω |Z| 17,47 Ω -0,4962 % Passed
X/Ω

10,0

7,5

5,0

2,5

0,0

-2,5

-5,0

-7,5

-10,0

-2,5 0,0 2,5 5,0 7,5 10,0 12,5 15,0 17,5


R/Ω

Search Test: Fault Type L3-L1


Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 17,38 Ω 0,00 ° 17,38 Ω 0,00 Ω |Z| 17,47 Ω -0,4962 % Passed
X/Ω

10,0

7,5

5,0

2,5

0,0

-2,5

-5,0

-7,5

-10,0

-2,5 0,0 2,5 5,0 7,5 10,0 12,5 15,0 17,5


R/Ω

Page A1 _ 24 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Search Test: Fault Type L1-E

Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z2 17,42 Ω 0,00 ° 17,42 Ω 0,00 Ω |Z| 17,48 Ω -0,3718 % Passed
X/Ω

40

30

20

10

-10

-20

-30 -20 -10 0 10 20 30


R/Ω

Search Test: Fault Type L2-E


Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z2 17,42 Ω 0,00 ° 17,42 Ω 0,00 Ω |Z| 17,48 Ω -0,3718 % Passed
X/Ω

40

30

20

10

-10

-20

-30 -20 -10 0 10 20 30


R/Ω

Page A1 _ 25 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Search Test: Fault Type L3-E

Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z2 17,42 Ω 0,00 ° 17,42 Ω 0,00 Ω |Z| 17,48 Ω -0,3718 % Passed
X/Ω

40

30

20

10

-10

-20

-30 -20 -10 0 10 20 30


R/Ω

Search Test: Fault Type L1-L2

Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z2 17,42 Ω 0,00 ° 17,42 Ω 0,00 Ω |Z| 17,48 Ω -0,3718 % Passed
X/Ω

40

30

20

10

-10

-20

-30 -20 -10 0 10 20 30


R/Ω

Page A1 _ 26 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Search Test: Fault Type L2-L3

Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z2 17,42 Ω 0,00 ° 17,42 Ω 0,00 Ω |Z| 17,48 Ω -0,3718 % Passed
X/Ω

40

30

20

10

-10

-20

-30 -20 -10 0 10 20 30


R/Ω

Search Test: Fault Type L3-L1


Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z2 17,42 Ω 0,00 ° 17,42 Ω 0,00 Ω |Z| 17,48 Ω -0,3718 % Passed
X/Ω

40

30

20

10

-10

-20

-30 -20 -10 0 10 20 30


R/Ω

Page A1 _ 27 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Search Test: Fault Type L1-E

Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z3 17,48 Ω 0,00 ° 17,48 Ω 0,00 Ω |Z| 17,55 Ω -0,4152 % Passed
X/Ω

20

15

10

-5

-10 -5 0 5 10 15 20
R/Ω

Search Test: Fault Type L2-E

Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z3 17,48 Ω 0,00 ° 17,48 Ω 0,00 Ω |Z| 17,55 Ω -0,4152 % Passed
X/Ω

20

15

10

-5

-10 -5 0 5 10 15 20
R/Ω

Page A1 _ 28 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Search Test: Fault Type L3-E

Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z3 17,48 Ω 0,00 ° 17,48 Ω 0,00 Ω |Z| 17,55 Ω -0,4152 % Passed
X/Ω

20

15

10

-5

-10 -5 0 5 10 15 20
R/Ω

Search Test: Fault Type L1-L2

Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z3 17,48 Ω 0,00 ° 17,48 Ω 0,00 Ω |Z| 17,55 Ω -0,4152 % Passed
X/Ω

20

15

10

-5

-10 -5 0 5 10 15 20
R/Ω

Page A1 _ 29 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Search Test: Fault Type L2-L3

Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z3 17,48 Ω 0,00 ° 17,48 Ω 0,00 Ω |Z| 17,55 Ω -0,4152 % Passed
X/Ω

20

15

10

-5

-10 -5 0 5 10 15 20
R/Ω

Search Test: Fault Type L3-L1

Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z3 17,48 Ω 0,00 ° 17,48 Ω 0,00 Ω |Z| 17,55 Ω -0,4152 % Passed
X/Ω

20

15

10

-5

-10 -5 0 5 10 15 20
R/Ω

Page A1 _ 30 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

- Sudut 30°

Search Test: Fault Type L1-E


Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 12.96 Ω 30.00 ° 11.23 Ω 6.481 Ω |Z| 12.92 Ω 0.324 % Passed
Z2 19.44 Ω 30.00 ° 16.84 Ω 9.721 Ω |Z| 19.38 Ω 0.324 % Passed
Z3 23.88 Ω 30.00 ° 20.68 Ω 11.94 Ω |Z| 23.98 Ω -0.4152 % Passed
X/Ω

25

20

15

10

-5

-5 0 5 10 15 20 25
R/Ω

Search Test: Fault Type L2-E


Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 12.96 Ω 30.00 ° 11.23 Ω 6.481 Ω |Z| 12.92 Ω 0.324 % Passed
Z2 19.44 Ω 30.00 ° 16.84 Ω 9.721 Ω |Z| 19.38 Ω 0.324 % Passed
Z3 23.88 Ω 30.00 ° 20.68 Ω 11.94 Ω |Z| 23.98 Ω -0.4152 % Passed
X/Ω

25

20

15

10

-5

-5 0 5 10 15 20 25
R/Ω

Page A1 _ 31 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Search Test: Fault Type L3-E


Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 12.96 Ω 30.00 ° 11.23 Ω 6.481 Ω |Z| 12.92 Ω 0.324 % Passed
Z2 19.44 Ω 30.00 ° 16.84 Ω 9.721 Ω |Z| 19.38 Ω 0.324 % Passed
Z3 23.88 Ω 30.00 ° 20.68 Ω 11.94 Ω |Z| 23.98 Ω -0.4152 % Passed
X/Ω

25

20

15

10

-5

-5 0 5 10 15 20 25
R/Ω

Search Test: Fault Type L1-L2


Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 12.96 Ω 30.00 ° 11.23 Ω 6.481 Ω |Z| 12.92 Ω 0.324 % Passed
Z2 19.44 Ω 30.00 ° 16.84 Ω 9.721 Ω |Z| 19.38 Ω 0.324 % Passed
Z3 23.88 Ω 30.00 ° 20.68 Ω 11.94 Ω |Z| 23.98 Ω -0.4152 % Passed
X/Ω

25

20

15

10

-5

-5 0 5 10 15 20 25
R/Ω

Page A1 _ 32 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Search Test: Fault Type L2-L3

Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 12.96 Ω 30.00 ° 11.23 Ω 6.481 Ω |Z| 12.92 Ω 0.324 % Passed
Z2 19.44 Ω 30.00 ° 16.84 Ω 9.721 Ω |Z| 19.38 Ω 0.324 % Passed
Z3 23.88 Ω 30.00 ° 20.68 Ω 11.94 Ω |Z| 23.98 Ω -0.4152 % Passed
X/Ω

25

20

15

10

-5

-5 0 5 10 15 20 25
R/Ω

Search Test: Fault Type L3-L1


Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 12.96 Ω 30.00 ° 11.23 Ω 6.481 Ω |Z| 12.92 Ω 0.324 % Passed
Z2 19.44 Ω 30.00 ° 16.84 Ω 9.721 Ω |Z| 19.38 Ω 0.324 % Passed
Z3 23.88 Ω 30.00 ° 20.68 Ω 11.94 Ω |Z| 23.98 Ω -0.4152 % Passed
X/Ω

25

20

15

10

-5

-5 0 5 10 15 20 25
R/Ω

Page A1 _ 33 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

- Sudut 60°

Search Test: Fault Type L1-E


Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 7.484 Ω 60.00 ° 3.742 Ω 6.481 Ω |Z| 7.459 Ω 0.324 % Passed
Z2 11.23 Ω 60.00 ° 5.613 Ω 9.721 Ω |Z| 11.19 Ω 0.324 % Passed
Z3 25.17 Ω 60.00 ° 12.59 Ω 21.80 Ω |Z| 25.09 Ω 0.324 % Passed
X/Ω

20

15

10

-5

-10 -5 0 5 10 15 20
R/Ω

Search Test: Fault Type L2-E


Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 7.484 Ω 60.00 ° 3.742 Ω 6.481 Ω |Z| 7.459 Ω 0.324 % Passed
Z2 11.23 Ω 60.00 ° 5.613 Ω 9.721 Ω |Z| 11.19 Ω 0.324 % Passed
Z3 25.17 Ω 60.00 ° 12.59 Ω 21.80 Ω |Z| 25.09 Ω 0.324 % Passed
X/Ω

20

15

10

-5

-10 -5 0 5 10 15 20
R/Ω

Page A1 _ 34 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Search Test: Fault Type L3-E

Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 7.484 Ω 60.00 ° 3.742 Ω 6.481 Ω |Z| 7.459 Ω 0.324 % Passed
Z2 11.23 Ω 60.00 ° 5.613 Ω 9.721 Ω |Z| 11.19 Ω 0.324 % Passed
Z3 25.17 Ω 60.00 ° 12.59 Ω 21.80 Ω |Z| 25.09 Ω 0.324 % Passed
X/Ω

20

15

10

-5

-10 -5 0 5 10 15 20
R/Ω

Search Test: Fault Type L1-L2


Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 7.484 Ω 60.00 ° 3.742 Ω 6.481 Ω |Z| 7.459 Ω 0.324 % Passed
Z2 11.23 Ω 60.00 ° 5.613 Ω 9.721 Ω |Z| 11.19 Ω 0.324 % Passed
Z3 25.17 Ω 60.00 ° 12.59 Ω 21.80 Ω |Z| 25.09 Ω 0.324 % Passed
X/Ω

20

15

10

-5

-10 -5 0 5 10 15 20
R/Ω

Page A1 _ 35 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Search Test: Fault Type L2-L3


Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 7.484 Ω 60.00 ° 3.742 Ω 6.481 Ω |Z| 7.459 Ω 0.324 % Passed
Z2 11.23 Ω 60.00 ° 5.613 Ω 9.721 Ω |Z| 11.19 Ω 0.324 % Passed
Z3 25.17 Ω 60.00 ° 12.59 Ω 21.80 Ω |Z| 25.09 Ω 0.324 % Passed
X/Ω

20

15

10

-5

-10 -5 0 5 10 15 20
R/Ω

Search Test: Fault Type L3-L1

Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 7.484 Ω 60.00 ° 3.742 Ω 6.481 Ω |Z| 7.459 Ω 0.324 % Passed
Z2 11.23 Ω 60.00 ° 5.613 Ω 9.721 Ω |Z| 11.19 Ω 0.324 % Passed
Z3 25.17 Ω 60.00 ° 12.59 Ω 21.80 Ω |Z| 25.09 Ω 0.324 % Passed
X/Ω

20

15

10

-5

-10 -5 0 5 10 15 20
R/Ω

Page A1 _ 36 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

- Sudut 90

Search Test: Fault Type L1-E


Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 6.439 Ω 90.00 ° 0.00 Ω 6.439 Ω |Z| 6.460 Ω -0.324 % Passed
Z2 9.721 Ω 90.00 ° 0.00 Ω 9.721 Ω |Z| 9.690 Ω 0.324 % Passed
Z3 21.80 Ω 90.00 ° 0.00 Ω 21.80 Ω |Z| 21.73 Ω 0.324 % Passed
X/Ω

20

15

10

-5

-10 -5 0 5 10 15 20
R/Ω

Search Test: Fault Type L2-E


Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 6.481 Ω 90.00 ° 0.00 Ω 6.481 Ω |Z| 6.460 Ω 0.324 % Passed
Z2 9.721 Ω 90.00 ° 0.00 Ω 9.721 Ω |Z| 9.690 Ω 0.324 % Passed
Z3 21.80 Ω 90.00 ° 0.00 Ω 21.80 Ω |Z| 21.73 Ω 0.324 % Passed
X/Ω

20

15

10

-5

-10 -5 0 5 10 15 20
R/Ω

Page A1 _ 37 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Search Test: Fault Type L3-E


Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 6.481 Ω 90.00 ° 0.00 Ω 6.481 Ω |Z| 6.460 Ω 0.324 % Passed
Z2 9.721 Ω 90.00 ° 0.00 Ω 9.721 Ω |Z| 9.690 Ω 0.324 % Passed
Z3 21.80 Ω 90.00 ° 0.00 Ω 21.80 Ω |Z| 21.73 Ω 0.324 % Passed
X/Ω

20

15

10

-5

-10 -5 0 5 10 15 20
R/Ω

Search Test: Fault Type L1-L2


Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 6.481 Ω 90.00 ° 0.00 Ω 6.481 Ω |Z| 6.460 Ω 0.324 % Passed
Z2 9.721 Ω 90.00 ° 0.00 Ω 9.721 Ω |Z| 9.690 Ω 0.324 % Passed
Z3 21.80 Ω 90.00 ° 0.00 Ω 21.80 Ω |Z| 21.73 Ω 0.324 % Passed
X/Ω

20

15

10

-5

-10 -5 0 5 10 15 20
R/Ω

Page A1 _ 38 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Search Test: Fault Type L2-L3

Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 6.481 Ω 90.00 ° 0.00 Ω 6.481 Ω |Z| 6.460 Ω 0.324 % Passed
Z2 9.721 Ω 90.00 ° 0.00 Ω 9.721 Ω |Z| 9.690 Ω 0.324 % Passed
Z3 21.80 Ω 90.00 ° 0.00 Ω 21.80 Ω |Z| 21.73 Ω 0.324 % Passed
X/Ω

20

15

10

-5

-10 -5 0 5 10 15 20
R/Ω

Search Test: Fault Type L3-L1


Zone Z act Phi act R act X act Assessed Qty. Nom. Dev. Result
Z1 6.481 Ω 90.00 ° 0.00 Ω 6.481 Ω |Z| 6.460 Ω 0.324 % Passed
Z2 9.721 Ω 90.00 ° 0.00 Ω 9.721 Ω |Z| 9.690 Ω 0.324 % Passed
Z3 21.66 Ω 90.00 ° 0.00 Ω 21.66 Ω |Z| 21.73 Ω -0.324 % Passed
X/Ω

20

15

10

-5

-10 -5 0 5 10 15 20
R/Ω

Page A1 _ 39 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

11. 85-21 Parameter

Relay Setting 85 - 21

Characteristic PUTT
Trigger Zone 2
Trip Time* 0s
Auto Reclose Enabled
*Tolerance 50 ms

12. 85-21 Test


Distance Expected Actual
No Fault Simulation Action Result
Received Time Time
1 Zone 2 No 0.4 s 0.408 s Trip Passed
2 Zone 2 Yes 0s 20 ms Reclose Passed
*Test used Dummy CB

Characteristic PUTT

X/Ω

20

15

10

-5

-10 -5 0 5 10 15 20
R/Ω

Shot Test: Fault Type L1-E


|Z| Phi t nom t act. Dev. VTest: Result
20.00 Ω 26.36 ° 400.0 ms 76.40 ms -80.9 % 40.00 V Failed
9.285 Ω 107.30 ° 400.0 ms 74.40 ms -81.4 % 40.00 V Failed
8.000 Ω 106.70 ° 400.0 ms 58.20 ms -85.45 % 40.00 V Failed
18.71 Ω 23.63 ° 400.0 ms 61.70 ms -84.58 % 40.00 V Failed
14.53 Ω 40.00 ° 400.0 ms 79.30 ms -80.17 % 40.00 V Failed
9.538 Ω 87.24 ° 400.0 ms 72.70 ms -81.83 % 40.00 V Failed

Page A1 _ 40 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Shot Test: Fault Type L2-E


|Z| Phi t nom t act. Dev. VTest: Result
20.00 Ω 26.36 ° 400.0 ms 78.30 ms -80.42 % 40.00 V Failed
9.285 Ω 107.30 ° 400.0 ms 74.30 ms -81.42 % 40.00 V Failed
8.000 Ω 106.70 ° 400.0 ms 59.00 ms -85.25 % 40.00 V Failed
18.71 Ω 23.63 ° 400.0 ms 62.20 ms -84.45 % 40.00 V Failed
14.53 Ω 40.00 ° 400.0 ms 78.00 ms -80.5 % 40.00 V Failed
9.538 Ω 87.24 ° 400.0 ms 71.20 ms -82.2 % 40.00 V Failed

Shot Test: Fault Type L3-E


|Z| Phi t nom t act. Dev. VTest: Result
20.00 Ω 26.36 ° 400.0 ms 76.90 ms -80.78 % 40.00 V Failed
9.285 Ω 107.30 ° 400.0 ms 73.40 ms -81.65 % 40.00 V Failed
8.000 Ω 106.70 ° 400.0 ms 57.90 ms -85.53 % 40.00 V Failed
18.71 Ω 23.63 ° 400.0 ms 59.60 ms -85.1 % 40.00 V Failed
14.53 Ω 40.00 ° 400.0 ms 74.70 ms -81.33 % 40.00 V Failed
9.538 Ω 87.24 ° 400.0 ms 71.80 ms -82.05 % 40.00 V Failed

Shot Test: Fault Type L1-L2


|Z| Phi t nom t act. Dev. VTest: Result
20.00 Ω 26.36 ° 400.0 ms 79.40 ms -80.15 % 40.00 V Failed
9.285 Ω 107.30 ° 400.0 ms 76.20 ms -80.95 % 40.00 V Failed
8.000 Ω 106.70 ° 400.0 ms 61.10 ms -84.72 % 40.00 V Failed
18.71 Ω 23.63 ° 400.0 ms 75.50 ms -81.13 % 40.00 V Failed
14.53 Ω 40.00 ° 400.0 ms 73.70 ms -81.58 % 40.00 V Failed
9.538 Ω 87.24 ° 400.0 ms 75.50 ms -81.13 % 40.00 V Failed

Shot Test: Fault Type L2-L3


|Z| Phi t nom t act. Dev. VTest: Result
20.00 Ω 26.36 ° 400.0 ms 79.20 ms -80.2 % 40.00 V Failed
9.285 Ω 107.30 ° 400.0 ms 75.10 ms -81.22 % 40.00 V Failed
8.000 Ω 106.70 ° 400.0 ms 56.50 ms -85.88 % 40.00 V Failed
18.71 Ω 23.63 ° 400.0 ms 76.90 ms -80.78 % 40.00 V Failed
14.53 Ω 40.00 ° 400.0 ms 76.50 ms -80.88 % 40.00 V Failed
9.538 Ω 87.24 ° 400.0 ms 72.20 ms -81.95 % 40.00 V Failed

Shot Test: Fault Type L3-L1


|Z| Phi t nom t act. Dev. VTest: Result
20.00 Ω 26.36 ° 400.0 ms 78.60 ms -80.35 % 40.00 V Failed
9.285 Ω 107.30 ° 400.0 ms 71.40 ms -82.15 % 40.00 V Failed
8.000 Ω 106.70 ° 400.0 ms 59.20 ms -85.2 % 40.00 V Failed
18.71 Ω 23.63 ° 400.0 ms 78.70 ms -80.33 % 40.00 V Failed
14.53 Ω 40.00 ° 400.0 ms 75.30 ms -81.17 % 40.00 V Failed
9.538 Ω 87.24 ° 400.0 ms 71.50 ms -82.13 % 40.00 V Failed

Page A1 _ 41 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

13. 67N Parameter

Relay Setting 67N

Blocking by Distance Zone 1, 2 , 3


Threeshold 0.075 A
Operated Delay 0.1 s

*Tolerance 50 ms

14. 85-67 Test


DEF Expected Actual
No Fault Simulation Action Result
Received Time Time
1 DEF No 0.1 s 130 ms No Trip Passed
2 DEF Yes 0.1 s 127 ms Reclose Passed
*Test used Dummy CB

Characteristic DEF

X/Ω
50

40

30

20

10

-10

-20

-30

-40

-50

-60

-70

-80

-90

-60 -40 -20 0 20 40 60


R/Ω

Page A1 _ 42 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Shot Test: Fault Type L1-E


|Z| Phi t nom t act. Dev. VTest: Result
35.45 Ω 0.00 ° no trip 131.0 ms n/a 40.00 V Failed
35.45 Ω 10.00 ° no trip 129.9 ms n/a 40.00 V Failed
35.45 Ω 20.00 ° no trip 134.2 ms n/a 40.00 V Failed
35.45 Ω 30.00 ° no trip 128.9 ms n/a 40.00 V Failed
35.45 Ω 40.00 ° no trip 133.3 ms n/a 40.00 V Failed
35.45 Ω 50.00 ° no trip 131.0 ms n/a 40.00 V Failed
35.45 Ω 60.00 ° no trip 132.0 ms n/a 40.00 V Failed
35.45 Ω 70.00 ° no trip 136.2 ms n/a 40.00 V Failed
35.45 Ω 80.00 ° no trip 130.0 ms n/a 40.00 V Failed
35.45 Ω 90.00 ° no trip 133.8 ms n/a 40.00 V Failed
35.45 Ω 100.00 ° no trip 134.4 ms n/a 40.00 V Failed
35.45 Ω 110.00 ° no trip 131.5 ms n/a 40.00 V Failed
35.45 Ω 120.00 ° no trip 132.3 ms n/a 40.00 V Failed
35.45 Ω 130.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 140.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 150.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 160.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 170.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 180.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 190.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 200.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 210.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 220.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 230.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 240.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 250.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 260.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 270.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 280.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 290.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 300.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 310.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 320.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 330.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 340.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 350.00 ° no trip 130.1 ms n/a 40.00 V Failed
35.45 Ω 360.00 ° no trip 134.3 ms n/a 40.00 V Failed

Page A1 _ 43 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Shot Test: Fault Type L2-E


|Z| Phi t nom t act. Dev. VTest: Result
35.45 Ω 0.00 ° no trip 130.7 ms n/a 40.00 V Failed
35.45 Ω 10.00 ° no trip 134.0 ms n/a 40.00 V Failed
35.45 Ω 20.00 ° no trip 130.3 ms n/a 40.00 V Failed
35.45 Ω 30.00 ° no trip 130.6 ms n/a 40.00 V Failed
35.45 Ω 40.00 ° no trip 128.6 ms n/a 40.00 V Failed
35.45 Ω 50.00 ° no trip 133.6 ms n/a 40.00 V Failed
35.45 Ω 60.00 ° no trip 132.9 ms n/a 40.00 V Failed
35.45 Ω 70.00 ° no trip 136.8 ms n/a 40.00 V Failed
35.45 Ω 80.00 ° no trip 132.8 ms n/a 40.00 V Failed
35.45 Ω 90.00 ° no trip 129.4 ms n/a 40.00 V Failed
35.45 Ω 100.00 ° no trip 130.4 ms n/a 40.00 V Failed
35.45 Ω 110.00 ° no trip 129.3 ms n/a 40.00 V Failed
35.45 Ω 120.00 ° no trip 130.5 ms n/a 40.00 V Failed
35.45 Ω 130.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 140.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 150.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 160.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 170.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 180.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 190.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 200.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 210.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 220.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 230.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 240.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 250.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 260.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 270.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 280.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 290.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 300.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 310.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 320.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 330.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 340.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 350.00 ° no trip 134.0 ms n/a 40.00 V Failed
35.45 Ω 360.00 ° no trip 132.4 ms n/a 40.00 V Failed

Page A1 _ 44 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Shot Test: Fault Type L3-E


|Z| Phi t nom t act. Dev. VTest: Result
35.45 Ω 0.00 ° no trip 129.8 ms n/a 40.00 V Failed
35.45 Ω 10.00 ° no trip 130.4 ms n/a 40.00 V Failed
35.45 Ω 20.00 ° no trip 130.4 ms n/a 40.00 V Failed
35.45 Ω 30.00 ° no trip 133.3 ms n/a 40.00 V Failed
35.45 Ω 40.00 ° no trip 132.8 ms n/a 40.00 V Failed
35.45 Ω 50.00 ° no trip 133.5 ms n/a 40.00 V Failed
35.45 Ω 60.00 ° no trip 132.3 ms n/a 40.00 V Failed
35.45 Ω 70.00 ° no trip 132.4 ms n/a 40.00 V Failed
35.45 Ω 80.00 ° no trip 130.0 ms n/a 40.00 V Failed
35.45 Ω 90.00 ° no trip 132.2 ms n/a 40.00 V Failed
35.45 Ω 100.00 ° no trip 132.1 ms n/a 40.00 V Failed
35.45 Ω 110.00 ° no trip 133.0 ms n/a 40.00 V Failed
35.45 Ω 120.00 ° no trip 133.4 ms n/a 40.00 V Failed
35.45 Ω 130.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 140.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 150.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 160.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 170.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 180.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 190.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 200.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 210.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 220.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 230.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 240.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 250.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 260.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 270.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 280.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 290.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 300.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 310.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 320.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 330.00 ° no trip no trip n/a 40.00 V Passed
35.45 Ω 340.00 ° no trip 129.0 ms n/a 40.00 V Failed
35.45 Ω 350.00 ° no trip 129.8 ms n/a 40.00 V Failed
35.45 Ω 360.00 ° no trip 130.0 ms n/a 40.00 V Failed

15. SOTF Parameter

Relay Setting SOTF

Mode Distance Protection


Trigger Zone 1, Zone 2
Trip Time* 0s

*Tolerance 50 ms

16. SOTF Test


Expected Actual
No Fault Simulation Result
Time Time
1 Zone 1 0s 18.00 ms Good
2 Zone 2 0s 19.00 ms Good

Page A1 _ 45 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

17. Power Swing Block Test


Expected Actual
No Fault Simulation 68 Received Result
Time Time
1 Zone 1 Yes Block Block Good
2 Zone 2 Yes Block Block Good
3 Zone 3 Yes Block Block Good

18. Sycnh. Check (25) Parameter

Relay Setting Synchronization Check

Min. Operating Voltage 90 V / 100 V


Max. Operating Voltage 110 V / 100 V
DL LB Yes
LL DB Yes
DL DB No
Dead Voltage Limit 17 V / 100 V
Live Voltage Limit 40 V / 100 V
Voltage Diff. Limit 6 V / 100V
Angle Diff. Limit 15°
Frequency Diff. Limit 0.16 Hz

19. Characteristic Test


U Incoming U Running Synch.
Conditions Result
L-N L-N Check
Synch under Min. Operating Voltage 17V<U<90V 17<U< 90V Failure Good
Synch over Max. Operating Voltage U > 110 U > 110 Failure Good
Dead Line Dead Bus U < 17 U < 17 Failure Good
Dead Line Live Bus U < 17 U > 40 Failure Good
Live Line Dead Bus U > 40 U < 17 Failure Good

20. Synch. Check Limit Test


Synch.
Description U Incoming U Running Result
Check

Voltage Diff 5.9 V / 100V 57.74V < -120ᵒ 51.84V/63.64V < -120ᵒ Success Good
Voltage Diff 6.2 V / 100V 57.74V < -120ᵒ 51.54V/63.69V < -120ᵒ Failure Good
Phase Diff 14 ᵒ 57.74V < -120ᵒ 57.74V < -106ᵒ/ <-134ᵒ Success Good
Phase Diff 16 ᵒ 57.74V < -120ᵒ 57.74V < -104ᵒ/ <-136ᵒ Failure Good
Freq. Diff 0.14 Hz 57.74V 50.00Hz 57.74V 49.86Hz/50.14Hz Success Good
Freq. Diff 0.2 Hz 57.74V 50.00Hz 57.74V 49.80Hz/50.20Hz Failure Good

Page A1 _ 46 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

21. Function Test Distance


Switch AR Fungsi Trip PMT Simulasi AR
No Simulasi Gangguan Indikasi LED Relay
On Off No Trip 1 Pole 3 Pole Success
1 Z1 Ph R-N    Trip Ph A , Trip Zone 1
2 Z1 Ph S-N    Trip Ph B , Trip Zone 1
3 Z1 Ph T-N    Trip Ph C , Trip Zone 1
Trip Ph A , Trip PUTT , Distance
4 Z2 Ph R-N + Cr Receive   
Receive
Trip Ph B , Trip PUTT , Distance
5 Z2 Ph S-N + Cr Receive   
Receive
Trip Ph C , Trip PUTT , Distance
6 Z2 Ph T-N + Cr Receive   
Receive
DEF Forward Ph R-N Trip Ph A , Aided DEF , DEF
7   
+ Cr Receive Receive
DEF Forward Ph S-N Trip Ph B , Aided DEF , DEF
8   
+ Cr Receive Receive
DEF Forward Ph T-N Trip Ph C , Aided DEF , DEF
9   
+ Cr Receive Receive
Z1 Ph R-S
10    Trip Ph A , Trip Ph B , Trip Zone 1
( Sync. VT Bus )
Z1 Ph S-T
11    Trip Ph B , Trip Ph C , Trip Zone 1
( Sync. VT Bus )
Z1 Ph R-T
12    Trip Ph A , Trip Ph C , Trip Zone 1
( Sync. VT Bus )
Z2 Ph R-S + Cr Receive Trip Ph A , Trip Ph B , Trip PUTT ,
13   
( Sync. VT Bus ) Distance Receive
Z2 Ph S-T + Cr Receive Trip Ph B , Trip Ph C , Trip PUTT ,
14   
( Sync. VT Bus ) Distance Receive
Z2 Ph R-T + Cr Receive Trip Ph A , Trip Ph C , Trip PUTT ,
15   
( Sync. VT Bus ) Distance Receive
Squencer :
1. Z1 Ph R ( 80ms ) ->
2. Z1 Ph S ( 80ms ) -> Trip Ph A , Trip Ph B , Trip Ph C ,
16   
3. After dead time Z1 Ph Trip Zone 1
S ( 80ms )
Sync. with VT Bus
17 Z2 Ph R-N   X Trip Ph A , Z2
18 Z3 Ph S-N   X Trip Ph B , Z3
19 DEF Forward Ph T-N   -
Z1 Ph R-S Trip Ph A , Trip B , Trip C , Z1 ,
20   X
( Async. VT Bus ) Definitive Trip
21 SOTF Z1 / Z2   X SOTF , Definitive Trip
Trip Ph A , Trip Ph B, Trip Ph C, Z1,
22 Z1 Ph R-N   X
Definitive Trip , AR Not Ready
Trip Ph A , Trip Ph B, Trip Ph C,
23 Z2 Ph R-N + Cr Receive   X Trip PUTT, Definitive Trip , AR Not
Ready
Trip Ph A , Trip Ph B, Trip Ph C,
DEF Forward Ph T-N
24   X Aided DEF, Definitive Trip , AR Not
+ Cr Receive
Ready
Z1 Ph R-S Trip Ph A , Trip Ph B , Trip Ph C ,
25   X
( Sync. VT Bus ) Z1, Definitive Trip , AR not Ready
Z2 Ph S-T + Cr Receive Trip Ph A , Trip Ph B , Trip Ph C ,
26   X
( Sync. VT Bus ) Z1, Definitive Trip , AR not Ready
Gangguan saat relay
27   -
restart
28 PSB   PSB
Blocking pada saat VT
29   VT Fail
Fail

Page A1 _ 47 of 48
Type of Document : Title : Panel No.
Site Acceptance Test Protection Relay Test PHT Garuda
Report Sakti 2
End User : Project Name: Line Up
PT. PLN (Persero) Penggantian Rele Proteksi GI 150 kV Pasir
Obsollete dan Relay Proteksi Putih
Jalur Backnone P3B Sumatera

Page A1 _ 48 of 48