MATERIALS PLANNING

items
lamps 3
base 7
assemblies 4
shaft 2
tubing 16

LAMP
Gross requipment 25
Quantity on hand 3
Net requirement 22

BASE ASSEMBILIES (1 per lamps)


Gross requipment 22
Quantity on hand 7
Net requirement 15

SHAFT (1 per base assembly)


Gross requipment 15
Quantity on hand 4
Net requirement 11

TUBING (2 per shaft assembly)


Gross requipment 22
Quantity on hand 16
Net requirement 6
MRP CHART 5.1
lead time 3; lost size 25; safety stock 0; quantity on hand 30
PERIOD
1 2 3 4 5 6
gross requipment 10 15 15 10 15 10
schduled receipt 25
projected on hand 30 20 5 15 5 15 5
net requipment 10
planned order receipt 25
planned order
releases
25

MRP CHART 5.2


lead time 3; lot size 25; safety stock 0; quantity on hand 30
1 2 3 4 5 6
gross requipment 10 15 5 10 15 10
schduled receipt 25
projected on hand 30 20 5 25 15 0 15
net requipment 10
planned order receipt 25
planned order releases 25