11-03-23 9:00 AM – 05:00 PM Hospital Building Ground Floor Column Steel Fixing.
Note: Please include attachment whenever necessary
Declaration:
13-03-23 9:00 AM – 05:00 PM Marking 4 Points of the columns with the help of Total Station
With Coordinates drawing.
14-03-23 9:00 AM – 05:00 PM Check these points again with the help of cording and marks lines
According to the points for shuttering.
16-03-23 9:00 AM – 05:00 PM Concrete Pouring (1:2:4) for columns with the help of mobile
Concrete Pump and use vibrator.
Marking points for lift system and steel fixing continuous from
18-03-23 9:00 AM – 05:00 PM
Basement to ground floor.
Note: Please include attachment whenever necessary
Declaration:
20-03-23 9:00 AM – 05:00 PM Provide shuttering of lift system with the help of wooden
Planks and sheets and checking there vertical level.
21-03-23 9:00 AM – 05:00 PM Concrete pouring for lift (1:2:4) with the help of mobile pump.
Formwork for ground floor slab and beams and also manually
23-03-23 9:00 AM – 05:00 PM
checking the horizontal level of slab and beams.
Checking the vertical level of slab and beams with the help of
24-03-23 9:00 AM – 05:00 PM Auto Level and mark it.
Declaration:
27-03-23 9:00 AM – 05:00 PM Provide side stoppers on all sides of the slab and check again
Steel fixing is ok according to the drawing.
28-03-23 9:00 AM – 05:00 PM Providing MEP Pipes etc according to the MEP drawings.
29-03-23 9:00 AM – 05:00 PM Providing Spacers at all sides of beams and also at bottom
Upper and sides of the slabs for concrete cover.
Declaration:
03-04-23 9:00 AM – 05:00 PM Curing 10 days with jute cloth of beam and slab.
04-04-23 9:00 AM – 05:00 PM Marking boundary walls with the help of Total station &
Prism according to the drawing coordinates system.
05-04-23 9:00 AM – 05:00 PM Excavation work 2.5 ft depth and compact it with plate
Compactor
07-04-23 9:00 AM – 05:00 PM Steel fixing for columns b/w Spacing provided in drawing
08-04-23 9:00 AM – 05:00 PM Provide spacer on all sides of columns and then provide
Shuttering for columns.
Note: Please include attachment whenever necessary
Declaration:
10-04-23 9:00 AM – 05:00 PM Concrete pouring for these columns (1:2:4) and use vibrator.
11-04-23 9:00 AM – 05:00 PM Curing 7 days with jute cloth and also shuttering of beam for
Between these columns.
12-04-23 9:00 AM – 05:00 PM Steel fixing for beams and concrete pouring (1:2:4).
13-04-23 9:00 AM – 05:00 PM Marking DPC level with the help of auto level and providing
DPC.
Declaration:
17-04-23 9:00 AM – 05:00 PM Steel fixing of columns for 1st floor of hospital building.
18-04-23 9:00 AM – 05:00 PM Marking the points of columns with the help of total station
For shuttering.
Declaration:
26-04-23 9:00 AM – 05:00 PM Concrete pouring for columns (1:2:4) with vibrator and
checking brick Work at boundary walls.
28-04-23 9:00 AM – 05:00 PM Shuttering for beam and slab system with wooden planks
And battens.
29-04-23 9:00 AM – 05:00 PM Checking level of 1st floor slab and beams with auto-level.
Declaration:
01-05-23 9:00 AM – 05:00 PM Steel Fixing for Beams and slabs according to the drawing
Where everything is mentioned Spacing Steel No etc.
02-05-23 9:00 AM – 05:00 PM Provide side stoppers on all sides of the slab for 6’’ slab
Thickness.
03-05-23 9:00 AM – 05:00 PM Providing MEP Pipes etc according to the MEP drawings.
04-05-23 9:00 AM – 05:00 PM Providing Spacers at all sides of beams and also at bottom
Upper and sides of the slabs for concrete cover.
05-05-23 9:00 AM – 05:00 PM Steel fixing for hidden beams according to drawing and
check
Steel size according to the bar size in drawing.
06-05-23 9:00 AM – 05:00 PM
Top steel fixing on slab after MEP work is completed.
Note: Please include attachment whenever necessary
Declaration:
08-05-23 9:00 AM – 05:00 PM Concrete Pouring of beams and slab system continuous check
Level of slab with auto level.
09-05-23 9:00 AM – 05:00 PM Curing 10 days with jute cloth and removing shuttering of
Columns.
10-05-23 9:00 AM – 05:00 PM Plaster work start at boundary wall (1:6) and also provide
Chicken mesh between beam and brick work.
13-05-23 9:00 AM – 05:00 PM Steel fixing of columns for 2nd floor of hospital building.
Note: Please include attachment whenever necessary
Declaration:
15-05-23 9:00 AM – 05:00 PM Marking the points of columns with the help of total station
For shuttering.
16-05-23 9:00 AM – 05:00 PM Provide spacers on four sides of the column with steel with
The help of binding wires.
17-05-23 9:00 AM – 05:00 PM Steel fixing continuous and also marking lift points and steel
Fixing for lift system.
18-05-23 9:00 AM – 05:00 PM Steel fixing continuous and also checking boundary wall
And academic block brick work.
19-05-23 9:00 AM – 05:00 PM Provide shuttering for columns and check their vertical
Level.
20-05-23 9:00 AM – 05:00 PM Pouring of columns at 2nd floor of the hospital building.
Declaration:
22-05-23 9:00 AM – 05:00 PM Concrete cylinder casting for test of Concrete Compressive
Strength and continuous curing of 2nd floor columns.
23-05-23 9:00 AM – 05:00 PM Excavation started for emergency lift outside the Academic
Block.
24-05-23 9:00 AM – 05:00 PM Marking points for emergency lift with the help of total
Station and also check the depth of the foundation.
Steel Fixing for 2nd floor Beams and slabs according to the
27-05-23 9:00 AM – 05:00 PM drawing
Declaration:
29-05-23 9:00 AM – 05:00 PM Provide side stoppers on all sides of the slab for 6’’ slab
Thickness.
30-05-23 9:00 AM – 05:00 PM Providing MEP Pipes etc according to the MEP drawings.
Declaration:
05-06-23 9:00 AM – 05:00 PM Steel fixing of circular columns for car parking area.
06-06-23 9:00 AM – 05:00 PM Checking the level of Stairs Steps at Auditorium building.
07-06-23 9:00 AM – 05:00 PM Concrete Pouring of beams and slab system on 2nd floor of
hospital building with Mobile pump concrete.
08-06-23 9:00 AM – 05:00 PM Curing 10 days with jute cloth and removing shuttering of
Columns.
09-06-23 9:00 AM – 05:00 PM Again soil test on emergency lift and test is finally passed.
Declaration:
12-06-23 9:00 AM – 05:00 PM Checking Admin block top floor cement work and Non load
Bearing walls and electricity work is also started.
13-06-23 9:00 AM – 05:00 PM Academic block flooring work started providing 3’’ brick
Blast and P.C.C (1:4:8).
14-06-23 9:00 AM – 05:00 PM Removing 2nd Floor beam slab and lift shuttering clear
Minor concrete problems.
17-06-23 9:00 AM – 05:00 PM Concrete pounding for circular columns and use vibrator.
Note: Please include attachment whenever necessary
Declaration:
19-06-23 9:00 AM – 05:00 PM Use Core Cutter for removing concrete cylinder because
Need strong bond between building and parking area slab.
20-06-23 9:00 AM – 05:00 PM Concrete pounding for columns at the 3rd floor of the hospital
Building and use vibrator.
21-06-23 9:00 AM – 05:00 PM Shuttering for beam and slab system with wooden planks
And battens.
23-06-23 9:00 AM – 05:00 PM Steel Fixing For slab and beams according to the drawing.
24-06-23 9:00 AM – 05:00 PM Provide Hidden beams according to the drawing with size.
Note: Please include attachment whenever necessary
Declaration: