Figure 1
What are the biggest threats to reliable grid operations and performance in your region? (Select up to three)
Source: Black & Veatch
41.9% 29.0% Not enough energy storage 12.9% Lack of adequately trained
Network capacity investment not capacity manpower and appropriate tools
keeping pace with demand
2
Invest in Efficient, Resilient and STEP 1. Planning phase Thinking of interconnecting assets in totality may enhance
project optimization. Increasingly a renewable generation
Reliable Systems Robust upfront interconnect planning will mitigate the risk for
sub-optimal generation deployment because of inadequate
project developer may have the option to build
transmission assets beyond those required to deliver
The highlighted renewable energy integration challenges create transmission infrastructure. Advanced interconnection planning plant output at the prevailing transmission system
opportunities — and arguably a necessity — to expand and will also minimize incidences of curtailment where a renewable voltage. When options exist to build or expand
invest in higher quality transmission and distribution systems asset is constrained from generating power due to transmission the interconnect substation along with any
that improve the efficiency, resiliency and reliability of supply congestion resulting from peak generation from other generation plant tie lines, there can be benefits
and balance the variability of renewable sources. A reliable grid, neighboring generation sources. to a generation owner in cost reductions
keeping pace with the growth of decentralized power, will help
as it relates to design, construction and
Load flow studies, short circuit studies, transient stability analysis
to optimize generation and enhance grid stability. schedule.
and harmonic studies are some power system studies that will
assess and validate the effectiveness of renewable generation Other factors that will need to be
Transmission expansion strategies include deploying
assets’ ability to integrate into the transmission system. considered during the planning
interconnection lines, interconnection substations, and switching
facilities in areas with high potential for renewable generation stage, include technology, voltage
Once it has been validated that the project integrates sufficiently,
to allow seamless connection to the grid. These facilities, when and configuration. Details include
and as desired, estimates can then be performed to understand
appropriately deployed can also manage some of the challenges the number of circuits required,
possible additional facilities needed to accommodate the
with renewable generation related to lower inertia and lack collector substation configuration
proposed renewable generation resources.
of dynamic reactive power capability while also facilitating along with any reactive power
integration with the collector substations which accompany During the planning phase, it is important to consider cost compensation needs, such as
each large-scale renewable development. allocation strategies with respect to required facility updates capacitor bank, shunt reactors or
as the impacts from a proposed renewable facility can often dynamic reactive power.
With multiple moving parts in a regional energy transition have consequences which extend beyond the identified
increasing grid management complexities, digitalization of the Planning will need to reflect the
interconnection point. Should the cost allocation strategy
grid will be necessary to address the rapidly changing landscape potential power that is likely to be
be assigned to each project as they progress through an
of Asia’s power industry. evacuated from the interconnection
interconnect queue process, development can be stifled due
asset in the future. Space availability
to the inequitable sharing of system upgrades among proposed
This eBook presents key approaches for different phases of is another consideration when deciding
generation projects.
renewable energy projects and proposes transmission expansion between Air Insulated Substations (AIS) or
strategies that will accelerate renewable integration in Asia. It is also important in the planning stage to look beyond the space-saving Gas Insulated Substations (GIS).
known transmission constraint solution tools such as line and
Understanding grid compatibility
remote substation upgrades. As an example, we are seeing
requirements is critical as interconnection
global interest in storage as a solution to eliminate transmission
assets, like substations, may need to comply
constraints. Having a storage solution — such as lithium-ion
with the specifications and regulations of the
battery energy storage systems (BESS) — that can absorb
transmission owners. Similar equipment requirements
power and dispatch power on demand alleviates transmission
of the transmission owners can impact the procurement
constraints and has an added benefit of being able to time shift
process; developers who do not think beyond the collector
generation availability to resolve constraints inherent in the
substation can be saddled with a completed renewable energy
generation resource.
3
facility with delayed connection to customers and revenue due STEP 2. Design phase Design Expertise and Skillsets Needed
to lack of compatibility with the transmission owner’s system. to Modernize Asia’s Transmission
Compatibility issues can extend into protection, control and With the volume of land required for large-scale renewable
projects, alongside increased distances to connect transmission Core skillsets required in the detailed design teams
automation schemes which may seem trivial to review or
lines to major urban centers, land and environmental issues deploying projects, include:
consider at the project outset.
require detailed consideration when planning and designing the ● Substation professionals familiar with outdoor design
Relevant to many Southeast Asia renewable development systemwide integration of renewable energy resources. standards. Indoor design expertise is also essential when a
locations, inter-island connectivity may also need consideration project includes Gas-Insulated Substation (GIS) technology.
and advanced planning in partnership with regulators or local For example, climate change is significantly threatening the ● Physical design, and protection and control capabilities for
utilities that may require accountability for unique dynamics resilience of Asia’s power systems. Flooding, forest fires and underground cable design
which are encountered with inter-island connection limitations. storm damage all pose major risks and call for increasingly ● Renewable energy projects require a significant amount
hardened design. Smart grid improvements too — to improve the of cable to collect the power and deliver it to a step-up
responsiveness of the system during outages — are paramount transformer for integration into the transmission system.
A team with cable design experience can deliver savings by
as well as other factors from vegetation management to
optimizing designs that lower the number and/or size of
considering underground transmission options where affordable conductors needed in a collection system.
Revamping existing grid infrastructure and appropriate. ● Deep design modularization experience to deliver cost and
In cases where transmission congestion is present schedule certainty
in a system, expanding bulk power transfer may ● Renewable energy facilities typically have a standard feeder
arrangement to collect power from each string of inverters
be required to allow for the movement of power
or wind turbines. That offers opportunities to modularize
from areas with locational favorability to renewable the design and leverage pre-fabrication and pre-assembly
generation, such as areas with strong solar or wind off-site — increasingly critical as we continue to face
potential. When examining new bulk power transfer impact of COVID-19 in the region. Controlled construction
capability, it is important to consider land acquisition in a factory environment allows for pre-checkout before
costs, required Right of Way (ROW) and aesthetics of showing up at site and limiting the on-site integration time
for a collector substation.
transmission towers due to the increasing concerns
from communities with transmission expansion.
4
Better planned and designed transmission systems
are key to success in Asia’s decarbonization journey.
Addressing voltage and frequency variability and grid
code requirements effectively across the grid will reduce
system losses, conserve energy and manage peak demand.
With greater levels of intermittent and variable resources
connecting to the grid, power quality is key to reliability
and effective grid management.
5
STEP 3. Construction phase Conclusion
As Asia’s electric industry faces increasing pressure to decarbonize
Construction success happens before ground is broken.
and integrate more renewable energy, investment in transmission
Having robust execution plans at the earliest stages of the
and distribution systems will enable a more resilient and reliable
project is critical to project delivery certainty. With testing and
energy transition. The operational complexities of grids are
commissioning adequately addressed in the plans, project
shifting from large power plants sited near the point of power
delays can be minimized.
consumption to more remote renewable plants and DERs. These
Other key considerations during construction are material dynamics require re-evaluation of transmission and distribution
management, having the right specialty resources on the team systems, requiring more advanced and interconnected planning
to complete the design and construction, having the right and design across the system as a whole.
professionals available to support the project ensuring that
With more than 50 years across all forms of traditional and
communication occurs across all team members allowing for
renewable generation and transmission in Asia, Black & Veatch
prompt resolution of challenges.
is ready to deliver the solutions which stakeholders will rely
It is also important to formulate comprehensive plans to test the upon. We look forward to working with the industry to support a
integration of the renewable plant with the transmission system deeper appreciation of the benefits of our approach to planning,
to ensure grid code compliance. It is not uncommon for projects execution and solution delivery.
to meet energization and generation targets well in advance of
achieving commercial operation due to inadequate plans with
respect to grid code compliance.