Professional Documents
Culture Documents
First and foremost I want to thank almighty God for helping me in this internship program and in
general for his munificent to keep my life. Special thanks deserve to Addis Ababa Science and
Technology University, University Industry Linkage Office, Civil Engineering Department and
my supervisor Mr. Yohannes and Instructor Ayenew ( my mentor). It is also my honor and pleas-
ure to thank YOTEK CONSTRUCTION P.L.C, for their willingness to accept my request to prac-
tice in their company.
This is final report paper covers all the activities on the project from March up to June during my
internship program in YOTEK CNSTRUCTION P.L.C.
The project named as Addis Ababa Science and Technology University Research and Technology
Center, which covers around 1.81 hectare and have three blocks (block A, D &E) each with 0.582,
0.612 & 0.612 hectares respectively. The purpose of buildings are block A for common facility,
block D for Nano technology and bio processing and block E for construction quality and technol-
ogy and also mineral exploration and processing.
The day to day activities I observed in the site and office are included in this document such as
earth work,masonary work,concrete work and bill of quantity preparation . Generally it includes
sub structure work ,super structure work and office work.
The content of the report divided in to five chapters and the topics covers including the company
back ground, construction activities, overall internship experience, and the benefits we gained from
the program, our conclusions and recommendations for the company.
List of Table
Table 1 : Man Power in the Project ...................................................................................................... 6
Table 2 Equipment List ......................................................................................................................... 7
Table 3: Concrete Grade ..................................................................................................................... 16
Table 4 : Takeoff Sheet ....................................................................................................................... 26
Table 5 : Bar Schedule ........................................................................................................................... 27
Table 6 : Bill of Quantity ...................................................................................................................... 28
ACKNOWLEDGEMENT .......................................................................................................... II
List of Table............................................................................................................................. IV
Introduction ................................................................................................................................ 1
5.1 Conclusion....................................................................................................................... 35
5.2 Recommendation ............................................................................................................. 36
REFERENCE ........................................................................................................................... 37
Introduction
1.1 Company Profile
YOTEK CONSTRUCTION P.L.C was established in 1991E.C. The owner of the company is Yo-
hanis Teklay and its name is derived from the first two letters of the owner name ‘Yo’ from Yo-
hanis and taking three letters ‘Tek’ from his father’s name Teklay and the combination gives
YOTEK. Before 1991, Yohannis Teklay was a project manager of sitcom P.L.C but later he was
assisted by his brothers to establish his own company.
YOTEK has undertaken various projects in different parts of Ethiopia. It started with rural schools
in Tigray regional state, particularity at Mekelle and Adwa ,and health center in Afar regional
state. From 1993-1995, the company had constructed Mekele university buildings. In addition to
buildings, the company is now constructing bridge structures and asphalt road. YOTEK P.L.C is
currently a general class I contractor. The company has involved in a wide range of civil engineer-
ing construction such as high rise buildings, complex educational establishment ,inter urban as-
phalt roads ,machine foundation for factories and many other engineering construction. The com-
pany have experienced engineers, skilled laborers and different equipments .The company strives
continuously to implement a systematic organizational development.
In Amhara regional state: Bahirdar law and land administration faculty buildings.
In Oromia regional state: Jimma university Kittofurdissa campus dormitory, Ambo univesity
college phase 2 project, Ambo town road project.
In South nation nationality and people’s regional state (SNNP): Yirgalem police college,
Mizantepi school,Welkite industrial engineering college and Mizanteferi TVET phase II pro-
jects.
In Afar regional state: health center and school.
Jimma university conference Hall building in Jimma town
Bahir Dar University law and land administration facility building phase 2 projects
Mekelle city administration city building
Arbaminch university business and economics faculity
Ambo university college cafeteria and sport field
Bahirdar university president office building
Arteriel asphalt road project in Dilla town
Bahir Dar university phase III building project
Jimma university library project
Transport Network service building in Addis Ababa
stadium in Ambo
Welisso university Cafeteria and Dormitory
Currently, the company undertaking different kind of construction projects throughout the coun-
try. Some of them are Meles leadership institute, Addis Ababa University students dormitory,real
state in jemo and Addis Ababa Science and Technology University Research and Technology
Center.
1. Engineering department
2. Finance department
4. Procurement department
In each department, there are also organizational sub divisions having their own responsibili-
ties. The overall organization set is shown below.
As presented from the figure engineering department is grouped in to office and site. It is better to
discuss the work flow separately.
Project manager
He control the overall activities being undertaken in the site. He organizes different components
of the site and assign professionals such as Engineer’s, Forman’s and others to the components.
Project manager control and allocate resources to various section of the site among those deciding
on how much workers should be included under each Engineer or Forman, on monthly budget and
its distribution, on distribution of construction materials through different components. He organ-
ize and prepare meetings with different stake holders in the site.
1. Laborers 216
2. Office engineers 11
3. Junior surveyor 1
4. Site engineer 7
6. Gung chief 8
7. Carpenter leader 4
8. Carpenter 94
9. Assistant Carpenter 16
10. Mason leader 1
11. Mason 18
12. Assistant mason 7
13. Time keeper 5
14. Quantity surveyor 7
15. Electrician 1
16. Staff man 2
17 Deflector man 1
18 Guards 19
Construction Activities
2.1 Construction Equipment’s
Tower Crane: - is a lifting device either it is fixed or mobile. In our site fixed crane has been used.
Its function are;
To transport concrete for high rise building construction.
To transport rebar’s for higher rise buildings as in the above and from place to place.
To transport water for different purpose including curing of concrete.
Hand compactor:-is used to;
Compact the soil near to the structure.
Compact the back fill of structure.
Dump truck: - used to;
Transport selected materials for the site such as soil, stone, aggregate.
Loader:-is used to;
To load different material on dump truck from the target site.
To transport construction materials.
To fill concrete when the site entrance is difficult for truck mixer.
Jack Hammer :- used to fracture a rock which is difficult for man power.
Vibrator:-is used to;
Eliminate entreated air and forcing the particles in to a closer configuration
Mixer: - is used to;
Mix the concrete at the construction site
Mobile Mixer :- A car mixer that mix concrete on site .
Truck Mixer :- A truck used to mix concrete on site even also outside . For instance, in our site
the truck mixer mixing concrte from Goro site up to this project.
Concrete Pumper :- used to pour concrete in to different structure by using a pipe .
Bar Bender : used to bend reinforcement bars for different purpose .
The carpenter calls The straight portion is ‘hodu’ and the bent portion is ‘ganchu’. Making bar
schedules for the bar benders requires a careful study of detail drawings.
Concrete is made by mixing: Cement, water, course and fine aggregates and admixtures (if re-
quired).
The aim is to mix these materials in measured amounts to make the concrete easy to:
Transport, place, compact, finish and harden, to give a strong and durable product.
The three ingredients of concrete such as aggregate, cement and water are combined to give a
hard and monolithic solid that would take the form of the formwork.
For the concrete to meet its intended purposes its ingredients have to be of good quality and the
batching and mixing of the ingredients/constituents should be handled in a concrete friendly
environment.
Concrete grades of kinds of members used in our site is in the table below.
Table 3: Concrete Grade
A. Batching plant
Batching plant is a place where ingredients of a concrete are mixed with in a right proportion. For
good mixing of ingredients it is essential to measure the materials accurately. The concrete may
be batched either by weight or by volume.
BetonWin software is used for ordering and controlling of concrete mixing .
This is a method where a beam balance or scale balance is used to measure and adjust the right
quantity (in grams, kilograms…) of sand and aggregate. For instance: for a mix ratio by volume
of 1:2:3 (1 cement, 2 sand & 3 aggregate) the ratio could be converted in to weight as follows.
1 bag/sack of cement weighs 50Kg
Therefore the sand should weigh 2*50Kg = 100Kg and
The aggregate should weigh 3*50Kg = 150Kg.
This method of measuring is time taking and not applicable in smaller constructions, but our pro-
ject is huge so they have been using this method.
Truck mixer comprises around 10 m3 ingredient of concrete used are
Course aggregate = 798 kg
Fine aggregate = 328 kg
Sand = 765 kg
Cement = 430 kg
Water = 160 kg
Admixture = 6 kg
Measure by Volume
This method is highly practiced on site and widely spread on the project sites. In applying this
method it is usual to see people in the construction world use boxes made either from wood or
metal of various sizes and volumes.
B. Mixing of concrete
In the site concrete was mixed using an efficient automatic mechanical mixer, mobile mixer
and truck mixer, with 350 ,750 and 10000 lit capacities respectively. We used the following
procedures to mix concrete;
Water is poured to the mix drum to wash away all unnecessary materials in it.
Cement, fine aggregate and coarse aggregate added according to specific grade of con-
crete.
Sufficient water added that will result a workable mix, to pour efficiently in the posi-
tion around reinforcement and will produce a dense concrete of specific strength.
I did not see the major site clearance work but I saw site clearing work at the edge 2 meter away
from the building in all direction for the purpose of sewerage line. The surveyor take an elevation
using leveling and coordinating with design level, the depth which needs cut or fill is determined
easily. By adding bench mark level and back side reading we got instrument level then by sub-
tracting design level staff reading determined. Using leveling read the staff level and subtract the
previous value. If negative value got fill otherwise cut.
B. Setting out
The first task before the erection of any building is proper setting out. Setting out, which is a task
of field surveyors, is a process of putting the exact/actual form of the building from a plan or map
provided to the ground. Given the site plan, the surveyors will indicate the exterior column edges
of the buildings corners using pegs.
Steps of Setting out:-
First site engineer and supervisor locate the corners of the building by a surveyor and his
surveying instrument (total station and leveling). The surveyor refers the corners of the
building layouts in the drawing.
Different wood structure are provided to hold or keep the position of the formwork. Its site name
and definition written below
After finishing the standing of formwork, the column alignment checked with horizontally using
rope and vertically using Tumby (a rope contain conical shape iron at the end point). Spacer
is placed between the formwork and the reinforcement to keep concrete clear cover.
The concrete is compacted immediately as it poured. The fresh concrete would gain the strength
within 24 hours and also gain its maximum strength by curing of water after the formwork is
demolished.
2.4 Office Works
General information of the project
Client: Addis Ababa Science and Technology university
Contractor: Yotek construction p.l.c (work implementation and execution)
Consultant: Yohannes Abbay consulting architects and engineers (design and supervision works)
Number of building is 3
Purpose of buildings:
nano technology and bio processing
construction quality and technology and mineral technology and exploration.
common facility
Total budget of the project are 2.4 billion birr.
Description: - under this the type of which its rebar’s is being quantified and the specific position
of the bars are listed.
Bar shape: - it describes the shape of the bars being quantified.
No of bars: - under this the quantity of bars notified at a specific position are listed.
No of members: - under this the no that this type of bars repeats itself is described.
Total length: - total number of bars multiplied by the unit bar length.
Preparing bill of quantity
Bill of quantity- is a sheet holds more general description, measurements, unit prices and total
prices of the project. It has the following format.
After the takeoff sheets have been completed and checked, the final bill of quantity is written. The
description of each item in the final BOQ should be short, precise and descriptive as per the spec-
ification.
At the project level, after the contracts are transferred from the head office to the contractors and
sub-contractors, as the head office is the one who is responsible to give the project budget and
regulate it. Sometimes complains arise from the workers of the project when wage not paid on
time as I saw in our project in June 12 / 2019.
It was very difficult to adapt the hot scorching sun light for two weeks. since they had not enough
helmet in the site I started to wore topper.
Site words were new for me but after a time I became able to communicate with them. For exam-
ple: Tumby for plumb bob, Modini for profile ,Staffa for stirrup, kerabat for the strut on column
.Hence, step by step I improved my knowledge on technical (site) terms by giving attention when
the Forman, carpenter and daily laborers communicate with each other and when I am confused, I
asked them for better description.
Site ground is difficult to easily circulate because it is very sloppy and having complex formwork
supporters. I saw also some daily laborers injured because of site condition. Hence, I was very
careful to move in the sie.
Punctuality:-means keeping the companies work beginning and ending time and to com-
plete a given task with in the given period.
Office disciplines:-It is forbidden to disturb the working atmosphere. For example, abstain
from making loud voice, music,songs and things which disturb other workers mood.
Reliability:-the worker should be qualified for the part he is supposed to perform and must
have appropriate skill and knowledge for the task assigned.
Honesty:-regarding this value each worker regardless of its status should abstain from bad
behaviors such as cheating, bias, corruption etc.
Cooperation:-All workers should interact and cooperate with each other while working.
Self-confident multi-skilled: The person who can make the product, market and count
money, but above all they have the confidence that lets them move comfortably through
unchartered waters. It creates Confident in the face of difficulties and discouraging cir-
cumstances.
Innovative skills: Not an 'inventor' in the traditional sense but one who is able to carve out
a new niche in the market place, often invisible to others.
Result orientated: Successfulness requires the drive that only comes from setting goals and
targets and getting pleasure from achieving them.
The project AASTU Research and Technology Center is very huge in area and with unsuitable site
condition. Hence, many Engineers and professionals participated in it. Different measurements
had been taken to solve problems for example seepage water, expansive soil , very sloppy nature
of the site .
It is helpful for the students to know what the outside environment look like
It helps the students to get a practical knowledge.
It helps the students to improve or enhance their social interaction skill by communicating
with people who have different behaviors, knowledge and cultures.
It is necessary for the student to make a bridge between theoretical concept and real world
problems.
To improve self-confidences and to make full understanding about the outside environment
( construction site)
In general, these four consecutive months widened my practical skills and theoretical knowledge.
So that, in my opinion because of its paramount importance, the internship program should con-
tinue in a well-organized manner.
YOTEK constructions P.L.C executed the works according to the schedule, specifications and in-
terest of its clients. However, there were some wrong actions which, I suggest, it should be im-
proved.
The first is that, sometimes when the workers cast the beam, they cast the concrete discontinuously
which means when the work time is up the workers continues to pour the mixed concrete. It will
dry in the day after but uncasted portion of the beam will be left for the next day. When they came
the next day, they start from where they stopped. For better bondage and inter lock within the
concrete itself and with the reinforcement bar the concrete must be casted monolithically, if not
cracks may appear in short period of time.
The second problem which I tried to notice is installation work. As I understood the conduit which
carry electric wire did not placed inside the column but the drawing suggest that it should be in-
corporated inside the column. Therefore I recommend that for now by the agreements of consult-
ant, client and contractor they should be insert the conduit in to the column by drilling but for the
next step it is preferable to incorporate with in the slab and columns reinforcement.
The last problems are the effect of concrete pumper on daily workers. When the concrete was
pumped daily workers are carry the end part of the pipe to move in to the target place but the pipe
is heavy in weight and have a great power. Because of this it causes injuries in workers. Hence it
is necessary to make the end part is very flexible to move.
Finally, despite of the above problems which should be improved, I wants to admire YOTEK
Construction P.L.C for their greatest achievements and success. Especially I appreciate the com-
panies endeavor to make its clients happy
[3] Internet.13/6/2019