Professional Documents
Culture Documents
CONSTRUCTION I
1.1 STAKING-OUT THE BUILDING
STAKING-OUT - the process of relocating the
point of boundaries and property line of the
site where the building is to be constructed.
1. Measure the required setback from the 1.2 LAYING THE BATTERBOARDS
front corner monuments. Drive two stakes
and stretch a string between them to BATTER BOARDS
represent the front building line. • horizontal boards
2. Measure the required side setback from • establishes height of the footing trenches
one of the side lot lines along the front
building line. Drive stake A which will and foundations
represent the first corner of the building. • establishes height of finish floor levels
From Stake A, measure the width of the
building and mark with stake B to obtain the LEVELING
other front corner.
• done with a line level or carpenter’s level,
3. Estimate right angles from stakes A and B
or with a transit
and measure the length of the building. In
those two points, drive two temporary • height of the batter boards may be level
stakes C and D which will mark the rear
with or a little higher that the top of the
corners of the building. C-D should be equal
finished foundation.
to A-B.
BATTER BOARDS – wood sticks or boards
4. Draw lines along the diagonals A-D and B-
nailed horizontally at the stake which serve
C and ensure that these are equal.
as the horizontal plane where the reference
5. Transfer the building lines to batter point of the building measurements are
boards. established.
PLYWOOD FORMS WS
FORM TIES
SNAP TIES - have notches or crimps that
allow their ends to be snapped off below
the concrete surface after stripping off the
forms.
-small, truncated cones of wood, steel or
plastic attached to form ties to space and
spread wall forms, leave a neatly finished
COLUMN FORMS depression in the concrete surface to be
WOOD FORMWORKS - Reusable forms may filled or left exposed
have a square or rectangular cross section SHE BOLTS - consist of waler rods that are
YOKES - are clamping devices for keeping inserted through the form and threaded
column forms and tops of wall forms from onto the ends of an inner rod. After striping,
spreading under the fluid pressure of newly the waler rods are removed for reuse while
placed concrete the inner rod remains in the concrete
SB
v. of
wedges
3. Basement – the lower story of a building, Footing courses - lower portions of walls,
either partly or entirely below grade. piers, or columns which are spread to
provide a safe base.
CONCRETE
FOUNDATION WALLS
SUPERSTRUCTURE BASEMENT
CRAWL
SPACE
SLAB
ON FILL CONCRETE MASONRY
STRUCTURE FOUNDATION WALLS
FOUNDATION
FOOTING
FOUNDATION WALL
1.6.1 TYPES OF FOUNDATION BEDS 8. Hard-pan. Any strong coherent mixture of
clay or other cementing material with sand,
Foundation beds may be classified as
follows: gravel and boulders.
1. Rock (solid rock, bedrock or ledge). 9. Silt. A finely divided earthy material
Undisturbed rock masses forming an deposited from running water.
undisturbed part of the original rock-
10. Mud. Finely divided earthy material
formation. Some examples of harder rocks
generally containing vegetable matter and
are granite, slate, sandstone, and limestone
deposited from still or slowly moving water.
which are all capable of carrying the load of
any ordinary structure. Examples of softer 11. Mould. Earthy material containing a
rocks are shale, shaley slates and certain large proportion of humus or vegetable
marley limestone and clay stones. matter.
2. Decayed rock (rotten rock). Sand, clays 12. Loam. Earthy material containing a
and other materials resulting from the proportion of vegetable matter.
disintegration of rock masses, lacking the
13. Peat. Compressed and partially
coherent qualities but occupying the space
carbonized vegetable matter.
formerly occupied by the original rock.
14. Filled Ground. All artificial fills and some
3. Loose rock. Rock masses detached from
natural fills are liable to a more or less
the ledge of which they originally formed a
uniform but continuous settlement or
part.
shrinkage due to the gradual consolidation
4. Gravel. Detached rock particles are of the material of which the fill is composed
generally water-worn, rounded, and
intermediate in size between sand particles
and boulders. 1.6.2 ALLOWABLE LOADS ON FOUNDATION
BEDS
5. Boulders. Detached rock masses larger
than gravel, generally rounded and worn as Thorough investigation is required before
a result of having been transported by water one can determine the allowable unit load
a considerable distance from the ledges of on the foundation bed. When material and
which they originally formed a part. conditions are uniform over the entire site of
the building, a uniform unit load may be
6. Sand. Non-coherent rock particles smaller
used. In cases when entirely different
than 1⁄4” in maximum dimension.
conditions exist under different portions of
7. Clay. A plastic material resulting from the the same building, the unit load on the
decomposition and hydration of feldspathic foundation bed must be reduced as much as
rocks, being hydrated silicate of alumina, possible so as to reduce the differences in
generally mixed with powdered feldspar, settlements between the two sections of the
quartz and other materials. building to a minimum.
1.7 SITE INVESTIGATION A. Course-grained soil – consist of relatively
large particles, visible to the naked eyes.
Before any design is made, the architect is
required to get as much valuable data about B. Fine-grained soil – consist of much
site excavation and building erection at the smaller particles, such as silt and clay.
project site in order to determine the
character of the materials which will be
encountered at the level of a foundation
bed.
- Dry density is the density of soil, or the like, b) wales or continuous horizontal beams
after it has been heated at a temperature of which tie the sheet piles in place or
221 deg F (105 deg C) to a dry condition.
c) soldier piles, which are steel H-sections
C. Shearing Strength – measure of the ability driven vertically into the ground to support
to resist displacement when an external
d) lagging or heavy timber planks joined
force is applied, due largely to the combined
together horizontally to retain the face of an
effects of cohesion and internal friction.
excavation.
D. Water Table – level beneath which the
e) crossbracing or rakers are diagonals
soil is saturated with groundwater.
which support the wales and soldier piles
1.9 EXCAVATION AND EARTHWORKING bearing on heel blocks or footings.
These processes entail the following: f) tiebacks secured to rock or soil anchors
are resorted to when crossbracing or rakers
1. Excavating is the process of digging the
would interfere with the excavation
earth to provide a place for the foundation
procedure.
of the building.
SHEET PILING
2. Leveling and Grading are processes that
change land elevation and slope by filling in
SOLDIER PILES/BEAMS
low spots and shaving off high spots. (STEEL H-SECTIONS)
PRECAST
4. The protection of adjoining structure is a
law that provides that any person making an
excavation is responsible for resulting
damage to adjoining property.
6. Needling and underpinning is a process 7. Dewatering refers to the process of
where needles or girders are used in cases lowering a water table or preventing an
where part or all of the weight of the wall has excavation from filling with groundwater. It
to be carried, as when the old footing is is accomplished by driving perforated tubes
removed and the wall underpinned or called wellpoints into the ground to collect
carried down to a new footing at a greater water from the surrounding area so it can be
depth. pumped away.
NEEDLE; a short beam passed through a wall Water, near the surface of the ground, which
as a temporary support while the foundation passes through the subsoil.
or the part beneath is repaired, altered or
strengthened
BASIC TYPES OF SITE DRAINAGE
A. SUB-SURFACE DRAINAGE –
DEAD SHORE; an upright timber for
consists of an underground network of
supporting a dead load during the structural
piping for conveying groundwater to a point
alteration of a building, esp. one of two
supports for a needle of disposal, as a storm sewer system or a
natural outfall at a lower elevation on the
site. Excess groundwater can reduce the Components of the surface drainage system
load-carrying capacity of a foundation soil are:
and increase the hydrostatic pressure on a
SWALES
building foundation. Waterproofing is
shallow depressions formed by the
required for basement structures situated
intersection of two ground slopes, designed
close to or below the water table of a site.
to direct or divert the runoff of surface
Components of the sub-surface drainage water. Grass swales slope 1.5% to 2%; while
system are: paved swales, 4% to 6%.
CATCH BASINS AREA DRAIN
receptacles for the runoff of surface water. receptacle designed to collect surface water
They have a basin or sump that retains heavy or rainwater from an open area.
sediment before it can pass into an
DRY WELLS
underground drainpipe.
are drainage pits lined with gravel or rubble
CULVERTS to receive surface water and allow it to
are drains or channels passing under a road percolate away to absorbent earth
or walkway. underground. Also called an absorbing well.
FOUNDATION DRAINAGE TILE OR PIPE ABSORPTION FIELD OR DISPOSAL FIELD
Tile or piping for the collection of sub- a system of trenches containing coarse
surface water, dispersion of septic tank aggregate and distribution pipes through
effluent, and the like. which septic-tank effluent may seep into the
surrounding soil.
DRAINAGE TILE
is a hollow tile, usually laid end to end as ABSORPTION TRENCH
piping (with open joints) in soil in order to a trench containing coarse aggregate and a
drain water saturated soil, or used to permit distribution tile pipe through which septic-
fluid in the hollow-tile pipe to disperse into tank effluent may flow, covered with earth.
the ground (as in an absorption field).
PONDS AND MARSHES
B.SURFACE DRAINAGE designed catchments areas for surface
refers to the grading and surfacing of a site water.
in order to divert rain and other surface
1.11 SLOPE PROTECTION AND RETAINING
water into natural drainage patterns or a
STRUCTURES
municipal storm sewer system. Grass and
lawn areas are sloped 1.5% to 10%; while
paved parking areas, 2% to 3%. A holding
1. The need for stabilizing a sloping ground
pond may be necessary when the amount of
can be reduced by diverting the runoff at the
surface runoff exceeds the capacity of the
top of the slope or by creating a series of
storm sewer system.
terraces to reduce the velocity of the runoff.
4. Cribbing is a cellular framework of
squared steel, concrete, or timber
members, assembled in layers at right
angles, and filled with earth or stones.
5. A Bin Wall is a type of gravity retaining
wall formed by stacking modular,
interlocking pre-cast concrete units and
2. Natural means of stabilization include soil filling the voids with crushed stone or gravel.
binders --- plant materials that inhibit or
prevent erosion by providing a ground cover
and forming a dense network of roots that
bind the soil.
1.4
2” (51) min
3” (75) min 1.2
1.5
b) T-type Cantilevered Retaining Wall –
limited to a height of 20’ (6 M); beyond this c) Counterfort Retaining Wall – utilizes
height, a counterfort wall is employed. triangular-shaped cross walls to stiffen the
vertical slab and add weight to the base. The
8” (205)
counterforts are spaced at equal intervals
equal to one-half the wall height.
1.0
0.6H
(0.9H w/ surcharge)
d) L-type Cantilevered Retaining Wall –
used when the wall abuts a property line or
other
1.0.) Batter refers to backward sloping face
of a wall as it rises to offset illusion of face
leaning forward.
1.1.) Temperature steel for walls more than
10” (255) thick
0.7H
1.2.) Structural Steel reinforcement (1.25 w/ surcharge)