You are on page 1of 14

Doc No:

1814AB-F17C1-RVQ-
Method of Statement for I&A-MST-0001 (R1)
Installation of Cable Tray /
Trunking

Method of Statement
Installation of Cable Tray / Trunking at
Solvent Recovery Plant Area(Pipe Racking)

Ref: 1814AB-F17C1-RVQ-I&A-MST-0001
Rev: 01

Prepared by: Reviewed by: Reviewed by: Approved by:


RVQ Automation Sdn VENDOR HSE VENDOR WKL Design S/B
Bhd.
Name: Ashafik MS Name: Name: Name:
Designation: Designation: Designation: Designation:
Project Manager
Date: 15/11/2023 Date: Date: Date:

Page 1 of 10
Doc No:
1814AB-F17C1-RVQ-
Method of Statement for I&A-MST-0001 (R1)
Installation of Cable Tray /
Trunking

TABLE OF CONTENTS

Item DESCRIPTION Page

WORK METHOD STATEMENT AMENDMENT RECORD 3

1.0 OBJECTIVES 4

2.0 SCOPE OF WORK 4

3.0 RESOURCES PLANNING 4-5

3.1 Material

3.2 Equipment and Tools

3.3 Manpower

3.4 Personal Protective Equipment (PPE)

4.0 HANDLING AND STORAGE 5-6

5.0 WORK METHODOLOGY 6

5.1 Trunking

6.0 INSPECTION AND TESTING 7

6.1 General

6.2 Receiving Inspection And Testing

6.3 In-Process And Final Inspection And Testing

7.0 HEALTH, SAFETY, SECURITY & ENVIRONMENT 7

8.0 LIST OF APPENDICES 8 - 10

METHOD STATEMENT AMENDMENT RECORD

Page 2 of 10
Doc No:
1814AB-F17C1-RVQ-
Method of Statement for I&A-MST-0001 (R1)
Installation of Cable Tray /
Trunking

Pages Revision Revision Details Revision Date

All 0 First Issue 06/11/2023

All 1 Additional Information 15/11/2023

Page 3 of 10
Doc No:
1814AB-F17C1-RVQ-
Method of Statement for I&A-MST-0001 (R1)
Installation of Cable Tray /
Trunking

1.0 OBJECTIVES

To outline the work method for Installation of cable trays / trunking or conduit works at user area for Field
Instrumentation – Distillation Column and tanks - Package No. F17C Project Code P1814 Infra.

2.0 SCOPE OF WORKS

2.1 Supply, Installation of prefabricated perforated heavy duty Hot Dip cable trays with
cover including joining of cable trays with coupling plates, E bend & TEE Bend,
Expander, Reducer. Work shall be carried out as per drawing approved by owner
/consultant (support hanging arrangement provided at each 1.5 M interval).
2.2 Qty and Routing of cable trays as per the Plant layout and Piping layout will be
calculated by Instrument Vendor and submit the Cable tray layout to Jacobs for
review/Approval

3.0 RESOURCES PLANNING

3.1 Material

Item Description Size


a) 300 X50 X 1.5mm
Cable tray with Cover (Hot Dip GI) size bellow; b) 200 X50 X 1.5mm
3.1.1
c) 100 X50 X 1.5mm
d) 50 X25 X 1.5mm
Tray, Accessories and Fittings submission for
3.1.2 T.B.A
approval.

3.2 Equipment and Tools

Item Description Equipment


3.2.1 To hold, twist or cutting wires for conduit mounting to Combination Pliers
re-bars / walls /beams.

3.2.2 To make small ditch to accommodate conduit Grinder Machine,


Chisel, Hammer

3.2.4 Cut trunking / Unistrut, angle irons Ratchet Pipe


Cutter, Saw

3.2.6 Hole Drilling for Drop – in – Anchor installation Hammer Drill

3.2.7 Installation of L – Angle Bracket and Galvanized Fibre Cutter, Hand


Threaded Hanger rod for cable ladder, tray & drill, Spanner,
trunking

Page 4 of 10
Doc No:
1814AB-F17C1-RVQ-
Method of Statement for I&A-MST-0001 (R1)
Installation of Cable Tray /
Trunking

Screwdriver,
Hacksaw, Hammer

3.2.8 Trunking jointing, panel installations Screwdriver,


Spanner, Pliers

3.2.9 Trunking colour code identification Stick-on sticker

3.3 Manpower

Item Description No. of Personnel


3.3.1 Engineer 1

3.3.2 Skilled Workers 1 – 2 & above (as per site


condition required)

3.3.3 Safety Supervisor 1

3.3.4 General Workers 1 – 2 & above (as per site


condition required)

3.4 Personal Protective Equipment (P.P.E)

Item Description
3.4.1 Safety Shoes
3.4.2 Safety Helmet
3.4.3 Full Body Safety Harness

4.0 HANDLING AND STORAGE

a) All material will be submit a material receiving report (MRR) after arrive at site.
b) DO, MDS and report with picture with submit for acceptance.
c) Materials shall be new, unused and free of damage.
b) Make sure materials are secured and stable during storage or handling.
c) Suitable lifting equipment for heavy lifts shall be used. Manual handling/lifting of smaller
bundles of material shall be undertaken at a minimum of two points by experienced personnel.
d) To prevent damage to material, never drag during loading / unloading.
e) Material shall be stored in a clean, dry and secured location. Especially avoiding
places where water might accumulate or where significant dust or dirt is present. If such a

Page 5 of 10
Doc No:
1814AB-F17C1-RVQ-
Method of Statement for I&A-MST-0001 (R1)
Installation of Cable Tray /
Trunking

location is not available; materials shall be stored on pallets or other appropriate means to
rise above the floor to avoid possible water levels, and wrapped in protective plastic sheeting
at both ends of the bundles.

5.0 WORKING METHODOLOGY

5.1 Trays / Trunking

a) Cable tray / trunking installation is either suspended across the hanging bracket from
soffit wall or direct mounted to wall/soffit when required. (e.g. connection to concealed
wiring point at electrical riser).

b) For direct mounted cable trunking, holes will be drilled to the base trunking and fasten
screw directly to the holes with plastic anchor which tightly inserted to the wall with 1200
mm (max.) spacing between the supporting screw. (Refer Appendix 4 Figure 4 & 5)

c) For suspended trunking system installation, the trunking will be laid horizontally on the
hanger system with minimum of 150 mm clearance from other mechanical and plumbing
services when in parallel running. In that case, holes will be drilled to the base of the
trunking in order to fasten screw to the angle iron and shall be provided with a minimum
clearance of 20mm in between side of trunking to threaded rod hanger for suspended
installation. (Refer Appendix 4 Figure 1,2,3)

d) Coupling sleeve shall be used to joint two lengths of trunking or connecting trunking to
their accessories i.e. elbow, tee etc. as according to manufacturer recommendation.
(Refer Appendix 3 Figure 1 for Trunking Coupling and accessories)

e) When a conduit or flexible conduit is required to joint with trunking, a standard hole (20
mm or 25mm dia.) will be bored at side of trunking and male bush with conduit socket or
lock nut with flexible adaptor to be used for the connection. (Refer to Appendix 3 Figure
2&3)

Page 6 of 10
Doc No:
1814AB-F17C1-RVQ-
Method of Statement for I&A-MST-0001 (R1)
Installation of Cable Tray /
Trunking

6.0 INSPECTION AND TESTING

6.1 General

All inspection and testing shall be carried out to satisfy the criteria that shall be
evidence in the relevant inspection documents as detailed in the inspection and test
plan.

6.2 Material Receiving Inspection and Testing (MRR)

The receiving inspection is carried out to ensure that incoming materials will not be
used until it has been inspected and verified for conformance to specification.
Inspection and verification shall be done on the material’s Delivery Order (D.O) with
Request for Material Inspection Check List. This inspection shall be performed in
conjunction with Sub-Contractor’s Supervisor, MAIN CONTRACTOR Site Supervisor
and Clerk of Work. Rejection or acceptance of material delivered shall be by the
discretion of the Sub-Contractor’s Supervisor with verification by his immediate
superior, the Engineer.

6.3 In-process and Final Inspection and Testing

The in-process and final inspection shall be carried out to ensure conformance of the
installation works carried out on site to the method stated above. Prior to the inspection, a
copy of “Request for Inspection” form will be submitted to MAIN CONTRACTOR to request
for the inspection on the work done on site. The inspection result shall meet the
requirement as stated in the earlier methodology.

7.0 HEALTH, SAFETY, SECURITY AND ENVIRONMENT

Item Product General Safety and Health Measure


Description

1 Panels, trays, -No health hazard At storage area:


trunkings, G.I
conduit fittings -Non-Flammable
& To be kept indoor, in a clean, dry and well
Accessories,
ventilated.
Trunking

Page 7 of 10
Doc No:
1814AB-F17C1-RVQ-
Method of Statement for I&A-MST-0001 (R1)
Installation of Cable Tray /
Trunking

fittings &
accessories.

Working Area:

- Folding or ‘A’ ladder for height up to 3


meters
- Portable scaffolding for height more
than 3 meters
(Removable or movable with wheels)

- Wear Safety Harness with height more


than 2 meters.
- Barricading unsafe area during the
installation of heavy equipment.
- Safety helmet at any working
environment.
- Safety Glasses for any drilling.

8.0 LIST OF APPENDICES

Appendix Description Remarks

1 Installation of Trunking Accessories (Sketch) NIL

2 Cable Trunking Installation (Sketch) NIL

3 Anchor Pull Test Method Sample

Page 8 of 10
Doc No:
1814AB-F17C1-RVQ-
Method of Statement for I&A-MST-0001 (R1)
Installation of Cable Tray /
Trunking

APPENDIX 1

Page 9 of 10
Doc No:
1814AB-F17C1-RVQ-
Method of Statement for I&A-MST-0001 (R1)
Installation of Cable Tray /
Trunking

APPENDIX 2

Note :

1) To cover last edge of cable tray by paper box or soft material for temporary before
installation next to ensure no damage to prevent any damage off cable sleeve

Page 10 of 10
PULL OUT TEST METHOD STATEMENT FOR
HYDRAJAW PULL – OUT TESTER

1.0 OBJECTIVE

 The objective of this pull-out test is to determine the adequacy of the existing or new

anchors to support the required tensile pull out resistance by using Hydrajaw Pull -

Out Tester

 The Hydrajaw Pull – Out Tester able to test anchor from M5 – M20 and the maximum
capacity of the Hydrajaw are 2.5 tones / 25kN only.

HYDRAJAW PULL OUT TESTER


2.0 DIAGRAM OF TEST EQUIPMENT SETUP

Turning Knob

Load gauge

Handle

Load Spreading Bridge

Hexagon Head Bolt Grad 8.8 Adjustable Legs

Drop – In Anchor
Reinforced Concrete

3.0 SAMPLE OF FIXING HEXAGON HEAD BOLT TO PULL OUT TESTER

1. 2. 3.
4.0 TESTING PROCEDURES

The general guideline of operating Hydrajaw Pull-Out Tester may differ depending on site
condition & type of anchor to be tested.

1. The client or consultant may randomly choose the test points on site.

2. The surface of the surrounding of anchor to be tested should be even and clear of
obstructions to allow fixing of load spreading bridge.

3. Once the anchor has been set as per manufacturer’s instructions, the threaded-adaptor can
be fit. The minimum thread length of the anchor shall be at least equal to the diameter of the
anchor to ensure secure engagement into the threaded adaptor.

4. Remove the nut of the anchor if the minimum thread length of the anchor is insufficient to
ensure in secure engagement with threaded-adaptor. When the threaded-adaptor is securely
fitted to the anchor thread position, place the Hydrajaw pull-out tester over the threaded-
adaptor by slotting in through the hole in the load spreading bridge and make sure it is well
engaged in the pulling jaw of the pull-out tester.

5. Level the load spreading bridge with the adjustable legs before commencing the application
of the load.

6. Before the test, adjust the red pointer on the load gauge meter reading to zero.

7. Apply the tensile load by manually turning the knob handle screw clockwise gradually until
the required test load is obtained. Hold this load and observe any falling back of the gauge
pointer which would indicate movement and possible failure of the anchor.

8. Maintain the applied load for one (1) minute for observations and increase load if necessary,
for further observations.

9. Release the load on the anchor by turning the knob handle screw anti-clockwise and allowing
the jaw to return to the original position.

10. Test results are recorded in the field test report.

Remark: At high test load, the tested anchor will undergo ‘stress relaxation which causes a minor
decrease in load value (1- 2kN depending on the size of an anchor) and eventually stabilized within
2-5 minutes, this is normal and does not consider as a failure of an anchor. If this happens, simply re-
tighten the loading screw to the desire test load.
FIELD TEST REPORT
Ref. No. : Date :
Customer Name :
Address :

Tel No. : ( ) Fax No. : ( )


Contact Person : Position : P.Manager
Test Location :
Job Scope : □ Install& Test □ Test Only □ Third PartyTest
Type of Test : □Pull Out Test □ ShearTest
Product Tested : STATHEROS DI DROP-IN ANCHOR M10
Product Part No: DIM10
Product Used For: Wire Trucking

Type of Substrate : □Reinforced Concrete □Concrete Block □Brick Wall □Lightweight Block □Others: _____
Substrate Strength : □25MPa□30MPa □35MPa □40MPa □45MPa□50MPa□55MPa □60MPa □Others:__

SA
Field Test Results
Required Test Load
No . Embedment Depth (mm) Observations

M
Load (kN) (kN)
1.

RE PL
M10 x 50mm 4.7 5.0 No Visible Failure

2. M10 x 50mm

PO E 4.7 2.5 No Visible Failure

RT
5.0 No Visible Failure

Equipment Used for Testing : □ Enerpac RCH –202 /RCH -603 □Hydrajaw 2000 / 2000/c □ Others :
Pressure/ForceGaugeModel: AD21-8494
Remark: ____________________________________________________________________________________________________________________________________________________________________

RFMCP Representative: (Signature) Client Representative: (Signature) Consultant Representative: (Signature)

You might also like