PR # 1300002093
SATORP completed it’s Home Ownership Project (HOP) Phase 1 with 105 Villas in Mutrafiah
District F2 with a 60,000 sqm Area.
HOP Phase 2 is located in Mutrafiah District F3 with an approx. 200,000 sqm area where
currently the Site Secondary Infrastructure is completed.
The overall site will accommodate within its boundaries the following structure:
HOPII Residential Family Villas (279)
Imam and Mo’athen Duplex Villa
Neighborhood Center Plaza and Daily Mosque (450 prayers)
BUILT-UP
VILLA NO. OF TOTAL BUILT-UP AREA
AREA
TYPE VILLAS (m²)
(m²)
B 520.00 47 24,440.00
C 551.00 45 24,795.00
VILLA TYPE
A
D 438.00 14 6,132.00
B
C
TOTAL 279 127,508.00 D
CLASSIC ZONE 91 27 19 7
MODERN ZONE 82 20 26 7
M TOTAL 173 47 45 14
Plan
COMPLETION DATE Q1 -2025 Milestone Description Plan Completion
Start
(PHASE 1 - CONSTRUCTION) PHASE 1 – NORTH (143 villas)
1. GENERAL REQUIREMENTS Q1 2023 Q1 2027
2. SITE/LOT DEVELOPMENT - FAMILY RESIDENTIAL VILLAS Q1 2023 Q1 2027
3. HOUSING UNITS TYPE – A (88 UNITS) Q1 2023 Q1 2025
4. HOUSING UNITS TYPE – B (31 UNITS) Q1 2023 Q1 2025
5. HOUSING UNITS TYPE – C (22 UNITS) Q1 2023 Q1 2025
6. HOUSING UNITS TYPE – E (2 UNITS) Q1 2023 Q1 2025
HOUSING UNIT "IMAM AND MO’ATHEN DUPLEX VILLAS TYPE - E" - TWO (2)
8. Q1 2023 Q1 2025
NOS.
9. SITE/LOT DEVELOPMENT - NEIGHBORHOOD CENTER Q1 2023 Q1 2025
10. NEIGHBORHOOD CENTER DAILY MOSQUE (450) Q1 2023 Q1 2025
16 Complete One (1) TYPE A Villa Mock-up (Lot B1-3) Q1 2023 End of Q3-2023
17 Complete One (1) TYPE B Villa Mock-up (Lot B1-8) Q1 2023 End of Q3-2023
18 Complete One (1) TYPE C Villa Mock-up (Lot B1-2) Q1 2023 End of Q3-2023
19 Complete One (1) TYPE D Villa Mock-up (Lot B2-6) Q1 2023 End of Q3-2023
RESPONSIBILITIES OF PMC:
PMC scope shall include but not limited in providing support to SATORP in managing &
supervising the project in reference to SATORP & RC Guidelines & procedure, IFC drawings,
approved Specification, approved Bills of Quantities, Saudi Building Code & standards,
International Standards & guidelines and other related documents to finish the project under the
approved schedule and budget:
1. Pre-Construction Phase
2. Construction Phase
3. Post-Construction Phase
4. QUALITY CONTROL
LOCATION OF WORK:
a. Work Location defined as onshore geographic area within One Hundred Fifty (150)
Kilometer radius from Al Khobar and Jubail in the Eastern Province.
SATORP OBLIGATIONS:
a. SATORP shall support PMC if there is any required supporting documentation required by
Royal Commission and Third parties.
b. SATORP shall provide onsite offices and office basic equipment (Office furniture, computers
and basic stationaries).
c. SATORP shall provide PMC access in the site.
d. SATORP shall issue an official request if any additional support discipline or replacement is
required.
e. SATORP shall evaluate all PMC candidate CVs and may request interview of the candidates
to verify the information in their CVs.
All Bidders are required to submit the following items to enable SATORP to
technically evaluate the proposal.
Proposal shall include all 9 items (detailed in next slide) to proceed to the
Technical Evaluation not fulfilling the above will result in disqualification.
6 Safety Procedure/Program for the project Bidder to exhibit Specific Safety Plan for the project.
Technical Proposal:
• Technical Proposal
• RFP Vendor Confidentiality Agreement
Commercial Proposal:
• Priced Quotation (Excluding VAT)
• Offer Validity 90 Days after Bid closing Date
Bidder to submit separate Technical & Commercial Proposals in SAP Ariba under the Sections:
4 Technical Proposal
4.1 Do you comply exactly with the provided specification?
4.2 Please provide your own technical specification document (attach a file)
5 Commercial Proposal
5.3.1 PMC - HOP-II Villa Construction Project (attach a file – SCHEDULE C)
Any non-compliance to the above points would disqualify bidder from this bidding.
PROPOSAL SUBMISSION
INSTRUCTIONS
24
SATORP-Company General Use
RFP REQUIREMENT
CONTRACT SCHEDULES
Any Questions?