Supervision Daily Record of Batang Toru HEPP

巴塘托鲁水电站监理日志
Recorder 1. Hersonedi G Date 2023.11 Weather Bright Temperature 25℃

2. Adhi H .23 ℃

Position Tunnel Employer North Sumatera Contractor Sinohydro


Engineer Hydro Energy
Construction Site
Waterway system

1. (1) Tunnel Adit 1


 Construction site Upstream – Intake Tunnel
 Construction content  Excavation, Supporting excavation, progress excavation is 2 m, rock class III
 Construction image  Rock Supporting Wiremesh installation on roof, initial shotcrete, Steel ribs

(2) Tunnel Adit 2


Downstream
 Excavation, Supporting excavation, progress excavation is 4 m, rock class III

Upstream
 Continued Concrete placing for Block 9 (12 M’)
 Continue Installation embedded part, rebar circle and horizontal, Spacer, Tie
Wire, Install rubber waterstop Block 10 (12 m’)
 Preparation to Moving Steel Form, Platform trolley
 Continue Survay stacking out Tunnel section bedding

(3) Tunnel Adit 3


Upstream
 Excavation, Supporting excavation, progress excavation is 2 m, rock class IV

Downstream
 Excavation, Supporting excavation, progress excavation is 4 m, rock class III

2. (1) Tunnel Adit 1 – Intake Tunnel


 Input of main personnel  There are 4 operator, 4 chines worker, 5 supporting worker, 3 management staff
 Input of construction
personnel (2) Tunnel Adit 2
 There are 4 operator drill, 13 helper, 29 supporting worker, 4 management staff

(3) Tunnel Adit 3


 There are 7 operator drill, 13 supporting worker, 3 management staff
3. (1) Tunnel Adit 1
 Construction equipment  Robotic shotcrete sprayer 1 unit, Truck mixer 2 unit, Welding tools 1 unit
and working condition
 Construction materials (2) Tunnel Adit 2
 1 unit Jumbo drill 3 arm, 2 unit loader, 1 unit excavator, 1 unit robotic
shotcrete, 4 unit dumptruck, 3 unit mixer truck, 2 Set Welding machine

(3) Tunnel Adit 3


 1 unit Jumbo drill 2 arm, 2 unit loader, 1 unit excavator, 1 unit robotic
shotcrete, 3 unit dumptruck, 2 unit mixer truck

Construction material :
1. Construction material such as ; Hbeam, steel bar, meets the construction
schedule.
2. Stock of Explosive material according to Construction schedule.

4.
 Construction quality  RFI No. BT-SH-C-05-QC-RFI-2622 Underground Excavation Adit 3 DS
inspection and testing (Top heading)
Sta 7+588.8

 RFI No. BT-SH-C-05-QC-RFI-2615 Underground Excavation Adit 3 US


(Top heading)
Sta 6+159.5-6+160.5

 RFI No. BT-SH-C-05-QC-RFI-2620 HRT Adit 2 US (Full Section) Rebar


Foundation
Sta 2+447.35-2+459.45

 RFI No. BT-SH-C-05-QC-RFI-2628 HRT Adit 2 US (Full Section)


Embedded Part, Formwork, Concrete
Sta 2+447.35-2+459.45

Question and Solution of Quality or Safety:

The Opinion of Contractor and the Disposal Opinion of Employer’s Engineer:


(1)
Others:

Attachments:
1. HRT Adit 1 Upstream – Intake Tunnel 2. HRT Adit 1 Upstream – Intake Tunnel
Scaling and mucking material Mucking Material

3. HRT Adit 2 Upstream 4. HRT Adit 2 Upstream


Preparation check before Pouring Concrete Continue for installation rebars

5. HRT Adit 2 Upstream 6. HRT Adit 2 Upstream


Pouring Concrete Lining Pouring Concrete Lining
7. HRT Adit 2 Downstream 8. HRT Adit 2 Downstream
Drilling Repair Electricity Transformer

9. HRT Adit 3 Downstream 10. HRT Adit 3 Upstream


Excavation, Drilling Supporting Preparation to Install Steel Rib Supporting