Recorder 1. Hersonedi G Date 2023.11 Weather Bright Temperature 25℃
2. Adhi H .23 ℃
Upstream
Continued Concrete placing for Block 9 (12 M’)
Continue Installation embedded part, rebar circle and horizontal, Spacer, Tie
Wire, Install rubber waterstop Block 10 (12 m’)
Preparation to Moving Steel Form, Platform trolley
Continue Survay stacking out Tunnel section bedding
Downstream
Excavation, Supporting excavation, progress excavation is 4 m, rock class III
Construction material :
1. Construction material such as ; Hbeam, steel bar, meets the construction
schedule.
2. Stock of Explosive material according to Construction schedule.
4.
Construction quality RFI No. BT-SH-C-05-QC-RFI-2622 Underground Excavation Adit 3 DS
inspection and testing (Top heading)
Sta 7+588.8
Attachments:
1. HRT Adit 1 Upstream – Intake Tunnel 2. HRT Adit 1 Upstream – Intake Tunnel
Scaling and mucking material Mucking Material