ACTIVITY SHE
A. SAFETY INDUCTION
DATE
No. NAME/COMPANY Remarks
2 3 4 5 6 7 8
1 PT LOW 0 0 0 0 0 0 0
2 CV Hasan Teknik 0 0 0 4 2 0 0 Some man power already
3 0 0 0 0 0 0 0 induction on March 17 & 18
Total of Safety Induction (Person) 0 0 0 4 2 0 0
- Duration time for safety induction: 1 hours - Training Hours:
- Materi: 6 man hours for safety induction
1. PPE
2. General Safety Rules - Inductor:
3. SOP work in IFC Project 1. Imam (HSE Kajima)
4. Emergency Procedure
5. 5R/5S Implementation
4/3/2021
(07.30 a.m) No Activities
4/4/2021
(07.30 a.m) No Activities
4/5/2021
(07.30 a.m) No Activities
4/6/2021 Gufron, Hilal, Hastek : 4 man power Manual handling, Risk of preparation
(07.30 a.m) Muji LOW : 2 man power warehouse area
4/7/2021 Gufron, Hilal, Hastek : 7 man power Completion PPE to worker, Provide hand
(07.30 a.m) Wawan, Muji LOW : 2 man power sanitizer and disinfectant, Hp register
Wira and procedures
4/8/2021 Gufron, Hilal, Hastek : 7 man power COVID 19 Protocol, Forklift Inspection
(07.30 a.m) Wawan, Muji LOW : 2 man power HP allowed to site
Wira
0 0 0 0 0 0 0 0
1 Rain Hours
SHE PERFORMANCE
D. MAN HOURS STATISTICS
DATE
No. ITEM 2 3 4 5 6 7 8 Remarks
I. Normal Time
1 Man Power (Personnal) 0 0 0 5 9 9 9
2 Man Hours (Hours) 0 0 0 40 72 72 72
II. Over Time
1 Man Power (Personnal) 0 0 0 0 0 0 0
2 Man Hours (Hours) 0 0 0 0 0 0 0
III. Total Man Hours per day 0 0 0 40 72 72 72
(Hours)
IV. Total Man Hours only This
256
Week (Hours)
V. Total Man Hours per end 0 0 0 40 112 184 256
date(Hours)
Note:
6 7
5
4
3 4
2
1 2 2 2
1
0
2 3 4 5 6 7 8
Date
E. ACCIDENT RECORD
DATE TOTAL
No. ITEM
2 3 4 5 6 7 8 THIS WEEK
1 Medical Treatment (Freq.) 0 0 0 0 0 0 0
2 Lost Time Injured (Freq.) 0 0 0 0 0 0 0
3 Fatality (Frequency/Person) 0 0 0 0 0 0 0
4 Zero Accident 0 0 0 40 112 184 256
CORRELATION MAN HOURS ≈ ZERO ACCIDENT ≈ MAN POWER
112 p
4 l
100 9
9 3 e
40 5 2
50
0 0 1
0
0 0
Page 2 of 31 2 3 4 5 6 7 8 SHE Report
Date
250 256 8
200 184 7
6
150 WEEKLY SAFETY REPORT 9 5
Hours
112
100 WASTE WATER TREATMENT PLANT PROJECT
9
4
9 LOCATION 3
REVISI : 00 40 5 : Gerem, Cilegon
2
50
NO. PROJECT : 2006-MFI02 0 AREA : WWTP Existing MFI
0 0 1
PERIODE 0 : 02-08 April 2021 REPORTED BY : Much. Gufron 0
2 3 4 5 6 7 8
Date
3 Fatality (Frequency/
Person)
2
1
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0
2 3 4 5 6 7 8
Date
Description:
1. Total Manhours a week : 256 hours during project: 256 hours (2-8 April 2021)
2. Total Zero Accident : 256 hours
3. Total Man Power : 9 mp
4. Total of Mandays : 4 days (2-8 April 2021)
5. Total training Hours : 12 hours (Since 17 March 2021)
6. Safety awareness : Zero accident
7. Safety activity : Safety talks & TBM, Safety monitoring, Safety Inspection, Safety meeting
7-Apr Premobilization Crane Inspection by MFI & TPI Inspector before come to site
002 Muchamad Gufron HSE Coordinator PT Lautan Organo Water 18 Maret 2021 √ √ On Site
003 Dadan Kadarsah Electrical Engineer PT Lautan Organo Water 17 Maret 2021 √ √ Off Site
004 Hoerudin Electrical Engineer PT Lautan Organo Water 18 Maret 2021 √ √ Off Site
005 Agus Salim Spv Subcon CV Hasan Teknik 18 Maret 2021 √ Off Site Tentative
006 Setiawan Utomo Leader Mechanical CV Hasan Teknik 18 Maret 2021 √ On Site
007 Muji Rahardjo Leader Electrical CV Hasan Teknik 5 Apr 2021 √ On Site
008 Putra Wira Pratama Safety Officer CV Hasan Teknik 5 Apr 2021 √ On Site
009 Sacse Enceng Hidayat Mechanical CV Hasan Teknik 5 Apr 2021 √ On Site
010 Muhamad Yahya Iswanto Helper CV Hasan Teknik 5 Apr 2021 √ On Site
ACTIVITY SHE
A. SAFETY INDUCTION
DATE
No. NAME/COMPANY Remarks
9 10 11 12 13 14 15
1 PT LOW 0 0 0 0 0 0 0
2 CV Hasan Teknik 4 0 0 3 2 1 0
3 0 0 0 0 0 0 0
Total of Safety Induction (Person) 4 0 0 3 2 1 0
- Duration time for safety induction: 1 hours - Training Hours:
- Materi: 10 man hours for safety induction
1. PPE
2. General Safety Rules - Inductor:
3. SOP work in IFC Project 1. Wahyu/ Bagus (Taisei)
4. Emergency Procedure
5. 5R/5S Implementation
0 0 0 0 0 0 0 0
1 Rain Hours
SHE PERFORMANCE
D. MAN HOURS STATISTICS
DATE
No. ITEM 9 10 11 12 13 14 15 Remarks
I. Normal Time
1 Man Power (Personnal) 13 13 12 16 19 18 17
2 Man Hours (Hours) 104 104 96 128 152 144 136
II. Over Time
1 Man Power (Personnal) 0 0 10 12 12 12 13
2 Man Hours (Hours) 0 0 40 48 48 48 52
III. Total Man Hours per day 104 104 136 176 200 192 188
(Hours)
IV. Total Man Hours only This
1,100
Week (Hours)
V. Total Man Hours per end 360 464 600 776 976 1,168 1,356
date(Hours)
Note:
12 16 15 14
10 13
11 10 10
8
6
4
2 2 3 2 3 3 3 3
0
9 10 11 12 13 14 15
Date
E. ACCIDENT RECORD
DATE TOTAL
No. ITEM
9 10 11 12 13 14 15 THIS WEEK
1 Medical Treatment (Freq.) 0 0 0 0 0 0 0
2 Lost Time Injured (Freq.) 0 0 0 0 0 0 0
3 Fatality (Frequency/Person) 0 0 0 0 0 0 0
4 Zero Accident 360 464 600 776 976 1,168 1,356
CORRELATION MAN HOURS ≈ ZERO ACCIDENT ≈ MAN POWER
600 p
464 16 8 l
600 18
36013 13 19 6 e
12
400
4
200 2
0 0
Page 9 of 31 9 10 11 12 13 14 15 SHE Report
Date
1,400 18
1,168 1,356 16
1,200
976 14
1,000 WEEKLY SAFETY
776
REPORT 12
800 WASTE WATER TREATMENT PLANT PROJECT 17 10
Hours
600 16
464 8
REVISI 600 : 00360 13 LOCATION 18: Gerem, Cilegon
13 12 19 6
NO. PROJECT
400 : 2006-MFI02 AREA : WWTP Existing MFI
4
PERIODE200 : 09-15 April 2021 REPORTED BY : Putra Wira P. 2
0 0
9 10 11 12 13 14 15
Date
3 Person)
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0
9 10 11 12 13 14 15
Date
Description:
1. Total Manhours a week : 1,100 hours during project: 1,356 hours (5-15 April 2021)
2. Total Zero Accident : 1,356 hours
3. Total Man Power : 19 mp
4. Total of Mandays : 11 days (5-15 April 2021)
5. Total training Hours : 22 hours (Since 17 March 2021)
6. Safety awareness : Zero accident
7. Safety activity : Safety talks & TBM, Safety monitoring, Safety Inspection, Safety meeting
9, 12, 13,
Safety Induction by TPI Company for new comer
14
09-15 Apr
Inspection Chain block tools by HSE TPI
2021
002 Muchamad Gufron HSE Coordinator PT Lautan Organo Water 18 Maret 2021 √ √ On Site
003 Dadan Kadarsah Electrical Engineer PT Lautan Organo Water 17 Maret 2021 √ √ Off Site
004 Hoerudin Electrical Engineer PT Lautan Organo Water 18 Maret 2021 √ √ Off Site
005 Agus Salim Spv Subcon CV Hasan Teknik 18 Maret 2021 √ √ Off Site Tentative
006 Setiawan Utomo Leader Mechanical CV Hasan Teknik 18 Maret 2021 √ √ On Site
007 Muji Rahardjo Leader Electrical CV Hasan Teknik 5 Apr 2021 √ √ On Site
008 Putra Wira Pratama Safety Officer CV Hasan Teknik 5 Apr 2021 √ √ On Site
009 Sacse Enceng Hidayat Mechanical CV Hasan Teknik 5 Apr 2021 √ √ On Site
010 Muhamad Yahya Iswanto Helper CV Hasan Teknik 5 Apr 2021 √ √ On Site
Muchamad Gufron
WEATHER RECORD PT. LAUTAN ORGANO WATER
Project Name : WASTE WATER TREATMENT PLAN EXPANSION PROJECT (MFI Project) Client : PT MFI
ACTIVITY SHE
A. SAFETY INDUCTION
DATE
No. NAME/COMPANY Remarks
16 17 18 19 20 21 22
1 PT LOW 0 0 0 0 0 0 0
2 CV Hasan Teknik 0 1 0 0 0 0 0
3 0 0 0 0 0 0 0
Total of Safety Induction (Person) 0 1 0 0 0 0 0
- Duration time for safety induction: 1 hours - Training Hours:
- Materi: 1 man hours for safety induction
1. PPE
2. General Safety Rules - Inductor:
3. SOP work in IFC Project 1. Wahyu/ Denny (Taisei)
4. Emergency Procedure
5. 5R/5S Implementation
4/21/2021 Gufron, Hilal, Hastek : 12 man power Mechanical/Electrical Job, Usage first aid box,
(07.30 a.m) Wawan, Muji LOW : 3 man power Screening worker for safety, Fire work protection,
Wira Usage body harness at Height work
4/22/2021 Gufron, Hilal, Hastek : 14 man power Mechanical/Electrical Job, Implementation
(07.30 a.m) Wawan, Uddin LOW :3 man power Housekeeping, Placement B3 material properly,
Wira Usage & Install fire blanket
0 0 0 0 1 0 0 1
1 Rain Hours
10 14 14 14 14 12
14 10
8
6
4
2 2 2 3
2 1 2 2
0
16 17 18 19 20 21 Date 22
E. ACCIDENT RECORD
DATE TOTAL
No. ITEM
16 17 18 19 20 21 22 THIS WEEK
1 Medical Treatment (Freq.) 0 0 0 0 0 0 0
2 Lost Time Injured (Freq.) 0 0 0 0 0 0 0
3 Fatality (Frequency/Person) 0 0 0 0 0 0 0
4 Zero Accident 1,539 1,667 1,795 1,971 2,155 2,291 58,853
CORRELATION MAN HOURS ≈ ZERO ACCIDENT ≈ MAN POWER
60,000 16
58,853 14
50,000 P
12
e
40,000 10 o
15
Hours
30,000 16 16 15 8 p
16 l
6 e
20,000 16
12 4
10,000 1,539 1,667 1,971 2
1,795 2,155 2,291
0 0
16 17 18 19 20 21 22
Date
3 Person)
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0
16 17 18 19 20 21 22
Date
Description:
1. Total Manhours a week : 1,103 hours during project: 58,853 hours (5-22 April 2021)
2. Total Zero Accident : 58,853 hours
3. Total Man Power : 16 mp
4. Total of Mandays : 18 days (5-22 April 2021)
5. Total training Hours : 23 hours (Since 17 March 2021)
6. Safety awareness : Zero accident
7. Safety activity : Safety talks & TBM, Safety monitoring, Safety Inspection, Safety meeting
16-22 Apr
Safety Meeting by Client, Contractor, Sub- Contractor
2021
16-22 Apr
Inspection Scaffolding by HSE TPI
2021
002 Muchamad Gufron HSE Coordinator PT Lautan Organo Water 18 Maret 2021 √ √ On Site
003 Dadan Kadarsah Electrical Engineer PT Lautan Organo Water 17 Maret 2021 √ √ On Site Tentative
004 Hoerudin Electrical Engineer PT Lautan Organo Water 18 Maret 2021 √ √ Off Site
005 Agus Salim Spv Subcon CV Hasan Teknik 18 Maret 2021 √ √ Off Site Tentative
006 Setiawan Utomo Leader Mechanical CV Hasan Teknik 18 Maret 2021 √ √ On Site
007 Muji Rahardjo Leader Electrical CV Hasan Teknik 5 Apr 2021 √ √ On Site
008 Putra Wira Pratama Safety Officer CV Hasan Teknik 5 Apr 2021 √ √ On Site
009 Sacse Enceng Hidayat Mechanical CV Hasan Teknik 5 Apr 2021 √ √ On Site
010 Muhamad Yahya Iswanto Helper CV Hasan Teknik 5 Apr 2021 √ √ On Site
020 Syarif Hidayat Scaffolder CV Hasan Teknik 17 Apr 2021 Resign Finish 19 Apr 2021
Note: Reported by,
Total on site : 17
Resign :1
Man Power (registered) : 20
Muchamad Gufron
WEATHER RECORD PT. LAUTAN ORGANO WATER
Project Name : WASTE WATER TREATMENT PLAN EXPANSION PROJECT (MFI Project) Client : PT MFI
ACTIVITY SHE
A. SAFETY INDUCTION
DATE
No. NAME/COMPANY Remarks
4 5 6 7 8 9 10
1 PT SCYY 0 0 0 0 0 0 0
2 CV Hasan Teknik 0 0 0 2 0 0 0
3 0 0 0 0 0 0 0
Total of Safety Induction (Person) 0 0 0 2 0 0 0
- Duration time for safety induction: 1 hours - Training Hours:
- Materi: 2 man hours for safety induction
1. PPE
2. General Safety Rules - Inductor:
3. SOP work in area Cogen 7 Proejct 1. Firdaus (IKS)
4. Emergency Procedure
5. 5R/5S Implementation
0 0 0 0 0 0 0
1 Rain Hours
12
10 18
15 17 17
16 16
8
6
4
2
0 0 0 0 0 0 0
4 5 6 7 8 Date 9
E. ACCIDENT RECORD
DATE TOTAL
No. ITEM
4 5 6 7 8 9 10 THIS WEEK
1 Medical Treatment (Freq.) 0 0 0 0 0 0 0
2 Lost Time Injured (Freq.) 0 0 0 0 0 0 0
3 Fatality (Frequency/Person) 0 0 0 0 0 0 0
4 Zero Accident 58,973 59,109 59,245 59,373 59,501 59,645 59,789
CORRELATION MAN HOURS ≈ ZERO ACCIDENT ≈ MAN POWER
59,200 10
58,973 17 p
17 16 8 l
59,000 15 18
6 e
58,800 16 4
58,600 2
58,400 0
4 5 6 7 8 9 10
Date
3 Person)
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0
4 5 6 7 8 9 10
Date
Description:
1. Total Manhours a week : 936 hours during project: 59,789 hours (4-10 Juli 2021)
2. Total Zero Accident : 59,789 hours
3. Total Man Power : 18 mp
4. Total of Mandays : 25 days (4-10 Juli 2021)
5. Total training Hours : 25 hours (Since 01 July 2020)
6. Safety awareness : Zero accident
7. Safety activity : Safety talks & TBM, Safety monitoring, Safety Inspection, Safety meeting
16-22 Apr
Safety Meeting by Client, Contractor, Sub- Contractor
2021
16-22 Apr
Inspection Scaffolding by HSE TPI
2021
002 Muchamad Gufron HSE Coordinator PT Lautan Organo Water 18 Maret 2021 √ √ On Site
003 Dadan Kadarsah Electrical Engineer PT Lautan Organo Water 17 Maret 2021 √ √ On Site Tentative
004 Hoerudin Electrical Engineer PT Lautan Organo Water 18 Maret 2021 √ √ Off Site
005 Agus Salim Spv Subcon CV Hasan Teknik 18 Maret 2021 √ √ Off Site Tentative
006 Setiawan Utomo Leader Mechanical CV Hasan Teknik 18 Maret 2021 √ √ On Site
007 Muji Rahardjo Leader Electrical CV Hasan Teknik 5 Apr 2021 √ √ On Site
008 Putra Wira Pratama Safety Officer CV Hasan Teknik 5 Apr 2021 √ √ On Site
009 Sacse Enceng Hidayat Mechanical CV Hasan Teknik 5 Apr 2021 √ √ On Site
010 Muhamad Yahya Iswanto Helper CV Hasan Teknik 5 Apr 2021 √ √ On Site
017 Rifat Muamar Helper CV Hasan Teknik 12 Apr 2021 Resign Finish 22 Apr 2021
020 Syarif Hidayat Scaffolder CV Hasan Teknik 17 Apr 2021 Resign Finish 19 Apr 2021
Note: Reported by,
Total on site : 17
Resign :2
Man Power (registered) : 20
Muchamad Gufron
WEATHER RECORD PT. LAUTAN ORGANO WATER
Project Name : WASTE WATER TREATMENT PLAN EXPANSION PROJECT (MFI Project) Client : PT MFI