Power Protection for

Business Critical Continuity

Liebert NPS I
Ensuring Continuity of Power to Load

User Manual
for Installation & Operation

Network Power Switch - I


Single Phase - 1 Pole
Single Phase - 2 Pole
* 3U Image
Sr. No. :P1707NPS1250
Rev. No. : 03

Liebert
Network Power Switch I

Models
16Amp 2 POLE
32Amp
1 POLE
63Amp

Network Power Switch I (1 & 2 Pole)*

Model Details NPS I - R 3 2

No. of Pole :- 1Pole / 2Pole

Hight in U :- 3U / 4U
Mounting type :- R - Rack
Liebert Nework Power Switch I

* Available in output voltage at 110Vac apart from standard 230Vac output voltage.

NPS - I 3.0
Emerson Network Power: The global leader in enabling
business-critical continuity.
Emerson Network Power (India) Private Ltd.(formerly Tata Liebert Limited) is a wholly owned
subsidiary of Emerson Electric USA. a $US 20.9 billion company that is ranked 94th on the Fortune 500
list of America's largest companies. Set up in September 1993. the Indian subsidiary has seen a
consistent growth rate of more than 30% p.a . over the last 16 years. After the company transitioned
itself to Emerson Network Power India in 2001. the company has made a conscious effort to align itself
with its global parent. From grid to chip for telecommunication networks, data center, health care and
industrial facilities. Emerson has moved from being a UPS and Precision AC manufacturer to a "Global
Leader in enabling Business Critical Continuity solutions:'

Emerson Network Power India's solutions cater to an array of large enterprises spanning across
Government, BFSls, BPOs, Industrial Process Control Rooms, Food Processing Industries, Broadcast
Facilities, Building Services Control Room, Surveillance and Monitoring Centers and Retail Malls.

Emerson Network Power has been amongst the pioneers to develop and introduce energy efficient product
concepts ln a break through move in 2008, Emerson Network Power India unveiled Energy
Logic concept for data centers that has virtually removed the three most critical constraints faced by
data center managers today: power cooling and space.

An ISO9001 certified company: Emerson Network power(lndia) Private Ltd . crossed a major milestone
in its quality journey when it was accorded Level II recognition by MAlT (Manufacturers Association for
Information Technology) in 1998. This is the highest ever recognition accorded by MAlT in India for a
company and the first in the manufacturing sector. In 1999 the Confederation of Indian Industries.(CII)
recognised the company for its strong commitment to Quality through a Certificate under the CII-Exim
Business Excellence Award.

Emerson also has a long list of awards to its credit. notable ones being:

• MAlT Excellence in Exports award in the Hardware category

• The Maharashtra IT Award in the IT Hardware category

• Frost & Sullivan "Voice of Customers Awards" for the Indian UPS Industry

Apart form this the company has won various product line & customer service leadership awards in
IT/lTES/Data Centers. Large Enterprises, Hospitals, Telecom and Customer service leadership award in
Banking/lnsurance/ Non-banking financial.

Emerson Network Power (India) Private Ltd. is headquartered in Thane. Maharashtra and is
supplemented by a strong national network of 31 branch offices. Emerson Network Power (India)
Private Ltd. today addresses the requirements of various markets through 60+ business partners,
network solution partners and resellers pan India.

Liebert Asco Power Technologies, and Emerson Energy Systems are divisions of Emerson and Emerson
Network Power. Through its Emerson Network Power companies. Emerson is serving network dependent
data. telecommunications and Internet-related businesses with a full spectrum of reliable power and
connectivity solutions.

More information on Emerson Network Power, its services and solutions is available at:
www.emersonnetworkpower.com

Liebert Network Power Switch I


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013
Unpacking of Corrugated packed systems

1 2

3 4

5
Modbus

Liebert Network Power Switch I


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013
INDEX

1. Introduction 1

2. About Symbols 2

3. Safety 3

4. Preparation for Use 5

5. Installation 7

6. Parts Designation 8

7. System Description 9

8. Single Line Diagram - 2 Pole 10

8.1. Single Line Diagram - 1 Pole 11

9. Front View 12

9.1. Mimic 14

9.2. Settings & Controls 15

10. Connection Details 16

11. Operating Instructions 18

12. Specifications 19

13. Test Report 21

14. Trouble Shooting 23

15. Maintenance 24

16. Environmental Compatibility, Disposal 25

17. Service Centers 28

Liebert Network Power Switch I


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013
1. Introduction
Dear Users,

We thank you for buying technologically advanced Liebert Network Power


Switch I for the specific application. Liebert Network Power Switch I is a
combination of static transfer switches with inbuilt intelligence. It has high
speed change over characteristics

Liebert Network Power Switch I is useful for providing instantaneous power to


the load. This intelligent static transfer switch ensures instantaneous transfer of
load between the two power sources. It is useful in many applications, where
redundant power supply is available.

We have been designing, manufacturing and supplying UPS system, Inverters


& Liebert Network Power Switch I of wide varieties and ranges for the last
thirty years. Besides Network Power Switch, we also have custom built
Liebert Network Power Switch I designs to give you complete power solutions.
Our R&D set up, one of the best in India, offers distinct advantages by
developing design philosophies which meet customer demands & needs.

You have made the right choice in buying our System, and become a customer
of Emerson Group. We presently have three modern manufacturing plants, and
after sales network operating from 50 destinations in India. We hope that you
will become our special customer & build permanent relation with us.

There are two important factors for the reliable functioning of Liebert Network
Power Switch I, its proper installation & proper operation. This manual gives
you in detail instructions on the installation operation and maintenance of the
Liebert Network Power Switch I.

We look forward for a longer association to cater your future power


requirements.

Caution
We request you to read the entire manual prior to installation,
performing system operation or maintenance. Should you
require any assistance for operation or installation please call
on our nearest service center by giving information such as
Model, Sr. No., Date of Purchase and your observations.

Liebert Network Power Switch I 1


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 01
2. About Symbols
The following symbols are used in this manual:

Caution

As defined by these operating instructions and the danger notices on the


products. Failure to observe the appropriate safety measures will result in
accidental hazards, severe injury or considerable damage to the property.

Warning

As defined by these operating instructions and the warning notices on the


products. Failure to carry out described operations or observe proper
precautions may result in accidental hazards, severe injury or considerable
damage to property.

Notice

This pictogram draws attention to important information about the product or part
of the operating instructions.

Indicates a step that must be carried out.

Static sensitive devices. Please handle with care.

Liebert Network Power Switch I 2


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 02
3. Safety

3.1. General
The interior of Liebert Network Power Switch I , when it is powered, has
hazardous AC voltage present inside. The control logic, which is supplied by
low voltage, has low power. Part of this type of equipment is powered by +/-
5 V, +/- 15 V & +30 V logic power supplies. These are referenced to
potentials other than earth zero. So high voltages with respect to earth exist
on some circuit boards in it.
3.2 Safety Warning
Ensure somebody is available to isolate the electricity supply if necessary.
Stand on an approved rubber insulating mat when working on the
equipment.
WARNING ! : Some rubber mats contain a carbon base pigment and are
not suitable!

q Remove watches, rings, earrings and other metal jeweleries and any loose
material like pens, tools or metal objects from pocket before working on the
equipment.

q Do not touch printed circuit boards. High voltages exist, there is an electric
shock hazard.

q Use only isolated tools.

q Never work alone, learn first aid, especially cardiopulmonary resuscitation


(CPR), for electrical accident victims. Unless power is removed from the
equipment, one person should never work alone. A second person should be
standing by to assist him.

q Turn off power before working on electric or electronic circuit, except when
absolutely necessary. Consider all wire and terminals to be live until proven
otherwise by a safe test method.

q Turn off power to equipment before checking or replacing fuses. Locate and
correct the cause of a blown fuse or tripped circuit breaker before replacing
the fuse or resetting the breaker.

q Always check the electrical rating of equipment you use, and be sure you
use that equipment within its ratings.

Liebert Network Power Switch I 3


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 03
q Never block or insert any object in to the ventilation holes or other
openings

q Turn the Liebert Network Power Switch I off and isolate the Liebert
Network Power Switch I before cleaning. Use only a soft cloth, never use
liquid or aerosol cleaners. Keep the front and rear vents free of dust
accumulation that could restrict airflow, required for cooling. This
equipment contains several circuit that are energized with high voltage.
Only test equipment designated for troubleshooting should be used. This is
particularly applicable for oscilloscopes.

Only qualified service personnel should perform maintenance on the


Liebert Network Power Switch I . When performing maintenance with any
part of the equipment under power, service personnel and test equipment
should be standing on rubber mats. The service personnel should wear
insulating shoes for isolation from direct contact with the floor (Earth
ground).

3.3 Emergency actions & treatment

3.3.1 Electrical shock

• Immediate action is essential. Severe electric shock may affect heart action
and breathing.

• Make sure it is safe to approach. If the casualty is in contact with a live


conductor, isolate by switching off the supply. If this is not possible, or it is
doubtful whether the system is electrically isolated, stand on a dry
insulating material and pull or push the casualty clear using dry insulating
material, e.g. wood, plastic, fabrics etc.

• If necessary, give artificial respiration.

• Seek the assistance of others to summon medical attention.

3.3.2 Electrical burns

• Apply a dry sterile dressing.

3.4 Safety precautions for AC capacitor

• Handle capacitor units carefully as they remain charged even after


disconnection, may be due to faulty discharge devices. Consider capacitor
terminals, connected bus bars, cables and other devices which are
connected with them, as energized. Voltage might be present there.

Liebert Network Power Switch I 4


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 04
4. Preparation for Use
4.1 Transportation

Warning: Use suitable means of transportation and secure


the Network Power Switch against tipping over when
transporting. Improper transportation can result in damage
to the Liebert Network Power Switch I & battery as well as
injury to personnel.

Transport the Liebert Network Power Switch I on the pallet in the original
packaging, using a suitable lifting truck, to the storage or installation site
4.2 Unloading
After receipt of the Liebert Network Power Switch I, before unloading, compare
contents of Delivery Challan with the Invoice.
Ensure proper unloading facility exists with transporter / local subcontractor.
Ensure that the equipment is kept upright as per the arrow marked indicated
on its packing.
During unloading, ensure that the unit is not tilted beyond 45 degree angle
with the ground surface, to prevent internal damages.
4.3 Storage
4.3.1 Liebert Network Power Switch I Storage
If the Liebert Network Power Switch I system is not going to get installed
immediately, we recommend keeping it in proper storage.
4.4 Floor Loading
The route / passage up to the installation site and the actual foundation
location must be capable of supporting the weight of the Network Power
Switch.

Caution Please observe the following: Store the Liebert Network


Power Switch I in its original Packing. Ensure the arrow on
the box is pointing vertically upward direction.
Store it in dry location. Storage temperature must be
between 5 to 35 ºC.

6
Liebert Network Power Switch I
Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 05
4.5 Access to the Area
1. Plan the route such a way that the Liebert Network Power Switch I will
pass through
all elevations, corners and doorways, smoothly.
2. Ensure adequate service maintenance space min 1000 mm is
provided from front & back side, and 600 mm from both sides of the
equipment.
4.6 Ventilation
All ventilation apertures must be kept free and clean. These systems can work
in a continuous environmental within 0 to 40°C temperature range, although,
ideally the ambient temperature should be below 25 °C.
The heat can be removed from the equipment room by a forced cooling
ventilation system or, alternatively, an air conditioning system.
The required air changes per hour will depend on the system rating, the heat
loss and the cooling air temperature.
4.7 Installation Altitude
The maximum altitude without de-rating of the Liebert Network Power Switch I
should be 1000 meter above sea level. Consult factory for the de-rating factor
above 1000 meter altitude.

Liebert Network Power Switch I 6


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 06
5. Installation
5.1 Unpacking

1 Unit is covered with plastic bag. Further it is enclosed in the suitable


enclosure box.

2 Keep box on the plain surface such that THE ARROW ON BOX
SHOULD POINT VERTICALLY UPWARDS.

3 If the unit is packed in wooden container, remove buttons from all sides,
EXCEPT from BOTTOM SIDE. Remove these bolts to remove the
wooden base.

4 If unit is with corrugated packing, simply remove external box and


then the plastic cover, now the unit is ready for external wiring and
operation. The equipment Serial No. Plate should be checked to ensure
that Serial No. is as mentioned on the Invoice / Challan.

Dispose of the packaging material in accordance with the local


Invironment regulations.

5.2 External Inspection

The NPS I is inspected mechanically & electrically before being shipped


from the factory, they should be kept in the same condition when they
arrive. The NPS I should be inspected visually / mechanically for any
damages which may have caused during shipping and / or movement up to
the site.If damage is apparent, do not attempt to install the NPS I, please
report to the transporter & our Service Center.

Caution
Improper installation of the system may cause injury to
personnel or damage the equipment. The system must be
installed & grounded in accordance with the Local as well
as National Electrical codes

Liebert Network Power Switch I 7


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 07
6. PARTS DESIGNATION

Part Designation
C Capacitor

F Fuse

HS Heat Sink

KA Relay

PB Printed Circuit Board

R Resistor

RV Metal Oxide Varistor

S Switch, Isolator

TA Current Transformer

VD Diode

VTT Thyristor - Thyristor Module

X Connector

XM, XD Terminal Block

Liebert Network Power Switch I 7


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013
08
7. System Description
The Liebert Network Power Switch I is an intelligent static transfer switch
designed to provide fast automatic transfer between two independent AC
power source to critical equipment.
One of the two AC input is designated as the "priority" source to which the
Liebert Network Power Switch I will connect the load as long as the input
source is within acceptable voltage & frequency limits. If the priority Source
falls outside the acceptable limits, the Liebert Network Power Switch I will
transfer the output load to the other "alternate" input. It will remain on this
source as long as the alternate Source is within acceptable voltage and
frequency limits. In case of overload, Liebert Network Power Switch I gives
alarm. Under short circuit condition the load is protected by a fast acting semi
conductor fuse & by electronic circuitry.
The Liebert Network Power Switch I consists of two modules. Fixed module
consists of input and output connection and manual bypass transfer switch.
Second module is hot swappable plug in type removable electronic & static
switch module.
The Liebert Network Power Switch I is designed to allow replacement of the
removable electronic module without having to de-energize the load
equipment.

Liebert Network Power Switch I 8


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 09
SOURCE 1 2 Pole
PHASE

VTT1
F1

MANUAL
VTT3 BYPASS
TA
SWITCH

Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013


SOURCE 1 A2 A3
NEUTRAL OUTPUT

Liebert Network Power Switch I


PHASE
A1

VTT2
8. SINGLE LINE DIAGRAM

F2
SOURCE 2 A3
A2 OUTPUT
PHASE
NEUTRAL
A1
VTT4

SOURCE 2
NEUTRAL

EARTH

10
8
8.1 SINGLE LINE DIAGRAM
1 Pole

OUTPUT

NEUTRAL
PHASE

OUTPUT
SW2

A1
A3
A2
TA

VTT2
VTT1
F1

F2
SOURCE 1
SOURCE 1

SOURCE 2
NEUTRAL

SOURCE 2
NEUTRAL
PHASE

PHASE

EARTH

Liebert Network Power Switch I 8


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 11
9. FRONT VIEW

FRONT VIEW (3U Cabinet)

Modbus

Liebert Network Power Switch I 8


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 12
FRONT VIEW (4U Cabinet)

Liebert Network Power Switch I 8


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 13
9.1 MIMIC

Alram
Sources

Feeding
Healthy
Priority
1

Liebert Network Power Switch I 8


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 14
9.2. SETTINGS & CONTROLS
A) Indication

1 Source 1 Healthy
2 Source 2 Healthy
3 Source 1 Priority
4 Source 2 Priority
5 Source 1 Feeding
6 Source 2 Feeding

B) Alarms indications

1 No Sync

2 Over Load

3 Source 1 Fuse Fail

4 Source 2 Fuse Fail

C) Switch Indication

0 - Load on Static switch

1 - Load on Manual Bypass - S1

2 - Load on Manual Bypass - S2

Liebert Network Power Switch I 8


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 15
10. CONNECTION DETAILS

A ) Recommended Cable Details

Description Copper Uninyvin Cable


16-32AMP 63AMP

INPUT / OUTPUT Size # 12 Size # 10

B ) Power Connections For 3U

SR. N0.
PLATE
16Amp
32Amp 2 POLE
63Amp XM3 XM2
63Amp 1 POLE

XM1

XM1

N L
OUTPUT SOURCE1
L N

EARTH
L
SOURCE2
N
XM2, Xm3 are the Additional Output Sockets

C ) Potential Free Contact (PFC) Details (On Front Sticker)

S1
ALARM ABNORMAL

S2
ABNORMAL

Liebert Network Power Switch I 8


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 16
D ) Power Connections For 4U

INSTA SWITCH
N L E N L N L
Output Source 2 Source 1

PFC

N L
OUTPUT SOURCE1
L N

EARTH
L
SOURCE2
N
In 4U Cabinet there are no connections at the back side

E ) Potential Free Contact (PFC) Details (On Front Sticker)

S1
ALARM ABNORMAL

S2
ABNORMAL

Liebert Network Power Switch I 8


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 17
11. OPERATING INSTRUCTIONS
Normal mode
1. Keep manual bypass switch on 'O' position
(Normal output mode)

2. Select source priority as per requirement (source1 or 2)

3. Apply input supply through MCB of suitable rating to both input sources.

4. Check other settings to default.

Manual Bypass Switch Operation


Make before break switch is use as Manual bypass switch. This switch has 1-
0-2 position.
1. '1' position is giving direct supply from source 1 to output connector.
2. '2' position is giving direct supply from source 2 to output connector.
3. '0' position is giving output from Liebert Network Power Switch I to output.

Selecting Liebert Network Power Switch I mode to Maintenance mode.


1. Depending upon the feeding source (i.e. eigher Source 1 or 2 Source)
Select manual bypass switch position to either source1 or source2
2. If the Manual Bypass Switch position is on Source 1, LED indication
for load on Manual Bypass Switch will glow.
3. Remove the Hot Swapable module out of the Liebert Network Power
Switch I which contains SCR's assembly & control circuitry
4. Rectify problem if any.

Selecting Maintenance mode to Normal mode.


1. Rectify problem if any.
2. Slide in the module into the Liebert Network Power Switch I unit.
3. Lock the sliding module using its screws.
4. If the Manual Bypass Switch Position is on Source1, select priority source
1 or if the Manual Bypass Switch Position is on Source 2, select priority
source 2.
5. Selected priority source feeding LED should glow, then change the switch
position on Liebert Network Power Switch I output position.
6. Load will get transferred to selected source.
7. Load on STSW indication LED will glow.

Liebert Network Power Switch I 8


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 18
12. SPECIFICATIONS
A) Input / Output
q Nominal Voltage 110/230V AC, Single phase, (-15 % to +10 %)
q Output Current 16Amp / 32Amp / 63Amp
q Frequency 50Hz/60Hz (± 3Hz)
q No of Pole 1POLE 2POLE
16Amp 16Amp
32Amp 32Amp
63Amp 63Amp
q Load Power Factor range 0.6 to unity leading or lagging
q Sync Phase error limit 18 deg
q * Efficiency Static Switch Efficiency (%)
Rating 2P 1P
63A/110V 97 98
63A/230V 98 99
32A/110V 96.5 98
32A/230V 98 99
16A/110V 96 97
16A/230V 98 98.5

q Overload capacity 125 to 150% for 10 min.,


150 to 200 % for 1 min.,
200 to 400 % for 5 sec., (Settable from Insta Mon)
400 to 700 % for 600 ms,
> 700% for 250 ms
q Over current protection By semiconductor fuse and
By electronics circuitry
q Integral Maintenance Bypass Make before break operation
q Alarm contacts PFC
Contact Rating - 2 A for 30V DC
- 0.5 A for 230V AC

q Transfer Time Sync Condition < 5 ms


No-sync Condition < 6 ms or < 15 ms
(Settable from Insta Mon)

Liebert Network Power Switch I 8


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 19
B) ENVIRONMENTAL Static Switch Total Heat Losses (W)
Rating 2P 1P
q Heat dissipation
63A/110V 233 129
63A/230V 233 129
32A/110V 131 78
32A/230V 131 78
16A/110V 78 51
16A/230V 78 51

q Storage Temperature range 0 to 70 ºC


q Operating Temperature range 0 to 40 ºC
q Relative humidity Up to 95% RH, Non condensing
q Altitude Up to 1000m (without derating)
C) PHYSICAL
q Enclosure Protection Grade IP - 20
q Cooling Natural Cooling
q Colour (RAL 7021) Black - Grey.
q Cable Entry Back
q Installation 19” Rack Mounted
q Dimensions & Weight

Height W D H Weight (Max) Weight (Max)


Model in U (in mm) (in mm) (in mm) (1Pole) (2Pole)

Liebert Network Power


3U 480 450 132 17Kg 20Kg
Switch I
4U 480 450 175 27Kg 30Kg
D)Indications on MIMIC
Ü Source 1 Healthy Ü Source 1 Priority Ü Source 1 Feeding Ü Source 1 Fuse Fail
Ü Source 2 Healthy Ü Source 2 Priority Ü Source 2 Feeding Ü Source 2 Fuse Fail

Ü No Sync Ü Alarm

Ü Load on STSW

Ü Load on Manual Bypass Source1

Ü Load on Manual Bypass Source 2


E) Technical Standard IEC 62310 - 1, IEC 62310 - 2, IEC 62310 - 3.
E) Reference Standard IEEE-446

Notes : Efficiency and Transfer time specified is for Linear load.


* For tolerances, see IEC/EN60146-1

Liebert Network Power Switch I 8


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 20
13. TEST REPORT
Sr. No. P1707NPS1250 DATE 04.08.2017
CLIENT Model LIEBERT NPS I
TESTED BY Amol Kodre

SR.NO PARAMETER CONDITION TEST CONDITION REMARK


2.1 Input voltage of 1 Ø, 2 wire, 110 V / 230 AC Both source - ON OK / NOT OK
both source (Actual Voltage to be recorded)
2.2 Input Frequency 50 Hz / 60 Hz, Both source - ON OK / NOT OK
(Actual Freq. to be recorded)
2.3 Source1 priority 1. Source 1- priority indication Both source - ON OK / NOT OK
selection will glow
2. Load on source 1 indication
will glow
2.4 Source2 priority 1. Source 2 - priority indication Both source - ON OK / NOT OK
selection will glow
2. Load on source 2 indication
will glow
2.5 Transfer delay from 1. Load on source 2 indication Select S1 priority
source1 to source2 will glow Initially both Input OK / NOT OK
2. Transfer delay at output is Sources ON.
< 5 m sec in sync as well as Switch OFF Source 1
in no sync condition.
2.6 Retransfer delay from 1.After switching OFF source1, Select S1 priority OK / NOT OK
source2 to source1 load on source 2 indication Initially both input
will glow & Load on source 1, Sources ON.
Indication will goes OFF. SW1-1 - ON.
2.After switching ON Switch ON Switch OFF S1 For
source 1, Load on source 1 1 min & Again Switch
Indication will glow & Load on
source 2 Indication
will goes OFF
3.After switching ON source1
load retransfer to source1
within < 5 m sec in sync or
no sync condition
2.7 Transfer / Retransfer 1.When priority source is below Select S1 priority, OK / NOT OK
due to input UV / OV For 230 V = 196 V & Initially both input
For 110 V= 94 V, load transfer Sources ON.
to other healthy source & When
priority source is more than
For 230 V = 206 V & For
110 V =104 V load retransfer
again to priority source

Liebert Network Power Switch I 8


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 21
SR.NO PARAMETER CONDITION TEST CONDITION REMARK
2.7 Transfer / Retransfer 2.When priority source voltage is Select S1 priority, OK / NOT OK
due to input UV / OV More than For 230 V = 253 V, & nitially both input
Sources ON. For 110 V = 121 V
load transfer to other healthy
source & when priority source
voltage is below
For 230 V = 246 V, &
For 110 V = 115 V load retransfer
again to priority source
2.8 Transfer Retransfer due 1. When priority source frequency Select S1 priority, OK / NOT OK
to frequency abnormal is below 47 Hz or above 53 Hz, Initially both the
load transfer to other healthy sources ON.
source & when priority source
freq. is in normal band, load
retransfer to priority source.
2.9 Fuse fail indication source 1 or source 2 fuse fail Both sources - ON OK / NOT OK
indication will glow Fuse in S1 or S2
path is Open.
2.10 S1 Abnormal - PFC Check continuity at PFC Source2 –ON OK / NOT OK
connector Source1 – Fail
2.11 S2 Abnormal - PFC Check continuity at Source1 –ON
PFC connector Source2 – Fail OK / NOT OK
3. CONNECTIVITY
3.1 Connectivity to Parameters/status on OK / NOT OK / NA Both source ON
INSTA - MON Software INSTAMON software
3.2 Connectivity to Parameters/status OK / NOT OK / NA Both source ON
MODBUS (optional) on MODBUS
3.3 Connectivity to Parameters/status OK / NOT OK / NA Both source ON
Ethernet (optional) on MODBUS

Liebert Network Power Switch I 8


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 22
14. TROUBLE SHOOTING
OBSERVATION CAUSE SOLUTION

1.Alarm LED Overload at the output. Reduce the load.


glowing on Load > 100% Check CT (TA 1) &
mimic feedback resistor.

2.Load On non Check selected priority Set required priority


Priority source (Check switch position)

Source voltage out of limit Check priority source voltage

Frequency out of limit Check priority source frequency.

Manual bypass switch of Switch OFF manual bypass switch.


opposite source is operated. (Read the operating instructions
carefully)

Fault in Liebert Network Replace the faulty card.


Power Switch I control card Contact Emerson CSS.

3.No Output Both the source failed. Check source condition at input side.
available Fuse blown in the priority Replace the faulty fuse. Find out the
source. cause of fuse failure / Probable
cause

Short circuit in the output circuit.

Output overload.

Loose connection at fuse

Fault in Liebert Network Replace the faulty card


Power Switch I control card Contact Emerson CSS.

4.No Voltage fuse blown. Replace the faulty fuse. Try to find
at Output out the cause of fuse failure.
Refer CI. No.1.2 of fault No 3

No firing pulses to SCR Fault in Liebert Network


Power Switch I control card
Replace the faulty card.
Contact Emerson CSS.
SCR-SCR module faulty Replace faulty module,
Contact Emerson CSS

5.No SYNC LED


glowing on mimic Sources not in sync. Check source voltage & phase
difference

Liebert Network Power Switch I 8


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 23
15. Maintenance
We recommends to carry out periodic maintenance of the Liebert Network
Power Switch I by our authorised service engineer.

Following are the general guide lines for the same.

Please ensure that the ventilation and cleanliness surrounding the


Liebert Network Power Switch I .

Regularly check, the arrangements made for the same are good & are in
working condition.

CHECKLIST

A. Quarterly

F All electrical power connections for tightness.


F Verify the Input, Output, cabling and its terminations.

Liebert Network Power Switch I 8


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 24
16. Environmental Compatibility, Disposal
Environmental concerns during development

In contrast to earlier Liebert Network Power Switch I devices, the number of


components has been greatly reduced through the use of highly integrated
components and modular construction. As a result, energy consumption
during production has been reduced.

Particular attention was paid to reducing the volume, mass and variety of
metals and plastics used. Environmental compatibility was an important
criterion in to the selection of parts obtained from vendors.

Environmental concerns during production

Components obtained from vendors are delivered primarily in reusable


packaging.

ASIC components and SMD elements are used on the flat component groups.

Environmental concerns during disposal

The device can be stripped down into recyclable mechanical components with
screw and snap connections. Within the area of the EU, disposal should be
carried out by a certified disposal company .In other countries local
regulations must be observed.

Liebert Network Power Switch I 8


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 25
EMERSON NETWORK POWER INDIA PRIVATE LIMITED.

Liebert Network Power Switch I Model : Liebert NPS-I

Serial No. : P1707NPS1250

Date of Purchase : / /

Date of Commissioning : / /

CUSTOMER COPY

WARRANTY
We guarantee our equipment for satisfactory working within the
limitations of the specifications offered, under normal conditions of
use for a period of twelve months from the date of commissioning or
eighteen months from date of despatch from the factory, whichever is
earlier. In the event of a defect, during the warranty, enough to cause
malfunction in the working as a result of faulty workmanship or
defective material of a major component, we promise to repair or
replace the part, free of charges. But we will be sole judges to
determine the real cause of the defect and if the same is found to have
developed due to abnormal use, high surges due to lightning,
accident, unapproved modifications, ignorance of operators, or a
willful act, the Risk will be entirely the Owner’s. Further, the
defective part as may be the case, shall have to be sent to the factory,
freight paid both ways and also Octroi if payable shall be to the
Owner’s account. Such defective parts, if replaced by new ones, will
be the property of Emerson. Any indirect or consequential damage or
loss is entirely excluded from the obligations of this warranty.

DATE OF DESPATCH

Liebert Network Power Switch I 8


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 26
EMERSON NETWORK POWER INDIA PRIVATE LIMITED.

Liebert Network Power Switch I Model : Liebert NPS-I

Serial No. : P1707NPS1250

Date of Purchase : / /

Date of Commissioning : / /

MANUFACTURER COPY

WARRANTY
We guarantee our equipment for satisfactory working within the
limitations of the specifications offered, under normal conditions
of use for a period of twelve months from the date of
commissioning or eighteen months from date of despatch from
the factory, whichever is earlier. In the event of a defect, during the
warranty, enough to cause malfunction in the working as a result
of faulty workmanship or defective material of a major
component, we promise to repair or replace the part, free of
charges. But we will be sole judges to determine the real cause of
the defect and if the same is found to have developed due to
abnormal use, high surges due to lightning, accident, unapproved
modifications, ignorance of operators, or a willful act, the Risk
will be entirely the Owner’s. Further, the defective part as may
be the case, shall have to be sent to the factory, freight paid both
ways and also Octroi if payable shall be to the Owner’s account.
Such defective parts, if replaced by new ones, will be the property
of Emerson. Any indirect or consequential damage or loss is
entirely excluded from the obligations of this warranty.

DATE OF DESPATCH

IMPORTANT : The equipment warranty shall be void, if this copy is not


despatched to the manufacturer within 30 days of equipment receipt.

Liebert Network Power Switch I 8


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 27
17. SERVICE CENTERS

REGISTERED HEAD OFFICE

Network Power
Emerson Network Power (India) Private Limited
Plot No. C - 20, Road No. 19
Wagle Industrial Estste
Thane - 400 604
Maharashtra, India

Telephone: (00 91 22) 022-33154400


Fax: (91-22) 25828358
Website: www.emersonnetworkpower.com

***WEST ZONE***
Mumbai Emerson Network Power (India) Pvt. Ltd.
Address Dheeraj Kawal, Next to Vikroli Station, L.B.S Marg, Vikroli (W)
Mumbai - 400079.
Tel 91- 22 - 40780303
Fax 91- 22 - 40110183
Ahmedabad Emerson Network Power (India) Pvt. Ltd.
Address 205, Sukhsagar Complex, Beside Fortune Landmark Hotel, Usmanpura,
Ashram Road, Ahmedabad - 380013.
Tel 079 - 27560230
Fax 079 - 27560240
Baroda Emerson Network Power (India) Pvt. Ltd.
Address 39/2, Arunodaya Society, Alkapuri,
Baroda - 390005.
Tel 0265 - 3929500
Fax 0265 - 2330383
Pune Emerson Network Power (India) Pvt. Ltd.
Address 4th floor, C wing, VEGA Center, Shankar-Sheth Road,
Swargate, Pune 411037. (India)
Tel 020 - 6626 2004

Indore Emerson Network Power (India) Pvt. Ltd.


Address 109, Ratnmani Complex, 7/1, New Palasia,
Indore (M.P.)
Tel 0731 - 3262657/ 4023806
Fax
Nagpur Emerson Network Power (India) Pvt. Ltd.
2nd Floor, "Kartik", 69, Hindustan Colony, Vivekanand Nagar Post,Wardha Road,
Nagpur - 440015
Tel 0712 - 6534997
Fax

Liebert Network Power Switch I 8


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 28
***WEST ZONE***
Goa Emerson Network Power (India) Pvt. Ltd.
Address House No. 426, Raj Soda Factory, New Vaddem, Vaso
Goa. - 403802
Tel 9764385055
Fax

***NORTH ZONE***
Gurgoan Emerson Network Power (India) Pvt. Ltd.
Address Plot No. 2, Udyog Vihar,
Gurgoan - 122016 (Haryana)
Tel 0124 - 3315500
Fax 0124 - 3315480
Chandigarh Emerson Network Power (India) Pvt. Ltd.
Address SCO 58, 2nd Flr Sector 47C,
Chandigarh - 160047
Tel 0172 - 3931893
Fax 0172 - 3931894
Lucknow Emerson Network Power (India) Pvt. Ltd.
Address No. 5, 3rd Floor Block B1, Raja Ram Kumar Plaza,
75 Hazratganj, Lucknow - 226001
Tel 0522 - 33154000
Fax 0522 - 4103933
Jaipur Emerson Network Power (India) Pvt. Ltd.
Address 209 Shalimar Complex 1st Floor, Church Road MI Road,
Jaipur - 302001
Tel 0141 - 4024774
Fax --

***EAST ZONE***
Kolkata Emerson Network Power (India) Pvt. Ltd.
Address Advantage Tower, EN - 27, 7th Floor,
Sector-V, Salt Lake,
Kolkata - 700 091
Tel 91 - 33 - 33154000
Fax 91 - 33 - 33154001
Guwahati Emerson Network Power (India) Pvt. Ltd.
Address Institution of Enginners Building (3rd floor)
Near Lakhtakia Overbridge, Panbazar
Guwahati - 781 0071
Tel 91-361-2734485
Fax 91-361-2734486
Bhubaneshwar Emerson Network Power (India) Pvt. Ltd.
Address Plot No. 267, AN Plaza, Rasulgarh, Bhubaneshwar
Bhubaneshwar - 751 0101
Tel 0674 2586003 / 6743353
Fax 0674- 6742580058
Jamshedpur Emerson Network Power (India) Pvt. Ltd.
Address Ground Floor, Contractor's Area,
Kashi Kunj, Road No. 2, Bistupur,
Jamshedpur - 831 001.
Tel 0657-6546636
Fax –

Liebert Network Power Switch I 8


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 29
***EAST ZONE***
Siliguri Emerson Network Power (India) Pvt. Ltd.
Address Smriti Dham Building 3rd floor, Sevok Road, (opposite Gateway Hotel)
Siliguri - 734001
Tel 0353-2535243
Fax -
Bihar Emerson Network Power (India) Pvt. Ltd.
Address L1/26,Sree Krishna Puri, Boring Road,
Patna , Bihar - 800001
Tel 97714 90861
Fax -

***SOUTH 1 ZONE***
Bangalore Emerson Network Power (India) Pvt. Ltd.
Address 3rd Floor, Jindal Centre,
412, IV Block, Koramangala,
Bangalore - 560 034
Tel 080-33154000
Fax 080-33154000
Mangalore Emerson Network Power (India) Pvt. Ltd.
Address Raj Business Centre, 3rd Floor, Raj Towers,
Balamatta Road, Mangalore - 575 001
Tel -
Fax -
Cochin Emerson Network Power (India) Pvt. Ltd.
Address No.40/9338 (New No. 59/4517)
4th Floor, Chakos Towers, Padma Pullepady Road,
Cochin - 682 035
Tel 0484 - 3325405
Fax 0484 - 2381986
Thiruvananthapuram Emerson Network Power (India) Pvt. Ltd.
Address No.T.C.2/8(8), 1st Floor, 'Chandragiri'
Ulloor, Medical College P.O
Thiruvananthapuram - 695 011
Tel 0484 - 3325405
Fax 0484 - 2381986
Chennai Emerson Network Power (India) Pvt. Ltd.
Address "OMS Court"
1, Nathamuni Street,T. Nagar,
Chennai - 600 017
Tel 044 - 33154000
Fax 044 - 33154035
Chennai Emerson Network Power (India) Pvt. Ltd.
Address 343, SVP Complex, D-1st Floor, Sidhapudur,
Avarampalyam Road,
Coimbatore - 641 044
Tel 0422 - 3325400
Fax 0422 - 4389625

Liebert Network Power Switch I 8


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 30
***SOUTH 1 ZONE***

Coimbatore Emerson Network Power (India) Pvt. Ltd.


Address 343, SVP Complex,
D-1st Floor, Sidhapudur, Avarampalyam Road,
Coimbatore - 641 044
Tel 0422 - 3325400
Fax 0422 - 4389625
Madurai Emerson Network Power (India) Pvt. Ltd.
Address V.S.V.K.J. Malligai Towers ,3rd Floor,
113A,West Perumal Maistry Street,
Madurai - 625 001.
Tel -
Fax -
Secunderabad Emerson Network Power (India) Pvt. Ltd.
Address 405/406, 4th Floor,
No.62, Navketan Complex, S.D Road,
Secunderabad - 500 003
Tel 040 - 33154000
Fax 040 - 2780677
Visakhapatanam Emerson Network Power (India) Pvt. Ltd.
Address Flat No - 202a, Door No.- 49-24-51/a/12,
Sri Pavan Estates, Madhura Nagar, Sankaramattam Road,
Visakhapatanam - 530 016
Tel 0891 - 2564349/59
Fax 0891 - 2564349

Liebert Network Power Switch I 8


Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 31
Liebert Network Power Switch I 8
Instruction Manual/Liebert NPS I /Ver3.0/ OCT 2013 32
Country Office
Emerson Network Power (India) Pvt. Ltd.
Plot No. C-20, Road No. 19, Wagle Estate,
Thane (W), Maharashtra - 400 604. India.
Tel : 91-22-33154400
Fax : 91-22-25828358
Toll Free No. 18002096070
Email : marketing.india@emerson.com

www.emersonnetworkpower.co.in

Emerson Network Power


The Global leader in enabling Business-Critical ContinuityTM.

¢ AC Power <Embedded Computing <Outside Plant <Racks & Integrated Cabinets


¢ Connectivity <Embedded Power <Power Switching & Control <Services
¢ DC Power <Monitoring <Precision Cooling <Surge Protection

While every precaution has been taken to ensure accuracy and completeness in this manual, Emerson
Network Power assumes no responsibility, and disclaims all liability for damages resulting from use of this
information or for any errors or omissions.

For disposal of Batteries please visit the below link:


http://www.cpcb.nic.in/divisionsofheadoffice/hwmd/lead.pdf

Note : Specifications & Features may vary based on the condition.