You are on page 1of 1

BoP COORDINATOR DAILY REPORT

AME: DICIPLINE: DATE:


STEPHEN/CLETUS MECHANICAL COORDINATOR 07/10/2023

STATUS
ITEM TAG NUMBER SITE DESCRIPTION In progress or
completed
TO RECTIFY 1670-PA-04C PUMP TRIPPING ON
1 1670-PA-04C OBOB OVERLOAD:- Completed
 Commissioned ok and handed over to operation
TO REPLACE INBOARD AND OUTBOARD BEARING
2 1670-PA-02A OBOB OF 1670-PA-02A. Completed
 Replacement completed; waiting to commission
TO REPLACE FAN COOLER E.MOTOR OF
1670-HC-01B2:-
3 1670-HC-01B2 OBOB In progress
 E.MOTOR is installed already in position in 1670
waiting for Pulley taper lock re-threading

4 Tank pump B EOC REMOVAL OF TANK PUMP B In progress

TO RECTIFY STUCK 1420-MOV-50B VALVE


5 1420-MOV-50B OBOB In progress
ACTUATOR

Page 1 of 1
COORDINATOR DAILY REPORT FNL/DOC/052/REV_0

You might also like