Professional Documents
Culture Documents
PROCEDURE UIC-AFE12815-ENG-PRO-0503 1
UIC-AFE14088-SPE-0706 A
DATE: 28 JULY 2005 SHEET: 1 OF 9
Page 2 of 9
UIC-AFE12815-ENG-PRO-0503 Rev. 1
SAPI FIELD DEVELOPMENT
RECEIVER & LAUNCHER FACILITIES
TABLE OF CONTENTS
Page
1.0 GENERAL 4
2.0 REFERENCES...................................................................................................................... 4
3.0 SCOPE OF WORK................................................................................................................ 4
4.0 SAFETY OBJECTIVE............................................................................................................9
5.0 APPENDIX............................................................................................................................ 9
Page 3 of 9
UIC-AFE12815-ENG-PRO-0503 Rev. 1
SAPI FIELD DEVELOPMENT
RECEIVER & LAUNCHER FACILITIES
1.0 GENERAL
This procedure describes the minimum requirement and scope of piping system for the
General Tie-in Procedure on Equipment and Piping System Facilities. The procedure applies
to all process and utility piping work including interconnecting piping between the facilities
and existing pipeline systems as necessary on Receiving and Launcher Pipeline Facilities for
SAPI Field Development to be supplied for UNOCAL Indonesia Company.
2.0 REFERENCES
The reference for the design verification as follows:
3.0 ANSI/ASME B31.3 Process Piping
4.0 Relevant ANSI / ASTM / API / other codes, standards and Unocal Specifications.
5.0 SCOPE OF WORK
The procedure describes the tie-in parameter and sequences to install the new process
piping system and interconnection to the Gas Handling Station Facilities (GHSF) and to
existing pipeline facilities gas and liquid pipeline with hot work, includes all such activities as
required of all materials and components as required.
5.1 Piping Tie-in List
COMPANY
o Make sure that the Ball Valve 12”D2R
has been tested before
o Remove existing 12” Blind Flange on
Ball Valve 12”D2R, which have already
installed by COMPANY
o Install SP-02-09 (12” Bleed Ring),
functional as the Double Block and
Bleed
o Continue to install Ball Valve 12”D2R
early close with existing Ball Valve
12”D2R
o Tight-up all flanges connection, make
sure that the gasket, bolt & nuts are
complete
o Continue to fit-up and install piping
spool for Line No. 216-D-12”
o Continue to fit-up and install pipe
support
2 02 o Make sure that the piping spool and Ball Line No. 116-
Valve 8”B2R at down-stream Line No. B-8”
116-B-8” have already installed by
COMPANY
o Make sure that the Ball Valve 8”B2R has
been tested before
o Remove existing 8” Blind Flange on Ball
Valve 8”B2R, which have already
installed by COMPANY
o Install SP-02-12 (8” Bleed Ring),
functional as the Double Block and
Bleed
o Continue to install Ball Valve 8”B2R
early close with existing Ball Valve
8”B2R
o Tight-up all flanges connection, make
sure that the gasket, bolt & nuts are
complete
o Continue to fit-up and install piping
spool for Line No. 116-B-8”
o Continue to fit-up and install pipe
support
3 03 o Make sure that the piping spool 356-A- Line No. 356-
2” at closed drain line to GHSF closed A-2”
drain header has been installed
o Make sure that the end connection of
closed drain line 356-A-2” has been
Page 6 of 9
UIC-AFE12815-ENG-PRO-0503 Rev. 1
SAPI FIELD DEVELOPMENT
RECEIVER & LAUNCHER FACILITIES
4 04 o Make sure that the piping spool 206-D- Line No. 206-
12” at down stream 12” Check Valve to D-12”
GHSF process header has been
installed
o Make sure that the end connection of
process line 206-D-12” has been
blinded with 12”-600# RF blind flange
o Remove 12”-600# blind flange, if the
GHSF process line has been installed
o Continue to fit-up and install the piping
spool process line tie-in to GHSF
5 05 o Make sure that the piping spool 407-A- Line No. 407-
2” at vent line to GHSF vent header has A-2”
been installed
o Make sure that the end connection of
vent line has been blinded with 2”-150#
RF blind flange
o Remove 2”-150# blind flange, if the
GHSF vent line has been installed
o Continue to fit-up and install the piping
spool vent line tie-in to GHSF
6 06 o Make sure that the piping spool 305-A- Line No. 305-
2” at open drain line to GHSF open A-2”
drain header has been installed
o Make sure that the end connection of
open drain line has been blinded with
2”-150# RF blind flange
o Remove 2”-150# blind flange, if the
GHSF open drain header has been
installed
o Continue to fit-up and install the piping
spool open drain line tie-in to GHSF
7 07 o Make sure that the piping spool 208-D- Line No. 208-
12” at gas line from GHSF Plant has D-12”
been installed
o Make sure that the end connection of
gas line has been blinded with 12”-600#
Page 7 of 9
UIC-AFE12815-ENG-PRO-0503 Rev. 1
SAPI FIELD DEVELOPMENT
RECEIVER & LAUNCHER FACILITIES
RF blind flange
o Remove 12”-600# blind flange, if the
gas line from GHSF Plant has been
installed
o Continue to fit-up and install the piping
spool gas line tie-in to GHSF
8 08 o Make sure that the piping spool 410-D- Line No. 410-
3” at vent line from GHSF has been D-3”
installed
o Make sure that the end connection of
gas line has been blinded with 3”-600#
RF blind flange
o Remove 3”- 600# blind flange, if the
vent line from GHSF has been installed
o Continue to fit-up and install the piping
spool gas line tie-in to GHSF
9
DELETED
10
11 11 o Make sure that the piping spool 110-B- Line No. 110-
6” at liquid line from GHSF has been B-6”
installed
o Make sure that the end connection of
liquid line has been blinded with 6”-
300# RF blind flange
o Remove 6”-300# blind flange, if the gas
line from GHSF has been installed
o Continue to fit-up and install the piping
spool liquid line tie-in to GHSF
12 DELETED
13 13 o Make sure that the piping spool 307-A- Line No. 307-
2” at open drain line from GHSF has A-2”
been installed
o Make sure that the end connection of
open drain line has been blinded with
2”-150# RF blind flange
o Remove 2”-150# blind flange, if the
open drain line from GHSF has been
installed
o Continue to fit-up and install the piping
spool open drain line tie-in to GHSF
14 14 o Make sure that the piping spool 360-A- Line No. 360-
2” at closed drain line from GHSF has A-2”
been installed
Page 8 of 9
UIC-AFE12815-ENG-PRO-0503 Rev. 1
SAPI FIELD DEVELOPMENT
RECEIVER & LAUNCHER FACILITIES
Cautions:
1. Never open or shut a valve
2. Never roll a spectacle blind or install a blind
3. Never open or close a drain valve
4. Never open or closed high point vent
5. Never hook-up stream or line to any system
6. Never shut down a steam or air line that is being used to clean a system
7.0 APPENDIX
7.1 PFD ESD and Spec Break, SPI-SPA-4013
7.2 P&ID Receiver and Launcher Facilities, SPI-SPA-4101
7.3 Tie-in List, UIC-AFE12815-ENG-LIS-0409
7.4 Isometric Drawings
Page 9 of 9
UIC-AFE12815-ENG-PRO-0503 Rev. 1