Professional Documents
Culture Documents
Client :- Century Addis Real Estate PLC Total Main Contract 8,414,655.00
Variation orders -
15 % VAT 1,262,198.25
Total 9,676,853.25
A. Advance Payment
ITEM Date Before VAT 15% VAT Total Amount
1 Main Contract 841,465.50 126,219.83 967,685.33 (A) Work Executed to Date #REF!
- -
- -
1 - - 2.Retention 5 % #REF!
2 - - 3.Rebate
3 - - 4.Penality
5.Advance Repayment for main contract
4 - - 125% #REF!
5 - -
8 - -
9 - -
10 - - VAT PAYMENT
11
Deduction
Total Amount (A+B) 841,465.50 126,219.83 967,685.33 15% VAT Payable in this payment #REF!
C. Advance Repayment
We certify that the contractor is now entitled to the sum of Birr 1,805,770.86 ( One Million Eight Hundred Five ThousandSeven Hundred Seventy and 86/100 birr only) .
1.01 - - -
a) to plastered internal wall,column and shear wall M2 19,782.00 7,032.70 - 7,032.70 45.00 890,190.00 316,471.50 - 316,471.50
b) to plastered soffits of stair casel,beams and ceiling M2 5,339.00 - 50.00 266,950.00 -
Fix gypsum board ceiling on concrete ceiling. Price shall include all
necessary works for the completion of the work .all according detail
drawing.( materail to be supplied by cleint
1.02 M2 23,599.00 3,020.26 6,933.12 9,953.38 235.00 5,545,765.00 709,761.10 100% 1,629,282.54 2,339,043.64
Fix 60*60cm perforated aluuminum suspended ceiling fixed to
1.03 concrete slab with suspension material for all wet areas M 2
1,261.00 - 110.00 138,710.00 -
02. Painting Works
- - -
3.01 Big corner list work labor and materail Ml 1.00 - 95.00 -
3.02 Big corner list work labor and materail Ml 1.00 - 85.00 -
3.03 Big corner list work labor and materail Ml 1.00 - 70.00 -
-
Deduction Column
1.02 , Fix gypsum board ceiling on
concrete ceiling. Price shall include ( 1-E), (1-F)& (1-G)
all necessary works for the -3 0.40 L= 0.4m
completion of the work .all according 1.40 H=1.4m
detail drawing. ( materail to be -1.68 m2
supplied by cleint on axis b/n 4-3&A-H
1 49.70 L= 49.7m
5.80 h= 5.8m
6 Floor
th
288.26 m2
Deduction Column
(4-B) (4-C) (4-D) (4-E), (,4-F)& (4-G)
-6 0.40 L= 0.4m
1 13.60 L= 13.60m 1.40 H=1.4m
5.80 H=5.8m -3.36 m2
78.88 m2 525.33 Total area of 12 th Floor only
Deduction Column Excuted Structure Work
( 1-B) 525.33 13th floor the same as 12th
-1 0.50 L= 0.5m 525.33 14th floor the same as 12th
1.50 H=1.5m 525.33 15th floor the same as 12th
-0.75 m2 525.33 16th floor the same as 12th
(1-C) 17th Floor
-1 0.35 L= 0.35m
1.50 H=1.5m b/n Axis A - B and 1' - 2
-0.52 m2
on axis b/n D-H& 1-2 1 13.60 L= 13.60m
5.80 H=5.8m
1 28.30 L= 28.3m 78.88 m2
5.80 H=5.8m Deduction Column
164.14 m2 ( 1-B)
Diduction Column -1 0.30 L= 0.3m
( 1-E), (1-F)& (1-G) 1.30 H=1.3m
-3 0.50 L= 0.5m -0.39 m2
1.50 H=1.5m (1-C)
-2.25 m2 -1 0.15 L= 0.15m
on axis b/n 4-3&A-H 1.30 H=1.3m
1 49.70 L= 49.7m -0.20 m2
5.80 h= 5.8m on axis b/n D-H& 1-2
288.26 m2
Diduction Column 1 28.30 L= 28.3m
(4-B) (4-C) (4-D) (4-E), (,4-F)& (4-G) 5.80 H=5.8m
-6 0.50 L= 0.5m 164.14 m2
1.50 H=1.5m Deduction Column
-4.5 m2 ( 1-E), (1-F)& (1-G)
(A,4) &(H,4) -3 0.30 L= 0.3m
523.255 Total area of 6th Floor only Excuted 1.30 H=1.3m
Structure Work -1.17 m2
523.26 7th floor the same as 6th on axis b/n 4-3&A-H
523.255 8th floor the same as 6th 1 49.70 L= 49.7m
523.255 9th floor the same as 6th 5.80 h= 5.8m
523.255 10th floor the same as 6th 288.26 m2
523.255 11th floor the same as 6th Diduction Column
(4-B) (4-C) (4-D) (4-E), (,4-F)& (4-G)
12th Floor -6 0.30 L= 0.3m
b/n Axis A - B and 1' - 2 1.30 H=1.3m
-2.34 m2
1 13.60 L= 13.60m 527.19 Total area of 17 th Floor only
5.80 H=5.8m Excuted Structure Work
78.88 m2
Deduction Column 527.19 18 th floor the same as 17th floor
( 1-B) 527.19 19 th floor the same as 17th floor
-1 0.40 L= 0.4m
1.40 H=1.4m Ceiling structur Work but
-0.56 m2 Demolishing Work
(1-C) 6th Floor
-1 0.25 L= 0.25m Axis 4'-3 b/n F-H
1.40 H=1.4m 1 13.20 L= 13.2m
-0.35 m2 5.70 H=5.7m
75.24 m2
on axis b/n D-H& 1-2 DDT Column 3-G&2-G
1 28.30 L= 28.3m -1 1.60 L= 1.6m
5.80 H=5.8m 0.60 H=0.6m
164.14 m2 -0.96 m2
1 1.8 L=1.8m
0.59 H=0.59m
1.06 m2 682.84 Total excuted area of 5th floor
1 3.35 L=3.35m
1.45 H=1.45m
4.86 m2
Total area of Ceiling Structure
Axis 4 b/n A-H 6933.12 excuted work work
1 49.7 L=49.7m
5.1 H=5.1m
253.47 m2
Axis 1 b/n A-C
1 13.6 L=13.6m
7.8 H=7.8m
106.08 m2
Axis 1 b/n D-H
1 28.5 L=28.5m
7.8 H=7.8m
222.30 m2
DDT column 1-B,1-D,1-E,-1F,1-G
-4 0.6 L=0.6m
1.6 H=1.6m
-3.84 m2
DDT column 1A,1C,1H
-1 0.45 L=0.45m
1.6 H=1.6m
-0.72 m2
a) to plastered internal wall,column and shear wall M2 19,782.00 7,032.70 - 7,032.70 45.00 890,190.00 316,471.50 - -
Fix gypsum board ceiling on concrete ceiling. Price shall include all
necessary works for the completion of the work .all according detail
1.02 drawing.( materail to be supplied by cleint M2 23,599.00 3,020.26 #REF! #REF! 235.00 5,545,765.00 709,761.10 100% #REF! #REF!
3.01 Big corner list work labor and materail Ml 1.00 - 95.00
3.02 Big corner list work labor and materail Ml 1.00 - 85.00
3.03 Big corner list work labor and materail Ml 1.00 - 70.00
-
Total Amount #REF! 8,414,655.00 1.00 #REF! #REF!