Professional Documents
Culture Documents
MONTH 1 (June 2023 - July 2023) MONTH 2 (July 2023 - August 2023) MONTH 3 (August 2023 - September 2023) MONTH 4 (September 2023 - October 2023) MONTH 5 (October 2023 - November 2023) MONTH 6 (November 2023 - December 2023) MONTH 7 (December 2023 - January 2024)
TOTAL PRICE W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31
NO. WORK DESCRIPTION Weight (%)
18-Jun 25-Jun 2-Jul 9-Jul 16-Jul 23-Jul 30-Jul 6-Aug 13-Aug 20-Aug 27-Aug 3-Sep 10-Sep 17-Sep 24-Sep 1-Oct 8-Oct 15-Oct 22-Oct 29-Oct 5-Nov 12-Nov 19-Nov 26-Nov 3-Dec 10-Dec 17-Dec 24-Dec 31-Dec 7-Jan 14-Jan
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
24-Jun 1-Jul 8-Jul 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 2-Dec 9-Dec 16-Dec 23-Dec 30-Dec 6-Jan 13-Jan 18-Jan
I CONSTRUCTION SMK NEGERI 8 PALU 5,131,118,000.00 30.521 0.054 0.081 0.108 0.134 0.134 0.391 0.548 0.548 0.815 1.334 1.305 1.450 1.511 1.576 1.597 1.918 1.831 1.714 1.657 1.682 1.815 1.653 1.518 1.121 1.020 0.956 0.934 0.402 0.332 0.243 0.139
0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
II CONSTRUCTION SMP NEGERI 14 PALU 5,242,761,000.00 31.185 0.040 0.060 0.080 0.100 0.120 0.157 0.906 0.692 1.318 1.143 1.381 1.491 1.502 1.526 1.495 1.466 1.506 1.413 1.435 1.443 1.625 1.434 1.431 1.522 1.454 0.801 1.475 0.982 0.462 0.372 0.356
0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
III CONSTRUCTION SD NEGERI 21 PALU 3,109,428,000.00 18.496 0.038 0.057 0.115 0.115 0.057 0.331 0.198 0.198 0.575 0.721 0.631 0.722 0.710 0.645 0.578 0.885 1.017 1.064 1.027 0.995 0.902 0.849 0.881 0.807 0.837 0.837 0.740 0.767 0.702 0.332 0.162
0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
IV CONSTRUCTION SD NEGERI PENGAWU 3,328,489,000.00 19.799 0.042 0.063 0.104 0.104 0.104 0.203 0.476 0.747 0.982 0.997 1.012 1.018 1.008 1.013 0.971 0.980 0.940 0.953 0.951 0.924 0.850 0.709 0.774 0.730 0.630 0.552 0.538 0.532 0.478 0.269 0.146
0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
TOTAL COST 16,811,796,000 100.000
Weekly Progress Plan 0.174 0.260 0.406 0.453 0.416 1.082 2.128 2.184 3.689 4.194 4.329 4.681 4.731 4.760 4.641 5.249 5.294 5.144 5.069 5.044 5.192 4.646 4.604 4.180 3.941 3.146 3.686 2.683 1.974 1.216 0.804
Cumulative Weekly Progress Plan 0.174 0.434 0.841 1.294 1.710 2.791 4.919 7.104 10.793 14.988 19.316 23.998 28.728 33.488 38.129 43.378 48.672 53.815 58.884 63.928 69.121 73.767 78.370 82.550 86.491 89.637 93.323 96.006 97.980 99.196 100.000
Weekly Progress Realization 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
Cumulative Weekly Progress Realization 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
Deviasi -0.174 -0.434 -0.841 -1.294 -1.710 -2.791 -4.919 -7.104 -10.793 -14.988 -19.316 -23.998 -28.728 -33.488 -38.129 -43.378 -48.672 -53.815 -58.884 -63.928 -69.121 -73.767 -78.370 -82.550 -86.491 -89.637 -93.323 -96.006 -97.980 -99.196 -100.000
Weight (%) Weight (%) Weight (%) Weight (%) Weight (%)
I LOT 1
A. SMK N 8 PALU 7.512 1.139 8.651 4.242 4.409
II LOT 2
A. SMP N 14 PALU 4.682 2.021 6.703 8.442 -1.739
III LOT 3
A. SDN 21 PALU 6.354 1.429 7.783 5.156 2.627
B. SDN PENGAWU 2.675 1.224 3.899 9.099 -5.200
Assignor : Supervision Consultant : Contractor :
III LOT 3 6,437,917,000.00 38.294 4.452 1.705 1.323 0.507 5.775 2.212
WEEKLY REPORT
Project : CONSTRUCTION OF SCHOOLS FACILITIES IN CENTRAL SULAWESI (LOT 1) Week : 7 (seven)
Contract No. : Ref.: 10057438 Period : 30 July 2023 - 05 August 2023
Location : SMK Negeri 8 Palu Weight Until Last Week : 7.512 %
Owner : United Nations Development Programme Weight This Week : 1.139 %
Contract Price : IDR 5,131,118,000 Weight Until This Week : 8.651 %
VI TEACHER OFFICE-C
A PREPARATION WORK 1.00 0.358
B ARCHITECTURAL WORKS 1.00 12.019
C. STRUCTURAL WORK 1.00 3.226
D. MECHANICAL AND ELECTRICAL WORKS 1.00 0.687
IX SITE PLAN
A SITEPLAN STRUCTURAL WORKS 1.00 0.056
B. SITEPLAN PLUMBING WORKS 1.00 2.807
C. SITE PLAN ELECTRICAL WORKS 1.00 0.811
WEEKLY REPORT
Project : CONSTRUCTION OF SCHOOLS FACILITIES IN CENTRAL SULAWESI (LOT 1) Week : 7 (seven)
Contract No. : Ref.: 10057438 Period : 30 July 2023 - 05 August 2023
Location : SMK Negeri 8 Palu Weight Until Last Week : 7.512 %
Owner : United Nations Development Programme Weight This Week : 1.139 %
Contract Price : IDR 5,131,118,000 Weight Until This Week : 8.651 %
I PREPARATION WORK
1 Project Safety Fencing m' 160.00 251,460.00 40,233,600.00 0.784 160.000 100.000 0.784 160.000 100.000 0.784
2 Project Signage Unit 1.00 474,732.50 474,732.50 0.009 1.000 100.000 0.009 1.000 100.000 0.009
3 Renovation Temporary Office Construction; Plaster Floor ls 1.00 13,342,332.72 13,342,332.72 0.260 1.000 100.000 0.260 1.000 100.000 0.260
4 Renovation Storage Construction & Bordinghouse ls 1.00 4,884,598.44 4,884,598.44 0.095 1.000 100.000 0.095 1.000 100.000 0.095
5 Mobilization, Demobilization of Personnel and Tools ls 1.00 5,000,000.00 5,000,000.00 0.097 0.200 20.000 0.019 0.200 20.000 0.019
6 HSE (Safety Net, Hat, Helmet,etc.) ls 1.00 10,175,000.00 10,175,000.00 0.198 0.200 20.000 0.040 0.200 20.000 0.040
7 Site Cleaning m2 2,110.00 4,158.00 8,773,380.00 0.171 2110.000 100.000 0.171 2110.000 100.000 0.171
8 Rebar Cleaning ls 1.00 7,500,000.00 7,500,000.00 0.146 0.800 80.000 0.117 0.800 80.000 0.117
Total Preparation Work Cost 90,383,643.66 1.761 1.496 1.496
D Door
Door and WindowFrame
Alumunium Installation Work (complete w. Aluminium frame)
1 Installation Work (type Unit 4.00 1,082,950.00 4,331,800.00 0.084
Leaf Door Instalation
2 P1)
Door Alumunium Unit 4.00 2,625,000.00 10,500,000.00 0.205
Work (type P1) Frame
3 Installation Work (type Unit 4.00 1,533,286.70 6,133,146.80 0.120
Leaf Door Instalation
P2)
4 Window Allumunium Unit 4.00 5,250,000.00 21,000,000.00 0.409
Work (type P2)
5 Frame Installation Work Unit 16.00 3,546,928.00 56,750,848.00 1.106
E (type J3)Works
Painting
1 Wall Painting; Interior m2 404.08 40,563.60 16,390,939.49 0.319
2 Wall Painting; Exterior m2 283.64 54,313.60 15,405,509.50 0.300
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
C STRUCTURAL WORK
I 1ST LEVEL
1 30/30 Column
- K-250 Concrete m3 12.14 1,226,720.35 14,888,091.52 0.290 12.136 100.000 0.290 12.136 100.000 0.290
- Reinforcement kg 178.78 16,006.10 2,861,568.49 0.056 178.780 100.000 0.056 178.780 100.000 0.056
- Column Formwork m2 161.82 275,300.00 44,549,046.00 0.868 161.820 100.000 0.868 161.820 100.000 0.868
2 20/20 Column
- K-250 Concrete m3 2.26 1,226,720.35 2,774,841.43 0.054
- Reinforcement kg 35.64 16,006.10 570,448.93 0.011 35.639 100.000 0.011 35.639 100.000 0.011
- Column Formwork m2 45.24 275,300.00 12,454,572.00 0.243 45.240 100.000 0.243 45.240 100.000 0.243
3 25/30 Tie Beam S1
- Concrete K-250 m3 7.64 1,226,720.35 9,366,009.87 0.183 7.635 100.000 0.183 7.635 100.000 0.183
- Tie Beam Formwork m2 14.16 195,085.00 2,762,403.60 0.054 7.080 50.000 0.027 7.080 50.000 0.027
4 20/25 Tie Beam S2
- Concrete K-250 m3 2.12 1,226,720.35 2,597,580.34 0.051 2.117 100.000 0.051 2.117 100.000 0.051
- Tie Beam Formwork m2 9.27 195,085.00 1,809,413.37 0.035 4.637 50.000 0.018 4.637 50.000 0.018
5 20/25 Beam B1
- Concrete K-250 m3 7.21 1,226,720.35 8,841,586.92 0.172
- Reinforcement kg 1240.96 16,006.10 19,862,891.99 0.387
- Beam Formwork m2 100.91 282,050.00 28,460,255.25 0.555
6 Floor Slab t=12 cm
- Concrete K-250 m3 40.20 1,226,720.35 49,314,158.04 0.961 40.200 100.000 0.961 40.200 100.000 0.961
- Formwork Floor m3 11.17 225,800.00 2,522,637.60 0.049 11.172 100.000 0.049 11.172 100.000 0.049
Total Structural Cost 203,635,505.34 3.969 2.466 0.290 2.756
- Concrete K-250 m3 2.12 1,226,720.35 2,597,580.34 0.051 1.694 80.000 0.040 1.694 80.000 0.040
- Tie Beam Formwork m2 9.27 195,085.00 1,809,413.37 0.035 4.637 50.000 0.018 4.637 50.000 0.018
6 20/25 Beam B1
- Concrete K-250 m3 7.21 1,226,720.35 8,841,586.92 0.172
- Reinforcement kg 1240.96 16,006.10 19,862,891.99 0.387
- Beam Formwork m2 100.91 282,050.00 28,460,255.25 0.555
7 Floor Slab t=12 cm
- Concrete K-250 m3 40.20 1,226,720.35 49,314,158.04 0.961 32.160 80.000 0.769 8.040 20.000 0.192 40.200 100.000 0.961
- Reinforcement wire ties m3 3116.59 16,006.10 49,884,490.41 0.972 3116.592 100.000 0.972 3116.592 100.000 0.972
- Formwork Floor m3 11.17 225,800.00 2,522,637.60 0.049 11.172 100.000 0.049 11.172 100.000 0.049
Total Structural Cost 253,479,073.02 4.940 2.021 0.192 2.214
B ARCHITECTURAL WORKS
I 1ST FLOOR
A WALLWORK
1 1/2 Brick Wall 1:5 m2 120.73 139,920.88 16,892,647.84 0.329
2 Mortar Plaster Work m2 469.86 67,316.74 31,629,445.34 0.616
3 Mortar Neat Plaster Work m2 469.86 42,427.00 19,934,750.22 0.389
4 Practical Column & Lintel Beam Work
- K250 Concrete m3 1.01 1,226,720.35 1,238,987.55 0.024
- Reinforcement kg 155.36 16,006.10 2,486,772.52 0.048
- Formwork m2 16.83 185,185.00 3,117,280.83 0.061
B Ceiling Installation Work
1 Ceiling Hollow frame m2 240.29 149,919.00 36,023,436.83 0.702
2 6 mm of Calcium Board GRC (Ceiling Interior) m2 140.18 72,230.40 10,125,257.47 0.197
3 6 mm of Calcium Board GRC (Ceiling Exterior) m2 100.11 72,230.40 7,230,696.42 0.141
C Floor Installation Work
1 Tile 40x40 cm (Polished) Rooms m2 135.53 162,962.80 22,086,348.28 0.430
2 Tile 40x40 cm (Unpolished) Hallway m2 35.96 166,262.80 5,979,475.34 0.117
D Door and Window Installation Work (complete w. Aluminium frame)
1 Door Alumunium Frame Installation Work (type P1) Unit 2.00 1,082,950.00 2,165,900.00 0.042
2 Leaf Door Instalation Work (type P1) Unit 2.00 2,625,000.00 5,250,000.00 0.102
3 Door Alumunium Frame Installation Work (type P2) Unit 2.00 1,533,286.70 3,066,573.40 0.060
4 Leaf Door Instalation Work (type P2) Unit 2.00 5,250,000.00 10,500,000.00 0.205
5 Window Allumunium Frame Installation Work (type J3) Unit 8.00 3,546,928.00 28,375,424.00 0.553
E Painting Works
1 Wall ; Interior m2 201.68 40,563.60 8,180,866.85 0.159
2 Wall Painting; Exterior m2 268.18 54,313.60 14,565,821.25 0.284
3 Ceiling Painting; Interior m2 140.18 40,563.60 5,686,205.45 0.111
4 Ceiling Painting; Exterior m2 100.11 54,313.60 5,437,117.24 0.106
5 Calsiplank Painting m2 19.28 54,313.60 1,047,383.46 0.020
F Other Works
1 Stair
- Retaining Wall 1 Pc : 5 Ps m2 6.48 139,920.88 906,687.30 0.018
- Landfill for floor elevation m3 0.97 163,075.00 158,508.90 0.003
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.18 912,325.16 164,218.53 0.003
- Chevron Works m 36.00 40,315.00 1,451,340.00 0.028
- Mortar Plaster Work m2 4.86 67,316.74 326,890.11 0.006
- Mortar Neat Plaster Work m2 4.86 42,427.00 206,025.51 0.004
B.2 ROOF WORKS
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
C STRUCTURAL WORK
I 1ST LEVEL
1 K1 Column 30/30
- K-250 Concrete m3 6.66 1,226,720.35 8,164,437.28 0.159
- Reinforcement kg 94.66 16,006.10 1,515,157.55 0.030
- Column Formwork m2 88.74 275,300.00 24,430,122.00 0.476
2 K2 Column 20/20
- K-250 Concrete m3 1.22 1,226,720.35 1,494,145.39 0.029
- Reinforcement kg 18.72 16,006.10 299,676.98 0.006
- Column Formwork m2 24.36 275,300.00 6,706,308.00 0.131
3 25/30 Tie Beam S1
- Concrete K-250 m3 4.10 1,226,720.35 5,023,419.83 0.098 4.095 100.000 0.098 4.095 100.000 0.098
- Tie Beam Formwork m2 9.30 195,085.00 1,814,290.50 0.035 4.650 50.000 0.018 4.650 50.000 0.018
4 20/25 Tie Beam S2
- Concrete K-250 m3 1.10 1,226,720.35 1,352,459.18 0.026 1.102 100.000 0.026 1.102 100.000 0.026
- Tie Beam Formwork m2 5.07 195,085.00 990,056.37 0.019 2.537 50.000 0.010 2.537 50.000 0.010
5 20/25 Beam B1
- Concrete K-250 m3 3.83 1,226,720.35 4,701,405.74 0.092
- Reinforcement kg 670.48 16,006.10 10,731,782.56 0.209
- Beam Formwork m2 53.66 282,050.00 15,133,392.75 0.295
6 Floor Slab t=12 cm
- Concrete K-250 m3 20.10 1,226,720.35 24,657,079.02 0.481 20.100 100.000 0.481 20.100 100.000 0.481
- Reinforcement kg 1031.59 16,006.10 16,511,723.90 0.322 1031.589 100.000 0.322 1031.589 100.000 0.322
- Floor Formwork m2 6.85 225,800.00 1,547,181.60 0.030 6.852 100.000 0.030 6.852 100.000 0.030
Total Structural Cost 125,072,638.65 2.438 0.984 0.984
B ARCHITECTURAL WORKS
I 1ST FLOOR
A WALLWORK
1 1/2 Brick Wall 1:5 m2 120.73 139,920.88 16,892,647.84 0.329
2 Mortar Plaster Work m2 469.86 67,316.74 31,629,445.34 0.616
3 Mortar Neat Plaster Work m2 469.86 42,427.00 19,934,750.22 0.389
4 Practical Column & Lintel Beam Work
- K250 Concrete m3 1.01 1,226,720.35 1,238,987.55 0.024
- Reinforcement kg 155.36 16,006.10 2,486,772.52 0.048
- Formwork m2 16.83 185,185.00 3,117,280.83 0.061
B Ceiling Installation Work
1 Ceiling Hollow frame m2 240.29 149,919.00 36,023,436.83 0.702
2 6 mm of Calcium Board GRC (Ceiling Interior) m2 140.18 72,230.40 10,125,257.47 0.197
3 6 mm of Calcium Board GRC (Ceiling Exterior) m2 100.11 72,230.40 7,230,696.42 0.141
C Floor Installation Work
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
C STRUCTURAL WORK
I 1ST FLOOR
1 K1 Column 30/30
- K-250 Concrete m3 6.66 1,226,720.35 8,164,437.28 0.159
- Reinforcement kg 104.13 16,006.10 1,666,726.35 0.032
- Column Formwork m2 88.74 275,300.00 24,430,122.00 0.476
2 K2 Column 20/20
- K-250 Concrete m3 1.21 1,226,720.35 1,483,840.93 0.029
- Reinforcement kg 22.18 16,006.10 354,936.44 0.007
- Column Formwork m2 24.36 275,300.00 6,706,308.00 0.131
3 25/30 Tie Beam S1
- Concrete K-250 m3 4.10 1,226,720.35 5,023,419.83 0.098
- Tie Beam Formwork m2 9.30 195,085.00 1,814,290.50 0.035 4.650 50.000 0.018 4.650 50.000 0.018
4 20/25 Tie Beam S2
- Concrete K-250 m3 1.10 1,226,720.35 1,352,459.18 0.026
- Tie Beam Formwork m2 5.07 195,085.00 990,056.37 0.019 2.537 50.000 0.010 2.537 50.000 0.010
5 20/25 Beam B1
- Concrete K-250 m3 3.83 1,226,720.35 4,701,405.74 0.092
- Reinforcement kg 670.48 16,006.10 10,731,782.56 0.209
- Beam Formwork m2 53.66 282,050.00 15,133,392.75 0.295
6 Floor Slab t=12 cm
- Concrete K-250 m3 20.10 1,226,720.35 24,657,079.02 0.481 7.035 35.000 0.168 7.035 35.000 0.168
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
- Reinforcement kg 1564.25 16,006.10 25,037,469.10 0.488 1564.245 100.000 0.488 1564.245 100.000 0.488
- Floor Formwork m2 6.85 225,800.00 1,547,181.60 0.030 6.852 100.000 0.030 6.852 100.000 0.030
Total Structural Cost 133,794,907.67 2.608 0.545 0.168 0.714
D CLASSROOM ELECTRICAL WORKS
D.1 LOW VOLTAGE PANEL WORKS
Procurement and
1 installation
MCB-BOX of of the
a complete
Classroom unit 4.00 1,124,332.00 4,497,328.00 0.088
Panel
D.2 LIGHTING WORKS
Procurement, installation of lighting and sockets
a. CLASSROOM A1 ( 4 ROOMS )
1 Roset Led 22 W Type Bulb unit 28.00 143,896.50 4,029,102.00 0.079
2 Single Electrical Switch unit 1.00 34,727.00 34,727.00 0.001
3 Double Electrical Switch unit 3.00 42,350.00 127,050.00 0.002
4 100 W Wall Electric Socket unit 8.00 49,929.00 399,432.00 0.008
5 Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 28.00 194,035.42 5,432,991.67 0.106
6 Electrical Socket NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 8.00 218,556.25 1,748,450.00 0.034
b. CLASSROOM B1 ( 2 ROOMS )
1 Roset Led 22 W Type Bulb unit 14.00 143,896.50 2,014,551.00 0.039
2 Single Electrical Switch unit 1.00 34,727.00 34,727.00 0.001
3 Double Electrical Switch unit 2.00 42,350.00 84,700.00 0.002
4 100 W Wall Electric Socket unit 4.00 49,929.00 199,716.00 0.004
5 Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 14.00 194,035.42 2,716,495.83 0.053
6 Electrical Socket NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 4.00 218,556.25 874,225.00 0.017
c. CLASSROOM A2 ( 4 ROOMS )
1 Roset Led 22 W Type Bulb unit 28.00 143,896.50 4,029,102.00 0.079
2 Single Electrical Switch unit 1.00 34,727.00 34,727.00 0.001
3 Double Electrical Switch unit 3.00 42,350.00 127,050.00 0.002
4 100 W Wall Electric Socket unit 8.00 49,929.00 399,432.00 0.008
5 Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 28.00 194,035.42 5,432,991.67 0.106
6 Electrical Socket NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 8.00 218,556.25 1,748,450.00 0.034
d. CLASSROOM B2 ( 2 ROOMS )
1 Roset Led 22 W Type Bulb unit 14.00 143,896.50 2,014,551.00 0.039
2 Single Electrical Switch unit 1.00 34,727.00 34,727.00 0.001
3 Double Electrical Switch unit 2.00 42,350.00 84,700.00 0.002
4 100 W Wall Electric Socket unit 4.00 49,929.00 199,716.00 0.004
5 Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 14.00 194,035.42 2,716,495.83 0.053
6 Electrical Socket NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 4.00 218,556.25 874,225.00 0.017
d. CLASSROOM A2 (4 ROOM)
1 Ø 3/4 30cm Air Terminal , Completed With Ø 3/4 70cm GIP set 6.00 442,541.00 2,655,246.00 0.052
2 BC 25 mm² Cable Installation m 48.00 75,065.83 3,603,160.00 0.070
3 600mm² x 600mm² c/w Junction Box with Grounding System set 1.00 948,398.00 948,398.00 0.018
4 Auxiliary Materials lot 1.00 720,680.40 720,680.40 0.014
Total Electrical Cost 65,462,286.36 1.276
VI TEACHER OFFICE-C
A PREPARATION WORK
1 Site Measurement and Bowplank Installation m' 66.00 278,630.00 18,389,580.00 0.358
PREPARATION 18,389,580.00 0.358
B ARCHITECTURAL WORKS
B.1 1ST FLOOR
I WALLWORK
1 Brick Wall 1:5 M2 191.45 139,920.88 26,788,412.16 0.522
2 Brick Wall 1:3 M2 77.23 139,920.88 10,805,949.64 0.211
3 Mortar Plaster Work M2 709.39 67,316.74 47,753,488.44 0.931
4 Mortar Neat Plaster Work M2 709.39 42,427.00 30,097,077.40 0.587
5 Practical Column & Lintel Beam Work
- K250 Concrete M3 3.63 1,226,720.35 4,450,541.43 0.087
- Reinforcement kg 542.33 16,006.10 8,680,650.20 0.169
- Formwork Kg 60.47 185,185.00 11,197,519.67 0.218
6 Wall Roster M2 3.86 565,882.90 2,182,044.46 0.043
7 Wall Tiles 25x40cm (Unpolished) M2 44.13 183,499.80 8,097,479.17 0.158
8 Table Pantry Wall Tiles 25x40cm (Polished) M2 1.13 180,474.80 203,034.15 0.004
9 Table Pantry Tiles 40x40cm (Polished) M3 2.13 162,962.80 346,295.95 0.007
II Floor Installation Work
1 Tile 40x40 cm (Polished) Rooms M2 92.85 162,962.80 15,130,607.09 0.295
2 Tile 40x40 cm (Unpolished) Hallway M2 47.46 166,262.80 7,891,165.01 0.154
3 Tile 40x40 cm (Unpolished) Toilet M2 18.88 166,262.80 3,139,706.72 0.061
4 Waterproofing Coating + mortar M2 18.88 119,614.62 2,258,802.41 0.044
III Sanitary Work and Installation
Sanitary work includes procurement & installation
1 Sitting Toilet Unit 3.00 3,699,704.80 11,099,114.40 0.216
2 Shower spray Unit 3.00 960,355.00 2,881,065.00 0.056
3 Floor Drain Unit 5.00 675,235.00 3,376,175.00 0.066
4 Washtafel Unit 2.00 3,723,830.00 7,447,660.00 0.145
5 Soap Dispenser Unit 2.00 165,275.00 330,550.00 0.006
6 6mm; uk 500x700 of mirror work Unit 2.00 126,379.00 252,758.00 0.005
7 Faucet Unit 5.00 746,652.50 3,733,262.50 0.073
8 Robe Hook Unit 3.00 334,235.00 1,002,705.00 0.020
9 Tissue Holder Unit 3.00 585,475.00 1,756,425.00 0.034
10 Kitchen zink Unit 1.00 743,336.00 743,336.00 0.014
IV Painting Works
1 Wall ; Interior M2 460.92 40,563.60 18,696,615.08 0.364
2 Wall Painting; Exterior M2 248.46 54,313.60 13,494,974.31 0.263
3 Ceiling Painting; Interior M2 149.87 40,563.60 6,079,347.86 0.118
4 Ceiling Painting; Exterior M2 143.25 54,313.60 7,780,531.83 0.152
5 Calsiplank Painting M2 22.23 54,313.60 1,207,174.07 0.024
V Door and Window Installation Work (complete w. Aluminium frame)
1 Door Alumunium Frame Installation Work (type P1) Unit 9.00 1,082,950.00 9,746,550.00 0.190
2 Leaf Door Instalation Work (type P1) Unit 9.00 2,625,000.00 23,625,000.00 0.460
3 Door Alumunium Frame Installation Work (type P2) Unit 3.00 1,533,286.70 4,599,860.10 0.090
4 Leaf Door Instalation Work (type P2) Unit 3.00 5,250,000.00 15,750,000.00 0.307
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
5 Door Alumunium Frame Installation Work (type P3) Unit 4.00 2,368,025.00 9,472,100.00 0.185
6 Door And Window Aluminium Installation Work (type PJ1) Unit 1.00 6,195,904.00 6,195,904.00 0.121
7 Partition M2 13.74 457,506.50 6,285,224.30 0.122
8 Window Installation Work (type J3) Unit 1.00 3,546,928.00 3,546,928.00 0.069
9 Window Installation Work (type J2) Unit 8.00 3,417,381.00 27,339,048.00 0.533
10 Window Installation Work (type V1) Unit 5.00 615,450.00 3,077,250.00 0.060
VI Ceiling Installation Work
1 Ceiling Hollow frame M2 293.12 149,919.00 43,944,856.96 0.856
2 6 mm of Calcium Board GRC (Ceiling Interior) m2 149.87 72,230.40 10,825,314.51 0.211
3 6 mm of Calcium Board GRC (Ceiling Exterior) m2 143.25 72,230.40 10,347,149.26 0.202
VII Other Works
1 Disability Ramp
- Disability Handrail Ramp work M1 14.10 760,976.98 10,729,014.37 0.209
- Lean Ramp 1 Pc : 3 Ps : 5 Kr M3 0.78 912,325.16 711,613.62 0.014
- Chevron Works M1 20.90 40,315.00 842,381.92 0.016
- Retaining Wall Ramp 1 Pc : 5 Ps M2 5.75 139,920.88 803,985.38 0.016
- Landfill for floor elevation M3 1.25 163,075.00 204,332.97 0.004
- Mortar Plaster Work M2 5.76 67,316.74 387,609.81 0.008
- Mortar Neat Plaster Work M2 5.76 42,427.00 244,294.67 0.005
2 Stair
- Retaining Wall 1 Pc : 5 Ps M2 8.02 139,920.88 1,122,445.30 0.022
- Landfill for floor elevation M3 1.42 163,075.00 231,240.35 0.005
- Lean Ramp 1 Pc : 3 Ps : 5 Kr M3 0.27 912,325.16 246,327.79 0.005
- Chevron Works M1 18.00 40,315.00 725,670.00 0.014
- Mortar Plaster Work M2 2.71 67,316.74 182,159.11 0.004
- Mortar Neat Plaster Work M2 2.71 42,427.00 114,807.46 0.002
B.2 ROOF WORKS
A Roof Covering Works
1 Zincalume Spandex h 0,40mm Installation M2 376.81 171,306.67 64,550,750.29 1.258
2 Light Steel Frame; including rafter and accessoris M2 376.81 213,420.90 80,419,983.01 1.567
3 Insulation layer / Aluminium Foil Installation M2 376.81 27,087.50 10,206,949.23 0.199
4 Roof Ridges Zincalum Spandex M1 40.49 73,810.00 2,988,493.09 0.058
5 Calsiplank M1 88.41 59,070.00 5,222,496.84 0.102
6 Roof Jalousie Unit 2.00 1,563,743.50 3,127,487.00 0.061
Total Architectural Cost 616,721,695.29 12.019
C. STRUCTURAL WORK
I FOUNDATION WORK
1 Tie Beam S1-25/30
- Concrete K-250 M3 6.68 1,226,720.35 8,197,558.73 0.160
- Reinforcement Kg 2.65 16,006.10 42,431.37 0.001
- Reinforcement wire ties m3 101.27 16,006.10 1,620,878.36 0.032
- Tie Beam Formwork M2 10.41 195,085.00 2,030,834.85 0.040
2 Tie Beam S2-20/25
- Concrete K-250 M3 1.90 1,226,720.35 2,332,302.06 0.045
- Reinforcement Kg 365.78 16,006.10 5,854,675.41 0.114
- Tie Beam Formwork M2 6.53 195,085.00 1,272,929.63 0.025
II 1ST LEVEL
1 K1 Column 30/30
- Concrete K-250 M3 7.83 1,226,720.35 9,605,220.33 0.187
- Reinforcement Kg 108.05 16,006.10 1,729,501.09 0.034
- Reinforcement wire ties m3 92.79 16,006.10 1,485,227.76 0.029
- Formwork Column M2 104.40 275,300.00 28,741,320.00 0.560
2 K2 Column 20/20
- Concrete K-250 M3 1.39 1,226,720.35 1,707,594.73 0.033
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
D. ELECTRICAL WORKS
D.1 LOW VOLTAGE PANEL WORKS
Procurement and installation
1 MCB-BOX of The Extra Curricullar Building unit 1.00 1,156,969.00 1,156,969.00 0.023
1 Ø 3/4 30cm Air Terminal , Completed With Ø 3/4 70cm GIP set 4.00 442,541.00 1,770,164.00 0.034
2 BC 25 mm² Cable Installation m 38.00 75,065.83 2,852,501.67 0.056
3 600mm² x 600mm² c/w Junction Box with Grounding System set 1.00 948,398.00 948,398.00 0.018
4 Auxiliary Materials lot 1.00 366,501.21 366,501.21 0.007
Total Mechanical And Electrical Cost 35,232,209.38 0.687
B ARCHITECTURAL WORKS
B.1 1ST FLOOR
A WALLWORK
1Brick Wall 1:5 M2 46.48 139,920.88 6,503,522.50 0.127
2Brick Wall 1:3 M2 33.19 139,920.88 4,643,414.32 0.090
3Mortar Plaster Work M2 222.35 67,316.74 14,967,608.76 0.292
4Mortar Neat Plaster Work M2 222.35 42,427.00 9,433,473.74 0.184
5Practical Column & Lintel Beam Work
- K250 Concrete M3 1.42 1,226,720.35 1,735,809.29 0.034
- Reinforcement Kg 213.36 16,006.10 3,415,134.60 0.067
- Formwork M2 23.58 185,185.00 4,367,279.58 0.085
6 Wall Roster M2 2.88 565,882.90 1,629,742.75 0.032
7 Wall Tiles 25x40cm (Unpolished) M2 15.68 183,499.80 2,877,276.86 0.056
B Ceiling Installation Work
1 Ceiling Hollow frame M2 102.48 149,919.00 15,363,699.12 0.299
2 6 mm of Calcium Board GRC (Ceiling Interior) m2 27.30 72,230.40 1,971,889.92 0.038
3 6 mm of Calcium Board GRC (Ceiling Exterior) m2 75.18 72,230.40 5,430,281.47 0.106
C Floor Installation Work
1 Tiles 40x40 cm (Polished) M2 43.28 162,962.80 7,053,029.98 0.137
2 Tiles 40x40 cm (Unpolished) M2 7.72 166,262.80 1,283,548.82 0.025
D Door and Window Installation Work (complete w. Aluminium frame)
1 Door Alumunium Frame Installation Work (type P1) Unit 2.00 1,082,950.00 2,165,900.00 0.042
2 Leaf Door Instalation Work (type P1) Unit 2.00 2,625,000.00 5,250,000.00 0.102
3 Door Alumunium Frame Installation Work (type P2) Unit 1.00 1,533,286.70 1,533,286.70 0.030
4 Leaf Door Instalation Work (type P2) Unit 1.00 5,250,000.00 5,250,000.00 0.102
5 Door Alumunium Frame Installation Work (type P3) Unit 2.00 2,368,025.00 4,736,050.00 0.092
6 Window Installation Work (type J1) Unit 2.00 2,539,878.00 5,079,756.00 0.099
7 Window Installation Work (type J2) Unit 4.00 2,928,090.00 11,712,360.00 0.228
8 Window Installation Work (type V1) Unit 2.00 615,450.00 1,230,900.00 0.024
E Sanitary Work and Installation
Sanitary work includes procurement & installation
1 Sitting Toilet Unit 2.00 3,699,704.80 7,399,409.60 0.144
2 Shower spray Unit 2.00 960,355.00 1,920,710.00 0.037
3 Floor Drain Unit 2.00 675,235.00 1,350,470.00 0.026
4 Robe Hook Unit 2.00 334,235.00 668,470.00 0.013
5 Faucet Unit 6.00 746,652.50 4,479,915.00 0.087
F Painting Works
1 Wall ; Interior M2 75.71 40,563.60 3,070,907.90 0.060
2 Wall Painting; Exterior M2 146.64 54,313.60 7,964,546.30 0.155
3 Ceiling Painting; Interior M2 27.30 40,563.60 1,107,386.28 0.022
4 Ceiling Painting; Exterior M2 75.18 54,313.60 4,083,296.45 0.080
5 Calsiplank Painting M2 15.12 54,313.60 821,449.75 0.016
G Other Works
1 Railling for Disability access
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
- Formwork Column M 2
54.91 275,300.00 15,117,273.60 0.295
3 S1 25/30 Tie Beam
- Concrete K-250 M 3
1.38 1,226,720.35 1,692,874.08 0.033
- Reinforcement Kg 318.51 16,006.10 5,098,120.91 0.099
- Tie Beam Formwork M2 11.04 195,085.00 2,153,738.40 0.042
4 S2 20/25 Tie Beam
- Concrete K-250 M3 1.60 1,226,720.35 1,960,299.12 0.038
- Reinforcement Kg 324.91 16,006.10 5,200,476.43 0.101
- Tie Beam Formwork M2 15.98 195,085.00 3,117,458.30 0.061
5 B1 20/25 Beam
- Concrete K-250 M3 2.59 1,226,720.35 3,179,659.15 0.062
- Reinforcement Kg 514.35 16,006.10 8,232,811.65 0.160
- Beam Formwork M2 36.29 282,050.00 10,235,030.40 0.199
6 Floor Slab h=12 cm
- K-250 Concrete M3 5.31 1,226,720.35 6,507,996.80 0.127
- Reinforcement Kg 491.87 16,006.10 7,872,894.16 0.153
- Floor Formwork M2 3.70 225,800.00 834,556.80 0.016
- Sand layer t=10cm M3 3.64 192,830.00 702,094.03 0.014
- Base Concrete t=5cm M3 1.82 912,325.16 1,660,887.95 0.032
Total Structural Cost 135,787,010.43 2.646 0.193 0.193
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3
0.78 912,325.16 711,613.62 0.014
- Retaining Wall Ramp 1 Pc : 5 Ps m2 5.75 139,920.88 803,985.38 0.016
- Landfill for floor elevation m3 1.25 163,075.00 204,332.97 0.004
- Mortar Plaster Work m2 5.76 67,316.74 387,609.81 0.008
- Mortar Neat Plaster Work m2 5.76 42,427.00 244,294.67 0.005
2 Stair
- Retaining Wall 1 Pc : 5 Ps m2 3.24 139,920.88 453,343.65 0.009
- Landfill for floor elevation m3 0.49 163,075.00 79,254.45 0.002
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.09 912,325.16 82,109.26 0.002
- Chevron Works m 18.00 40,315.00 725,670.00 0.014
- Mortar Plaster Work m2 2.43 67,316.74 163,445.05 0.003
- Mortar Neat Plaster Work m2 2.43 42,427.00 103,012.76 0.002
B.2 ROOF WORKS
A Roof Covering Works
1 Zincalume Spandex H. 0,30 mm Installation m2 113.01 171,306.67 19,360,051.63 0.377
2 Light Steel Frame; including rafter and accessoris m2 113.01 213,420.90 24,119,549.59 0.470
3 Aluminium Foil Installation m2 113.01 27,087.50 3,061,266.73 0.060
4 Roof Ridges, Zincalum Spandex m 30.09 73,810.00 2,220,795.28 0.043
5 Calsiplank m 38.50 59,070.00 2,274,195.00 0.044
Total Architectural Cost 210,986,332.35 4.112
C STRUCTURAL WORK
I FOUNDATION WORK
1 Foundation PD1
- Backfill m3 6.90 62,150.00 428,959.30 0.008
II 1ST LEVEL
1 K1 Column 20/20
- K-250 Concrete m3 2.24 1,226,720.35 2,742,946.70 0.053
- Reinforcement kg 455.87 16,006.10 7,296,729.82 0.142
- Column Formwork m2 44.20 275,300.00 12,168,260.00 0.237
2 K2 Column 15/20
- K-250 Concrete m3 0.52 1,226,720.35 632,987.70 0.012
- Reinforcement kg 142.35 16,006.10 2,278,485.67 0.044
-Column Formwork m2 11.90 275,300.00 3,276,070.00 0.064
3 20/25 Tie Beam S1
- Concrete K-250 m3 2.19 1,226,720.35 2,686,517.56 0.052
- Reinforcement kg 402.44 16,006.10 6,441,419.17 0.126
- Tie Beam Formwork m2 21.90 195,085.00 4,272,361.50 0.083
4 15/20 Tie Beam S2
- Concrete K-250 m3 0.42 1,226,720.35 512,462.43 0.010
- Reinforcement kg 130.78 16,006.10 2,093,321.48 0.041
- Tie Beam Formwork m2 5.57 195,085.00 1,086,623.45 0.021
5 15/20 Beam B1
- Concrete K-250 m3 1.81 1,226,720.35 2,221,897.23 0.043
- Reinforcement kg 496.92 16,006.10 7,953,819.27 0.155
- Beam Formwork m2 33.21 282,050.00 9,365,822.81 0.183
6 Floor Slab h=12 cm
- Concrete K-250 m3 5.28 1,226,720.35 6,477,083.44 0.126
- Reinforcement kg 459.12 16,006.10 7,348,718.71 0.143
- Floor Formwork m2 3.58 225,800.00 807,460.80 0.016
- Sand layer t=10cm m3 4.40 192,830.00 848,452.00 0.017
- Base Concrete t=5cm m3 2.20 912,325.16 2,007,115.35 0.039
Total Structural Cost 82,947,514.40 1.617
IX SITE PLAN
A SITEPLAN STRUCTURAL WORKS
1.1 STRUCTURAL FOUNDATION TOWER WATER TANK
a. Foundation Footplat
- Foundation Cutting m3 1.12 27,610.00 30,812.76 0.001
- Backfill m3 0.73 62,150.00 45,493.80 0.001
- Concrete K-250 m3 0.29 1,226,720.35 353,295.46 0.007
- Reinforcement kg 11.54 16,006.10 184,724.48 0.004
- Formwork m2 1.92 185,185.00 355,555.20 0.007
- Sand layer t=10cm m3 0.07 192,830.00 13,883.76 0.000
- Base Concrete t=5cm m3 0.07 912,325.16 65,687.41 0.001
b. 20/20 Column
- Concrete K-250 m3 0.10 1,226,720.35 117,765.15 0.002
- Reinforcement kg 13.31 16,006.10 213,067.85 0.004
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
B Infiltration
- Soil Exavation m3 1.22 105,435.00 128,103.53 0.002
- Brick Wall 1 Pc : 3 Ps m2 5.40 147,363.92 795,765.17 0.016
- Sand Layer m3 0.48 192,830.00 92,558.40 0.002
- Gravel m3 0.48 429,330.00 206,078.40 0.004
Total Infiltration-2 Cost 1,222,505.49 0.024
WEEKLY REPORT
: Project : CONSTRUCTION OF SCHOOLS FACILITIES IN CENTRAL SULAWESI (LOT 2) Week : 7 (seven)
Contract No. : Ref.: 10057438 Period : 30 July 2023 - 05 August 2023
Location : SMP Negeri 14 Palu Weight Until Last Week : 4.682 %
Owner : United Nations Development Programme Weight This Week : 2.021 %
Contract Price : IDR 5,242,761,000 Weight Until This Week : 6.703 %
VI TOILET 6 ROOMS-E
A PREPARATION WORK 1.00 0.013 100.000 0.013 100.000 0.013
B ARCHITECTURAL WORKS 1.00 3.688
C STRUCTURAL WORK 1.00 1.505
D. MECHANICAL AND ELECTRICAL WORKS 1.00 0.345
X CONNECTING CORRIDOR -
A Connecting Corridor 1.00 0.654
TOTAL LOT 2 100.000 4.682 2.021 6.703
Plan 8.442 Realization 6.703 Deviation (1.739)
WEEKLY REPORT
: Project : CONSTRUCTION OF SCHOOLS FACILITIES IN CENTRAL SULAWESI (LOT 2) Week : 7 (seven)
Contract No. : Ref.: 10057438 Period : 30 July 2023 - 05 August 2023
Location : SMP Negeri 14 Palu Weight Until Last Week : 4.682 %
Owner : United Nations Development Programme Weight This Week : 2.021 %
Contract Price : IDR 5,242,761,000 Weight Until This Week : 6.703 %
I PREPARATION WORK
1 Project Safety Fencing M1 70.00 251,460.00 17,602,200.00 0.336
2 Project Signage Unit 1.00 474,732.50 474,732.50 0.009 1.000 100.000 0.009 1.000 100.000 0.009
3 Renovastion Temporary Office Construction Ls 1.00 14,683,944.00 14,683,944.00 0.280 1.000 100.000 0.280 1.000 100.000 0.280
4 Renovation Storage Construction & Bordinghouse Ls 1.00 5,738,238.00 5,738,238.00 0.109 0.650 65.000 0.071 0.650 65.000 0.071
5 Mobilization, Demobilization of Personnel and Tools Ls 1.00 5,000,000.00 5,000,000.00 0.095 0.200 20.000 0.019 0.200 20.000 0.019
6 HSE (Safety Net, Hat, Helmet,etc.) Ls 1.00 10,175,000.00 10,175,000.00 0.194 0.200 20.000 0.039 0.200 20.000 0.039
7 Site Cleaning M 2
1,419.00 4,158.00 5,900,202.00 0.113 1419.000 100.000 0.113 1419.000 100.000 0.113
8 Rebar Cleaning Ls 1.00 7,500,000.00 7,500,000.00 0.143 0.650 65.000 0.093 0.650 65.000 0.093
Total Preparation Work Cost 67,074,316.50 1.279 0.624 0.624
II CLASSROOM 9X8 (4 ROOMS)-A
A PREPARATION WORK
1 Site Measurement M1 92.00 22,990.00 2,115,080.00 0.040 46.000 50.000 0.020 46.000 50.000 0.020 92.000 100.000 0.040
2 Demolition of Tie Beam Formwork M2 32.71 24,970.00 816,768.70 0.016 8.000 24.457 0.004 24.710 75.543 0.012 32.710 100.000 0.016
PREPARATION 2,931,848.70 0.056 0.024 0.032 0.056
B ARCHITECTURAL WORKS
B.1 1ST LEVEL
I. WALLWORK
1 1/2 Brick Wall 1:5 M2 254.66 139,920.88 35,632,251.30 0.680 68.758 27.000 0.184 68.758 27.000 0.184
2 Mortar Plaster Work M2 687.72 67,316.74 46,295,071.18 0.883
3 Mortar Neat Plaster Work M 2
687.72 42,427.00 29,177,896.44 0.557
4 Practical Column & Lintel Beam Work -
- K250 Concrete M 3
2.57 1,226,720.35 3,147,764.42 0.060
- Reinforcement Kg 399.17 16,006.10 6,389,182.51 0.122
- Formwork M2 42.77 185,185.00 7,919,745.17 0.151
II. Ceiling Installation Work -
1 Ceiling Hollow frame M2 453.07 149,919.00 67,923,801.33 1.296
2 6 mm of Calcium Board GRC (Ceiling Interior) M2 280.36 72,230.40 20,250,514.94 0.386
3 6 mm of Calcium Board GRC (Ceiling Exterior) M2 172.71 72,230.40 12,474,912.38 0.238
III. Floor Installation Work -
1 Tile 40x40 cm (Polished) Rooms M2 282.15 162,962.80 45,979,628.09 0.877
2 Tile 40x40 cm (Unpolished) Hallway M2 70.53 166,262.80 11,726,182.76 0.224
IV. Door and Window Installation Work -
1 Door Alumunium Frame Installation Work (type P1) Unit 4.00 1,082,950.00 4,331,800.00 0.083
2 Leaf Door Instalation Work (type P1) Unit 4.00 2,625,000.00 10,500,000.00 0.200
3 Door Alumunium Frame Installation Work (type P2) Unit 4.00 1,533,286.70 6,133,146.80 0.117
4 Leaf Door Instalation Work (type P2) Unit 4.00 5,250,000.00 21,000,000.00 0.401
5 Window Allumunium Frame Installation Work (type J3) Unit 16.00 3,546,928.00 56,750,848.00 1.082
V. Painting Works -
1 Wall Painting; Interior M2 404.08 40,563.60 16,390,939.49 0.313
2 Wall Painting; Exterior M2 283.64 54,313.60 15,405,509.50 0.294
3 Ceiling Painting; Interior M2 280.36 40,563.60 11,372,410.90 0.217
4 Ceiling Painting; Exterior M2 172.71 54,313.60 9,380,501.86 0.179
5 Calsiplank Painting M2 30.40 54,313.60 1,650,916.19 0.031
VI. Other Works -
1 Railling for Disability access -
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
V Painting Works -
1 Wall ; Interior M2 310.86 40,563.60 12,609,438.44 0.241
2 Wall Painting; Exterior M2 428.32 54,313.60 23,263,492.52 0.444
3 Ceiling Painting; Interior M2 208.77 40,563.60 8,468,462.77 0.162
4 Ceiling Painting; Exterior M 2
139.19 54,313.60 7,559,909.98 0.144
5 Calsiplank Painting M 2
28.28 54,313.60 1,535,988.61 0.029
B.3 ROOF WORKS -
I Roof Covering Works -
1 Zincalume Spandex h 0,30 mm Installation M2 449.90 171,306.67 77,070,869.33 1.470
2 Light Steel Frame; including rafter and accessoris M2 449.90 213,420.90 96,018,062.91 1.831
3 Aluminium Foil Installation M2 449.90 27,087.50 12,186,666.25 0.232
4 Roof Ridges, Zincalum Spandex M1 42.29 73,810.00 3,121,424.90 0.060
5 Calsiplank M1 98.36 59,070.00 5,810,125.20 0.111
6 Roof Jalousie Unit 2.00 1,563,743.50 3,127,487.00 0.060
Total Architectural Cost 906,086,658.61 17.283
C STRUCTURAL WORK
I FOUNDATION WORK
1 Caison Foundation Ø140 cm
- Foundation Cutting M3 415.94 105,435.00 43,854,423.03 0.836
- Caison Formwork M2 422.02 185,185.00 78,151,032.96 1.491
- Reinforcement Kg 1,911.47 16,006.10 30,595,173.46 0.584
- Concrete Case Caison Ready Mix (K-300) M 3
42.20 2,211,061.94 93,310,351.50 1.780
- Concrete Cyclop Caison M3 21.98 1,271,133.63 27,939,517.30 0.533
- Concrete Ready Mix (K-300) Caison M3 21.99 2,211,061.94 48,611,523.35 0.927
- Angkur D16 Kg 410.09 16,006.10 6,563,939.65 0.125
- Backfill M3 40.35 62,150.00 2,507,752.50 0.048
2 PC1-Pile Cap Foundation 2000x2000x400 mm -
- Concrete Ready Mix K-300 M3 28.80 2,211,061.94 63,678,583.83 1.215
- Reinforcement Kg 2,821.92 16,006.10 45,167,886.75 0.862
- Formwork M2 57.60 185,185.00 10,666,656.00 0.203
- Sand Layer T=10 cm M3 0.36 192,830.00 69,418.80 0.001
- Base Concrete T=5 cm M3 0.18 912,325.16 164,218.53 0.003
3 PC2-Pile Cap Foundation 1500x1500x400 mm -
- Concrete Ready Mix K-300 M 3
9.00 2,211,061.94 19,899,557.45 0.380
- Reinforcement Kg 943.92 16,006.10 15,108,461.93 0.288
- Formwork M2 24.00 185,185.00 4,444,440.00 0.085
- Sand Layer T=10 cm M 3
0.11 192,830.00 21,596.96 0.000
- Base Concrete T=5 cm M3 0.06 912,325.16 51,090.21 0.001
4 Column Pedestal K1-45/50 -
- Concrete Ready Mix K-300 M3 4.61 2,211,061.94 10,198,523.19 0.195
- Reinforcement Kg 1,044.13 16,006.10 16,712,465.46 0.319
- Column Formwork M2 38.95 275,300.00 10,722,935.00 0.205
5 Column Pedestal K2-45/45 -
- Concrete Ready Mix K-300 M3 6.23 2,211,061.94 13,768,006.31 0.263
- Reinforcement Kg 1,398.13 16,006.10 22,378,632.11 0.427
- Column Formwork M2 55.35 275,300.00 15,237,855.00 0.291
6 Column Pedestal K3-30/45 -
- Concrete Ready Mix K-300 M 3
0.83 2,211,061.94 1,835,734.17 0.035
- Reinforcement Kg 186.10 16,006.10 2,978,804.49 0.057
- Column Formwork M2 9.23 275,300.00 2,539,642.50 0.048
II GROUND FLOOR -
1 Column K1-45/50 Ev. ±0,00 -
- Concrete Ready Mix K-300 M3 8.10 2,211,061.94 17,909,601.70 0.342
- Reinforcement Kg 1,804.93 16,006.10 28,889,826.57 0.551
- Column Formwork M2 68.40 275,300.00 18,830,520.00 0.359
2 Column K2-45/45 Ev. ±0,00 -
- Concrete Ready Mix K-300 M3 10.94 2,211,061.94 24,177,962.30 0.461
- Reinforcement Kg 2,441.84 16,006.10 39,084,337.74 0.745
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
Bordes Stairs -
- Concrete Ready Mix K-300 M3 0.32 2,211,061.94 700,995.08 0.013
- Reinforcement Kg 60.68 16,006.10 971,185.00 0.019
- Formwork M2 3.19 295,300.00 941,416.40 0.018
III SECOND FLOOR -
1 Column K1-45/50 Ev. +3,60 -
- Concrete Ready Mix K-300 M 3
8.10 2,211,061.94 17,909,601.70 0.342
- Reinforcement Kg 1,804.93 16,006.10 28,889,826.57 0.551
- Column Formwork M2 68.40 275,300.00 18,830,520.00 0.359
2 Column K2-45/45 Ev. +3,60 -
- Concrete Ready Mix K-300 M3 10.94 2,211,061.94 24,177,962.30 0.461
- Reinforcement Kg 2,441.84 16,006.10 39,084,337.74 0.745
- Column Formwork M2 97.20 275,300.00 26,759,160.00 0.510
3 Column K3-30/45 Ev. +3,60 -
- Concrete Ready Mix K-300 M3 1.46 2,211,061.94 3,223,728.31 0.061
- Reinforcement Kg 310.56 16,006.10 4,970,812.26 0.095
- Column Formwork M2 16.20 275,300.00 4,459,860.00 0.085
4 Beam RB1 (200x350) Ev. +7,20 -
- Concrete Ready Mix K-300 M 3
7.83 2,211,061.94 17,315,378.80 0.330
- Reinforcement Kg 1,600.94 16,006.10 25,624,774.94 0.489
- Beam Formwork M2 100.69 282,050.00 28,398,909.37 0.542
5 Beam RB 2 (200x350) Ev. +6,27 -
- Concrete Ready Mix K-300 M3 1.22 2,211,061.94 2,700,812.16 0.052
- Reinforcement Kg 275.72 16,006.10 4,413,175.52 0.084
- Beam Formwork M2 15.70 282,050.00 4,429,595.25 0.084
6 2nd Floor Slab H=12 cm Ev. +3,60 -
- Concrete Ready Mix K-300 M3 29.76 2,211,061.94 65,801,468.61 1.255
- Reinforcement Kg 3,159.12 16,006.10 50,565,251.22 0.964
- Floor Slab Formwork M2 248.00 295,300.00 73,234,695.30 1.397
7 2nd Roof Slab Stair H=10 cm Ev. +6,27 -
- Concrete Ready Mix K-300 M3 2.19 2,211,061.94 4,842,446.75 0.092
- Reinforcement Kg 214.04 16,006.10 3,425,987.82 0.065
- Floor Slab Formwork M2 21.90 295,300.00 6,467,365.30 0.123
Total Structural Cost 1,668,258,669.91 31.820
IV CLASSROOM 8X9 (2 ROOMS)-C
A PREPARATION WORK
1 Site Measurement m' 56.00 22,990.00 1,287,440.00 0.025 28.000 50.000 0.012 28.000 50.000 0.012 56.000 100.000 0.025
PREPARATION 1,287,440.00 0.025 0.012 0.012 0.025
B ARCHITECTURAL WORKS
B.1 1ST LEVEL
I. WALLWORK
1 1/2 Brick Wall 1:5 M2 155.16 139,920.88 21,709,564.06 0.414 93.094 60.000 0.248 93.094 60.000 0.248
2 Mortar Plaster Work M2 469.86 67,316.74 31,629,445.34 0.603
3 Mortar Neat Plaster Work M2 469.86 42,427.00 19,934,750.22 0.380
4 Practical Column & Lintel Beam Work -
- K250 Concrete M3 1.01 1,226,720.35 1,238,987.55 0.024
- Reinforcement Kg 155.36 16,006.10 2,486,772.52 0.047
- Formwork M2 16.83 185,185.00 3,117,280.83 0.059
II. Ceiling Installation Work -
1 Ceiling Hollow frame M 2
240.29 149,919.00 36,023,436.83 0.687
2 6 mm of Calcium Board GRC (Ceiling Interior) M 2
140.18 72,230.40 10,125,257.47 0.193
3 6 mm of Calcium Board GRC (Ceiling Exterior) M2 100.11 72,230.40 7,230,696.42 0.138
III. Floor Installation Work -
1 Tile 40x40 cm (Polished) Rooms M2 135.53 162,962.80 22,086,348.28 0.421
2 Tile 40x40 cm (Unpolished) Hallway M2 35.96 166,262.80 5,979,475.34 0.114
IV. Door and Window Installation Work -
1 Door Alumunium Frame Installation Work (type P1) Unit 2.00 1,082,950.00 2,165,900.00 0.041
2 Leaf Door Instalation Work (type P1) Unit 2.00 2,625,000.00 5,250,000.00 0.100
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
3 Door Alumunium Frame Installation Work (type P2) Unit 2.00 1,533,286.70 3,066,573.40 0.058
4 Leaf Door Instalation Work (type P2) Unit 2.00 5,250,000.00 10,500,000.00 0.200
5 Window Allumunium Frame Installation Work (type J1) Unit 8.00 2,539,878.00 20,319,024.00 0.388
V. Painting Works -
1 Wall Painting; Interior M 2
201.68 40,563.60 8,180,866.85 0.156
2 Wall Painting; Exterior M 2
268.18 54,313.60 14,565,821.25 0.278
3 Ceiling Painting; Interior M2 140.18 40,563.60 5,686,205.45 0.108
4 Ceiling Painting; Exterior M 2
110.22 54,313.60 5,986,553.62 0.114
5 Calsiplank Painting M2 19.28 54,313.60 1,047,383.46 0.020
VI. Other Works -
1 Stair -
- Retaining Wall 1 Pc : 5 Ps M2 6.48 139,920.88 906,687.30 0.017
- Landfill for floor elevation M3 0.97 163,075.00 158,508.90 0.003
- Lean Ramp 1 Pc : 3 Ps : 5 Kr M3 0.18 912,325.16 164,218.53 0.003
- Chevron Works M1 36.00 40,315.00 1,451,340.00 0.028
- Mortar Plaster Work M2 4.86 67,316.74 326,890.11 0.006
- Mortar Neat Plaster Work M2 4.86 42,427.00 206,025.51 0.004
B.2 ROOF WORKS -
Roof Covering Works -
1 Zincalume Spandex h 0,30 mm Installation M 2
324.55 171,306.67 55,597,578.67 1.060
2 Light Steel Frame; including rafter and accessoris M 2
324.55 213,420.90 69,265,753.10 1.321
3 Aluminium Foil Installation M2 324.55 27,087.50 8,791,248.13 0.168
4 Roof Ridges, Zincalum Spandex M1 34.88 73,810.00 2,574,492.80 0.049
5 Calsiplank H. 0,8 mm M1 80.31 59,070.00 4,744,029.84 0.090
6 Roof Jalousie Unit 2.00 1,563,743.50 3,127,487.00 0.060
Total Architectural Cost 385,644,602.77 7.356 0.248 0.248
C STRUCTURAL WORK
1 K1 Column 30/30
- K-250 Concrete Ready Mix M3 6.66 2,161,230.23 14,384,067.81 0.274 6.655 100.000 0.274 6.655 100.000 0.274
- Reinforcement Kg 9.47 16,006.10 151,568.80 0.003 9.469 100.000 0.003 9.469 100.000 0.003
- Column Formwork M2 88.74 275,300.00 24,430,122.00 0.466 88.740 100.000 0.466 88.740 100.000 0.466
2 K2 Column 20/20 -
- K-250 Concrete Ready Mix M 3
1.20 2,161,230.23 2,602,121.20 0.050 1.204 100.000 0.050 1.204 100.000 0.050
- Column Formwork M2 24.08 275,300.00 6,629,224.00 0.126 24.080 100.000 0.126 24.080 100.000 0.126
3 25/30 Tie Beam S1 -
- K-250 Concrete Ready Mix M 3
4.10 2,161,230.23 8,850,237.80 0.169 4.095 100.000 0.169 4.095 100.000 0.169
- Tie Beam Formwork M2 32.76 195,085.00 6,390,984.60 0.122 16.380 50.000 0.061 16.380 50.000 0.061
4 20/25 Tie Beam S2 -
- K-250 Concrete Ready Mix M3 1.10 2,161,230.23 2,382,756.33 0.045 1.102 100.000 0.045 1.102 100.000 0.045
- Tie Beam Formwork M2 11.02 195,085.00 2,150,812.12 0.041 5.512 50.000 0.021 5.512 50.000 0.021
5 20/25 Beam B1 -
- K-250 Concrete Ready Mix M3 3.83 2,161,230.23 8,282,914.86 0.158
- Reinforcement Kg 670.48 16,006.10 10,731,782.56 0.205
- Beam Formwork M2 53.66 282,050.00 15,133,392.75 0.289
6 Floor Slab t=12 cm -
- K-250 Concrete Ready Mix M3 20.10 2,161,230.23 43,440,727.66 0.829 20.100 100.000 0.829 20.100 100.000 0.829
- Floor Formwork M2 6.85 225,800.00 1,547,181.60 0.030 6.852 100.000 0.030 6.852 100.000 0.030
Total Structural Cost 147,107,894.10 2.806 2.073 2.073
D CLASSROOM ELECTRICAL WORKS
D.1 LOW VOLTAGE PANEL WORKS
Procurement and installation of a complete Panel
MCB-BOX of the Classroom unit 4.00 1,124,332.00 4,497,328.00 0.086
D.2 LIGHTING WORKS -
Procurement, installation of lighting and sockets -
a. CLASSROOM A ( 4 ROOMS ) -
1 Roset Led 22 W Type Bulb unit 28.00 143,896.50 4,029,102.00 0.077
2 Single Electrical Switch unit 1.00 34,727.00 34,727.00 0.001
3 Double Electrical Switch unit 4.00 42,350.00 169,400.00 0.003
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
- Foundation Cutting M3 22.66 105,435.00 2,388,735.36 0.046 22.656 100.000 0.046 22.656 100.000 0.046
- Backfill M3 16.29 62,150.00 1,012,299.20 0.019
- K-250 Concrete Ready Mix M3 4.80 2,161,230.23 10,373,905.11 0.198
- Reinforcement Kg 546.11 16,006.10 8,741,162.36 0.167
- Formwork Foundation M 2
19.20 185,185.00 3,555,552.00 0.068
- Sand Layer T=10 cm M 3
1.60 192,830.00 308,528.00 0.006
- Base Concrete T=5 cm M 3
0.80 912,325.16 729,860.13 0.014
2 PD2 Broken Stone Foundation -
- Foundation Cutting M3 8.54 105,435.00 900,836.64 0.017 8.544 100.000 0.017 8.544 100.000 0.017
- Sand Layer T=10 cm M3 2.10 192,830.00 404,943.00 0.008
- Masonry 1:4 M3 7.94 756,723.00 6,011,407.51 0.115
- Aanstamping Stone T=15 cm M3 3.15 332,739.00 1,048,127.85 0.020
- Backfill M3 2.28 62,150.00 141,702.00 0.003
3 PD3 Broken Stone Foundation -
- Foundation Cutting M3 9.60 105,435.00 1,012,281.44 0.019 9.601 100.000 0.019 9.601 100.000 0.019
- Sand Layer T=10 cm M3 2.27 192,830.00 438,456.85 0.008
- Masonry 1:4 M3 8.32 756,723.00 6,297,448.81 0.120
- Aanstamping Stone T=15 cm M3 3.41 332,739.00 1,134,872.91 0.022
- Backfill M 3
2.42 62,150.00 150,278.70 0.003
4 Tie Beam S1 - 20/25 -
- K-250 Concrete Ready Mix M 3
2.80 2,161,230.23 6,051,444.65 0.115
- Reinforcement Kg 484.44 16,006.10 7,754,007.38 0.148
- Tie Beam Formwork M2 28.00 195,085.00 5,462,380.00 0.104
5 Tie Beam S2 - 15/20 -
- K-250 Concrete Ready Mix M3 0.25 2,161,230.23 546,791.25 0.010
- Reinforcement Kg 57.82 16,006.10 925,432.04 0.018
- Tie Beam Formwork M2 1.69 195,085.00 329,043.37 0.006
II. STRUCTURAL WORK -
1 Column K1- 20/20 -
- K-250 Concrete Ready Mix M3 3.41 2,161,230.23 7,365,472.63 0.140
- Reinforcement Kg 712.36 16,006.10 11,402,079.02 0.217
- Formwork Column M2 68.16 275,300.00 18,764,448.00 0.358
2 Beam B1 - 20/25 -
- K-250 Concrete Ready Mix M 3
2.52 2,161,230.23 5,446,300.18 0.104
- Reinforcement Kg 412.74 16,006.10 6,606,386.81 0.126
- Formwork Column M2 35.28 275,300.00 9,712,584.00 0.185
3 Floor Slab T = 12 cm -
- Base Concrete T=5 cm m3 3.56 912,325.16 3,244,045.80 0.062
- Sand layer T=10 cm m3 7.11 192,830.00 1,371,329.83 0.026
- K-250 Concrete Ready Mix m3 8.56 2,161,230.23 18,495,808.32 0.353
- Reinforcement kg 739.89 16,006.10 11,842,683.30 0.226
- Floor Formwork m2 4.32 225,800.00 975,456.00 0.019
Total Structural Cost 160,946,090.45 3.070 0.082 0.08
D. MECHANICAL AND ELECTRICAL WORKS
1 UKS ROOM PLUMBING WORKS
1.1 CLEAN WATER SYSTEM
Procurement and installation of PVC Pipes including excavation, accessories, and auxiliary equipment
A Toilet and Clean Water Piping and Its Completeness
1 PVC AW Ø 25 mm m 10.00 28,026.63 280,266.25 0.005
2 PVC AW Ø 20 mm m 1.00 23,892.00 23,892.00 0.000
3 Fitting ls 1.00 43,076.83 43,076.83 0.001
4 Gate Valve Ø 32mm unit 1.00 126,610.00 126,610.00 0.002
1.2 VENT AND GREY WATER SYSTEM -
Procurement and installation of PVC Pipes including excavation, accessories, and auxiliary tool -
A Grey Water Piping and Its completeness in toilet to Sepictank.1 -
1 PVC-AW Ø 100 mm; SW (Sewage Water) m 13.00 185,950.88 2,417,361.38 0.046
2 PVC-AW Ø 80 mm; WW (Waste Water) m 12.00 123,292.13 1,479,505.50 0.028
3 Floor Clean Out Ø 80 mm, WW (Waste Water) bh 1.00 230,725.00 230,725.00 0.004
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
4 Floor Clean Out Ø 100 mm, SW (Sewage Water) bh 1.00 340,263.00 340,263.00 0.006
5 Fitting ls 1.00 446,785.49 446,785.49 0.009
D. UKS ELECTRICAL WORKS -
D.1 LOW VOLTAGE PANEL WORKS -
Procurement and installation -
MCB-BOX of The Extra Curricullar Building unit 1.00 930,149.00 930,149.00 0.018
D.2 LIGHTING WORKS -
Procurement and installation -
A UKS ELECTRICAL WORKS -
1 Roset Led 22 W Type Bulb unit 8.00 143,896.50 1,151,172.00 0.022
2 Roset Led 5 W Type Bulb (toilet and antrance) unit 2.00 69,399.00 138,798.00 0.003
3 Single Electrical Switch unit 4.00 34,727.00 138,908.00 0.003
4 Double Electrical Switch unit 1.00 42,350.00 42,350.00 0.001
5 200 W Wall Electric Socket unit 5.00 49,929.00 249,645.00 0.005
6 Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 10.00 194,035.42 1,940,354.17 0.037
7 Electrical Socket NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 5.00 218,556.25 1,092,781.25 0.021
D.3 Lightning Rod Installation -
Procurement and installation -
1 Ø 3/4 30cm Air Terminal , Completed With Ø 3/4 70cm GIP set 1.00 442,541.00 442,541.00 0.008
2 BC 25 mm² Cable Installation m 20.00 75,065.83 1,501,316.67 0.029
3 600mm² x 600mm² c/w Junction Box with Grounding System set 1.00 948,398.00 948,398.00 0.018
4 Auxiliary Materials lot 1.00 366,501.21 366,501.21 0.007
Total Mechanical And Electrical Cost 14,331,399.73 0.273
VI TOILET 6 ROOMS-E
A PREPARATION WORK
1 Site Measurement M1 29.00 22,990.00 666,710.00 0.013 29.000 100.000 0.013 29.000 100.000 0.013
PREPARATION 666,710.00 0.013 0.013 0.013
B ARCHITECTURAL WORKS
A WALLWORK
1 Brick Wall 1:3 M2 73.77 147,363.92 10,871,036.38 0.207
2 Mortar Plaster Work M2 124.71 67,316.74 8,395,071.14 0.160
3 Mortar Neat Plaster Work M2 124.71 42,427.00 5,291,071.17 0.101
4 Practical Column & Lintel Beam Work -
- K250 Concrete M 3
0.39 1,226,720.35 473,514.05 0.009
- Reinforcement Kg 59.38 16,006.10 950,390.29 0.018
- Formwork M2 6.43 185,185.00 1,191,356.83 0.023
5 Wall Tiles Work 25x40 cm (Unpolished) M 2
88.54 183,499.80 16,247,439.29 0.310
B Ceiling Installation Work -
1 Ceiling Hollow frame M2 64.97 149,919.00 9,739,637.75 0.186
2 6 mm of Calcium Board GRC (Ceiling Interior) M2 16.38 72,230.40 1,183,206.18 0.023
3 6 mm of Calcium Board GRC (Ceiling Exterior) M2 48.59 72,230.40 3,509,313.98 0.067
C Floor Installation Work -
1 40x40 cm of Ceramic Tile (Unpolished) Hallway M2 35.80 166,262.80 5,952,041.98 0.114
2 40x40 cm of Ceramic Tile (Unpolished) Rooms M2 15.55 162,962.80 2,534,071.54 0.048
3 Waterproofing Coating + Mortar M2 15.55 119,614.62 1,860,007.28 0.035
D Door and Window Installation Work (complete w. alluminium frame) -
1 Door Allumunium Frame Installation Work (type P4) Difabel Unit 1.00 2,585,000.00 2,585,000.00 0.049
2 Door Allumunium Frame Installation Work (type P3) Unit 5.00 2,368,025.00 11,840,125.00 0.226
E Sanitary Work and Installation -
Sanitary work includes procurement & installation -
1 Squatting Closet Unit 5.00 1,306,646.00 6,533,230.00 0.125
2 Sitting Closet Unit 1.00 3,699,704.80 3,699,704.80 0.071
3 Shower Spray Unit 1.00 960,355.00 960,355.00 0.018
4 Wastafel Hang Unit 5.00 3,723,830.00 18,619,150.00 0.355
5 Floor Drain Unit 6.00 675,235.00 4,051,410.00 0.077
6 Tissue Holder Unit 1.00 585,475.00 585,475.00 0.011
7 Soap Dispenser Unit 3.00 165,275.00 495,825.00 0.009
8 Robe Hook Unit 6.00 334,235.00 2,005,410.00 0.038
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
WEEKLY REPORT
Project : CONSTRUCTION OF SCHOOLS FACILITIES IN CENTRAL SULAWESI (LOT 3) Week : 7 (seven)
Contract No. : Ref.: 10057438 Period : 30 July 2023 - 05 August 2023
Location : SD Negeri 21 Palu Weight Until Last Week : 4.452 %
Owner : United Nations Development Programme Weight This Week : 1.323 %
Contract Price : IDR 6,437,917,000 Weight Until This week Week : 5.775 %
IV TEACHER'S OFFICE -B
A PREPARATION WORK 1.00 0.173
B ARCHITECTURAL WORKS 1.00 3.580
C. STRUCTURAL WORK 1.00 2.467
D. MECHANICAL AND ELECTRICAL WORKS 1.00 0.176
V LIBRARY 8x7 -C
A PREPARATION WORK 1.00 0.138
B ARCHITECTURAL WORKS 1.00 3.216
C. STRUCTURAL WORK 1.00 2.490
D. LIBRARY ELECTRICAL WORKS 1.00 0.118
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION VOLUME / UNIT Weight (%)
Physic (%) Weight (%) Physic (%) Weight (%) Physic (%) Weight (%)
VI MUSHOLA 8x7 -D
A PREPARATION WORK 1.00 0.130
B ARCHITECTURAL WORKS 1.00 3.073
C. STRUCTURAL WORK 1.00 2.308
D. MECHANICAL AND ELECTRICAL WORKS 1.00 0.165
IX SITE PLAN
A SITEPLAN STRUCTURAL WORKS 1.00 0.046
B SITEPLAN PLUMBING WORKS 1.00 0.551
C. SITE PLAN ELECTRICAL WORKS 1.00 0.450
VI MUSHOLA 10x9-C
A PREPARATION WORK 0.0828
B ARCHITECTURAL WORKS 3.5670
C. STRUCTURAL WORK 1.9898 2.738 0.054 11.570 0.230 14.308 0.285
D. MECHANICAL AND ELECTRICAL WORKS 0.1775
IX TOILET 6 ROOMS-D1
A PREPARATION WORK 0.1290
B ARCHITECTURAL WORKS 3.3730
C STRUCTURAL WORK 0.9485
D. MECHANICAL AND ELECTRICAL WORKS 0.3793
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION VOLUME / UNIT Weight (%)
Physic (%) Weight (%) Physic (%) Weight (%) Physic (%) Weight (%)
X SITE PLAN
A SITEPLAN STRUCTURAL WORKS 0.0447
B. SITEPLAN PLUMBING WORKS 1.1675
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION VOLUME / UNIT Weight (%)
Physic (%) Weight (%) Physic (%) Weight (%) Physic (%) Weight (%)
WEEKLY REPORT
Project : CONSTRUCTION OF SCHOOLS FACILITIES IN CENTRAL SULAWESI (LOT 3) Week : 7 (seven)
Contract No. : Ref.: 10057438 Period : 30 July 2023 - 05 August 2023
Location : SD Negeri 21 Palu Weight Until Last Week : 6.354 %
Owner : United Nations Development Programme Weight This Week : 1.429 %
Contract Price : IDR 3,109,428,000 Weight Until This week Week : 7.783 %
I PREPARATION WORK
1 Project Safety Fencing m' 50.00 251,460.00 12,573,000.00 0.404 30.000 60.000 0.243 30.000 60.000 0.243
2 Project Signage Unit 1.00 474,732.50 474,732.50 0.015 1.000 100.000 0.015 1.000 100.000 0.015
3 Renovation Temporary Office Construction; Plaster Floor ls 1.00 18,354,930.00 18,354,930.00 0.590 0.750 75.000 0.443 0.750 75.000 0.443
4 Renovation Storage Construction & Bordinghouse ls 1.00 5,738,238.00 5,738,238.00 0.185 1.000 100.000 0.185 1.000 100.000 0.185
5 Mobilization, Demobilization of Personnel and Tools ls 1.00 5,000,000.00 5,000,000.00 0.161 0.500 50.000 0.080 0.500 50.000 0.080
6 HSE (Safety Net, Hat, Helmet,etc.) ls 1.00 10,175,000.00 10,175,000.00 0.327 0.750 75.000 0.245 0.750 75.000 0.245
7 Site Cleaning m2 1,089.00 4,158.00 4,528,062.00 0.146 816.750 75.000 0.109 816.750 75.000 0.109
8 Rebar Cleaning ls 1.00 7,500,000.00 7,500,000.00 0.241 0.700 70.000 0.169 0.700 70.000 0.169
Total Preparation Work Cost 64,343,962.50 2.069 1.489 1.489
C STRUCTURAL WORK
I FOUNDATION WORK
1 Tie Beam 25/30
- Concrete K-250 m3 5.12 1,226,720.35 6,274,674.59 0.202 5.115 100.000 0.202 5.115 100.000 0.202
- Reinforcement kg 25.15 16,006.10 402,566.74 0.013
- Tie Beam Formwork m2 40.92 195,085.00 7,982,878.20 0.257 18.960 46.334 0.119 18.960 46.334 0.119
2 Tie Beam 20/25
- Concrete K-250 m3 1.46 1,226,720.35 1,791,011.71 0.058 1.460 100.000 0.058 1.460 100.000 0.058
- Reinforcement kg 5.43 16,006.10 86,984.70 0.003
- Tie Beam Formwork m2 14.60 195,085.00 2,848,241.00 0.092 7.075 48.459 0.044 7.075 48.459 0.044
II 1ST LEVEL
1 30/30 Column
- K-250 Concrete m3 9.40 1,226,720.35 11,526,264.40 0.371 9.396 100.000 0.371 9.396 100.000 0.371
- Reinforcement kg 287.34 16,006.10 4,599,254.30 0.148 287.344 100.000 0.148 287.344 100.000 0.148
- Column Formwork m2 125.28 275,300.00 34,489,584.00 1.109 125.280 100.000 1.109 125.280 100.000 1.109
2 20/20 Column
- K-250 Concrete m3 1.72 1,226,720.35 2,109,959.00 0.068 1.720 100.000 0.068 1.720 100.000 0.068
- Reinforcement kg 32.19 16,006.10 515,310.64 0.017 32.195 100.000 0.017 32.195 100.000 0.017
- Column Formwork m2 34.40 275,300.00 9,470,320.00 0.305 34.400 100.000 0.305 34.400 100.000 0.305
3 20/25 Beam
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
- Concrete K-250 m3 4.87 1,226,720.35 5,974,128.10 0.192 4.870 100.000 0.192 4.870 100.000 0.192
- Reinforcement kg 843.36 16,006.10 13,498,938.69 0.434 843.362 100.000 0.434 843.362 100.000 0.434
- Beam Formwork m2 68.18 282,050.00 19,230,169.00 0.618 68.180 100.000 0.618 68.180 100.000 0.618
4 Floor Slab h=12 cm
- Base Concrete t=5cm m3 2.61 912,325.16 2,384,361.80 0.077 2.614 100.000 0.077 2.614 100.000 0.077
- Sand layer t=10cm m3 5.23 192,830.00 1,007,922.41 0.032 5.227 100.000 0.032 5.227 100.000 0.032
- Concrete K-250 m3 23.79 1,226,720.35 29,186,621.24 0.939 23.792 100.000 0.939 23.792 100.000 0.939
- Reinforcement kg 1,894.27 16,006.10 30,319,878.73 0.975 1808.687 95.482 0.931 1808.687 95.482 0.931
- Floor Formwork m2 8.05 225,800.00 1,818,141.60 0.058 8.052 100.000 0.058 8.052 100.000 0.058
Total Structural Cost 185,517,210.85 5.966 4.477 1.245 5.721
- Chevron Works m 2
20.90 40,315.00 842,381.92 0.027
- Retaining Wall Ramp 1 Pc : 3 Ps : 5 Kr m2 5.75 139,920.88 803,985.38 0.026
- Landfill for floor elevation m3 1.25 163,075.00 204,332.97 0.007
- Mortar Plaster Work m2 5.76 67,316.74 387,609.81 0.012
- Mortar Neat Plaster Work m2 5.76 42,427.00 244,294.67 0.008
2 Stair
- Retaining Wall 1 Pc : 5 Ps m2 6.48 139,920.88 906,687.30 0.029
- Landfill for floor elevation m3 0.97 163,075.00 158,508.90 0.005
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.18 912,325.16 164,218.53 0.005
- Chevron Works m1 13.20 40,315.00 532,158.00 0.017
- Mortar Plaster Work m2 4.86 67,316.74 326,890.11 0.011
- Mortar Neat Plaster Work m2 4.86 42,427.00 206,025.51 0.007
B.2 ROOF WORKS
I Roof Covering Works
1 Zincalume Spandex H. 0,30 mm Installation m2 377.00 171,306.67 64,582,270.72 2.077
2 Light Steel Frame; including rafter and accessoris m2 377.00 213,420.90 80,459,252.46 2.588
3 Aluminium Foil Installation m2 377.00 27,087.50 10,211,933.33 0.328
4 Calsiplank 30x0,80 cm m 88.96 59,070.00 5,254,749.06 0.169
5 Roof Ridges, Zincalum Spandex m 37.97 73,810.00 2,802,860.94 0.090
6 Roof Jalousie Unit 2.00 1,563,743.50 3,127,487.00 0.101
Total Architectural Cost 491,894,984.12 15.819
C STRUCTURAL WORK
I FOUNDATION WORK
1 PD1 Foundation
- Backfill m3 22.07 62,150.00 1,371,650.50 0.044
2 PD1A Foundation
- Backfill m3 12.55 62,150.00 779,982.50 0.025
3 PD2 Foundation
- Backfill m3 1.61 62,150.00 100,061.50 0.003
4 PD4 Foundation
- Backfill m3 2.11 62,150.00 131,385.10 0.004
5 PD5 Foundation
- Backfill m3 2.69 62,150.00 167,183.50 0.005
6 Tie Beam 25/30
- Concrete K-250 m3 5.12 1,226,720.35 6,274,674.59 0.202
- Reinforcement kg 933.95 16,006.10 14,948,871.12 0.481 753.621 80.692 0.388 753.621 80.692 0.388
- Tie Beam Formwork m2 40.92 195,085.00 7,982,878.20 0.257
7 Tie Beam 20/25
- Concrete K-250 m3 1.46 1,226,720.35 1,791,011.71 0.058
- Reinforcement kg 263.61 16,006.10 4,219,310.78 0.136 263.606 100.000 0.136 263.606 100.000 0.136
- Tie Beam Formwork m2 12.85 195,085.00 2,506,842.25 0.081
II 1ST LEVEL
1 30/30 Column
- K-250 Concrete m3 9.40 1,226,720.35 11,526,264.40 0.371
- Reinforcement kg 118.08 16,006.10 1,889,961.93 0.061
- Column Formwork m2 125.28 275,300.00 34,489,584.00 1.109
2 20/20 Column
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
IV TEACHER'S OFFICE -B
A PREPARATION WORK
1 Site Measurement and Bowplank Intallation m' 40.00 278,630.00 11,145,200.00 0.358
PREPARATION 11,145,200.00 0.358
B ARCHITECTURAL WORKS
B.1 1ST LEVEL
I. WALLWORK
1 Brick Wall 1:5 m2 94.55 139,920.88 13,229,379.28 0.425
2 Brick Wall 1:3 m2 20.69 147,363.92 3,048,664.78 0.098
3 Mortar Plaster Work m2 289.28 67,316.74 19,473,387.70 0.626
4 Mortar Neat Plaster Work m2 289.28 42,427.00 12,273,282.56 0.395
5 Practical Column & Lintel Beam Work
- K250 Concrete m3 1.39 1,226,720.35 1,705,141.29 0.055
- Reinforcement kg 207.79 16,006.10 3,325,827.94 0.107
- Formwork m2 23.17 185,185.00 4,290,119.17 0.138
6 Wall Tiles 25x40cm (Unpolished) m2 16.09 183,499.80 2,952,511.78 0.095
II. Ceiling Installation Work
1 Ceiling Hollow frame m2 102.09 149,919.00 15,305,230.71 0.492
2 6 mm of Calcium Board GRC (Ceiling Interior) m2 46.63 72,230.40 3,368,103.55 0.108
3 6 mm of Calcium Board GRC (Ceiling Exterior) m2 55.46 72,230.40 4,005,897.98 0.129
III. Floor Installation Work
1 Tile 40x40 cm (Polished) Rooms m2 37.99 162,962.80 6,190,956.77 0.199
2 Tile 40x40 cm (Unpolished) Hallway m2 16.63 166,262.80 2,764,950.36 0.089
3 Tile 40x40 cm (Unpolished) Toilet m2 2.40 166,262.80 399,030.72 0.013
4 Waterproofing Coating + mortar m2 2.40 119,614.62 287,075.08 0.009
IV. Door and Window Installation Work (complete w. alluminium frame)
1 Door Alumunium Frame Installation Work (type P1) Unit 4.00 1,082,950.00 4,331,800.00 0.139
2 Leaf Door Instalation Work (type P1) Unit 4.00 2,625,000.00 10,500,000.00 0.338
3 Door Alumunium Frame Installation Work (type P2) Unit 1.00 1,533,286.70 1,533,286.70 0.049
4 Leaf Door Instalation Work (type P2) Unit 1.00 5,250,000.00 5,250,000.00 0.169
5 Door Alumunium Frame Installation Work (type P3) Unit 1.00 2,368,025.00 2,368,025.00 0.076
6 Window Installation Work (type J2) Unit 7.00 3,417,381.00 23,921,667.00 0.769
7 Window Installation Work (type V1) Unit 2.00 615,450.00 1,230,900.00 0.040
V. Sanitary Work and Installation
Sanitary work includes
procurement & installation
1 Sitting Closed Unit 1.00 3,699,704.80 3,699,704.80 0.119
2 Shower spray Unit 1.00 960,355.00 960,355.00 0.031
3 Floor Drain Unit 1.00 675,235.00 675,235.00 0.022
4 Robe hook Unit 1.00 334,235.00 334,235.00 0.011
5 Tissue Holder Unit 1.00 585,475.00 585,475.00 0.019
6 Faucet Unit 1.00 746,652.50 746,652.50 0.024
VI. Painting Works
1 Wall Painting; Interior m2 167.60 40,563.60 6,798,459.36 0.219
2 Wall Painting; Exterior m2 121.68 54,313.60 6,608,878.85 0.213
3 Ceiling Painting; Interior m2 46.63 40,563.60 1,891,480.67 0.061
4 Ceiling Painting; Exterior m2 55.46 54,313.60 3,012,232.26 0.097
5 Calsiplank Painting m2 12.66 54,313.60 687,610.18 0.022
VII Other Works
1 Stair
- Retaining Wall 1 Pc : 5 Ps m2 6.48 139,920.88 906,687.30 0.029
- Landfill for floor elevation m3 0.97 163,075.00 158,508.90 0.005
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.18 912,325.16 164,218.53 0.005
- Chevron Works m1 13.20 40,315.00 532,158.00 0.017
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
C. STRUCTURAL WORK
I FOUNDATION WORK
1 Foundation PD1
- Foundation Cutting m3 33.30 105,435.00 3,510,985.50 0.113
- Backfill m3 29.84 62,150.00 1,854,804.60 0.060
- Concrete K-250 m3 3.46 1,226,720.35 4,239,545.53 0.136
- Reinforcement kg 395.82 16,006.10 6,335,474.94 0.204
- Formwork m2 11.52 185,185.00 2,133,331.20 0.069
- Sand layer t=10cm m3 1.15 192,830.00 222,140.16 0.007
- Base Concrete t=5cm m3 0.58 912,325.16 525,499.29 0.017
2 Foundation PD1A
- Foundation Cutting m3 9.38 105,435.00 988,927.58 0.032
- Backfill m3 8.48 62,150.00 527,000.93 0.017
- Concrete K-250 m3 0.90 1,226,720.35 1,104,048.31 0.036
- Reinforcement kg 112.37 16,006.10 1,798,662.26 0.058
- Formwork m2 3.60 185,185.00 666,666.00 0.021
- Sand layer t=10cm m3 0.30 192,830.00 57,849.00 0.002
- Base Concrete t=5cm m3 0.15 912,325.16 136,848.77 0.004
3 PD2 Broken Stone Foundation
- Foundation Cutting m3 30.78 105,435.00 3,245,289.30 0.104
- Sand layer t=10cm m3 3.24 192,830.00 624,769.20 0.020
- Masonry 1:4 m3 16.59 756,723.00 12,551,764.40 0.404
- Aanstamping Stone H=15cm m3 4.86 332,739.00 1,617,111.54 0.052
- Backfill m3 10.71 62,150.00 665,626.50 0.021
4 PD3 Broken Stone Foundation
- Foundation Cutting m3 21.80 105,435.00 2,298,483.00 0.074
- Sand layer t=10cm m3 7.59 192,830.00 1,463,579.70 0.047
- Masonry 1:4 m3 5.81 756,723.00 4,399,587.52 0.141
- Aanstamping Stone H=15cm m3 3.44 332,739.00 1,144,622.16 0.037
- Backfill m3 7.59 62,150.00 471,718.50 0.015
5 PD4 Broken Stone Foundation
- Foundation Cutting m3 11.54 105,435.00 1,216,983.49 0.039
- Sand layer t=10cm m3 1.21 192,830.00 234,288.45 0.008
- Masonry 1:4 m3 6.86 756,723.00 5,192,160.27 0.167
- Aanstamping Stone H=15cm m3 1.82 332,739.00 606,416.83 0.020
- Backfill m3 4.02 62,150.00 249,609.94 0.008
6 Soil fill m3 1.20 128,715.71 154,922.23 0.005
II 1ST LEVEL
1 K1 30/30 Column
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
V LIBRARY 8x7 -C
A PREPARATION WORK
1 Site Measurement and Bowplank Installation m' 32.00 278,630.00 8,916,160.00 0.287
PREPARATION 8,916,160.00 0.287
B ARCHITECTURAL WORKS
B.1 1ST FLOOR
I. WALLWORK
1 Brick Wall 1:5 m2 68.36 139,920.88 9,564,991.36 0.308
2 Mortar Plaster Work m2 213.25 67,316.74 14,355,497.61 0.462
3 Mortar Neat Plaster Work m2 213.25 42,427.00 9,047,685.03 0.291
4 Practical Column & Lintel Beam Work
- K250 Concrete m3 0.88 1,226,720.35 1,073,380.31 0.035
- Reinforcement kg 132.32 16,006.10 2,117,910.89 0.068
- Formwork m2 14.58 185,185.00 2,700,614.58 0.087
II. Ceiling Installation Work
1 Ceiling Hollow frame m 2
108.15 149,919.00 16,213,589.93 0.521
2 6 mm of Calcium Board GRC (Ceiling Interior) m2 53.83 72,230.40 3,888,162.43 0.125
3 6 mm of Calcium Board GRC (Ceiling Exterior) m2 54.32 72,230.40 3,923,483.10 0.126
III. Floor Installation Work
1 Tile 40x40 cm (Polished) Rooms m2 54.46 162,962.80 8,874,465.20 0.285
2 Tile 40x40 cm (Unpolished) Hallway m2 14.46 166,262.80 2,404,326.35 0.077
IV. Door and Window Installation Work (complete w. alluminium frame)
Door Alumunium Frame
1 Unit 1.00 1,533,286.70 1,533,286.70 0.049
Installation Work (typeWork
Leaf Door Instalation P2)
2 Unit 1.00 5,250,000.00 5,250,000.00 0.169
(type P2)
3 Window Installation Work (type J2) Unit 11.00 3,417,381.00 37,591,191.00 1.209
V. Painting Works
1 Wall Painting; Interior m2 89.59 40,563.60 3,634,255.18 0.117
2 Wall Painting; Exterior m2 123.66 54,313.60 6,716,365.46 0.216
3 Ceiling Painting; Interior m2 53.83 40,563.60 2,183,538.59 0.070
4 Ceiling Painting; Exterior m2 54.32 54,313.60 2,950,260.44 0.095
5 Calsiplank Painting m2 15.98 54,313.60 867,877.01 0.028
VI. Other Works
1 Stair
- Retaining Wall 1 Pc : 5 Ps m2 3.24 139,920.88 453,343.65 0.015
- Landfill for floor elevation m3 0.49 163,075.00 79,254.45 0.003
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.09 912,325.16 82,109.26 0.003
- Chevron Works m1 6.60 40,315.00 266,079.00 0.009
- Mortar Plaster Work m2 2.43 67,316.74 163,445.05 0.005
- Mortar Neat Plaster Work m2 2.43 42,427.00 103,012.76 0.003
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
C. STRUCTURAL WORK
I FOUNDATION WORK
1 Foundation PD1
- Foundation Cutting m3 38.25 105,435.00 4,032,888.75 0.130
- Backfill m3 33.93 62,150.00 2,108,749.50 0.068
- Concrete K-250 m3 4.32 1,226,720.35 5,299,431.91 0.170
- Reinforcement kg 494.77 16,006.10 7,919,343.68 0.255
- Formwork m2 14.40 185,185.00 2,666,664.00 0.086
- Sand layer t=10cm m3 1.44 192,830.00 277,675.20 0.009
- Base Concrete t=5cm m3 0.72 912,325.16 656,874.11 0.021
2 Foundation PD1A
- Foundation Cutting m3 11.49 105,435.00 1,211,659.02 0.039
- Backfill m3 10.29 62,150.00 639,647.80 0.021
- Concrete K-250 m3 1.20 1,226,720.35 1,472,064.42 0.047
- Reinforcement kg 149.83 16,006.10 2,398,216.34 0.077
- Formwork m2 4.80 185,185.00 888,888.00 0.029
- Sand layer t=10cm m3 0.40 192,830.00 77,132.00 0.002
- Base Concrete t=5cm m3 0.20 912,325.16 182,465.03 0.006
3 Foundation PD2
- Foundation Cutting m3 25.65 105,435.00 2,704,407.75 0.087
- Sand layer t=10cm m3 2.70 192,830.00 520,641.00 0.017
- Masonry 1:4 m3 13.82 756,723.00 10,459,803.67 0.336
- Aanstamping Stone m3 4.05 332,739.00 1,347,592.95 0.043
- Backfill m3 5.36 62,150.00 333,279.37 0.011
4 Foundation PD3
- Foundation Cutting m3 18.64 105,435.00 1,965,202.96 0.063
- Sand layer t=10cm m3 1.96 192,830.00 378,332.46 0.012
- Masonry 1:4 m3 10.56 756,723.00 7,992,584.00 0.257
- Aanstamping Stone m3 2.94 332,739.00 979,250.88 0.031
- Backfill m3 3.90 62,150.00 242,183.01 0.008
5 Soil fill m3 1.57 128,715.71 201,839.11 0.006
VI MUSHOLA 8x7 -D
A PREPARATION WORK
1 Site Measurement and Bowplank Installation m' 30.00 278,630.00 8,358,900.00 0.269
PREPARATION 8,358,900.00 0.269
B ARCHITECTURAL WORKS
B.1 1ST FLOOR
I. WALLWORK
1 Brick Wall 1:5 m2 62.39 139,920.88 8,729,943.54 0.281
2 Mortar Plaster Work m2 205.78 67,316.74 13,852,372.26 0.445
3 Mortar Neat Plaster Work m2 205.78 42,427.00 8,730,585.63 0.281
4 Practical Column & Lintel Beam Work
- K250 Concrete m3 1.01 1,226,720.35 1,232,853.95 0.040
- Reinforcement kg 162.01 16,006.10 2,593,149.61 0.083
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
C. STRUCTURAL WORK
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
I FOUNDATION WORK
1 Foundation PD1
- Foundation Cutting m3 5.40 105,435.00 569,349.00 0.018
- Backfill m3 3.67 62,150.00 228,214.80 0.007
- Concrete K-250 m3 1.73 1,226,720.35 2,119,772.76 0.068
- Reinforcement kg 197.91 16,006.10 3,167,737.47 0.102
- Formwork m2 5.76 185,185.00 1,066,665.60 0.034
- Sand layer t=10cm m3 0.58 192,830.00 111,070.08 0.004
- Base Concrete t=5cm m3 0.29 912,325.16 262,749.65 0.008
2 Foundation PD1A
- Foundation Cutting m3 34.48 105,435.00 3,634,977.06 0.117
- Backfill m3 30.88 62,150.00 1,918,943.40 0.062
- Concrete K-250 m3 3.60 1,226,720.35 4,416,193.26 0.142
- Reinforcement kg 449.49 16,006.10 7,194,649.02 0.231
- Formwork m2 14.40 185,185.00 2,666,664.00 0.086
- Sand layer t=10cm m3 1.20 192,830.00 231,396.00 0.007
- Base Concrete t=5cm m3 0.60 912,325.16 547,395.10 0.018
3 Foundation PD2
- Foundation Cutting m3 16.76 105,435.00 1,766,879.73 0.057
- Sand layer t=10cm m3 1.76 192,830.00 340,152.12 0.011
- Masonry 1:4 m3 9.03 756,723.00 6,833,738.40 0.220
- Aanstamping Stone H=15cm m3 2.65 332,739.00 880,427.39 0.028
- Backfill m3 3.50 62,150.00 217,742.52 0.007
4 Foundation PD3
- Foundation Cutting m3 27.87 105,435.00 2,938,789.76 0.095
- Sand layer t=10cm m3 2.93 192,830.00 565,763.22 0.018
- Masonry 1:4 m3 15.79 756,723.00 11,952,212.77 0.384
- Aanstamping Stone H=15cm m3 4.40 332,739.00 1,464,384.34 0.047
- Backfill m3 5.83 62,150.00 362,163.59 0.012
5 Soil fill m3 1.20 128,715.71 154,922.23 0.005
C STRUCTURAL WORK
I FOUNDATION WORK
1 Foundation PD1
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
2 NYM 3x2,5 mm² Lamp Installation in 20 mmi conduit pipe m 53.00 43,081.50 2,283,319.50 0.073
of MCB-BOX from Classroom MCB-BOX to Toilet
2.2 LIGHTING WORKS
Procurement, installation of
lighting
a. Toilet (4 ROOMS)
1 Roset Led 5 W Type Bulb (Toilet) unit 8.00 69,399.00 555,192.00 0.018
2 Double Electrical Switch unit 4.00 42,350.00 169,400.00 0.005
3 Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 8.00 194,035.42 1,552,283.33 0.050
2.3 Lightning Rod Installation
Procurement, installation of a
complete lightning rod
a. Toilet (4 ROOMS)
1 Ø 3/4 30cm Air Terminal , Completed With Ø 3/4 70cm GIP set 1.00 442,541.00 442,541.00 0.014
2 BC 25 mm² Cable Installation m 16.00 75,065.83 1,201,053.33 0.039
3 600mm² x 600mm² c/w Junction Box with Grounding System set 1.00 948,398.00 948,398.00 0.031
4 Auxiliary Materials lot 1.00 366,501.21 366,501.21 0.012
Total Mechanical And Electrical Cost 15,700,685.55 0.505
IX SITE PLAN
A SITEPLAN STRUCTURAL WORKS
1.1 STRUCTURAL FOUNDATION TOWER WATER TANK
a. Foundation Footplat
- Foundation Cutting m3 1.12 105,435.00 117,665.46 0.004
- Backfill m3 0.73 62,150.00 45,493.80 0.001
- Concrete K-250 m3 0.29 1,226,720.35 353,295.46 0.011
- Reinforcement kg 11.54 16,006.10 184,724.48 0.006
- Formwork m2 1.92 185,185.00 355,555.20 0.011
- Sand layer t=5cm m3 0.07 192,830.00 13,883.76 0.0004
- Base Concrete t=5cm m3 0.07 912,325.16 65,687.41 0.002
b. 20/20 Column
- Concrete K-250 m3 0.10 1,226,720.35 117,765.15 0.004
- Reinforcement kg 13.31 16,006.10 213,067.85 0.007
- Formwork Column m2 1.92 275,300.00 528,576.00 0.017
c. 15/20 Tie Beam
- Concrete K-250 m3 0.16 1,226,720.35 191,368.37 0.006
- Reinforcement kg 23.15 16,006.10 370,535.20 0.012
- Tie Beam Formwork m2 2.08 195,085.00 405,776.80 0.013
Total Site Plan Structural Work Cost 2,963,394.95 0.095
WEEKLY REPORT
Project : CONSTRUCTION OF SCHOOLS FACILITIES IN CENTRAL SULAWESI (LOT 3) Week : 7 (seven)
Contract No. : Ref.: 10057438 Period : 30 July 2023 - 05 August 2023
Location : SD Negeri Pengawu Weight Until Last Week : 2.675 %
Owner : United Nations Development Programme Weight This Week : 1.224 %
Contract Price : IDR 3,328,489,000 Weight Until This week Week : 3.899 %
I PREPARATION WORK
1 Project Safety Fencing M1 80.00 251,460.00 20,116,800.00 0.604 76.000 95.000 0.574 4.000 5.000 0.030 80.000 100.000 0.604
2 Project Signage Unit 1.00 474,732.50 474,732.50 0.014 1.000 100.000 0.014 1.000 100.000 0.014
3 Renovation Temporary Office Construction; Plaster Floor ls 1.00 14,683,944.00 14,683,944.00 0.441 1.000 100.000 0.441 1.000 100.000 0.441
4 Renovation Storage Construction & Bordinghouse ls 1.00 5,738,238.00 5,738,238.00 0.172 1.000 100.000 0.172 1.000 100.000 0.172
5 Mobilization, Demobilization of Personnel and Tools ls 1.00 5,000,000.00 5,000,000.00 0.150 0.500 50.000 0.075 0.500 50.000 0.075
6 HSE (Safety Net, Hat, Helmet,etc.) ls 1.00 10,175,000.00 10,175,000.00 0.306 0.750 75.000 0.229 0.750 75.000 0.229
7 Site Cleaning M2 1,556.98 4,158.00 6,473,922.84 0.195 1167.735 75.000 0.146 1167.735 75.000 0.146
8 Rebar Cleaning ls 1.00 7,500,000.00 7,500,000.00 0.225 0.500 50.000 0.113 0.500 50.000 0.113
Total Preparation Work Cost 70,162,637.34 2.108 1.765 0.030 1.795
B ARCHITECTURAL WORKS
B.1 1ST FLOOR
I WALLWORK
1 1/2 Brick Wall 1:5 M2 43.54 139,920.88 6,092,183.10 0.183
2 Mortar Plaster Work M2 863.31 67,316.74 58,115,218.26 1.746
3 Mortar Neat Plaster Work M 2
863.31 42,427.00 36,627,653.37 1.100
4 Practical Column & Lintel Beam Work
- K250 Concrete M3 0.30 1,226,720.35 370,285.54 0.011
- Reinforcement Kg 46.56 16,006.10 745,297.20 0.022
- Formwork M2 5.03 185,185.00 931,634.87 0.028
II Floor Installation Work
1 Tile 40x40 cm (Polished) Rooms M2 272.74 162,962.80 44,446,474.07 1.335
2 Tile 40x40 cm (Unpolished) Hallway M2 81.82 166,262.80 13,604,453.61 0.409
III Painting Works
1 Wall Painting; Interior M 2
487.88 40,563.60 19,789,966.35 0.595
2 Wall Painting; Exterior M2 375.43 54,313.60 20,391,226.42 0.613
3 Ceiling Painting; Interior M2 269.42 40,563.60 10,928,645.11 0.328
4 Ceiling Painting; Exterior M2 197.57 54,313.60 10,730,737.95 0.322
5 Calsiplank Painting M2 36.02 54,313.60 1,956,625.71 0.059
IV Door and Window Installation Work (complete w. aluminiumframe)
Door Alumunium Frame Installation
1 Unit 5.00 1,082,950.00 5,414,750.00 0.163
Work (type P1)
2 Leaf Door Instalation Work (type P1) Unit 5.00 2,625,000.00 13,125,000.00 0.394
Door Alumunium Frame Installation
3 Unit 5.00 1,533,286.70 7,666,433.50 0.230
Work (type P2)
4 Leaf Door Instalation Work (type P2) Unit 5.00 5,250,000.00 26,250,000.00 0.789
5 Window Installation Work (type J2) Unit 5.00 3,417,381.00 17,086,905.00 0.513
6 Window Installation Work (type J3) Unit 15.00 3,546,928.00 53,203,920.00 1.598
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
C STRUCTURAL WORK
I 1ST LEVEL
1 30/30 Column
- K-250 Concrete m3 2.22 1,226,720.35 2,726,999.34 0.082
- Reinforcement kg 12.35 16,006.10 197,645.72 0.006
- Column Formwork m2 29.64 275,300.00 8,159,892.00 0.245
2 20/20 Column
- K-250 Concrete m3 0.43 1,226,720.35 526,017.69 0.016
- Reinforcement kg 7.33 16,006.10 117,269.26 0.004
- Column Formwork m2 8.58 275,300.00 2,360,972.80 0.071
3 20/25 Beam
- Concrete K-250 m3 7.85 1,226,720.35 9,623,621.14 0.289
- Reinforcement kg 1,554.99 16,006.10 24,889,320.06 0.748
- Beam Formwork m2 109.83 282,050.00 30,977,551.50 0.931
Total Structural Cost 79,579,289.50 2.391
B ARCHITECTURAL WORKS
B.1 1ST FLOOR
I WALLWORK
1 1/2 Brick Wall 1:5 m2 29.56 139,920.88 4,135,781.37 0.124
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
C STRUCTURAL WORK
I 1ST LEVEL
1 30/30 Column
- K-250 Concrete m3 2.05 1,077,138.88 2,210,288.98 0.066 2.052 100.000 0.066 2.052 100.000 0.066
- Column Formwork m2 27.36 327,500.00 8,960,400.00 0.269
2 20/20 Column
- K-250 Concrete m3 0.39 1,077,138.88 417,929.88 0.013 0.388 100.000 0.013 0.388 100.000 0.013
- Column Formwork m2 7.60 327,500.00 2,489,000.00 0.075
3 25/30 Beam
- Concrete K-250 m3 5.12 1,077,138.88 5,509,565.36 0.166 5.115 100.000 0.166 5.115 100.000 0.166
- Beam Formwork m2 60.01 335,750.00 20,148,357.50 0.605 12.000 19.997 0.121 12.000 19.997 0.121
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
4 20/25 Beam
- Concrete K-250 m3 1.46 1,077,138.88 1,572,622.76 0.047 1.460 100.000 0.047 1.460 100.000 0.047
- Beam Formwork m2 20.44 335,750.00 6,862,730.00 0.206 4.088 20.000 0.041 4.088 20.000 0.041
Total Structural Cost 48,170,894.49 1.447 0.232 0.222 0.454
B ARCHITECTURAL WORKS
B.1 1ST FLOOR
I WALLWORK
1 1/2 Brick Wall 1:5 m2 9.13 139,920.88 1,277,127.83 0.038
2 Mortar Plaster Work m2 302.43 67,316.74 20,358,670.20 0.612
3 Mortar Neat Plaster Work m 2
302.43 42,427.00 12,831,240.04 0.385
4 Practical Column & Lintel Beam Work
- K250 Concrete m3 0.07 1,226,720.35 81,883.58 0.002
- Reinforcement kg 10.09 16,006.10 161,566.35 0.005
- Formwork m2 1.11 185,185.00 206,018.31 0.006
B Ceiling Installation Work
1 Ceiling Hollow frame m2 135.10 149,919.00 20,254,506.66 0.609
2 6 mm of Calcium Board GRC (Ceiling Interior) M2 57.89 72,230.40 4,181,417.86 0.126
3 6 mm of Calcium Board GRC (Ceiling Exterior) M 2
77.21 72,230.40 5,577,125.88 0.168
C Floor Installation Work
1 Tile 40x40 cm (Polished) Rooms m2 88.34 162,962.80 14,395,644.86 0.432
2 Tile 40x40 cm (Unpolished) Hallway m2 19.96 166,262.80 3,318,106.70 0.100
D Door and Window Installation Work (complete w. aluminium frame)
Door Alumunium Frame Installation
1 Unit 1.00 1,082,950.00 1,082,950.00 0.033
Work (type P1)
2 Leaf Door Instalation Work (type P1) Unit 1.00 2,625,000.00 2,625,000.00 0.079
Door Alumunium Frame Installation
3 Unit 1.00 1,533,286.70 1,533,286.70 0.046
Work (type P2)
4 Leaf Door Instalation Work (type P2) Unit 1.00 5,250,000.00 5,250,000.00 0.158
5 Window Installation Work (type J3) Unit 4.00 3,546,928.00 14,187,712.00 0.426
E Painting Works
1 Wall Painting; Interior m2 125.88 40,563.60 5,106,348.79 0.153
2 Wall Painting; Exterior m2 176.55 54,313.60 9,588,848.83 0.288
3 Ceiling Painting; Interior m2 57.89 40,563.60 2,348,226.80 0.071
4 Ceiling Painting; Exterior m2 77.21 54,313.60 4,193,716.00 0.126
5 Calsiplank Painting m2 19.96 54,313.60 1,084,338.44 0.033
F Other Works
1 Railling for Disability access
- Disability Handrail Ramp work m 14.10 760,976.98 10,729,014.37 0.322
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.78 912,325.16 711,613.62 0.021
- Chevron Works m 20.90 40,315.00 842,381.92 0.025
- Retaining Wall Ramp 1 Pc : 5 Ps m2 5.75 139,920.88 803,985.38 0.024
- Landfill for floor elevation m3 1.25 163,075.00 204,332.97 0.006
- Mortar Plaster Work m2 5.76 67,316.74 387,609.81 0.012
- Mortar Neat Plaster Work m2 5.76 42,427.00 244,294.67 0.007
2 Stair
- Retaining Wall 1 Pc : 5 Ps m 2
3.24 139,920.88 453,343.65 0.014
- Landfill for floor elevation m3 0.49 163,075.00 79,254.45 0.002
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.09 912,325.16 82,109.26 0.002
- Chevron Works m 6.60 40,315.00 266,079.00 0.008
- Mortar Plaster Work m2 2.43 67,316.74 163,445.05 0.005
- Mortar Neat Plaster Work m2 2.43 42,427.00 103,012.76 0.003
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
C STRUCTURAL WORK
I 1ST LEVEL
1 K1 30/30 Column
- K-250 Concrete m3 0.27 1,226,720.35 331,214.49 0.010
- Reinforcement kg 21.09 16,006.10 337,493.20 0.010 21.085 100.000 0.010 21.085 100.000 0.010
- Column Formwork m2 3.60 275,300.00 991,080.00 0.030 3.600 100.000 0.030 3.600 100.000 0.030
2 K2 20/20 Column
- K-250 Concrete m3 0.03 1,226,720.35 39,255.05 0.001
- Reinforcement kg 9.99 16,006.10 159,827.72 0.005 9.985 100.000 0.005 9.985 100.000 0.005
- Column Formwork m2 0.64 275,300.00 176,192.00 0.005 0.640 100.000 0.005 0.640 100.000 0.005
3 B1 25/30 Beam
- Concrete K-250 m3 2.63 1,226,720.35 3,220,140.92 0.097
- Reinforcement kg 16.77 16,006.10 268,377.83 0.008
- Beam Formwork m2 29.92 282,050.00 8,438,936.00 0.254 29.920 100.000 0.254 29.920 100.000 0.254
4 B2 20/25 Beam
- Concrete K-250 m 3 0.64 1,226,720.35 778,967.42 0.023
- Reinforcement kg 43.28 16,006.10 692,693.12 0.021
- Beam Formwork m2 8.89 282,050.00 2,507,424.50 0.075
Total Structural Cost 17,941,602.25 0.539 0.304 0.304
B ARCHITECTURAL WORKS
B.1 1ST FLOOR
I WALLWORK
1 1/2 Brick Wall 1:5 m2 105.50 139,920.88 14,762,212.52 0.444
2 Mortar Plaster Work m2 302.43 67,316.74 20,358,670.20 0.612
3 Mortar Neat Plaster Work m2 302.43 42,427.00 12,831,240.04 0.385
4 Practical Column & Lintel Beam Work
- K250 Concrete m3 0.77 1,226,720.35 949,481.55 0.029
- Reinforcement kg 117.05 16,006.10 1,873,443.46 0.056
- Formwork m2 12.90 185,185.00 2,388,886.50 0.072
B Ceiling Installation Work
1 Ceiling Hollow frame m2 135.10 149,919.00 20,254,506.66 0.609
2 6 mm of Calcium Board GRC (Ceiling Interior) M2 57.89 72,230.40 4,181,417.86 0.126
3 6 mm of Calcium Board GRC (Ceiling Exterior) M2 77.21 72,230.40 5,577,125.88 0.168
C Floor Installation Work
1 Tile 40x40 cm (Polished) Rooms m 2
88.34 162,962.80 14,395,644.86 0.432
2 Tile 40x40 cm (Unpolished) Hallway m2 19.96 166,262.80 3,318,106.70 0.100
D Door and Window Installation Work (complete w. aluminium frame)
1 Door Alumunium Frame Installation Work (type P1) Unit 1.00 1,082,950.00 1,082,950.00 0.033
2 Leaf Door Instalation Work (type P1) Unit 1.00 2,625,000.00 2,625,000.00 0.079
3 Door Alumunium Frame Installation Work (type P2) Unit 1.00 1,533,286.70 1,533,286.70 0.046
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
4 Leaf Door Instalation Work (type P2) Unit 1.00 5,250,000.00 5,250,000.00 0.158
5 Window Installation Work (type J3) Unit 4.00 3,546,928.00 14,187,712.00 0.426
E Painting Works
1 Wall ; Interior m2 125.88 40,563.60 5,106,348.79 0.153
2 Wall Painting; Exterior m2 176.55 54,313.60 9,588,848.83 0.288
3 Ceiling Painting Interior m2 57.89 40,563.60 2,348,226.80 0.071
4 Ceiling Painting; Exterior m2 77.21 54,313.60 4,193,716.00 0.126
5 Calsiplank Painting m2 19.96 54,313.60 1,084,338.44 0.033
F Other Works
1 Stair
- Retaining Wall 1 Pc : 5 Ps m2 3.24 139,920.88 453,343.65 0.014
- Landfill for floor elevation m3 0.49 163,075.00 79,254.45 0.002
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.09 912,325.16 82,109.26 0.002
- Chevron Works m2 6.60 40,315.00 266,079.00 0.008
- Mortar Plaster Work m2 2.43 67,316.74 163,445.05 0.005
- Mortar Neat Plaster Work m2 2.43 42,427.00 103,012.76 0.003
B.2 ROOF WORKS
I Roof Covering Works
1 Zincalume Spandex H. 0,30 mm Installation m2 214.65 171,306.67 36,771,147.31 1.105
2 Light Steel Frame; including rafter and accessoris m2 214.65 213,420.90 45,811,009.61 1.376
3 Insulation Layer m2 214.65 27,087.50 5,814,358.96 0.175
4 Roof Ridges, Zincalum Spandex m 27.40 73,810.00 2,022,394.00 0.061
5 Calsiplank 30x0,80 cm m 66.50 58,520.00 3,891,345.92 0.117
6 Roof Jalousie Unit 2.00 1,776,981.25 3,553,962.50 0.107
Total Architectural Cost 246,902,626.25 7.418
C STRUCTURAL WORK
I FOUNDATION WORK
1 PD1 Foundation
- Backfill m3 36.18 62,150.00 2,248,587.00 0.068 28.944 80.000 0.054 7.236 20.000 0.014 36.180 100.000 0.068
2 PD1A Foundation
- Backfill m3 10.29 62,150.00 639,647.80 0.019 8.234 80.000 0.015 2.058 20.000 0.004 10.292 100.000 0.019
3 PD2 Broken Stone Foundation
- Foundation Cutting m3 0.86 105,435.00 90,146.93 0.003 0.855 100.000 0.003 0.855 100.000 0.003
- Masonry 1:4 m3 4.41 756,723.00 3,339,796.96 0.100 4.414 100.000 0.100 4.414 100.000 0.100
- Aanstamping Stone H=15cm m3 1.23 332,739.00 408,769.86 0.012 1.229 100.000 0.012 1.229 100.000 0.012
- Sand layer t=10cm m3 0.82 192,830.00 157,927.77 0.005 0.819 100.000 0.005 0.819 100.000 0.005
- Backfill m3 2.97 62,150.00 184,896.25 0.006 2.380 80.000 0.004 0.595 20.000 0.001 2.975 100.000 0.006
4 PD3 Broken Stone Foundation
- Foundation Cutting m3 5.02 105,435.00 528,861.96 0.016 5.016 100.000 0.016 5.016 100.000 0.016
- Masonry 1:4 m3 8.49 756,723.00 6,422,686.46 0.193 8.488 100.000 0.193 8.488 100.000 0.193
- Aanstamping Stone H=15cm m3 1.01 332,739.00 335,400.91 0.010 1.008 100.000 0.010 1.008 100.000 0.010
- Sand layer t=10cm m3 0.67 192,830.00 129,581.76 0.004 0.672 100.000 0.004 0.672 100.000 0.004
- Backfill m3 8.33 62,150.00 517,709.50 0.016 6.664 80.000 0.012 1.666 20.000 0.003 8.330 100.000 0.016
5 PD4 Broken Stone Foundation
- Foundation Cutting m3 0.76 105,435.00 80,130.60 0.002 0.760 100.000 0.002 0.760 100.000 0.002
- Masonry 1:4 m3 5.41 756,723.00 4,092,168.80 0.123 5.408 100.000 0.123 5.408 100.000 0.123
- Aanstamping Stone H=15cm m3 1.34 332,739.00 445,204.78 0.013 1.338 100.000 0.013 1.338 100.000 0.013
- Sand layer t=10cm m3 0.89 192,830.00 172,004.36 0.005 0.892 100.000 0.005 0.892 100.000 0.005
- Backfill m3 4.17 62,150.00 258,854.75 0.008 4.165 100.000 0.008 4.165 100.000 0.008
6 Soil fill m3 2.53 128,715.71 325,869.57 0.010 2.532 100.000 0.010 2.532 100.000 0.010
II 1ST LEVEL
1 K1 30/30 Column
- K-250 Concrete m3 3.91 1,077,138.88 4,216,998.71 0.127
- Reinforcement kg 64.14 16,006.10 1,026,676.55 0.031
- Column Formwork m2 52.20 275,300.00 14,370,660.00 0.432
2 K2 20/20 Column
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
VI MUSHOLA 10x9-C
A PREPARATION WORK
1 Site Measurement m' 38.00 22,990.00 873,620.00 0.026
2 Bowplank Installation m' 16.00 278,630.00 4,458,080.00 0.134
PREPARATION 5,331,700.00 0.160
B ARCHITECTURAL WORKS
B.1 1ST FLOOR
A WALLWORK
1 Brick Wall 1:5 m2 80.95 139,920.88 11,326,455.32 0.340
2 Mortar Plaster Work m2 253.08 67,316.74 17,036,790.84 0.512
3 Mortar Neat Plaster Work m 2
253.08 42,427.00 10,737,594.87 0.323
4 Practical Column & Lintel Beam Work
- K250 Concrete m3 1.12 1,226,720.35 1,372,700.07 0.041
- Reinforcement kg 179.42 16,006.10 2,871,750.75 0.086
- Formwork m2 18.65 185,185.00 3,453,700.25 0.104
B Ceiling Installation Work
1 Ceiling Hollow frame m2 101.41 149,919.00 15,202,836.03 0.457
2 6 mm of Calcium Board GRC (Ceiling Interior) M2 48.42 72,230.40 3,497,323.74 0.105
3 6 mm of Calcium Board GRC (Ceiling Exterior) M 2
52.99 72,230.40 3,827,344.44 0.115
C Floor Installation Work
1 Tile 40x40 cm (Polished) Rooms m2 80.16 162,962.80 13,063,586.94 0.392
2 Tile 40x40 cm (Unpolished) Hallway m2 8.43 166,262.80 1,400,930.35 0.042
D Door and Window Installation Work (complete w. aluminium frame)
1 Door Alumunium Frame Installation Work (type P2) Unit 3.00 1,533,286.70 4,599,860.10 0.138
2 Leaf Door Instalation Work (type P2) Unit 3.00 5,250,000.00 15,750,000.00 0.473
3 Window Installation Work (type J2) Unit 6.00 2,928,090.00 17,568,540.00 0.528
E Sanitary Work and Installation
Sanitary work includes procurement & installation
1 Faucet Unit 8.00 746,652.50 5,973,220.00 0.179
2 Floordrain Unit 2.00 675,235.00 1,350,470.00 0.041
F Painting Works
1 Wall Painting; Interior m2 93.02 40,563.60 3,773,226.07 0.113
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
C. STRUCTURAL WORK
I FOUNDATION WORK
1 Foundation PD1
- Backfill m3 14.47 62,150.00 899,434.80 0.027
2 Foundation PD1A
- Backfill m3 30.88 62,150.00 1,918,943.40 0.058
3 PD2 Broken Stone Foundation
- Foundation Cutting m3 2.57 105,435.00 270,440.78 0.008 2.565 100.000 0.008 2.565 100.000 0.008
- Sand layer t=10cm m3 2.38 192,830.00 458,164.08 0.014 2.376 100.000 0.014 2.376 100.000 0.014
- Masonry 1:4 m3 6.40 756,723.00 4,844,540.65 0.146 6.402 100.000 0.146 6.402 100.000 0.146
- Aanstamping Stone H=15 cm m3 1.78 332,739.00 592,940.90 0.018 1.782 100.000 0.018 1.782 100.000 0.018
- Backfill m3 8.21 62,150.00 510,313.65 0.015
4 PD3 Broken Stone Foundation
- Foundation Cutting m3 2.57 105,435.00 270,440.78 0.008 2.565 100.000 0.008 2.565 100.000 0.008
- Sand layer t=10cm m3 1.94 192,830.00 373,126.05 0.011 1.935 100.000 0.011 1.935 100.000 0.011
- Masonry 1:4 m3 9.43 756,723.00 7,138,357.24 0.214 9.433 100.000 0.214 9.433 100.000 0.214
- Aanstamping Stone H=15 cm m3 2.63 332,739.00 873,689.43 0.026 2.626 100.000 0.026 2.626 100.000 0.026
- Backfill m3 12.08 62,150.00 750,678.77 0.023
5 Soil fill m3 2.59 128,715.71 333,013.30 0.010
II. 1ST LEVEL
1 K1 30/30 Column
- Concrete K-250 m3 1.81 1,077,138.88 1,952,421.93 0.059 0.234 12.910 0.008 0.234 12.910 0.008
- Reinforcement kg 34.62 16,006.10 554,186.07 0.017
- Formwork Column m2 24.17 275,300.00 6,653,450.40 0.200 3.120 12.910 0.026 3.120 12.910 0.026
2 K2 20/20 Column
- Concrete K-250 m3 2.47 1,077,138.88 2,662,256.45 0.080 0.364 14.727 0.012 0.364 14.727 0.012
- Reinforcement kg 16.87 16,006.10 269,994.56 0.008
- Formwork Column m2 49.23 275,300.00 13,553,569.60 0.407 7.280 14.787 0.060 7.280 14.787 0.060
3 S1 25/30 Tie Beam
- Concrete K-250 m 3 1.98 1,077,138.88 2,132,734.98 0.064
- Reinforcement kg 432.54 16,006.10 6,923,274.55 0.208
- Tie Beam Formwork m2 15.84 195,085.00 3,090,146.40 0.093
4 S2 20/25 Tie Beam
- Concrete K-250 m3 1.88 1,077,138.88 2,030,406.79 0.061
- Reinforcement kg 352.14 16,006.10 5,636,368.57 0.169
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
B ARCHITECTURAL WORKS
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
IX TOILET 6 ROOMS-D1
A PREPARATION WORK
1 Site Measurement and Bowplank Installation m' 29.80 278,630.00 8,303,174.00 0.249
PREPARATION 8,303,174.00 0.249
B ARCHITECTURAL WORKS
B.1 1ST FLOOR
A WALLWORK
1 Brick Wall 1:3 m2 130.24 147,363.92 19,192,676.94 0.577
2 Mortar Plaster Work m2 190.62 67,316.74 12,831,648.47 0.386
3 Mortar Neat Plaster Work m2 190.62 42,427.00 8,087,265.03 0.243
4 Practical Column & Lintel Beam Work
- K250 Concrete m3 0.62 1,226,720.35 761,793.34 0.023
- Reinforcement kg 98.22 16,006.10 1,572,136.05 0.047
- Formwork m2 10.35 185,185.00 1,916,664.75 0.058
5 Wall Tiles 25x40cm (Unpolished) m 2
91.78 183,499.80 16,841,061.14 0.506
B Ceiling Installation Work
1 Ceiling Hollow frame m2 52.57 149,919.00 7,881,841.51 0.237
2 6 mm of Calcium Board GRC (Ceiling Interior) m2 15.33 72,230.40 1,107,147.57 0.033
3 6 mm of Calcium Board GRC (Ceiling Exterior) m2 37.25 72,230.40 2,690,293.48 0.081
C Floor Installation Work
1 40x40 cm of Ceramic Tile (Unpolished) Hallway m2 20.53 166,262.80 3,412,876.50 0.103
2 40x40 cm of Ceramic Tile (Unpolished) Rooms m2 16.99 162,962.80 2,768,900.93 0.083
3 Waterproofing Coating + mortar m2 16.99 119,614.62 2,032,371.94 0.061
D Door and Window Installation Work (complete w. alluminium frame)
1 Door Allumunium Frame Installation Work (type P4) Difabel Unit 1.00 2,585,000.00 2,585,000.00 0.078
2 Door Allumunium Frame Installation Work (type P3) Unit 5.00 2,368,025.00 11,840,125.00 0.356
E Sanitary Work and Installation
Sanitary work includes procurement & installation
1 Sitting Closet Unit 1.00 3,699,704.80 3,699,704.80 0.111
2 Squatting Closet Unit 5.00 1,306,646.00 6,533,230.00 0.196
3 Shower spray Unit 1.00 960,355.00 960,355.00 0.029
4 Wastafel hang Unit 5.00 3,723,830.00 18,619,150.00 0.559
5 Floor Drain Unit 6.00 675,235.00 4,051,410.00 0.122
6 Tissue Holder Unit 1.00 585,475.00 585,475.00 0.018
7 Soap Dispenser Unit 3.00 165,275.00 495,825.00 0.015
8 Robe hook Unit 6.00 334,235.00 2,005,410.00 0.060
9 Fibre Basin Unit 5.00 992,670.36 4,963,351.80 0.149
10 5mm; uk 500x700 of mirror work Unit 5.00 126,379.00 631,895.00 0.019
11 Handrail Stainless;Difabel m 1.20 610,995.00 733,194.00 0.022
12 Faucet Unit 6.00 746,652.50 4,479,915.00 0.135
F Painting Works
1 Wall Painting; Interior m 2
44.21 40,563.60 1,793,195.07 0.054
2 Wall Painting; Exterior m2 146.41 54,313.60 7,951,999.86 0.239
3 Ceiling Painting; Interior m2 15.33 40,563.60 621,758.86 0.019
4 Ceiling Painting; Exterior m3 37.25 54,313.60 2,022,964.35 0.061
5 Calsiplank Painting m2 7.59 54,313.60 412,044.70 0.012
G Other Works
1 Disability Ramp Work
- Disability Handrail Ramp work m 14.10 760,976.98 10,729,014.37 0.322
- Chevron Work m 0.78 40,315.00 31,445.70 0.001
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m 3
20.90 912,325.16 19,063,034.19 0.573
- Retaining Wall Ramp 1 Pc : 5 Ps m2 5.75 139,920.88 803,985.38 0.024
- Landfill for floor elevation m3 1.25 163,075.00 204,332.97 0.006
- Mortar Plaster Work m2 5.76 67,316.74 387,609.81 0.012
- Mortar Neat Plaster Work m2 5.76 42,427.00 244,294.67 0.007
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
2 Stair
- Retaining Wall 1 Pc : 5 Ps m2 3.24 139,920.88 453,343.65 0.014
- Landfill for floor elevation m3 0.49 163,075.00 79,254.45 0.002
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.09 912,325.16 82,109.26 0.002
- Chevron Works m 6.60 40,315.00 266,079.00 0.008
- Mortar Plaster Work m2 2.43 67,316.74 163,445.05 0.005
- Mortar Neat Plaster Work m2 2.43 42,427.00 103,012.76 0.003
B.2 ROOF WORKS
A Roof Covering Works
1 Zincalume Spandex h 0,30mm Installation m2 65.47 171,306.67 11,215,447.47 0.337
2 Light Steel Frame; including rafter and accessoris m2 65.47 213,420.90 13,972,666.32 0.420
3 Aluminium Foil Installation m2 65.47 27,087.50 1,773,418.63 0.053
4 Calsiplank 30x0,80 cm m 25.29 59,070.00 1,493,762.16 0.045
Total Architectural Cost 217,148,936.92 6.524
C STRUCTURAL WORK
I FOUNDATION WORK
1 Foundation PD1 Broken Stone
- Backfill m2 1.46 62,150.00 90,707.92 0.003
2 Foundation PD2 Broken Stone
- Backfill m3 1.48 62,150.00 91,733.40 0.003
II 1ST LEVEL
1 K1 200x200 Column
- K-250 Concrete m3 1.72 1,077,138.88 1,852,678.87 0.056
- Reinforcement kg 32.45 16,006.10 519,440.10 0.016
- Column Formwork m 2 34.40 275,300.00 9,470,320.00 0.285
2 K2 150x200 Column
- K-250 Concrete m3 0.90 1,077,138.88 972,656.41 0.029
- Reinforcement kg 149.77 16,006.10 2,397,236.67 0.072
-Column Formwork m2 21.07 275,300.00 5,800,571.00 0.174
3 S1 (200x250) Tie Beam
- Concrete K-250 m3 1.37 1,077,138.88 1,474,333.84 0.044
- Reinforcement kg 43.48 16,006.10 695,877.64 0.021
- Tie Beam Formwork m2 13.69 195,085.00 2,670,225.94 0.080
4 S2 (150x200) Tie Beam
- Concrete K-250 m3 0.79 1,077,138.88 851,478.28 0.026
- Reinforcement kg 39.94 16,006.10 639,310.90 0.019
- Tie Beam Formwork m2 10.54 195,085.00 2,056,195.90 0.062
5 B1 (150x200) Beam
- Concrete K-250 m3 1.58 1,077,138.88 1,706,187.98 0.051
- Reinforcement kg 472.93 16,006.10 7,569,753.39 0.227
- Beam Formwork m2 29.04 335,750.00 9,750,180.00 0.293
6 Floor Slab h=12 cm
- Concrete K-250 m3 3.72 1,077,138.88 4,006,067.99 0.120
- Reinforcement kg 352.34 16,006.10 5,639,622.57 0.169
- Floor Formwork m2 3.67 225,800.00 829,137.60 0.025
- Sand Layer t=10cm m3 3.10 183,637.14 569,148.89 0.017
- Base Concrete t=5cm m3 1.55 912,325.16 1,413,790.38 0.042
Total Structural Cost 61,066,655.68 1.835
X SITE PLAN
A SITEPLAN STRUCTURAL WORKS
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)