You are on page 1of 93

Assignor : Supervision Consultant : Contractor :

RECAP WEEKLY REPORT


Project : CONSTRUCTION OF SCHOOLS FICILITIES IN PALU AND PARIGI MOUTONG Week : 1 (One)
Location : KOTA PALU Period : 18 June 2023 - 24 june 2023
Weight Until Last Week : 0.000 %
Weight This Week : 0.000 %
Weight Until This week Week : 0.000 %
Weekly Cumulative Plan Progress : 0.000 %
38.294 Deviasi : -0.174 %

MONTH 1 (June 2023 - July 2023) MONTH 2 (July 2023 - August 2023) MONTH 3 (August 2023 - September 2023) MONTH 4 (September 2023 - October 2023) MONTH 5 (October 2023 - November 2023) MONTH 6 (November 2023 - December 2023) MONTH 7 (December 2023 - January 2024)
TOTAL PRICE W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31
NO. WORK DESCRIPTION Weight (%)
18-Jun 25-Jun 2-Jul 9-Jul 16-Jul 23-Jul 30-Jul 6-Aug 13-Aug 20-Aug 27-Aug 3-Sep 10-Sep 17-Sep 24-Sep 1-Oct 8-Oct 15-Oct 22-Oct 29-Oct 5-Nov 12-Nov 19-Nov 26-Nov 3-Dec 10-Dec 17-Dec 24-Dec 31-Dec 7-Jan 14-Jan
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
24-Jun 1-Jul 8-Jul 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 2-Dec 9-Dec 16-Dec 23-Dec 30-Dec 6-Jan 13-Jan 18-Jan

I CONSTRUCTION SMK NEGERI 8 PALU 5,131,118,000.00 30.521 0.054 0.081 0.108 0.134 0.134 0.391 0.548 0.548 0.815 1.334 1.305 1.450 1.511 1.576 1.597 1.918 1.831 1.714 1.657 1.682 1.815 1.653 1.518 1.121 1.020 0.956 0.934 0.402 0.332 0.243 0.139
0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
II CONSTRUCTION SMP NEGERI 14 PALU 5,242,761,000.00 31.185 0.040 0.060 0.080 0.100 0.120 0.157 0.906 0.692 1.318 1.143 1.381 1.491 1.502 1.526 1.495 1.466 1.506 1.413 1.435 1.443 1.625 1.434 1.431 1.522 1.454 0.801 1.475 0.982 0.462 0.372 0.356
0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
III CONSTRUCTION SD NEGERI 21 PALU 3,109,428,000.00 18.496 0.038 0.057 0.115 0.115 0.057 0.331 0.198 0.198 0.575 0.721 0.631 0.722 0.710 0.645 0.578 0.885 1.017 1.064 1.027 0.995 0.902 0.849 0.881 0.807 0.837 0.837 0.740 0.767 0.702 0.332 0.162
0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
IV CONSTRUCTION SD NEGERI PENGAWU 3,328,489,000.00 19.799 0.042 0.063 0.104 0.104 0.104 0.203 0.476 0.747 0.982 0.997 1.012 1.018 1.008 1.013 0.971 0.980 0.940 0.953 0.951 0.924 0.850 0.709 0.774 0.730 0.630 0.552 0.538 0.532 0.478 0.269 0.146
0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
TOTAL COST 16,811,796,000 100.000
Weekly Progress Plan 0.174 0.260 0.406 0.453 0.416 1.082 2.128 2.184 3.689 4.194 4.329 4.681 4.731 4.760 4.641 5.249 5.294 5.144 5.069 5.044 5.192 4.646 4.604 4.180 3.941 3.146 3.686 2.683 1.974 1.216 0.804
Cumulative Weekly Progress Plan 0.174 0.434 0.841 1.294 1.710 2.791 4.919 7.104 10.793 14.988 19.316 23.998 28.728 33.488 38.129 43.378 48.672 53.815 58.884 63.928 69.121 73.767 78.370 82.550 86.491 89.637 93.323 96.006 97.980 99.196 100.000
Weekly Progress Realization 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
Cumulative Weekly Progress Realization 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
Deviasi -0.174 -0.434 -0.841 -1.294 -1.710 -2.791 -4.919 -7.104 -10.793 -14.988 -19.316 -23.998 -28.728 -33.488 -38.129 -43.378 -48.672 -53.815 -58.884 -63.928 -69.121 -73.767 -78.370 -82.550 -86.491 -89.637 -93.323 -96.006 -97.980 -99.196 -100.000

Acknowledged by ; Approved by ; Submitted by;


UNITED NATIONS DEVELOPMENT PROGRAMME 38.294046632495 Supervision Consultant Contractor
PT. YODYA KARYA (PERSERO) JV PT. SETIA MULIA ABADI

(Whisnu Yonar Anggono) (Abjelvian Henri) (Faris Mubarok)


Community Mobilization Officer UNDP PETRA Team Leader Site Manager
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
( 18 JUNE 2023 - 29 JULY (30 JULY 2023 - 05 AUGUST (18 JUNE 2023 - 05
NO. WORK DESCRIPTION 2023) 2023) AUGUST 2023)
Weight (%) Weight (%) Weight (%)

I LOT 1 2.293 0.348 2.640

II LOT 2 1.460 0.630 2.090

III LOT 3 1.705 0.507 2.212


RECAP UNTIL WEEK 7

UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK


PROGRES
DEVIATION
( 18 JUNE 2023 - 29 (30 JULY 2023 - 05 (18 JUNE 2023 - 05 PLAN
NO. WORK DESCRIPTION
JULY 2023) AUGUST 2023) AUGUST 2023)

Weight (%) Weight (%) Weight (%) Weight (%) Weight (%)

I LOT 1
A. SMK N 8 PALU 7.512 1.139 8.651 4.242 4.409

II LOT 2
A. SMP N 14 PALU 4.682 2.021 6.703 8.442 -1.739

III LOT 3
A. SDN 21 PALU 6.354 1.429 7.783 5.156 2.627
B. SDN PENGAWU 2.675 1.224 3.899 9.099 -5.200
Assignor : Supervision Consultant : Contractor :

RECAP WEEKLY REPORT


Project : CONSTRUCTION OF SCHOOLS FACILITIES IN CENTRAL SULAWESI Week : 7 (seven)
Contract No. : Ref.: 10057438 Period : 30 July 2023 - 05 August 2023
Location : KOTA PALU Weight Until Last Week : 5.458 %
Owner : United Nations Development Programme Weight This Week : 1.485 %
Contract Price : IDR 16,811,796,000 Weight Until This Week : 6.942 %

UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK


TOTAL PRICE
NO. WORK DESCRIPTION Weight (%)
Physic (%) Weight (%) Physic (%) Weight (%) Physic (%) Weight (%)

I LOT 1 5,131,118,000.00 30.521 7.512 2.293 1.139 0.348 8.651 2.640

II LOT 2 5,242,761,000.00 31.185 4.682 1.460 2.021 0.630 6.703 2.090

III LOT 3 6,437,917,000.00 38.294 4.452 1.705 1.323 0.507 5.775 2.212

TOTAL 16,811,796,000 100.000 5.458 1.485 6.942

Plan 6.682 Realization 6.942 Deviation 0.260

Acknowledged by ; Approved by ; Submitted by;


UNITED NATIONS DEVELOPMENT PROGRAMME Supervision Consultant Contractor
PT. YODYA KARYA (PERSERO) JV PT. SETIA MULIA ABADI

(Whisnu Yonar Anggono) (Apjelvian Henri) (Lalu Resha Aditya)


Community Mobilization Officer UNDP PETRA Team Leader Direktur
Assignor : Supervision Consultant : Contractor :

WEEKLY REPORT
Project : CONSTRUCTION OF SCHOOLS FACILITIES IN CENTRAL SULAWESI (LOT 1) Week : 7 (seven)
Contract No. : Ref.: 10057438 Period : 30 July 2023 - 05 August 2023
Location : SMK Negeri 8 Palu Weight Until Last Week : 7.512 %
Owner : United Nations Development Programme Weight This Week : 1.139 %
Contract Price : IDR 5,131,118,000 Weight Until This Week : 8.651 %

UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK


NO. WORK DESCRIPTION VOLUME / UNIT Weight (%)
Physic (%) Weight (%) Physic (%) Weight (%) Physic (%) Weight (%)

1. SMK Negeri 8 Palu 30.521


I PREPARATION WORK
A SITE PREPARATION 1.00 1.761 84.909 1.496 84.909 1.496
II CLASSROOM 9X8 (4 ROOMS) - A1
A PREPARATION WORK 1.00 0.041 100.000 0.041 100.000 0.041
B ARCHITECTURAL WORKS 1.00 13.792
C STRUCTURAL WORK 1.00 3.969 62.132 2.466 7.311 0.290 69.443 2.756

III CLASSROOM 9X8 (4 ROOMS) - A2


A PREPARATION WORK 1.00 0.041 100.000 0.041 100.000 0.041
B ARCHITECTURAL WORKS 1.00 13.778
C STRUCTURAL WORK 1.00 4.940 40.917 2.021 3.891 0.192 44.808 2.214

IV CLASSROOM 9x8 (2 ROOMS) - B1


A PREPARATION WORK 1.00 0.025 100.000 0.025 100.000 0.025
B ARCHITECTURAL WORKS 1.00 7.568
C STRUCTURAL WORK 1.00 2.438 40.372 0.984 40.372 0.984

V CLASSROOM 9x8 (2 ROOMS)-B2


A PREPARATION WORK 1.00 0.025 100.000 0.025 100.000 0.025
B ARCHITECTURAL WORKS 1.00 7.568
C STRUCTURAL WORK 1.00 2.608 20.918 0.545 6.450 0.168 27.368 0.714
D CLASSROOM ELECTRICAL WORKS 1.00 1.276
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION VOLUME / UNIT Weight (%)
Physic (%) Weight (%) Physic (%) Weight (%) Physic (%) Weight (%)

VI TEACHER OFFICE-C
A PREPARATION WORK 1.00 0.358
B ARCHITECTURAL WORKS 1.00 12.019
C. STRUCTURAL WORK 1.00 3.226
D. MECHANICAL AND ELECTRICAL WORKS 1.00 0.687

VII MUSHOLA 8x7-D


A PREPARATION WORK 1.00 0.163 100.000 0.163 100.000 0.163
B ARCHITECTURAL WORKS 1.00 4.774
C. STRUCTURAL WORK 1.00 2.646 7.275 0.193 7.275 0.193
D. MECHANICAL AND ELECTRICAL WORKS 1.00 0.263

VIII TOILET 6 ROOMS-E


A PREPARATION WORK 1.00 0.013
B ARCHITECTURAL WORKS 1.00 4.112
C STRUCTURAL WORK 1.00 1.617
D. MECHANICAL AND ELECTRICAL WORKS 1.00 0.309

IX SITE PLAN
A SITEPLAN STRUCTURAL WORKS 1.00 0.056
B. SITEPLAN PLUMBING WORKS 1.00 2.807
C. SITE PLAN ELECTRICAL WORKS 1.00 0.811

X. SEPTIC TANK N25 WORKS-1


A STP 1.00 0.338
B Infiltration 1.00 0.024
XI. SEPTIC TANK N25 WORKS-2
A STP 1.00 0.338
B Infiltration 1.00 0.024
XII GUTTERS AROUND THE BUILDING AND INFILTRATION
A Gutters Around the Building 1.00 3.207
B Infiltration 1.00 0.095
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION VOLUME / UNIT Weight (%)
Physic (%) Weight (%) Physic (%) Weight (%) Physic (%) Weight (%)

XIII CONNECTING CORRIDOR


Connecting Corridor 1.00 2.283

TOTAL LOT 1 100.000 7.512 1.139 8.651

Plan 4.242 Realization 8.651 Deviation 4.409

Acknowledged by ; Approved by ; Submitted by;


UNITED NATIONS DEVELOPMENT PROGRAMME Supervision Consultant Contractor
PT. YODYA KARYA (PERSERO) JV PT. SETIA MULIA ABADI

(Whisnu Yonar Anggono) (Apjelvian Henri) (I Wayan Praja Murdana)


Community Mobilization Officer UNDP PETRA Team Leader Site Manager
Assignor : Supervision Consultant : Contractor :

WEEKLY REPORT
Project : CONSTRUCTION OF SCHOOLS FACILITIES IN CENTRAL SULAWESI (LOT 1) Week : 7 (seven)
Contract No. : Ref.: 10057438 Period : 30 July 2023 - 05 August 2023
Location : SMK Negeri 8 Palu Weight Until Last Week : 7.512 %
Owner : United Nations Development Programme Weight This Week : 1.139 %
Contract Price : IDR 5,131,118,000 Weight Until This Week : 8.651 %

UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK


UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

I PREPARATION WORK
1 Project Safety Fencing m' 160.00 251,460.00 40,233,600.00 0.784 160.000 100.000 0.784 160.000 100.000 0.784
2 Project Signage Unit 1.00 474,732.50 474,732.50 0.009 1.000 100.000 0.009 1.000 100.000 0.009
3 Renovation Temporary Office Construction; Plaster Floor ls 1.00 13,342,332.72 13,342,332.72 0.260 1.000 100.000 0.260 1.000 100.000 0.260
4 Renovation Storage Construction & Bordinghouse ls 1.00 4,884,598.44 4,884,598.44 0.095 1.000 100.000 0.095 1.000 100.000 0.095
5 Mobilization, Demobilization of Personnel and Tools ls 1.00 5,000,000.00 5,000,000.00 0.097 0.200 20.000 0.019 0.200 20.000 0.019
6 HSE (Safety Net, Hat, Helmet,etc.) ls 1.00 10,175,000.00 10,175,000.00 0.198 0.200 20.000 0.040 0.200 20.000 0.040
7 Site Cleaning m2 2,110.00 4,158.00 8,773,380.00 0.171 2110.000 100.000 0.171 2110.000 100.000 0.171
8 Rebar Cleaning ls 1.00 7,500,000.00 7,500,000.00 0.146 0.800 80.000 0.117 0.800 80.000 0.117
Total Preparation Work Cost 90,383,643.66 1.761 1.496 1.496

II CLASSROOM 9X8 (4 ROOMS) - A1


A PREPARATION WORK
1 Site Measurement m' 92.00 22,990.00 2,115,080.00 0.041 92.000 100.000 0.041 92.000 100.000 0.041
PREPARATION 2,115,080.00 0.041 0.041 0.041
ARCHITECTURAL WORKS
I 1ST FLOOR
A WALLWORK
1 1/2 Brick Wall 1:5 m2 254.66 139,920.88 35,632,251.30 0.694
2 Mortar Plaster Work m2 687.72 67,316.74 46,295,071.18 0.902
3 Mortar Neat Plaster Work m2 687.72 42,427.00 29,177,896.44 0.569
4 Practical Column & Lintel Beam Work
- K250 Concrete m3 2.57 1,226,720.35 3,147,764.42 0.061
- Reinforcement kg 399.17 16,006.10 6,389,182.51 0.125
- Formwork m2 42.77 185,185.00 7,919,745.17 0.154
B Ceiling Installation Work
1 Ceiling Hollow frame m2 453.07 149,919.00 67,923,801.33 1.324
2 6 mm of Calcium Board GRC (Ceiling Interior) m2 280.36 72,230.40 20,250,514.94 0.395
3 6 mm of Calcium Board GRC (Ceiling Exterior) m2 172.71 72,230.40 12,474,912.38 0.243
C Floor Installation Work
1 Tile 40x40 cm (Polished) Rooms m2 282.15 162,962.80 45,979,628.09 0.896
2 Tile 40x40 cm (Unpolished) Hallway m2 70.53 166,262.80 11,726,182.76 0.229

D Door
Door and WindowFrame
Alumunium Installation Work (complete w. Aluminium frame)
1 Installation Work (type Unit 4.00 1,082,950.00 4,331,800.00 0.084
Leaf Door Instalation
2 P1)
Door Alumunium Unit 4.00 2,625,000.00 10,500,000.00 0.205
Work (type P1) Frame
3 Installation Work (type Unit 4.00 1,533,286.70 6,133,146.80 0.120
Leaf Door Instalation
P2)
4 Window Allumunium Unit 4.00 5,250,000.00 21,000,000.00 0.409
Work (type P2)
5 Frame Installation Work Unit 16.00 3,546,928.00 56,750,848.00 1.106
E (type J3)Works
Painting
1 Wall Painting; Interior m2 404.08 40,563.60 16,390,939.49 0.319
2 Wall Painting; Exterior m2 283.64 54,313.60 15,405,509.50 0.300
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

3 Ceiling Painting; Interior m2


280.36 40,563.60 11,372,410.90 0.222
4 Ceiling Painting; Exterior m2 172.71 54,313.60 9,380,501.86 0.183
5 Calsiplank Painting m2 30.40 54,313.60 1,650,916.19 0.032
F Other Works
1 Stair
- Retaining Wall 1 Pc : 5 Ps m2 9.72 139,920.88 1,360,030.95 0.027
- Landfill for floor elevation m3 1.46 163,075.00 237,763.35 0.005
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.27 912,325.16 246,327.79 0.005
- Chevron Works m 54.00 40,315.00 2,177,010.00 0.042
- Mortar Plaster Work m2 7.28 67,316.74 490,335.16 0.010
- Mortar Neat Plaster Work m2 7.28 42,427.00 309,038.27 0.006
B.2 ROOF WORKS
I Roof Covering Works
1 Zincalume Spandex h. 0,30 mm Installation m2 604.91 171,306.67 103,625,115.73 2.020
2 Light Steel Frame; including rafter and accessoris m2 604.91 213,420.90 129,100,436.62 2.516
3 Aluminium Foil Installation m2 604.91 27,087.50 16,385,499.63 0.319
4 Roof Ridges, Zincalum Spandex m 52.88 73,810.00 3,903,072.80 0.076
5 CalsiplanK m 116.40 59,070.00 6,875,866.14 0.134
6 Roof Jalousie Unit 2.00 1,563,743.50 3,127,487.00 0.061
Total Architectural Cost 707,671,006.70 13.792

C STRUCTURAL WORK
I 1ST LEVEL
1 30/30 Column
- K-250 Concrete m3 12.14 1,226,720.35 14,888,091.52 0.290 12.136 100.000 0.290 12.136 100.000 0.290
- Reinforcement kg 178.78 16,006.10 2,861,568.49 0.056 178.780 100.000 0.056 178.780 100.000 0.056
- Column Formwork m2 161.82 275,300.00 44,549,046.00 0.868 161.820 100.000 0.868 161.820 100.000 0.868
2 20/20 Column
- K-250 Concrete m3 2.26 1,226,720.35 2,774,841.43 0.054
- Reinforcement kg 35.64 16,006.10 570,448.93 0.011 35.639 100.000 0.011 35.639 100.000 0.011
- Column Formwork m2 45.24 275,300.00 12,454,572.00 0.243 45.240 100.000 0.243 45.240 100.000 0.243
3 25/30 Tie Beam S1
- Concrete K-250 m3 7.64 1,226,720.35 9,366,009.87 0.183 7.635 100.000 0.183 7.635 100.000 0.183
- Tie Beam Formwork m2 14.16 195,085.00 2,762,403.60 0.054 7.080 50.000 0.027 7.080 50.000 0.027
4 20/25 Tie Beam S2
- Concrete K-250 m3 2.12 1,226,720.35 2,597,580.34 0.051 2.117 100.000 0.051 2.117 100.000 0.051
- Tie Beam Formwork m2 9.27 195,085.00 1,809,413.37 0.035 4.637 50.000 0.018 4.637 50.000 0.018
5 20/25 Beam B1
- Concrete K-250 m3 7.21 1,226,720.35 8,841,586.92 0.172
- Reinforcement kg 1240.96 16,006.10 19,862,891.99 0.387
- Beam Formwork m2 100.91 282,050.00 28,460,255.25 0.555
6 Floor Slab t=12 cm
- Concrete K-250 m3 40.20 1,226,720.35 49,314,158.04 0.961 40.200 100.000 0.961 40.200 100.000 0.961
- Formwork Floor m3 11.17 225,800.00 2,522,637.60 0.049 11.172 100.000 0.049 11.172 100.000 0.049
Total Structural Cost 203,635,505.34 3.969 2.466 0.290 2.756

III CLASSROOM 9X8 (4 ROOMS) - A2


A PREPARATION WORK
1 Site Measurement m' 92.00 22,990.00 2,115,080.00 0.041 92.000 100.000 0.041 92.000 100.000 0.041
PREPARATION 2,115,080.00 0.041 0.041 0.041
B ARCHITECTURAL WORKS
B.I 1ST FLOOR
A WALLWORK
1 1/2 Brick Wall 1:5 m2 254.66 139,920.88 35,632,251.30 0.694
2 Mortar Plaster Work m2 687.72 67,316.74 46,295,071.18 0.902
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

3 Mortar Neat Plaster Work m2


687.72 42,427.00 29,177,896.44 0.569
4 Practical Column & Lintel Beam Work
- K250 Concrete m3 2.57 1,226,720.35 3,147,764.42 0.061
- Reinforcement kg 399.17 16,006.10 6,389,182.51 0.125
- Formwork m2 42.77 185,185.00 7,919,745.17 0.154
B Ceiling Installation Work
1 Ceiling Hollow frame m2 453.07 149,919.00 67,923,801.33 1.324
2 6 mm of Calcium Board GRC (Ceiling Interior) m2 280.36 72,230.40 20,250,514.94 0.395
3 6 mm of Calcium Board GRC (Ceiling Exterior) m2 172.71 72,230.40 12,474,912.38 0.243
C Floor Installation Work
1 Tile 40x40 cm (Polished) Rooms m2 282.15 162,962.80 45,979,628.09 0.896
2 Tile 40x40 cm (Unpolished) Hallway m2 70.53 166,262.80 11,726,182.76 0.229
E Door and Window Installation Work (complete w. Aluminium frame)
1 Door Alumunium Frame Installation Work (type P1) Unit 4.00 1,082,950.00 4,331,800.00 0.084
2 Leaf Door Instalation Work (type P1) Unit 4.00 2,625,000.00 10,500,000.00 0.205
3 Door Alumunium Frame Installation Work (type P2) Unit 4.00 1,533,286.70 6,133,146.80 0.120
4 Leaf Door Instalation Work (type P2) Unit 4.00 5,250,000.00 21,000,000.00 0.409
5 Window Allumunium Frame Installation Work (type J3) Unit 16.00 3,546,928.00 56,750,848.00 1.106
D Painting Works
1 Wall Painting; Interior m2 404.08 40,563.60 16,390,939.49 0.319
2 Wall Painting; Exterior m2 283.64 54,313.60 15,405,509.50 0.300
3 Ceiling Painting; Interior m2 280.36 40,563.60 11,372,410.90 0.222
4 Ceiling Painting; Exterior m2 172.71 54,313.60 9,380,501.86 0.183
5 Calsiplank Painting m2 30.40 54,313.60 1,650,916.19 0.032
F Other Works
1 Stair
- Retaining Wall 1 Pc : 5 Ps m2 9.72 67,316.74 654,318.75 0.013
- Landfill for floor elevation m3 1.46 163,075.00 237,763.35 0.005
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.27 912,325.16 246,327.79 0.005
- Chevron Works m 54.00 40,315.00 2,177,010.00 0.042
- Mortar Plaster Work m2 7.28 67,316.74 490,335.16 0.010
- Mortar Neat Plaster Work m2 7.28 42,427.00 309,038.27 0.006
B.2 ROOF WORKS
I Roof Covering Works
1 Zincalume Spandex h 0,40mm Installation m2 604.91 171,306.67 103,625,115.73 2.020
2 Light Steel Frame; including rafter and accessoris m2 604.91 213,420.90 129,100,436.62 2.516
3 Aluminium Foil Installation m2 604.91 27,087.50 16,385,499.63 0.319
4 Roof Ridges, Zincalum Spandex m 52.88 73,810.00 3,903,072.80 0.076
5 Calsiplank m 116.40 59,070.00 6,875,866.14 0.134
6 Roof Jalousie Unit 2.00 1,563,743.50 3,127,487.00 0.061
Total Architectural Cost 706,965,294.50 13.778
C STRUCTURAL WORK
I 1ST LEVEL
1 30/30 Column
- K-250 Concrete m3 12.14 1,226,720.35 14,888,091.52 0.290
- Reinforcement kg 165.76 16,006.10 2,653,161.38 0.052
- Column Formwork m2 161.82 275,300.00 44,549,046.00 0.868
2 20/20 Column
- K-250 Concrete m3 2.27 1,226,720.35 2,787,599.32 0.054
- Reinforcement kg 45.31 16,006.10 725,175.41 0.014
- Column Formwork m2 45.24 275,300.00 12,454,572.00 0.243
3 25/30 Tie Beam S1
- Concrete K-250 m3 7.64 1,226,720.35 9,366,009.87 0.183 6.108 80.000 0.146 6.108 80.000 0.146
- Tie Beam Formwork m2 14.16 195,085.00 2,762,403.60 0.054 7.080 50.000 0.027 7.080 50.000 0.027
4 20/25 Tie Beam S2
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

- Concrete K-250 m3 2.12 1,226,720.35 2,597,580.34 0.051 1.694 80.000 0.040 1.694 80.000 0.040
- Tie Beam Formwork m2 9.27 195,085.00 1,809,413.37 0.035 4.637 50.000 0.018 4.637 50.000 0.018
6 20/25 Beam B1
- Concrete K-250 m3 7.21 1,226,720.35 8,841,586.92 0.172
- Reinforcement kg 1240.96 16,006.10 19,862,891.99 0.387
- Beam Formwork m2 100.91 282,050.00 28,460,255.25 0.555
7 Floor Slab t=12 cm
- Concrete K-250 m3 40.20 1,226,720.35 49,314,158.04 0.961 32.160 80.000 0.769 8.040 20.000 0.192 40.200 100.000 0.961
- Reinforcement wire ties m3 3116.59 16,006.10 49,884,490.41 0.972 3116.592 100.000 0.972 3116.592 100.000 0.972
- Formwork Floor m3 11.17 225,800.00 2,522,637.60 0.049 11.172 100.000 0.049 11.172 100.000 0.049
Total Structural Cost 253,479,073.02 4.940 2.021 0.192 2.214

IV CLASSROOM 9x8 (2 ROOMS) - B1


A PREPARATION WORK
1 Site Measurement m' 56.00 22,990.00 1,287,440.00 0.025 56.000 100.000 0.025 56.000 100.000 0.025
PREPARATION 1,287,440.00 0.025 0.025 0.025

B ARCHITECTURAL WORKS
I 1ST FLOOR
A WALLWORK
1 1/2 Brick Wall 1:5 m2 120.73 139,920.88 16,892,647.84 0.329
2 Mortar Plaster Work m2 469.86 67,316.74 31,629,445.34 0.616
3 Mortar Neat Plaster Work m2 469.86 42,427.00 19,934,750.22 0.389
4 Practical Column & Lintel Beam Work
- K250 Concrete m3 1.01 1,226,720.35 1,238,987.55 0.024
- Reinforcement kg 155.36 16,006.10 2,486,772.52 0.048
- Formwork m2 16.83 185,185.00 3,117,280.83 0.061
B Ceiling Installation Work
1 Ceiling Hollow frame m2 240.29 149,919.00 36,023,436.83 0.702
2 6 mm of Calcium Board GRC (Ceiling Interior) m2 140.18 72,230.40 10,125,257.47 0.197
3 6 mm of Calcium Board GRC (Ceiling Exterior) m2 100.11 72,230.40 7,230,696.42 0.141
C Floor Installation Work
1 Tile 40x40 cm (Polished) Rooms m2 135.53 162,962.80 22,086,348.28 0.430
2 Tile 40x40 cm (Unpolished) Hallway m2 35.96 166,262.80 5,979,475.34 0.117
D Door and Window Installation Work (complete w. Aluminium frame)
1 Door Alumunium Frame Installation Work (type P1) Unit 2.00 1,082,950.00 2,165,900.00 0.042
2 Leaf Door Instalation Work (type P1) Unit 2.00 2,625,000.00 5,250,000.00 0.102
3 Door Alumunium Frame Installation Work (type P2) Unit 2.00 1,533,286.70 3,066,573.40 0.060
4 Leaf Door Instalation Work (type P2) Unit 2.00 5,250,000.00 10,500,000.00 0.205
5 Window Allumunium Frame Installation Work (type J3) Unit 8.00 3,546,928.00 28,375,424.00 0.553
E Painting Works
1 Wall ; Interior m2 201.68 40,563.60 8,180,866.85 0.159
2 Wall Painting; Exterior m2 268.18 54,313.60 14,565,821.25 0.284
3 Ceiling Painting; Interior m2 140.18 40,563.60 5,686,205.45 0.111
4 Ceiling Painting; Exterior m2 100.11 54,313.60 5,437,117.24 0.106
5 Calsiplank Painting m2 19.28 54,313.60 1,047,383.46 0.020
F Other Works
1 Stair
- Retaining Wall 1 Pc : 5 Ps m2 6.48 139,920.88 906,687.30 0.018
- Landfill for floor elevation m3 0.97 163,075.00 158,508.90 0.003
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.18 912,325.16 164,218.53 0.003
- Chevron Works m 36.00 40,315.00 1,451,340.00 0.028
- Mortar Plaster Work m2 4.86 67,316.74 326,890.11 0.006
- Mortar Neat Plaster Work m2 4.86 42,427.00 206,025.51 0.004
B.2 ROOF WORKS
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

I Roof Covering Works


1 Zincalume Spandex h 0,30mm Installation m2 324.55 171,306.67 55,597,578.67 1.084
2 Light Steel Frame; including rafter and accessoris m2 324.55 213,420.90 69,265,753.10 1.350
3 Aluminium Foil Installation m2 324.55 27,087.50 8,791,248.13 0.171
4 Roof Ridges, Zincalum Spandex m 34.88 73,810.00 2,574,492.80 0.050
5 Calsiplank, fin. Paint m 80.31 59,070.00 4,744,029.84 0.092
6 Roof Jalousie Unit 2.00 1,563,743.50 3,127,487.00 0.061
Total Architectural Cost 388,334,650.18 7.568

C STRUCTURAL WORK
I 1ST LEVEL
1 K1 Column 30/30
- K-250 Concrete m3 6.66 1,226,720.35 8,164,437.28 0.159
- Reinforcement kg 94.66 16,006.10 1,515,157.55 0.030
- Column Formwork m2 88.74 275,300.00 24,430,122.00 0.476
2 K2 Column 20/20
- K-250 Concrete m3 1.22 1,226,720.35 1,494,145.39 0.029
- Reinforcement kg 18.72 16,006.10 299,676.98 0.006
- Column Formwork m2 24.36 275,300.00 6,706,308.00 0.131
3 25/30 Tie Beam S1
- Concrete K-250 m3 4.10 1,226,720.35 5,023,419.83 0.098 4.095 100.000 0.098 4.095 100.000 0.098
- Tie Beam Formwork m2 9.30 195,085.00 1,814,290.50 0.035 4.650 50.000 0.018 4.650 50.000 0.018
4 20/25 Tie Beam S2
- Concrete K-250 m3 1.10 1,226,720.35 1,352,459.18 0.026 1.102 100.000 0.026 1.102 100.000 0.026
- Tie Beam Formwork m2 5.07 195,085.00 990,056.37 0.019 2.537 50.000 0.010 2.537 50.000 0.010
5 20/25 Beam B1
- Concrete K-250 m3 3.83 1,226,720.35 4,701,405.74 0.092
- Reinforcement kg 670.48 16,006.10 10,731,782.56 0.209
- Beam Formwork m2 53.66 282,050.00 15,133,392.75 0.295
6 Floor Slab t=12 cm
- Concrete K-250 m3 20.10 1,226,720.35 24,657,079.02 0.481 20.100 100.000 0.481 20.100 100.000 0.481
- Reinforcement kg 1031.59 16,006.10 16,511,723.90 0.322 1031.589 100.000 0.322 1031.589 100.000 0.322
- Floor Formwork m2 6.85 225,800.00 1,547,181.60 0.030 6.852 100.000 0.030 6.852 100.000 0.030
Total Structural Cost 125,072,638.65 2.438 0.984 0.984

V CLASSROOM 9x8 (2 ROOMS)-B2


A PREPARATION WORK
1 Site Measurement m' 56.00 22,990.00 1,287,440.00 0.025 56.000 100.000 0.025 56.000 100.000 0.025
PREPARATION 1,287,440.00 0.025 0.025 0.025

B ARCHITECTURAL WORKS
I 1ST FLOOR
A WALLWORK
1 1/2 Brick Wall 1:5 m2 120.73 139,920.88 16,892,647.84 0.329
2 Mortar Plaster Work m2 469.86 67,316.74 31,629,445.34 0.616
3 Mortar Neat Plaster Work m2 469.86 42,427.00 19,934,750.22 0.389
4 Practical Column & Lintel Beam Work
- K250 Concrete m3 1.01 1,226,720.35 1,238,987.55 0.024
- Reinforcement kg 155.36 16,006.10 2,486,772.52 0.048
- Formwork m2 16.83 185,185.00 3,117,280.83 0.061
B Ceiling Installation Work
1 Ceiling Hollow frame m2 240.29 149,919.00 36,023,436.83 0.702
2 6 mm of Calcium Board GRC (Ceiling Interior) m2 140.18 72,230.40 10,125,257.47 0.197
3 6 mm of Calcium Board GRC (Ceiling Exterior) m2 100.11 72,230.40 7,230,696.42 0.141
C Floor Installation Work
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

1 Tile 40x40 cm (Polished) Rooms m2


135.53 162,962.80 22,086,348.28 0.430
2 Tile 40x40 cm (Unpolished) Hallway m2 35.96 166,262.80 5,979,475.34 0.117
D Door and Window Installation Work (complete w. Aluminium frame)
1 Door Alumunium Frame Installation Work (type P1) Unit 2.00 1,082,950.00 2,165,900.00 0.042
2 Leaf Door Instalation Work (type P1) Unit 2.00 2,625,000.00 5,250,000.00 0.102
3 Door Alumunium Frame Installation Work (type P2) Unit 2.00 1,533,286.70 3,066,573.40 0.060
4 Leaf Door Instalation Work (type P2) Unit 2.00 5,250,000.00 10,500,000.00 0.205
5 Window Allumunium Frame Installation Work (type J3) Unit 8.00 3,546,928.00 28,375,424.00 0.553
E Painting Works
1 Wall ; Interior m2
201.68 40,563.60 8,180,866.85 0.159
2 Wall Painting; Exterior m2 268.18 54,313.60 14,565,821.25 0.284
3 Ceiling Painting m2 140.18 40,563.60 5,686,205.45 0.111
4 Ceiling Painting; Exterior m2 100.11 54,313.60 5,437,117.24 0.106
5 Calsiplank Painting m2 19.28 54,313.60 1,047,383.46 0.020
F Other Works
1 Stair
- Retaining Wall 1 Pc : 5 Ps m2 6.48 139,920.88 906,687.30 0.018
- Landfill for floor elevation m3 0.97 163,075.00 158,508.90 0.003
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.18 912,325.16 164,218.53 0.003
- Chevron Works m 36.00 40,315.00 1,451,340.00 0.028
- Mortar Plaster Work m2 4.86 67,316.74 326,890.11 0.006
- Mortar Neat Plaster Work m2 4.86 42,427.00 206,025.51 0.004

B.2 ROOF WORKS


I Roof Covering Works
1 Zincalume Spandex h 0,30mm Installation m2 324.55 171,306.67 55,597,578.67 1.084
2 Light Steel Frame; including rafter and accessoris m2 324.55 213,420.90 69,265,753.10 1.350
3 Aluminium Foil Installation m2 324.55 27,087.50 8,791,248.13 0.171
4 Roof Ridges, Zincalum Spandex m 34.88 73,810.00 2,574,492.80 0.050
5 Calsiplank m 80.31 59,070.00 4,744,029.84 0.092
6 Roof Jalousie Unit 2.00 1,563,743.50 3,127,487.00 0.061
Total Architectural Cost 388,334,650.18 7.568

C STRUCTURAL WORK
I 1ST FLOOR
1 K1 Column 30/30
- K-250 Concrete m3 6.66 1,226,720.35 8,164,437.28 0.159
- Reinforcement kg 104.13 16,006.10 1,666,726.35 0.032
- Column Formwork m2 88.74 275,300.00 24,430,122.00 0.476
2 K2 Column 20/20
- K-250 Concrete m3 1.21 1,226,720.35 1,483,840.93 0.029
- Reinforcement kg 22.18 16,006.10 354,936.44 0.007
- Column Formwork m2 24.36 275,300.00 6,706,308.00 0.131
3 25/30 Tie Beam S1
- Concrete K-250 m3 4.10 1,226,720.35 5,023,419.83 0.098
- Tie Beam Formwork m2 9.30 195,085.00 1,814,290.50 0.035 4.650 50.000 0.018 4.650 50.000 0.018
4 20/25 Tie Beam S2
- Concrete K-250 m3 1.10 1,226,720.35 1,352,459.18 0.026
- Tie Beam Formwork m2 5.07 195,085.00 990,056.37 0.019 2.537 50.000 0.010 2.537 50.000 0.010
5 20/25 Beam B1
- Concrete K-250 m3 3.83 1,226,720.35 4,701,405.74 0.092
- Reinforcement kg 670.48 16,006.10 10,731,782.56 0.209
- Beam Formwork m2 53.66 282,050.00 15,133,392.75 0.295
6 Floor Slab t=12 cm
- Concrete K-250 m3 20.10 1,226,720.35 24,657,079.02 0.481 7.035 35.000 0.168 7.035 35.000 0.168
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

- Reinforcement kg 1564.25 16,006.10 25,037,469.10 0.488 1564.245 100.000 0.488 1564.245 100.000 0.488
- Floor Formwork m2 6.85 225,800.00 1,547,181.60 0.030 6.852 100.000 0.030 6.852 100.000 0.030
Total Structural Cost 133,794,907.67 2.608 0.545 0.168 0.714
D CLASSROOM ELECTRICAL WORKS
D.1 LOW VOLTAGE PANEL WORKS
Procurement and
1 installation
MCB-BOX of of the
a complete
Classroom unit 4.00 1,124,332.00 4,497,328.00 0.088
Panel
D.2 LIGHTING WORKS
Procurement, installation of lighting and sockets
a. CLASSROOM A1 ( 4 ROOMS )
1 Roset Led 22 W Type Bulb unit 28.00 143,896.50 4,029,102.00 0.079
2 Single Electrical Switch unit 1.00 34,727.00 34,727.00 0.001
3 Double Electrical Switch unit 3.00 42,350.00 127,050.00 0.002
4 100 W Wall Electric Socket unit 8.00 49,929.00 399,432.00 0.008
5 Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 28.00 194,035.42 5,432,991.67 0.106
6 Electrical Socket NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 8.00 218,556.25 1,748,450.00 0.034
b. CLASSROOM B1 ( 2 ROOMS )
1 Roset Led 22 W Type Bulb unit 14.00 143,896.50 2,014,551.00 0.039
2 Single Electrical Switch unit 1.00 34,727.00 34,727.00 0.001
3 Double Electrical Switch unit 2.00 42,350.00 84,700.00 0.002
4 100 W Wall Electric Socket unit 4.00 49,929.00 199,716.00 0.004
5 Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 14.00 194,035.42 2,716,495.83 0.053
6 Electrical Socket NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 4.00 218,556.25 874,225.00 0.017
c. CLASSROOM A2 ( 4 ROOMS )
1 Roset Led 22 W Type Bulb unit 28.00 143,896.50 4,029,102.00 0.079
2 Single Electrical Switch unit 1.00 34,727.00 34,727.00 0.001
3 Double Electrical Switch unit 3.00 42,350.00 127,050.00 0.002
4 100 W Wall Electric Socket unit 8.00 49,929.00 399,432.00 0.008
5 Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 28.00 194,035.42 5,432,991.67 0.106
6 Electrical Socket NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 8.00 218,556.25 1,748,450.00 0.034
d. CLASSROOM B2 ( 2 ROOMS )
1 Roset Led 22 W Type Bulb unit 14.00 143,896.50 2,014,551.00 0.039
2 Single Electrical Switch unit 1.00 34,727.00 34,727.00 0.001
3 Double Electrical Switch unit 2.00 42,350.00 84,700.00 0.002
4 100 W Wall Electric Socket unit 4.00 49,929.00 199,716.00 0.004
5 Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 14.00 194,035.42 2,716,495.83 0.053
6 Electrical Socket NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 4.00 218,556.25 874,225.00 0.017

D.3 Lightning Rod Installation


Procurement, installation of a complete lightning rod
a. CLASSROOM B1 (2 ROOM)
1 Ø 3/4 30cm Air Terminal , Completed With Ø 3/4 70cm GIP set 3.00 442,541.00 1,327,623.00 0.026
2 BC 25 mm² Cable Installation m 29.00 75,065.83 2,176,909.17 0.042
3 600mm² x 600mm² c/w Junction Box with Grounding System set 1.00 948,398.00 948,398.00 0.018
4 Auxiliary Materials lot 1.00 366,501.21 366,501.21 0.007
b. CLASSROOM A1 (4 ROOM)
1 Ø 3/4 30cm Air Terminal , Completed With Ø 3/4 70cm GIP set 6.00 442,541.00 2,655,246.00 0.052
2 BC 25 mm² Cable Installation m 48.00 75,065.83 3,603,160.00 0.070
3 600mm² x 600mm² c/w Junction Box with Grounding System set 1.00 948,398.00 948,398.00 0.018
4 Auxiliary Materials lot 1.00 720,680.40 720,680.40 0.014
c. CLASSROOM B2 (2 ROOM)
1 Ø 3/4 30cm Air Terminal , Completed With Ø 3/4 70cm GIP set 3.00 442,541.00 1,327,623.00 0.026
2 BC 25 mm² Cable Installation m 29.00 75,065.83 2,176,909.17 0.042
3 600mm² x 600mm² c/w Junction Box with Grounding System set 1.00 948,398.00 948,398.00 0.018
4 Auxiliary Materials lot 1.00 445,293.02 445,293.02 0.009
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

d. CLASSROOM A2 (4 ROOM)
1 Ø 3/4 30cm Air Terminal , Completed With Ø 3/4 70cm GIP set 6.00 442,541.00 2,655,246.00 0.052
2 BC 25 mm² Cable Installation m 48.00 75,065.83 3,603,160.00 0.070
3 600mm² x 600mm² c/w Junction Box with Grounding System set 1.00 948,398.00 948,398.00 0.018
4 Auxiliary Materials lot 1.00 720,680.40 720,680.40 0.014
Total Electrical Cost 65,462,286.36 1.276

VI TEACHER OFFICE-C
A PREPARATION WORK
1 Site Measurement and Bowplank Installation m' 66.00 278,630.00 18,389,580.00 0.358
PREPARATION 18,389,580.00 0.358

B ARCHITECTURAL WORKS
B.1 1ST FLOOR
I WALLWORK
1 Brick Wall 1:5 M2 191.45 139,920.88 26,788,412.16 0.522
2 Brick Wall 1:3 M2 77.23 139,920.88 10,805,949.64 0.211
3 Mortar Plaster Work M2 709.39 67,316.74 47,753,488.44 0.931
4 Mortar Neat Plaster Work M2 709.39 42,427.00 30,097,077.40 0.587
5 Practical Column & Lintel Beam Work
- K250 Concrete M3 3.63 1,226,720.35 4,450,541.43 0.087
- Reinforcement kg 542.33 16,006.10 8,680,650.20 0.169
- Formwork Kg 60.47 185,185.00 11,197,519.67 0.218
6 Wall Roster M2 3.86 565,882.90 2,182,044.46 0.043
7 Wall Tiles 25x40cm (Unpolished) M2 44.13 183,499.80 8,097,479.17 0.158
8 Table Pantry Wall Tiles 25x40cm (Polished) M2 1.13 180,474.80 203,034.15 0.004
9 Table Pantry Tiles 40x40cm (Polished) M3 2.13 162,962.80 346,295.95 0.007
II Floor Installation Work
1 Tile 40x40 cm (Polished) Rooms M2 92.85 162,962.80 15,130,607.09 0.295
2 Tile 40x40 cm (Unpolished) Hallway M2 47.46 166,262.80 7,891,165.01 0.154
3 Tile 40x40 cm (Unpolished) Toilet M2 18.88 166,262.80 3,139,706.72 0.061
4 Waterproofing Coating + mortar M2 18.88 119,614.62 2,258,802.41 0.044
III Sanitary Work and Installation
Sanitary work includes procurement & installation
1 Sitting Toilet Unit 3.00 3,699,704.80 11,099,114.40 0.216
2 Shower spray Unit 3.00 960,355.00 2,881,065.00 0.056
3 Floor Drain Unit 5.00 675,235.00 3,376,175.00 0.066
4 Washtafel Unit 2.00 3,723,830.00 7,447,660.00 0.145
5 Soap Dispenser Unit 2.00 165,275.00 330,550.00 0.006
6 6mm; uk 500x700 of mirror work Unit 2.00 126,379.00 252,758.00 0.005
7 Faucet Unit 5.00 746,652.50 3,733,262.50 0.073
8 Robe Hook Unit 3.00 334,235.00 1,002,705.00 0.020
9 Tissue Holder Unit 3.00 585,475.00 1,756,425.00 0.034
10 Kitchen zink Unit 1.00 743,336.00 743,336.00 0.014
IV Painting Works
1 Wall ; Interior M2 460.92 40,563.60 18,696,615.08 0.364
2 Wall Painting; Exterior M2 248.46 54,313.60 13,494,974.31 0.263
3 Ceiling Painting; Interior M2 149.87 40,563.60 6,079,347.86 0.118
4 Ceiling Painting; Exterior M2 143.25 54,313.60 7,780,531.83 0.152
5 Calsiplank Painting M2 22.23 54,313.60 1,207,174.07 0.024
V Door and Window Installation Work (complete w. Aluminium frame)
1 Door Alumunium Frame Installation Work (type P1) Unit 9.00 1,082,950.00 9,746,550.00 0.190
2 Leaf Door Instalation Work (type P1) Unit 9.00 2,625,000.00 23,625,000.00 0.460
3 Door Alumunium Frame Installation Work (type P2) Unit 3.00 1,533,286.70 4,599,860.10 0.090
4 Leaf Door Instalation Work (type P2) Unit 3.00 5,250,000.00 15,750,000.00 0.307
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

5 Door Alumunium Frame Installation Work (type P3) Unit 4.00 2,368,025.00 9,472,100.00 0.185
6 Door And Window Aluminium Installation Work (type PJ1) Unit 1.00 6,195,904.00 6,195,904.00 0.121
7 Partition M2 13.74 457,506.50 6,285,224.30 0.122
8 Window Installation Work (type J3) Unit 1.00 3,546,928.00 3,546,928.00 0.069
9 Window Installation Work (type J2) Unit 8.00 3,417,381.00 27,339,048.00 0.533
10 Window Installation Work (type V1) Unit 5.00 615,450.00 3,077,250.00 0.060
VI Ceiling Installation Work
1 Ceiling Hollow frame M2 293.12 149,919.00 43,944,856.96 0.856
2 6 mm of Calcium Board GRC (Ceiling Interior) m2 149.87 72,230.40 10,825,314.51 0.211
3 6 mm of Calcium Board GRC (Ceiling Exterior) m2 143.25 72,230.40 10,347,149.26 0.202
VII Other Works
1 Disability Ramp
- Disability Handrail Ramp work M1 14.10 760,976.98 10,729,014.37 0.209
- Lean Ramp 1 Pc : 3 Ps : 5 Kr M3 0.78 912,325.16 711,613.62 0.014
- Chevron Works M1 20.90 40,315.00 842,381.92 0.016
- Retaining Wall Ramp 1 Pc : 5 Ps M2 5.75 139,920.88 803,985.38 0.016
- Landfill for floor elevation M3 1.25 163,075.00 204,332.97 0.004
- Mortar Plaster Work M2 5.76 67,316.74 387,609.81 0.008
- Mortar Neat Plaster Work M2 5.76 42,427.00 244,294.67 0.005
2 Stair
- Retaining Wall 1 Pc : 5 Ps M2 8.02 139,920.88 1,122,445.30 0.022
- Landfill for floor elevation M3 1.42 163,075.00 231,240.35 0.005
- Lean Ramp 1 Pc : 3 Ps : 5 Kr M3 0.27 912,325.16 246,327.79 0.005
- Chevron Works M1 18.00 40,315.00 725,670.00 0.014
- Mortar Plaster Work M2 2.71 67,316.74 182,159.11 0.004
- Mortar Neat Plaster Work M2 2.71 42,427.00 114,807.46 0.002
B.2 ROOF WORKS
A Roof Covering Works
1 Zincalume Spandex h 0,40mm Installation M2 376.81 171,306.67 64,550,750.29 1.258
2 Light Steel Frame; including rafter and accessoris M2 376.81 213,420.90 80,419,983.01 1.567
3 Insulation layer / Aluminium Foil Installation M2 376.81 27,087.50 10,206,949.23 0.199
4 Roof Ridges Zincalum Spandex M1 40.49 73,810.00 2,988,493.09 0.058
5 Calsiplank M1 88.41 59,070.00 5,222,496.84 0.102
6 Roof Jalousie Unit 2.00 1,563,743.50 3,127,487.00 0.061
Total Architectural Cost 616,721,695.29 12.019

C. STRUCTURAL WORK
I FOUNDATION WORK
1 Tie Beam S1-25/30
- Concrete K-250 M3 6.68 1,226,720.35 8,197,558.73 0.160
- Reinforcement Kg 2.65 16,006.10 42,431.37 0.001
- Reinforcement wire ties m3 101.27 16,006.10 1,620,878.36 0.032
- Tie Beam Formwork M2 10.41 195,085.00 2,030,834.85 0.040
2 Tie Beam S2-20/25
- Concrete K-250 M3 1.90 1,226,720.35 2,332,302.06 0.045
- Reinforcement Kg 365.78 16,006.10 5,854,675.41 0.114
- Tie Beam Formwork M2 6.53 195,085.00 1,272,929.63 0.025
II 1ST LEVEL
1 K1 Column 30/30
- Concrete K-250 M3 7.83 1,226,720.35 9,605,220.33 0.187
- Reinforcement Kg 108.05 16,006.10 1,729,501.09 0.034
- Reinforcement wire ties m3 92.79 16,006.10 1,485,227.76 0.029
- Formwork Column M2 104.40 275,300.00 28,741,320.00 0.560
2 K2 Column 20/20
- Concrete K-250 M3 1.39 1,226,720.35 1,707,594.73 0.033
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

- Reinforcement Kg 27.46 16,006.10 439,526.24 0.009


- Reinforcement wire ties m3 90.77 16,006.10 1,452,916.15 0.028
- Formwork Column M2 27.84 275,300.00 7,664,352.00 0.149
3 Beam B1 20/25
- Concrete K-250 M3 2.76 1,226,720.35 3,383,294.72 0.066
- Reinforcement Kg 907.27 16,006.10 14,521,900.22 0.283
- Formwork Beam M2 38.61 282,050.00 10,890,514.60 0.212
4 Floor Slab T=12 cm
- Base Concrete T=5 cm M3 1.10 912,325.16 1,000,478.58 0.019
- Sand layer T=10 cm M3 0.53 192,830.00 101,235.75 0.002
- K-250 Concrete M3 22.78 1,226,720.35 27,942,726.80 0.545
- Reinforcement Kg 1894.27 16,006.10 30,319,878.73 0.591
- Floor Formwork M2 8.05 225,800.00 1,818,141.60 0.035
5 Plate Table Pantry
- Concrete K-250 M 3
0.39 1,226,720.35 474,740.78 0.009
- Reinforcement Kg 18.71 16,006.10 299,486.54 0.006
- Formwork Plate M2 2.12 295,300.00 624,559.50 0.012
Total Structural Cost 165,554,226.54 3.226
D. MECHANICAL AND ELECTRICAL WORKS
1 PLUMBING WORKS
1.1 CLEAN WATER SYSTEM
Procurement and installation of PVC Pipes including excavation, accessories, and auxiliary equipment
a. Toilet and Clean Water Piping and Its Completeness
1 PVC AW Ø 25 mm m 26.00 33,610.50 873,873.00 0.017
2 PVC AW Ø 20 mm m 2.00 28,026.63 56,053.25 0.001
3 Fitting ls 1.00 130,975.63 130,975.63 0.003
4 Gate Valve Ø 32mm unit 3.00 126,610.00 379,830.00 0.007
1.2 VENT AND GREY WATER SYSTEM
Procurement and installation of PVC Pipes including excavation, accessories, and auxiliary tool
a. Grey Water Piping and Its completeness in toilet to Sepictank
1 PVC-AW Ø 100 mm; SW (Sewage Water) m 11.00 185,950.88 2,045,459.63 0.040
2 PVC-AW Ø 80 mm; WW (Waste Water) m 28.00 123,292.13 3,452,179.50 0.067
3 PVC-AW Ø 65 mm; WW (Waste Water) m 3.00 95,628.50 286,885.50 0.006
4 PVC-AW Ø 50 mm; WW (Waste Water) m 3.00 55,061.88 165,185.63 0.003
5 Floor Clean Out Ø 80 mm, WW (Waste Water) bh 3.00 230,725.00 692,175.00 0.013
6 Floor Clean Out Ø 100 mm, SW (Sewage Water) bh 2.00 340,263.00 680,526.00 0.013
7 Fitting ls 1.00 732,241.13 732,241.13 0.014

D. ELECTRICAL WORKS
D.1 LOW VOLTAGE PANEL WORKS
Procurement and installation
1 MCB-BOX of The Extra Curricullar Building unit 1.00 1,156,969.00 1,156,969.00 0.023

D.2 LIGHTING WORKS


Procurement and installation
1 Roset Led 22 W Type Bulb unit 26.00 143,896.50 3,741,309.00 0.073
2 Roset Led 5 W Type Bulb (toilet and antrance) unit 10.00 69,399.00 693,990.00 0.014
3 Single Electrical Switch unit 6.00 34,727.00 208,362.00 0.004
4 Double Electrical Switch unit 6.00 42,350.00 254,100.00 0.005
5 100 W Wall Electric Socket unit 19.00 49,929.00 948,651.00 0.018
6 Electric socket for AC unit 6.00 57,783.00 346,698.00 0.007
7 Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 36.00 194,035.42 6,985,275.00 0.136
8 Electrical Socket NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 25.00 218,556.25 5,463,906.25 0.106
D.3 Lightning Rod Installation
Procurement and installation
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

1 Ø 3/4 30cm Air Terminal , Completed With Ø 3/4 70cm GIP set 4.00 442,541.00 1,770,164.00 0.034
2 BC 25 mm² Cable Installation m 38.00 75,065.83 2,852,501.67 0.056
3 600mm² x 600mm² c/w Junction Box with Grounding System set 1.00 948,398.00 948,398.00 0.018
4 Auxiliary Materials lot 1.00 366,501.21 366,501.21 0.007
Total Mechanical And Electrical Cost 35,232,209.38 0.687

VII MUSHOLA 8x7-D


A PREPARATION WORK
1 Site Measurement and Bowplank Installation M1 30.00 278,630.00 8,358,900.00 0.163 30.000 100.000 0.163 30.000 100.000 0.163
PREPARATION 8,358,900.00 0.163 0.163 0.163

B ARCHITECTURAL WORKS
B.1 1ST FLOOR
A WALLWORK
1Brick Wall 1:5 M2 46.48 139,920.88 6,503,522.50 0.127
2Brick Wall 1:3 M2 33.19 139,920.88 4,643,414.32 0.090
3Mortar Plaster Work M2 222.35 67,316.74 14,967,608.76 0.292
4Mortar Neat Plaster Work M2 222.35 42,427.00 9,433,473.74 0.184
5Practical Column & Lintel Beam Work
- K250 Concrete M3 1.42 1,226,720.35 1,735,809.29 0.034
- Reinforcement Kg 213.36 16,006.10 3,415,134.60 0.067
- Formwork M2 23.58 185,185.00 4,367,279.58 0.085
6 Wall Roster M2 2.88 565,882.90 1,629,742.75 0.032
7 Wall Tiles 25x40cm (Unpolished) M2 15.68 183,499.80 2,877,276.86 0.056
B Ceiling Installation Work
1 Ceiling Hollow frame M2 102.48 149,919.00 15,363,699.12 0.299
2 6 mm of Calcium Board GRC (Ceiling Interior) m2 27.30 72,230.40 1,971,889.92 0.038
3 6 mm of Calcium Board GRC (Ceiling Exterior) m2 75.18 72,230.40 5,430,281.47 0.106
C Floor Installation Work
1 Tiles 40x40 cm (Polished) M2 43.28 162,962.80 7,053,029.98 0.137
2 Tiles 40x40 cm (Unpolished) M2 7.72 166,262.80 1,283,548.82 0.025
D Door and Window Installation Work (complete w. Aluminium frame)
1 Door Alumunium Frame Installation Work (type P1) Unit 2.00 1,082,950.00 2,165,900.00 0.042
2 Leaf Door Instalation Work (type P1) Unit 2.00 2,625,000.00 5,250,000.00 0.102
3 Door Alumunium Frame Installation Work (type P2) Unit 1.00 1,533,286.70 1,533,286.70 0.030
4 Leaf Door Instalation Work (type P2) Unit 1.00 5,250,000.00 5,250,000.00 0.102
5 Door Alumunium Frame Installation Work (type P3) Unit 2.00 2,368,025.00 4,736,050.00 0.092
6 Window Installation Work (type J1) Unit 2.00 2,539,878.00 5,079,756.00 0.099
7 Window Installation Work (type J2) Unit 4.00 2,928,090.00 11,712,360.00 0.228
8 Window Installation Work (type V1) Unit 2.00 615,450.00 1,230,900.00 0.024
E Sanitary Work and Installation
Sanitary work includes procurement & installation
1 Sitting Toilet Unit 2.00 3,699,704.80 7,399,409.60 0.144
2 Shower spray Unit 2.00 960,355.00 1,920,710.00 0.037
3 Floor Drain Unit 2.00 675,235.00 1,350,470.00 0.026
4 Robe Hook Unit 2.00 334,235.00 668,470.00 0.013
5 Faucet Unit 6.00 746,652.50 4,479,915.00 0.087
F Painting Works
1 Wall ; Interior M2 75.71 40,563.60 3,070,907.90 0.060
2 Wall Painting; Exterior M2 146.64 54,313.60 7,964,546.30 0.155
3 Ceiling Painting; Interior M2 27.30 40,563.60 1,107,386.28 0.022
4 Ceiling Painting; Exterior M2 75.18 54,313.60 4,083,296.45 0.080
5 Calsiplank Painting M2 15.12 54,313.60 821,449.75 0.016
G Other Works
1 Railling for Disability access
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

-Disability Handrail Ramp work M1


14.10 760,976.98 10,729,014.37 0.209
- Retaining Wall Ramp 1 Pc : 5 Ps M2 0.78 139,920.88 109,138.29 0.002
- Lean Ramp 1 Pc : 3 Ps : 5 Kr M3 20.90 912,325.16 19,063,034.19 0.372
- Chevron Works M1 5.75 40,315.00 231,649.99 0.005
- Landfill for floor elevation M2 1.25 163,075.00 204,332.97 0.004
- Mortar Plaster Work M2 5.76 67,316.74 387,609.81 0.008
- Mortar Neat Plaster Work M2 5.76 42,427.00 244,294.67 0.005
2 Stair
- Retaining Wall 1 Pc : 5 Ps M2 6.48 139,920.88 906,687.30 0.018
- Landfill for floor elevation M3 0.97 163,075.00 158,508.90 0.003
- Lean Ramp 1 Pc : 3 Ps : 5 Kr M3 0.18 912,325.16 164,218.53 0.003
- Chevron Works M1 36.00 40,315.00 1,451,340.00 0.028
- Mortar Plaster Work M2 4.86 67,316.74 326,890.11 0.006
- Mortar Neat Plaster Work M2 4.86 42,427.00 206,025.51 0.004
B.2 ROOF WORKS
A Roof Covering Works
1 Zincalume Spandex h 0,30mm Installation M2 128.55 171,306.67 22,021,472.00 0.429
2 Light Steel Frame; including rafter and accessoris M2 128.55 213,420.90 27,435,256.70 0.535
3 Insulation Layer M2 128.55 27,087.50 3,482,098.13 0.068
4 Roof Ridges, Zincalum Spandex M1 28.80 73,810.00 2,125,728.00 0.041
5 Calsiplank M1 50.41 59,070.00 2,977,954.98 0.058
6 Crown (Makara) Ø 50 cm Unit 1.00 2,238,104.00 2,238,104.00 0.044
Total Architectural Cost 244,963,884.16 4.774
C. STRUCTURAL WORK
I FOUNDATION WORK
1 Foundation PD1
- Backfill M3 10.87 62,150.00 675,694.80 0.013
- Concrete K-250 M3 1.73 1,226,720.35 2,119,772.76 0.041
- Reinforcement Kg 167.71 16,006.10 2,684,452.05 0.052 167.714 100.000 0.052 167.714 100.000 0.052
- Formwork M2 5.76 185,185.00 1,066,665.60 0.021
2 Foundation PD1A
- Backfill M3 24.79 62,150.00 1,540,822.80 0.030
- Concrete K-250 M3 3.60 1,226,720.35 4,416,193.26 0.086
- Reinforcement Kg 449.49 16,006.10 7,194,649.02 0.140 449.494 100.000 0.140 449.494 100.000 0.140
- Formwork M2 14.40 185,185.00 2,666,664.00 0.052
3 PD2 Broken Stone Foundation
- Sand layer t=10cm M3 1.76 192,830.00 340,152.12 0.007
- Masonry 1:4 M3 9.03 756,723.00 6,833,738.40 0.133
- Aanstamping Stone M3 2.65 332,739.00 880,427.39 0.017
- Backfill M3 3.50 62,150.00 217,742.52 0.004
4 PD3 Broken Stone Foundation
- Sand layer t=10cm M3 2.93 192,830.00 565,763.22 0.011
- Masonry 1:4 M3 15.79 756,723.00 11,952,212.77 0.233
- Aanstamping Stone M3 4.40 332,739.00 1,464,384.34 0.029
- Backfill M3 5.83 62,150.00 362,163.59 0.007
5 Soil fill M3 0.64 128,715.71 82,519.64 0.002

II. 1ST LEVEL


1 K1 30/30 Column
- Concrete K-250 M3 2.06 1,226,720.35 2,526,062.54 0.049
- Reinforcement Kg 33.57 16,006.10 537,361.93 0.010
- Formwork Column M2 27.46 275,300.00 7,558,636.80 0.147
2 K2 20/20 Column
- Concrete K-250 M3 2.75 1,226,720.35 3,368,083.39 0.066
- Reinforcement Kg 197.84 16,006.10 3,166,675.70 0.062
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

- Formwork Column M 2
54.91 275,300.00 15,117,273.60 0.295
3 S1 25/30 Tie Beam
- Concrete K-250 M 3
1.38 1,226,720.35 1,692,874.08 0.033
- Reinforcement Kg 318.51 16,006.10 5,098,120.91 0.099
- Tie Beam Formwork M2 11.04 195,085.00 2,153,738.40 0.042
4 S2 20/25 Tie Beam
- Concrete K-250 M3 1.60 1,226,720.35 1,960,299.12 0.038
- Reinforcement Kg 324.91 16,006.10 5,200,476.43 0.101
- Tie Beam Formwork M2 15.98 195,085.00 3,117,458.30 0.061
5 B1 20/25 Beam
- Concrete K-250 M3 2.59 1,226,720.35 3,179,659.15 0.062
- Reinforcement Kg 514.35 16,006.10 8,232,811.65 0.160
- Beam Formwork M2 36.29 282,050.00 10,235,030.40 0.199
6 Floor Slab h=12 cm
- K-250 Concrete M3 5.31 1,226,720.35 6,507,996.80 0.127
- Reinforcement Kg 491.87 16,006.10 7,872,894.16 0.153
- Floor Formwork M2 3.70 225,800.00 834,556.80 0.016
- Sand layer t=10cm M3 3.64 192,830.00 702,094.03 0.014
- Base Concrete t=5cm M3 1.82 912,325.16 1,660,887.95 0.032
Total Structural Cost 135,787,010.43 2.646 0.193 0.193

D. MECHANICAL AND ELECTRICAL WORKS


D.1 MUSHOLA PLUMBING WORKS
1.1 CLEAN WATER SYSTEM
Procurement and installation of PVC Pipes including excavation, accessories, and auxiliary equipment
Toilet and Clean Water Piping and Its Completeness
1 PVC AW Ø 25 mm m 13.00 33,610.50 436,936.50 0.009
2 PVC AW Ø 20 mm m 1.00 28,026.63 28,026.63 0.001
3 Fitting ls 1.00 59,157.31 59,157.31 0.001
4 Gate Valve Ø 32mm unit 1.00 126,610.00 126,610.00 0.002

1.2 VENT AND GREY WATER SYSTEM


Procurement and installation of PVC Pipes including excavation, accessories, and auxiliary tool
Grey Water Piping and Its completeness in toilet to Sepictank.1
1 PVC-AW Ø 100 mm; SW (Sewage Water) m 3.00 185,950.88 557,852.63 0.011
2 PVC-AW Ø 80 mm; WW (Waste Water) m 19.00 123,292.13 2,342,550.38 0.046
3 Floor Clean Out Ø 80 mm, WW (Waste Water) unit 2.00 230,725.00 461,450.00 0.009
4 Floor Clean Out Ø 100 mm, SW (Sewage Water) unit 1.00 340,263.00 340,263.00 0.007
5 Fitting ls 1.00 370,211.60 370,211.60 0.007

D.2 MUSHOLA ELECTRICAL WORKS


2.1 PANEL WORKS
Procurement & Installation
1 MCB-BOX of the Mushola unit 1.00 930,149.00 930,149.00 0.018
2.2 LIGHTING WORKS
Procurement & Installation
1 Roset Led 22 W Type Bulb unit 8.00 143,896.50 1,151,172.00 0.022
2 Roset Led 5 W Type Bulb (Toilet) unit 2.00 69,399.00 138,798.00 0.003
3 Double Switch unit 3.00 42,350.00 127,050.00 0.002
4 100 W Wall Electric Socket unit 6.00 49,929.00 299,574.00 0.006
5 NYM 3x2,5 mm² Lamp Installation in 20 mm of Conduit Pipe point 10.00 194,035.42 1,940,354.17 0.038
6 Electr. Socket NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 6.00 218,556.25 1,311,337.50 0.026
2.3 Lightning Rod Installation
Procurement & Installation
1 Air Terminal, Ø 3/4 30cm; Completed with GIP, Ø 3/4 70cm set 1.00 442,541.00 442,541.00 0.009
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

2 BC Cable Installation, 25 mm² m 15.00 75,065.83 1,125,987.50 0.022


3 Earthing Pit, 600mm² x 600mm² c/w with grounding system set 1.00 948,398.00 948,398.00 0.018
4 Auxiliary Equipments lot 1.00 366,501.21 366,501.21 0.007
Total Mechanical And Electrical Cost 13,504,920.41 0.263

VIII TOILET 6 ROOMS-E


A PREPARATION WORK
1 Site Measurement m' 29.00 22,990.00 666,710.00 0.013
PREPARATION 666,710.00 0.013
B ARCHITECTURAL WORKS
B.1 1ST FLOOR
A WALLWORK
1 Brick Wall 1:3 m2 73.77 139,920.88 10,321,963.32 0.201
2 Mortar Plaster Work m2 124.71 67,316.74 8,395,071.14 0.164
3 Mortar Neat Plaster Work m2 124.71 42,427.00 5,291,071.17 0.103
4 Practical Column & Lintel Beam Work
- K250 Concrete m3 0.39 1,226,720.35 473,514.05 0.009
- Reinforcement kg 59.38 16,006.10 950,390.29 0.019
- Formwork m2 6.43 185,185.00 1,191,356.83 0.023
5 Wall Tiles 25x40cm (Unpolished) m2 88.54 183,499.80 16,247,439.29 0.317
B Ceiling Installation Work
1 Ceiling Hollow frame m2 64.97 149,919.00 9,739,637.75 0.190
2 6 mm of Calcium Board GRC (Ceiling Interior) m2 16.38 72,230.40 1,183,206.18 0.023
3 6 mm of Calcium Board GRC (Ceiling Exterior) m2 48.59 72,230.40 3,509,313.98 0.068
C Floor Installation Work
1 40x40 cm of Ceramic Tile (Unpolished) Hallway m2 35.80 166,262.80 5,952,041.98 0.116
2 40x40 cm of Ceramic Tile (Unpolished) Rooms m2 15.55 162,962.80 2,534,071.54 0.049
3 Waterproofing Coating + Mortar m2 51.35 119,614.62 6,142,090.92 0.120
D Door and Window Installation Work (complete w. Aluminium frame)
1 Door Allumunium Frame Installation Work (type P4) Difabel Unit 1.00 2,585,000.00 2,585,000.00 0.050
2 Door Allumunium Frame Installation Work (type P3) Unit 5.00 2,368,025.00 11,840,125.00 0.231
E Sanitary Work and Installation
Sanitary work includes procurement & installation
1 Squatting Closet Unit 5.00 1,306,646.00 6,533,230.00 0.127
2 Sitting Toilet Unit 1.00 3,699,704.80 3,699,704.80 0.072
3 Shower spray Unit 1.00 960,355.00 960,355.00 0.019
4 Wastafel hang Unit 5.00 3,723,830.00 18,619,150.00 0.363
5 Floor Drain Unit 6.00 675,235.00 4,051,410.00 0.079
6 Tissue Holder Unit 1.00 585,475.00 585,475.00 0.011
7 Soap Dispenser Unit 3.00 165,275.00 495,825.00 0.010
8 Robe Hook Unit 6.00 334,235.00 2,005,410.00 0.039
9 Fibre Basin Unit 5.00 992,670.36 4,963,351.80 0.097
10 5mm; uk 500x700 of mirror work Unit 5.00 126,379.00 631,895.00 0.012
11 Handrail Stainless;Difable m 1.20 610,995.00 733,194.00 0.014
12 Faucet Unit 6.00 746,652.50 4,479,915.00 0.087
F Painting Works
1 Wall Painting; Interior m2 28.29 40,563.60 1,147,544.24 0.022
2 Wall Painting; Exterior m2 96.42 54,313.60 5,236,917.31 0.102
3 Ceiling Painting; Interior m2 16.38 40,563.60 664,472.33 0.013
4 Ceiling Painting; Exterior m3 48.59 54,313.60 2,638,826.26 0.051
5 Calsiplank Painting m2 11.37 54,313.60 617,437.00 0.012
G Other Works
1 Railling for Disability access
- Disability Handrail Ramp work m 14.10 760,976.98 10,729,014.37 0.209
- Chevron Works m 20.90 40,315.00 842,381.92 0.016
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3
0.78 912,325.16 711,613.62 0.014
- Retaining Wall Ramp 1 Pc : 5 Ps m2 5.75 139,920.88 803,985.38 0.016
- Landfill for floor elevation m3 1.25 163,075.00 204,332.97 0.004
- Mortar Plaster Work m2 5.76 67,316.74 387,609.81 0.008
- Mortar Neat Plaster Work m2 5.76 42,427.00 244,294.67 0.005
2 Stair
- Retaining Wall 1 Pc : 5 Ps m2 3.24 139,920.88 453,343.65 0.009
- Landfill for floor elevation m3 0.49 163,075.00 79,254.45 0.002
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.09 912,325.16 82,109.26 0.002
- Chevron Works m 18.00 40,315.00 725,670.00 0.014
- Mortar Plaster Work m2 2.43 67,316.74 163,445.05 0.003
- Mortar Neat Plaster Work m2 2.43 42,427.00 103,012.76 0.002
B.2 ROOF WORKS
A Roof Covering Works
1 Zincalume Spandex H. 0,30 mm Installation m2 113.01 171,306.67 19,360,051.63 0.377
2 Light Steel Frame; including rafter and accessoris m2 113.01 213,420.90 24,119,549.59 0.470
3 Aluminium Foil Installation m2 113.01 27,087.50 3,061,266.73 0.060
4 Roof Ridges, Zincalum Spandex m 30.09 73,810.00 2,220,795.28 0.043
5 Calsiplank m 38.50 59,070.00 2,274,195.00 0.044
Total Architectural Cost 210,986,332.35 4.112

C STRUCTURAL WORK
I FOUNDATION WORK
1 Foundation PD1
- Backfill m3 6.90 62,150.00 428,959.30 0.008
II 1ST LEVEL
1 K1 Column 20/20
- K-250 Concrete m3 2.24 1,226,720.35 2,742,946.70 0.053
- Reinforcement kg 455.87 16,006.10 7,296,729.82 0.142
- Column Formwork m2 44.20 275,300.00 12,168,260.00 0.237
2 K2 Column 15/20
- K-250 Concrete m3 0.52 1,226,720.35 632,987.70 0.012
- Reinforcement kg 142.35 16,006.10 2,278,485.67 0.044
-Column Formwork m2 11.90 275,300.00 3,276,070.00 0.064
3 20/25 Tie Beam S1
- Concrete K-250 m3 2.19 1,226,720.35 2,686,517.56 0.052
- Reinforcement kg 402.44 16,006.10 6,441,419.17 0.126
- Tie Beam Formwork m2 21.90 195,085.00 4,272,361.50 0.083
4 15/20 Tie Beam S2
- Concrete K-250 m3 0.42 1,226,720.35 512,462.43 0.010
- Reinforcement kg 130.78 16,006.10 2,093,321.48 0.041
- Tie Beam Formwork m2 5.57 195,085.00 1,086,623.45 0.021
5 15/20 Beam B1
- Concrete K-250 m3 1.81 1,226,720.35 2,221,897.23 0.043
- Reinforcement kg 496.92 16,006.10 7,953,819.27 0.155
- Beam Formwork m2 33.21 282,050.00 9,365,822.81 0.183
6 Floor Slab h=12 cm
- Concrete K-250 m3 5.28 1,226,720.35 6,477,083.44 0.126
- Reinforcement kg 459.12 16,006.10 7,348,718.71 0.143
- Floor Formwork m2 3.58 225,800.00 807,460.80 0.016
- Sand layer t=10cm m3 4.40 192,830.00 848,452.00 0.017
- Base Concrete t=5cm m3 2.20 912,325.16 2,007,115.35 0.039
Total Structural Cost 82,947,514.40 1.617

D. MECHANICAL AND ELECTRICAL WORKS


UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

D.1 PLUMBING WORKS


1.1 CLEAN WATER SYSTEM
Procurement and
a. installation
Toilet CleanofWater
PVC Pipes
Piping and Accessories
1 PVC AW Ø 25 mm m 25.00 33,610.50 840,262.50 0.016
2 PVC AW Ø 20 mm m 2.00 28,026.63 56,053.25 0.001
3 Fitting ls 1.00 102,292.58 102,292.58 0.002
4 Gate Valve Ø 32mm unit 1.00 126,610.00 126,610.00 0.002
1.2 VENT AND GREY WATER SYSTEM
Procurement and
a. installation
Grey WaterofPiping
PVC Pipes
and accessories from toilet E to Sepictank 1
1 PVC-AW Ø 100 mm; SW (Sewage Water) m 6.00 185,950.88 1,115,705.25 0.022
2 PVC-AW Ø 80 mm; WW (Waste Water) m 26.00 123,292.13 3,205,595.25 0.062
3 PVC-AW Ø 65 mm; WW (Waste Water) m 4.00 95,628.50 382,514.00 0.007
4 PVC-AW Ø 50 mm; WW (Waste Water) m 5.00 55,061.88 275,309.38 0.005
5 Floor Clean Out Ø 80 mm, WW (Waste Water) unit 2.00 230,725.00 461,450.00 0.009
6 Floor Clean Out Ø 100 mm, SW (Sewage Water) unit 1.00 340,263.00 340,263.00 0.007
7 Fitting ls 1.00 578,083.69 578,083.69 0.011

D.2 TOILET ELECTRICAL WORKS


2.1 PANEL WORKS
Procurement & Installation
1 MCB BOX Toilet Unit 1.00 631,939.00 631,939.00 0.012
2 NYM 3x2,5 mm² Lamp Installation in 20 mmi conduit pipe m 41.00 43,081.50 1,766,341.50 0.034
of MCB-BOX from Classroom MCB-BOX to Toilet
2.2 LIGHTING WORKS
Procurement, installation of lighting
a. Toilet E (6 ROOMS)
1 Roset Led 5 W Type Bulb (Toilet) unit 10.00 69,399.00 693,990.00 0.014
2 Single Electrical Switch unit 2.00 34,727.00 69,454.00 0.001
3 Double Electrical Switch unit 4.00 42,350.00 169,400.00 0.003
4 Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 10.00 194,035.42 1,940,354.17 0.038
2.3 Lightning Rod Installation
Procurement, installation of a complete lightning rod
a. Toilet E (6 ROOMS)
1 Ø 3/4 30cm Air Terminal , Completed With Ø 3/4 70cm GIP set 1.00 442,541.00 442,541.00 0.009
2 BC 25 mm² Cable Installation m 18.00 75,065.83 1,351,185.00 0.026
3 600mm² x 600mm² c/w Junction Box with Grounding System set 1.00 948,398.00 948,398.00 0.018
4 Auxiliary Materials lot 1.00 366,501.21 366,501.21 0.007
Total Mechanical And Electrical Cost 15,864,242.76 0.309

IX SITE PLAN
A SITEPLAN STRUCTURAL WORKS
1.1 STRUCTURAL FOUNDATION TOWER WATER TANK
a. Foundation Footplat
- Foundation Cutting m3 1.12 27,610.00 30,812.76 0.001
- Backfill m3 0.73 62,150.00 45,493.80 0.001
- Concrete K-250 m3 0.29 1,226,720.35 353,295.46 0.007
- Reinforcement kg 11.54 16,006.10 184,724.48 0.004
- Formwork m2 1.92 185,185.00 355,555.20 0.007
- Sand layer t=10cm m3 0.07 192,830.00 13,883.76 0.000
- Base Concrete t=5cm m3 0.07 912,325.16 65,687.41 0.001
b. 20/20 Column
- Concrete K-250 m3 0.10 1,226,720.35 117,765.15 0.002
- Reinforcement kg 13.31 16,006.10 213,067.85 0.004
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

- Formwork Column m2 1.92 275,300.00 528,576.00 0.010


c. 15/20 Tie Beam
- Concrete K-250 m3 0.16 1,226,720.35 191,368.37 0.004
- Reinforcement kg 23.15 16,006.10 370,535.20 0.007
- Tie Beam Formwork m2 2.08 195,085.00 405,776.80 0.008
Total Site Plan Structural Work Cost 2,876,542.25 0.056

B. SITEPLAN PLUMBING WORKS


B.1 MAIN EQUIPMENTS OF CLEAN WATER SYSTEM
Pipeline procurement and
a. installation include
Piping and accessories
excavation, accessories,
1 80
and auxiliarydeep
m water well
equipment ls 1.00 80,000,000.00 80,000,000.00 1.559
2 PVC-D Ø 100 mm (cover) m 80.00 178,033.28 14,242,662.50 0.278
3 PVC-AW Ø 32 mm m 80.00 33,610.50 2,688,840.00 0.052
4 Fitting ls 1.00 846,575.13 846,575.13 0.016
b. CLEAN WATER PUMP
1 Type : Submersible Pump ls 1.00 9,729,500.00 9,729,500.00 0.190
Capacity : 35 Lpm, Suction head 93m, Discharge Head 126m
Output Power : 1,1 Kw (1,5 HP)
Installation include cable, control box etc
c. Piping from Jet Pump to water tank
1 PVC AW Ø 32 mm m 10.00 33,610.50 336,105.00 0.007
2 Gate Valve Ø 32mm unit 1.00 126,610.00 126,610.00 0.002
3 Fitting ls 1.00 46,271.50 46,271.50 0.001
e. Roof Tank
1 Type : Fibreglass unit 1.00 10,671,375.00 10,671,375.00 0.208
Capacity : 2 m3
Rooftank work c/w Water Tower 4 meters high

B.2 CLEAN WATER SYSTEM


Procurement and installation of PVC Pipes incl. excavation, accessories, and auxiliary
a. Piping and accessories from the Tank to Teacher Office
1 PVC AW Ø 40 mm m 4.00 50,373.13 201,492.50 0.004
2 PVC AW Ø 32 mm m 72.00 33,610.50 2,419,956.00 0.047
3 Fitting ls 1.00 275,919.60 275,919.60 0.005
4 Gate Valve Ø 40mm unit 1.00 137,747.50 137,747.50 0.003

b. Piping and accessories from the Tank to Mushola


1 PVC AW Ø 40 mm m 4.00 50,373.13 201,492.50 0.004
2 PVC AW Ø 32 mm m 25.00 33,610.50 840,262.50 0.016
3 Fitting ls 1.00 117,950.25 117,950.25 0.002
4 Gate Valve Ø 40mm unit 1.00 137,747.50 137,747.50 0.003
c. Piping and accessories from the Tank to Toilet
1 PVC AW Ø 40 mm m 4.00 50,373.13 201,492.50 0.004
2 PVC AW Ø 32 mm m 77.00 33,610.50 2,588,008.50 0.050
3 Fitting ls 1.00 292,724.85 292,724.85 0.006
4 Gate Valve Ø 40mm unit 1.00 137,747.50 137,747.50 0.003

B.3 VENT AND GREY WATER SYSTEM


Procurement and installation of PVC Pipes incl. excavation, accessories, and auxiliary
a. Grey Water Piping to Septictank 1 (Toilet)
1 PVC-AW Ø 100 mm; SW (Sewage Water) m 5.00 185,950.88 929,754.38 0.018
2 PVC-AW Ø 80 mm; WW (Waste Water) m 4.00 123,292.13 493,168.50 0.010
3 Fitting ls 1.00 142,292.29 142,292.29 0.003
b. Grey Water Piping to Septictank.2 (Mushola and Teacher Office)
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

1 PVC-AW Ø 100 mm; SW (Sewage Water) m 67.00 185,950.88 12,458,708.63 0.243


2 PVC-AW Ø 80 mm; WW (Waste Water) m 5.00 123,292.13 616,460.63 0.012
3 Fitting ls 1.00 1,307,516.93 1,307,516.93 0.025

B.4 DRAINAGE PIPE SYSTEM TO INFILTRATION WELL


Procurement and installation of PVC Pipes incl. excavation, accessories, and auxiliary
1 PVC-AW Ø 100 mm; PAH m 10.00 185,950.88 1,859,508.75 0.036
Total Site Plan Plumbing Cost 144,047,890.91 2.807
C. SITE PLAN ELECTRICAL WORKS
C.1 LOW VOLTAGE PANEL WORK
Procurement and
1 installation
School MainofPanel
Panel unit 1.00 3,173,775.00 3,173,775.00 0.062

New Installation of PLN


1 Connecting Fee VA 11000.00 993.33 10,926,666.67 0.213
2 Deposit Money VA 11000.00 333.33 3,666,666.67 0.071
3 SLO (Certificate of Eligibility for Operation) (adjusted for rates from SLO consultants) VA 11000.00 66.67 733,333.33 0.014

C.2 CONNECTOR CABLE PROVISION AND INSTALLATION


The work of procurement,
installation
Low Voltageand testing
Cable ;
1 From Main Panel to MCB-BOX.1, NYY 3 x 6 mm² + BC 6mm² (Office) m 18.00 80,521.83 1,449,393.00 0.028
2 From Main Panel to MCB-BOX.2, NYY 3 x 4 mm² + BC 6mm² (Classroom 4room-1) m 13.00 75,967.83 987,581.83 0.019
3 From Main Panel to MCB-BOX.3, NYY 3 x 4 mm² + BC 6mm² (Classroom 4room-2) m 41.00 75,967.83 3,114,681.17 0.061
4 From Main Panel to MCB-BOX.4, NYY 3 x 4 mm² + BC 6mm² (Classroom 2room-1) m 58.00 75,967.83 4,406,134.33 0.086
5 From Main Panel to MCB-BOX.5, NYY 3 x 4 mm² + BC 6mm² (Classroom 2room-2) m 70.00 75,967.83 5,317,748.33 0.104
6 From Main Panel to MCB-BOX.5, NYY 3 x 4 mm² + BC 6mm² (Mushola) m 84.00 75,967.83 6,381,298.00 0.124
7 From MCB-BOX.1 to Jet Pump, NYY 3 x 4 mm² + BC 6mm² m 19.00 75,967.83 1,443,388.83 0.028
Total Site Plan Mechanical And Electrical Cost 41,600,667.17 0.811

X. SEPTIC TANK N25 WORKS-1


A STP
1 Ground Work
- STP Foundation Cutting m3 26.21 27,610.00 723,665.77 0.014
- Backfill m3 21.64 62,150.00 1,345,026.55 0.026
2 (120X120) Column
- K-250 Concrete m3 0.12 1,226,720.35 144,851.14 0.003
- Reinforcement kg 30.76 16,006.10 492,358.63 0.010
- Column Formwork m2 3.94 275,300.00 1,083,580.80 0.021
3 (120X120)Tie Beam
- K-250 Concrete m3 0.08 1,226,720.35 92,210.12 0.002
- Reinforcement kg 19.17 16,006.10 306,882.62 0.006
- Tie Beam Formwork m2 1.25 195,085.00 244,402.49 0.005
4 B1 (120X120) Beam
- K-250 Concrete m3 0.08 1,226,720.35 92,210.12 0.002
- Reinforcement kg 19.17 16,006.10 306,882.62 0.006
- Beam Formwork m2 1.25 282,050.00 353,352.24 0.007
5 B2 (120X120) Beam
- K-250 Concrete m3 0.07 1,226,720.35 81,552.37 0.002
- Reinforcement kg 23.23 16,006.10 371,886.69 0.007
- Beam Formwork m2 1.11 282,050.00 312,511.40 0.006
6 Wall h=12 cm
- K-250 Concrete m3 1.30 1,226,720.35 1,596,760.54 0.031
- Reinforcement kg 72.51 16,006.10 1,160,547.33 0.023
- Formwork m2 22.22 282,050.00 6,266,361.26 0.122
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

7 Slab Top h=12cm


- K-250 Concrete m3 0.10 1,226,720.35 117,421.67 0.002
- Reinforcement kg 16.80 16,006.10 268,896.48 0.005
- Formwork m2 0.81 295,300.00 239,488.30 0.005
8 Floor Slab h=12 cm
- K-250 Concrete m3 0.22 1,226,720.35 265,707.63 0.005
- Reinforcement kg 16.80 16,006.10 268,896.48 0.005
- Floor Formwork m2 0.68 225,800.00 154,447.20 0.003
- Sand layer t=10cm m3 0.24 192,830.00 46,568.45 0.001
- Base Concrete t=5cm m3 0.12 912,325.16 110,163.26 0.002
- Waterproofing Coating m2 18.22 48,213.00 878,537.29 0.017
Total STP-1 Cost 17,325,169.42 0.338
B Infiltration
- Soil Exavation m3 1.22 105,435.00 128,103.53 0.002
- Brick Wall 1 Pc : 3 Ps m2 5.40 147,363.92 795,765.17 0.016
- Sand Layer m3 0.48 192,830.00 92,558.40 0.002
- Gravel m3 0.48 429,330.00 206,078.40 0.004
Total Infiltration-1 Cost 1,222,505.49 0.024
XI. SEPTIC TANK N25 WORKS-2
A STP
1 Ground Work
- STP Foundation Cutting m3 26.21 27,610.00 723,665.77 0.014
- Backfill m3 21.64 62,150.00 1,345,026.55 0.026
2 (120X120) Column
- K-250 Concrete m3 0.12 1,226,720.35 144,851.14 0.003
- Reinforcement kg 30.76 16,006.10 492,358.63 0.010
- Column Formwork m2 3.94 275,300.00 1,083,580.80 0.021
3 (120X120)Tie Beam
- K-250 Concrete m3 0.08 1,226,720.35 92,210.12 0.002
- Reinforcement kg 19.17 16,006.10 306,882.62 0.006
- Tie Beam Formwork m2 1.25 195,085.00 244,402.49 0.005
4 B1 (120X120) Beam
- K-250 Concrete m3 0.08 1,226,720.35 92,210.12 0.002
- Reinforcement kg 19.17 16,006.10 306,882.62 0.006
- Beam Formwork m2 1.25 282,050.00 353,352.24 0.007
5 B2 (120X120) Beam
- K-250 Concrete m3 0.07 1,226,720.35 81,552.37 0.002
- Reinforcement kg 23.23 16,006.10 371,886.69 0.007
- Beam Formwork m2 1.11 282,050.00 312,511.40 0.006
6 Wall h=12 cm
- K-250 Concrete m3 1.30 1,226,720.35 1,596,760.54 0.031
- Reinforcement kg 72.51 16,006.10 1,160,547.33 0.023
- Formwork m2 22.22 282,050.00 6,266,361.26 0.122
7 Slab Top h=12cm
- K-250 Concrete m3 0.10 1,226,720.35 117,421.67 0.002
- Reinforcement kg 16.80 16,006.10 268,896.48 0.005
- Formwork m2 0.81 295,300.00 239,488.30 0.005
8 Floor Slab h=12 cm
- K-250 Concrete m3 0.22 1,226,720.35 265,707.63 0.005
- Reinforcement kg 16.80 16,006.10 268,896.48 0.005
- Floor Formwork m2 0.68 225,800.00 154,447.20 0.003
- Sand layer t=10cm m3 0.24 192,830.00 46,568.45 0.001
- Base Concrete t=5cm m3 0.12 912,325.16 110,163.26 0.002
- Waterproofing Coating m2 18.22 48,213.00 878,537.29 0.017
Total STP-2 Cost 17,325,169.42 0.338
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

B Infiltration
- Soil Exavation m3 1.22 105,435.00 128,103.53 0.002
- Brick Wall 1 Pc : 3 Ps m2 5.40 147,363.92 795,765.17 0.016
- Sand Layer m3 0.48 192,830.00 92,558.40 0.002
- Gravel m3 0.48 429,330.00 206,078.40 0.004
Total Infiltration-2 Cost 1,222,505.49 0.024

XII GUTTERS AROUND THE BUILDING AND INFILTRATION


A Gutters Around the Building
- Soil Exavation m3 60.66 105,435.00 6,395,497.32 0.125
- Brick Wall 1 Pc : 3 Ps m2 305.92 147,363.92 45,081,570.41 0.879
- Sand Layer m3 39.08 192,830.00 7,535,121.50 0.147
- Lean Work 1 Pc : 2 Ps : 3 Kr m3 46.68 912,325.16 42,584,327.74 0.830
- Mortar Plaster Work m2 573.60 67,316.74 38,612,884.36 0.753
- Mortar Neat Plaster Work m2 573.60 42,427.00 24,336,127.20 0.474
Total Gutters Around The Building Cost 164,545,528.51 3.207
B Infiltration
- Soil Exavation m3 4.86 105,435.00 512,414.10 0.010
- Brick Wall 1 Pc : 3 Ps m2 21.60 147,363.92 3,183,060.67 0.062
- Sand Layer m3 1.92 192,830.00 370,233.60 0.007
- Gravel m3 1.92 429,330.00 824,313.60 0.016
Total Infiltration Cost 4,890,021.97 0.095
XIII CONNECTING CORRIDOR
- Soil Exavation m3 4.85 105,435.00 511,664.46 0.010
- Brick Wall 1 Pc : 5 Ps m2 93.82 147,363.92 13,826,057.28 0.269
- Landfill for floor elevation m3 26.69 163,075.00 4,352,617.70 0.085
- Sand layer m3 2.97 192,830.00 571,867.25 0.011
- Lean Work 1 Pc : 2 Ps : 3 Kr m3 4.91 912,325.16 4,476,607.12 0.087
- Chevron Works m' 70.10 40,315.00 2,825,972.65 0.055
- Mortar Plaster Work m2 61.47 67,316.74 4,137,956.21 0.081
- Mortar Neat Plaster Work m2 61.47 42,427.00 2,607,985.14 0.051
- Canopy (Module 1,4mx3m) Unit 2.00 3,168,440.00 6,336,880.00 0.123
- Handrail Corridor Work m 101.84 760,976.98 77,499,417.09 1.510
Total Connecting Corridor Cost 117,147,024.91 2.283

TOTAL 5,131,118,000.00 100.000 7.512 1.139 8.651

Plan 4.242 Realization 8.651 Deviation 4.409

Acknowledged by ; Approved by ; Submitted by;


UNITED NATIONS DEVELOPMENT PROGRAMME Supervision Consultant Contractor
PT. YODYA KARYA (PERSERO) JV PT. SETIA MULIA ABADI

(Whisnu Yonar Anggono) (Apjelvian Henri) (I Wayan Praja Murdana)


Community Mobilization Officer UNDP PETRA Team Leader Site Manager
Assignor : Supervision Consultant : Contractor :

WEEKLY REPORT
: Project : CONSTRUCTION OF SCHOOLS FACILITIES IN CENTRAL SULAWESI (LOT 2) Week : 7 (seven)
Contract No. : Ref.: 10057438 Period : 30 July 2023 - 05 August 2023
Location : SMP Negeri 14 Palu Weight Until Last Week : 4.682 %
Owner : United Nations Development Programme Weight This Week : 2.021 %
Contract Price : IDR 5,242,761,000 Weight Until This Week : 6.703 %

UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK


VOLUME /
NO. WORK DESCRIPTION Weight (%)
UNIT Physic (%) Weight (%) Physic (%) Weight (%) Physic (%) Weight (%)

1. SMP NEGERI 14 PALU 31.185


I PREPARATION WORK
A SITE PREPARATION 1.00 1.279 48.750 0.624 48.750 0.624
II CLASSROOM 9X8 (4 ROOMS)-A -
A PREPARATION WORK 1.00 0.056 42.884 0.024 57.116 0.032 100.000 0.056
B ARCHITECTURAL WORKS 1.00 13.733 1.336 0.184 1.336 0.184
C STRUCTURAL WORK 1.00 4.326 45.042 1.949 17.063 0.738 62.105 2.687

III CLASSROOM 9x8 (3 ROOMS) 2 STORAGE-B


A PREPARATION WORK 1.00 0.478 100.000 0.478 100.000 0.478
B ARCHITECTURAL WORKS 1.00 17.283
C STRUCTURAL WORK 1.00 31.820

IV CLASSROOM 8X9 (2 ROOMS)-C -


A PREPARATION WORK 1.00 0.025 50.000 0.012 50.000 0.012 100.000 0.025
B ARCHITECTURAL WORKS 1.00 7.356 3.378 0.248 3.378 0.248
C STRUCTURAL WORK 1.00 2.806 73.884 2.073 73.884 2.073
D CLASSROOM ELECTRICAL WORKS 1.00 1.118

V EXTRA CURRICULLAR BUILDING / GEDUNG UKS-D -


A PREPARATION WORK 1.00 0.234 100.000 0.234 100.000 0.234
B ARCHITECTURAL WORKS 1.00 5.464
C. STRUCTURAL WORK 1.00 3.070 2.673 0.082 2.673 0.082
D. MECHANICAL AND ELECTRICAL WORKS 1.00 0.273
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
VOLUME /
NO. WORK DESCRIPTION Weight (%)
UNIT Physic (%) Weight (%) Physic (%) Weight (%) Physic (%) Weight (%)

VI TOILET 6 ROOMS-E
A PREPARATION WORK 1.00 0.013 100.000 0.013 100.000 0.013
B ARCHITECTURAL WORKS 1.00 3.688
C STRUCTURAL WORK 1.00 1.505
D. MECHANICAL AND ELECTRICAL WORKS 1.00 0.345

VI. SITE PLAN -


A SITEPLAN STRUCTURAL WORKS 1.00 0.057
B. SITEPLAN PLUMBING WORKS 1.00 0.546
C. SITE PLAN ELECTRICAL WORKS 1.00 0.816

VII. SEPTIC TANK N25 WORKS -1 -


A STP 1.00 0.369
B Infiltration 1.00 0.023

VIII. SEPTIC TANK N25 WORKS -2 -


A STP 1.00 0.369
B Infiltration 1.00 0.023

IX GUTTERS AROUND THE BUILDING AND INFILTRATION -


A Gutters Around the Building 1.00 2.154
B Infiltration 1.00 0.117

X CONNECTING CORRIDOR -
A Connecting Corridor 1.00 0.654
TOTAL LOT 2 100.000 4.682 2.021 6.703
Plan 8.442 Realization 6.703 Deviation (1.739)

Acknowledged by ; Approved by ; Submitted by;


UNITED NATIONS DEVELOPMENT PROGRAMME Supervision Consultant Contractor
PT. YODYA KARYA (PERSERO) JV PT. SETIA MULIA ABADI
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
VOLUME /
NO. WORK DESCRIPTION Weight (%)
UNIT Physic (%) Weight (%) Physic (%) Weight (%) Physic (%) Weight (%)

(Whisnu Yonar Anggono) (Apjelvian Henri) (Faris Mubarok)


Community Mobilization Officer UNDP PETRA Team Leader Site Manager
Assignor : Supervision Consultant : Contractor :

WEEKLY REPORT
: Project : CONSTRUCTION OF SCHOOLS FACILITIES IN CENTRAL SULAWESI (LOT 2) Week : 7 (seven)
Contract No. : Ref.: 10057438 Period : 30 July 2023 - 05 August 2023
Location : SMP Negeri 14 Palu Weight Until Last Week : 4.682 %
Owner : United Nations Development Programme Weight This Week : 2.021 %
Contract Price : IDR 5,242,761,000 Weight Until This Week : 6.703 %

UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK


NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

I PREPARATION WORK
1 Project Safety Fencing M1 70.00 251,460.00 17,602,200.00 0.336
2 Project Signage Unit 1.00 474,732.50 474,732.50 0.009 1.000 100.000 0.009 1.000 100.000 0.009
3 Renovastion Temporary Office Construction Ls 1.00 14,683,944.00 14,683,944.00 0.280 1.000 100.000 0.280 1.000 100.000 0.280
4 Renovation Storage Construction & Bordinghouse Ls 1.00 5,738,238.00 5,738,238.00 0.109 0.650 65.000 0.071 0.650 65.000 0.071
5 Mobilization, Demobilization of Personnel and Tools Ls 1.00 5,000,000.00 5,000,000.00 0.095 0.200 20.000 0.019 0.200 20.000 0.019
6 HSE (Safety Net, Hat, Helmet,etc.) Ls 1.00 10,175,000.00 10,175,000.00 0.194 0.200 20.000 0.039 0.200 20.000 0.039
7 Site Cleaning M 2
1,419.00 4,158.00 5,900,202.00 0.113 1419.000 100.000 0.113 1419.000 100.000 0.113
8 Rebar Cleaning Ls 1.00 7,500,000.00 7,500,000.00 0.143 0.650 65.000 0.093 0.650 65.000 0.093
Total Preparation Work Cost 67,074,316.50 1.279 0.624 0.624
II CLASSROOM 9X8 (4 ROOMS)-A
A PREPARATION WORK
1 Site Measurement M1 92.00 22,990.00 2,115,080.00 0.040 46.000 50.000 0.020 46.000 50.000 0.020 92.000 100.000 0.040
2 Demolition of Tie Beam Formwork M2 32.71 24,970.00 816,768.70 0.016 8.000 24.457 0.004 24.710 75.543 0.012 32.710 100.000 0.016
PREPARATION 2,931,848.70 0.056 0.024 0.032 0.056
B ARCHITECTURAL WORKS
B.1 1ST LEVEL
I. WALLWORK
1 1/2 Brick Wall 1:5 M2 254.66 139,920.88 35,632,251.30 0.680 68.758 27.000 0.184 68.758 27.000 0.184
2 Mortar Plaster Work M2 687.72 67,316.74 46,295,071.18 0.883
3 Mortar Neat Plaster Work M 2
687.72 42,427.00 29,177,896.44 0.557
4 Practical Column & Lintel Beam Work -
- K250 Concrete M 3
2.57 1,226,720.35 3,147,764.42 0.060
- Reinforcement Kg 399.17 16,006.10 6,389,182.51 0.122
- Formwork M2 42.77 185,185.00 7,919,745.17 0.151
II. Ceiling Installation Work -
1 Ceiling Hollow frame M2 453.07 149,919.00 67,923,801.33 1.296
2 6 mm of Calcium Board GRC (Ceiling Interior) M2 280.36 72,230.40 20,250,514.94 0.386
3 6 mm of Calcium Board GRC (Ceiling Exterior) M2 172.71 72,230.40 12,474,912.38 0.238
III. Floor Installation Work -
1 Tile 40x40 cm (Polished) Rooms M2 282.15 162,962.80 45,979,628.09 0.877
2 Tile 40x40 cm (Unpolished) Hallway M2 70.53 166,262.80 11,726,182.76 0.224
IV. Door and Window Installation Work -
1 Door Alumunium Frame Installation Work (type P1) Unit 4.00 1,082,950.00 4,331,800.00 0.083
2 Leaf Door Instalation Work (type P1) Unit 4.00 2,625,000.00 10,500,000.00 0.200
3 Door Alumunium Frame Installation Work (type P2) Unit 4.00 1,533,286.70 6,133,146.80 0.117
4 Leaf Door Instalation Work (type P2) Unit 4.00 5,250,000.00 21,000,000.00 0.401
5 Window Allumunium Frame Installation Work (type J3) Unit 16.00 3,546,928.00 56,750,848.00 1.082
V. Painting Works -
1 Wall Painting; Interior M2 404.08 40,563.60 16,390,939.49 0.313
2 Wall Painting; Exterior M2 283.64 54,313.60 15,405,509.50 0.294
3 Ceiling Painting; Interior M2 280.36 40,563.60 11,372,410.90 0.217
4 Ceiling Painting; Exterior M2 172.71 54,313.60 9,380,501.86 0.179
5 Calsiplank Painting M2 30.40 54,313.60 1,650,916.19 0.031
VI. Other Works -
1 Railling for Disability access -
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

- Disability Handrail Ramp work M1 14.10 760,976.98 10,729,014.37 0.205


- Lean Ramp 1 Pc : 3 Ps : 5 Kr M3 0.78 912,325.16 711,613.62 0.014
- Chevron Works M1 20.90 40,315.00 842,381.92 0.016
- Retaining Wall Ramp 1 Pc : 5 Ps M2 5.75 139,920.88 803,985.38 0.015
- Landfill for floor elevation M 3
1.25 163,075.00 204,332.97 0.004
- Mortar Plaster Work M 2
5.76 67,316.74 387,609.81 0.007
- Mortar Neat Plaster Work M 2
5.76 42,427.00 244,294.67 0.005
2 Stair -
- Retaining Wall 1 Pc : 5 Ps M2 6.48 139,920.88 906,687.30 0.017
- Landfill for floor elevation M3 0.97 163,075.00 158,508.90 0.003
- Lean Ramp 1 Pc : 3 Ps : 5 Kr M3 0.18 912,325.16 164,218.53 0.003
- Chevron Works M1 36.00 40,315.00 1,451,340.00 0.028
- Mortar Plaster Work M2 4.86 67,316.74 326,890.11 0.006
- Mortar Neat Plaster Work M2 4.86 42,427.00 206,025.51 0.004
B.2 ROOF WORKS -
I Roof Covering Works -
1 Zincalume Spandex h 0,30 mm Installation M2 604.91 171,306.67 103,625,115.73 1.977
2 Light Steel Frame; including rafter and accessoris M2 604.91 213,420.90 129,100,436.62 2.462
3 Aluminium Foil Installation M2 604.91 27,087.50 16,385,499.63 0.313
4 Roof Ridges, Zincalum Spandex M 1
52.88 73,810.00 3,903,072.80 0.074
5 Calsiplank M 1
116.40 59,070.00 6,875,866.14 0.131
6 Roof Jalousie Unit 2.00 1,563,743.50 3,127,487.00 0.060
Total Architectural Cost 719,987,404.27 13.733 0.184 0.184
C STRUCTURAL WORK
1 30/30 Column
- K-250 Concrete Ready Mix M3 11.76 2,161,230.23 25,412,825.68 0.485 4.703 40.000 0.194 2.352 20.000 0.097 7.055 60.000 0.291
- Column Formwork M2 156.78 275,300.00 43,161,534.00 0.823 62.712 40.000 0.329 94.068 60.000 0.494 156.780 100.000 0.823
2 20/20 Column -
- K-250 Concrete M3 2.18 1,226,720.35 2,669,343.48 0.051 0.870 40.000 0.020 0.435 20.000 0.010 1.306 60.000 0.031
- Column Formwork M2 43.52 275,300.00 11,981,056.00 0.229 17.408 40.000 0.091 26.112 60.000 0.137 43.520 100.000 0.229
3 25/30 Tie Beam S1 -
- K-250 Concrete Ready Mix M3 4.50 2,161,230.23 9,725,536.04 0.186 4.500 100.000 0.186 4.500 100.000 0.186
- Tie Beam Formwork M2 36.00 195,085.00 7,023,060.00 0.134 18.000 50.000 0.067 18.000 50.000 0.067
4 20/25 Tie Beam S2 -
- K-250 Concrete Ready Mix M 3
1.24 2,161,230.23 2,685,328.56 0.051 1.243 100.000 0.051 1.243 100.000 0.051
- Tie Beam Formwork M2 12.42 195,085.00 2,423,931.13 0.046 6.212 50.000 0.023 6.212 50.000 0.023
5 20/25 Beam B1 -
- K-250 Concrete Ready Mix M3 7.21 2,161,230.23 15,577,066.90 0.297
- Reinforcement Kg 1,240.96 16,006.10 19,862,891.99 0.379
- Beam Formwork M2 122.53 282,050.00 34,558,881.38 0.659
6 Floor Slab t=12 cm -
- K-250 Concrete Ready Mix M3 23.28 2,161,230.23 50,318,626.75 0.960 23.282 100.000 0.960 23.282 100.000 0.960
- Floor Formwork M2 6.31 225,800.00 1,423,894.80 0.027 6.306 100.000 0.027 6.306 100.000 0.027
Total Structural Cost 226,823,976.70 4.326 1.949 0.738 2.687
III CLASSROOM 9x8 (3 ROOMS) 2 STORAGE-B
A PREPARATION WORK
1 Site Measurement and Bowplank Installation M1 90.00 278,630.00 25,076,700.00 0.478 90.000 100.000 0.478 90.000 100.000 0.478
PREPARATION 25,076,700.00 0.478 0.478 0.478
B ARCHITECTURAL WORKS
B.1 GROUND FLOOR
I WALLWORK
1 1/2 Brick Wall 1:5 M2 184.59 139,920.88 25,828,554.92 0.493
2 Mortar Plaster Work M2 562.71 67,316.74 37,879,805.02 0.723
3 Mortar Neat Plaster Work M2 562.71 42,427.00 23,874,097.17 0.455
4 Practical Column & Lintel Beam Work -
- K300 Concrete M3 1.56 1,271,133.63 1,982,968.47 0.038
- Reinforcement Kg 239.97 16,006.10 3,840,955.57 0.073
- Formwork M2 26.00 185,185.00 4,814,810.00 0.092
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

II Ceiling Installation Work -


1 Ceiling Hollow frame M2 262.09 149,919.00 39,292,270.71 0.749
2 6 mm of Calcium Board GRC (Ceiling Interior) M2 208.77 72,230.40 15,079,540.61 0.288
3 6 mm of Calcium Board GRC (Ceiling Exterior) M2 53.32 72,230.40 3,851,324.93 0.073
III Floor Installation Work -
1 Tile 40x40 cm (Polished) Rooms M 2
210.27 162,962.80 34,266,187.96 0.654
2 Tile 40x40 cm (Unpolished) Hallway M 2
68.86 166,262.80 11,448,856.41 0.218
3 Tile 40x40 cm (Unpolished) Stairs M2 16.13 166,262.80 2,681,818.96 0.051
4 Stair Step Nosing Rubber M1 30.67 48,482.50 1,487,055.24 0.028
IV Door and Window Installation Work (complete w. Allumunium frame) -
1 Door Alumunium Frame Installation Work (type P1) Unit 3.00 1,082,950.00 3,248,850.00 0.062
2 Leaf Door Instalation Work (type P1) Unit 3.00 2,625,000.00 7,875,000.00 0.150
3 Door Alumunium Frame Installation Work (type P2) Unit 3.00 1,533,286.70 4,599,860.10 0.088
4 Leaf Door Instalation Work (type P2) Unit 3.00 5,250,000.00 15,750,000.00 0.300
5 Window Allumunium Frame Installation Work (type J3) Unit 12.00 3,546,928.00 42,563,136.00 0.812
V Painting Works -
1 Wall Painting; Interior M2 273.64 40,563.60 11,099,904.63 0.212
2 Wall Painting; Exterior M2 289.07 54,313.60 15,700,323.72 0.299
3 Ceiling Painting; Interior M2 208.77 40,563.60 8,468,462.77 0.162
4 Ceiling Painting; Exterior M 2
53.32 54,313.60 2,896,001.15 0.055
VI Other Works -
1 Railling for Disability access -
- Disability Handrail Ramp work M1 14.10 760,976.98 10,729,014.37 0.205
- Lean Ramp 1 Pc : 3 Ps : 5 Kr M3 0.78 912,325.16 711,613.62 0.014
- Chevron Works M1 20.90 40,315.00 842,381.92 0.016
- Retaining Wall Ramp 1 Pc : 5 Ps M2 5.75 139,920.88 803,985.38 0.015
- Landfill for floor elevation M3 1.25 163,075.00 204,332.97 0.004
- Mortar Plaster Work M2 5.76 67,316.74 387,609.81 0.007
- Mortar Neat Plaster Work M2 5.76 42,427.00 244,294.67 0.005
2 Stair -
- Retaining Wall 1 Pc : 5 Ps M2 6.48 139,920.88 906,687.30 0.017
- Landfill for floor elevation M3 0.97 163,075.00 158,508.90 0.003
- Lean Ramp 1 Pc : 3 Ps : 5 Kr M3 0.18 912,325.16 164,218.53 0.003
- Chevron Works M 1
36.00 40,315.00 1,451,340.00 0.028
- Mortar Plaster Work M 2
4.86 67,316.74 326,890.11 0.006
- Mortar Neat Plaster Work M 2
4.86 42,427.00 206,025.51 0.004
B.2 SECOND FLOOR -
I WALLWORK -
1 1/2 Brick Wall 1:5 M2 215.10 139,920.88 30,096,841.37 0.574
2 Mortar Plaster Work M2 739.17 67,316.74 49,758,786.93 0.949
3 Mortar Neat Plaster Work M2 739.17 42,427.00 31,360,935.30 0.598
4 Practical Column & Lintel Beam Work -
- K300 Concrete M3 2.00 1,271,133.63 2,542,267.27 0.048
- Reinforcement Kg 308.52 16,006.10 4,938,195.83 0.094
- Formwork M2 33.33 185,185.00 6,172,833.33 0.118
II Ceiling Installation Work -
1 Ceiling Hollow frame M2 347.96 149,919.00 52,165,815.24 0.995
2 6 mm of Calcium Board GRC (Ceiling Interior) M 2
208.77 72,230.40 15,079,540.61 0.288
3 6 mm of Calcium Board GRC (Ceiling Exterior) M2 139.19 72,230.40 10,053,749.38 0.192
III Floor Installation Work -
1 Tile 40x40 cm (Polished) Rooms M 2
210.27 162,962.80 34,266,187.96 0.654
2 Tile 40x40 cm (Unpolished) Hallway M2 55.19 166,262.80 9,176,043.93 0.175
IV Door and Window Installation Work (complete w. Allumunium frame) -
1 Door Alumunium Frame Installation Work (type P1) Unit 3.00 1,082,950.00 3,248,850.00 0.062
2 Leaf Door Instalation Work (type P1) Unit 3.00 2,625,000.00 7,875,000.00 0.150
3 Door Alumunium Frame Installation Work (type P2) Unit 3.00 1,533,286.70 4,599,860.10 0.088
4 Leaf Door Instalation Work (type P2) Unit 3.00 5,250,000.00 15,750,000.00 0.300
5 Window Allumunium Frame Installation Work (type J3) Unit 12.00 3,546,928.00 42,563,136.00 0.812
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

V Painting Works -
1 Wall ; Interior M2 310.86 40,563.60 12,609,438.44 0.241
2 Wall Painting; Exterior M2 428.32 54,313.60 23,263,492.52 0.444
3 Ceiling Painting; Interior M2 208.77 40,563.60 8,468,462.77 0.162
4 Ceiling Painting; Exterior M 2
139.19 54,313.60 7,559,909.98 0.144
5 Calsiplank Painting M 2
28.28 54,313.60 1,535,988.61 0.029
B.3 ROOF WORKS -
I Roof Covering Works -
1 Zincalume Spandex h 0,30 mm Installation M2 449.90 171,306.67 77,070,869.33 1.470
2 Light Steel Frame; including rafter and accessoris M2 449.90 213,420.90 96,018,062.91 1.831
3 Aluminium Foil Installation M2 449.90 27,087.50 12,186,666.25 0.232
4 Roof Ridges, Zincalum Spandex M1 42.29 73,810.00 3,121,424.90 0.060
5 Calsiplank M1 98.36 59,070.00 5,810,125.20 0.111
6 Roof Jalousie Unit 2.00 1,563,743.50 3,127,487.00 0.060
Total Architectural Cost 906,086,658.61 17.283
C STRUCTURAL WORK
I FOUNDATION WORK
1 Caison Foundation Ø140 cm
- Foundation Cutting M3 415.94 105,435.00 43,854,423.03 0.836
- Caison Formwork M2 422.02 185,185.00 78,151,032.96 1.491
- Reinforcement Kg 1,911.47 16,006.10 30,595,173.46 0.584
- Concrete Case Caison Ready Mix (K-300) M 3
42.20 2,211,061.94 93,310,351.50 1.780
- Concrete Cyclop Caison M3 21.98 1,271,133.63 27,939,517.30 0.533
- Concrete Ready Mix (K-300) Caison M3 21.99 2,211,061.94 48,611,523.35 0.927
- Angkur D16 Kg 410.09 16,006.10 6,563,939.65 0.125
- Backfill M3 40.35 62,150.00 2,507,752.50 0.048
2 PC1-Pile Cap Foundation 2000x2000x400 mm -
- Concrete Ready Mix K-300 M3 28.80 2,211,061.94 63,678,583.83 1.215
- Reinforcement Kg 2,821.92 16,006.10 45,167,886.75 0.862
- Formwork M2 57.60 185,185.00 10,666,656.00 0.203
- Sand Layer T=10 cm M3 0.36 192,830.00 69,418.80 0.001
- Base Concrete T=5 cm M3 0.18 912,325.16 164,218.53 0.003
3 PC2-Pile Cap Foundation 1500x1500x400 mm -
- Concrete Ready Mix K-300 M 3
9.00 2,211,061.94 19,899,557.45 0.380
- Reinforcement Kg 943.92 16,006.10 15,108,461.93 0.288
- Formwork M2 24.00 185,185.00 4,444,440.00 0.085
- Sand Layer T=10 cm M 3
0.11 192,830.00 21,596.96 0.000
- Base Concrete T=5 cm M3 0.06 912,325.16 51,090.21 0.001
4 Column Pedestal K1-45/50 -
- Concrete Ready Mix K-300 M3 4.61 2,211,061.94 10,198,523.19 0.195
- Reinforcement Kg 1,044.13 16,006.10 16,712,465.46 0.319
- Column Formwork M2 38.95 275,300.00 10,722,935.00 0.205
5 Column Pedestal K2-45/45 -
- Concrete Ready Mix K-300 M3 6.23 2,211,061.94 13,768,006.31 0.263
- Reinforcement Kg 1,398.13 16,006.10 22,378,632.11 0.427
- Column Formwork M2 55.35 275,300.00 15,237,855.00 0.291
6 Column Pedestal K3-30/45 -
- Concrete Ready Mix K-300 M 3
0.83 2,211,061.94 1,835,734.17 0.035
- Reinforcement Kg 186.10 16,006.10 2,978,804.49 0.057
- Column Formwork M2 9.23 275,300.00 2,539,642.50 0.048
II GROUND FLOOR -
1 Column K1-45/50 Ev. ±0,00 -
- Concrete Ready Mix K-300 M3 8.10 2,211,061.94 17,909,601.70 0.342
- Reinforcement Kg 1,804.93 16,006.10 28,889,826.57 0.551
- Column Formwork M2 68.40 275,300.00 18,830,520.00 0.359
2 Column K2-45/45 Ev. ±0,00 -
- Concrete Ready Mix K-300 M3 10.94 2,211,061.94 24,177,962.30 0.461
- Reinforcement Kg 2,441.84 16,006.10 39,084,337.74 0.745
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

- Column Formwork M2 97.20 275,300.00 26,759,160.00 0.510


3 Column K3-30/45 Ev. ±0,00 -
- Concrete Ready Mix K-300 M3 1.46 2,211,061.94 3,223,728.31 0.061
- Reinforcement Kg 310.56 16,006.10 4,970,812.26 0.095
- Column Formwork M2 16.20 275,300.00 4,459,860.00 0.085
4 Floor Slab T=12 cm Ev. -0,050 -
- Concrete Ready Mix K-300 M 3
30.80 2,211,061.94 68,096,550.91 1.299
- Reinforcement Kg 2,528.34 16,006.10 40,468,870.56 0.772
- Slab Formwork M2 9.55 295,300.00 2,820,705.60 0.054
- Sand Layer T=10 cm M3 25.75 192,830.00 4,966,124.54 0.095
- Base Concrete T=5 cm M3 12.88 912,325.16 11,747,965.45 0.224
- Soil Fill M3 93.04 128,715.71 11,975,323.91 0.228
5 Tie Beam SL.1 (250x500) -
- Concrete Ready Mix K-300 M3 9.60 2,211,061.94 21,226,194.61 0.405
- Reinforcement Kg 2,041.17 16,006.10 32,671,224.79 0.623
- Tie Beam Formwork M2 76.80 195,085.00 14,982,528.00 0.286
- Base Concrete T=5 cm m3 0.96 912,325.16 875,832.15 0.017
- Sand layer T=10 cm m3 1.92 192,830.00 370,233.60 0.007
6 Tie Beam SL.2A (250x400) -
- Concrete Ready Mix K-300 M 3
0.62 2,211,061.94 1,370,858.40 0.026
- Reinforcement Kg 147.71 16,006.10 2,364,214.68 0.045
- Tie Beam Formwork M2 4.96 195,085.00 967,621.60 0.018
- Base Concrete T=5 cm m3 0.08 912,325.16 70,705.20 0.001
- Sand layer T=10 cm m3 0.16 192,830.00 29,888.65 0.001
7 Tie Beam SL.2B (250x400) -
- Concrete Ready Mix K-300 M3 4.13 2,211,061.94 9,120,630.50 0.174
- Reinforcement Kg 867.38 16,006.10 13,883,356.79 0.265
- Tie Beam Formwork M2 33.00 195,085.00 6,437,805.00 0.123
- Base Concrete T=5 cm m3 0.52 912,325.16 470,417.66 0.009
- Sand layer T=10 cm m3 1.03 192,830.00 198,855.94 0.004
8 Beam B1 (300x500) Ev.+3,60 -
- Concrete Ready Mix K-300 M3 7.04 2,211,061.94 15,571,403.70 0.297
- Reinforcement Kg 1,687.46 16,006.10 27,009,686.88 0.515
- Beam Formwork M2 61.04 282,050.00 17,214,921.75 0.328
9 Beam B2A (300x450) Ev. +3,60 -
- Concrete Ready Mix K-300 M 3
6.56 2,211,061.94 14,506,777.38 0.277
- Reinforcement Kg 1,252.47 16,006.10 20,047,111.80 0.382
- Beam Formwork M2 58.32 282,050.00 16,449,156.00 0.314
10 Beam B2B (300x450) Ev. +3,60 -
- Concrete Ready Mix K-300 M3 7.09 2,211,061.94 15,670,901.49 0.299
- Reinforcement Kg 1,160.77 16,006.10 18,579,423.88 0.354
- Beam Formwork M2 63.00 282,050.00 17,769,150.00 0.339
11 Beam B3 (30x400) Ev. +3,60 -
- Concrete Ready Mix K-300 M3 2.78 2,211,061.94 6,142,330.06 0.117
- Reinforcement Kg 536.27 16,006.10 8,583,548.12 0.164
- Beam Formwork M2 25.47 282,050.00 7,182,403.25 0.137
12 Beam B4 (20x350) Ev. +1,80 -
- Concrete Ready Mix K-300 M 3
0.84 2,211,061.94 1,865,030.75 0.036
- Reinforcement Kg 238.09 16,006.10 3,810,922.06 0.073
- Beam Formwork M2 10.84 282,050.00 3,058,832.25 0.058
13 Concrete Canopy H=10 cm Ev. +2,680 -
- Concrete Ready Mix K-300 M3 0.65 2,211,061.94 1,427,461.59 0.027
- Reinforcement Kg 67.34 16,006.10 1,077,796.29 0.021
- Canopy Formwork M2 8.35 295,300.00 2,464,928.16 0.047
14 Stairs -
- Concrete Ready Mix K-300 M3 1.58 2,211,061.94 3,498,508.03 0.067
- Reinforcement Kg 168.14 16,006.10 2,691,200.42 0.051
- Formwork M2 16.59 295,300.00 4,897,969.83 0.093
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

Bordes Stairs -
- Concrete Ready Mix K-300 M3 0.32 2,211,061.94 700,995.08 0.013
- Reinforcement Kg 60.68 16,006.10 971,185.00 0.019
- Formwork M2 3.19 295,300.00 941,416.40 0.018
III SECOND FLOOR -
1 Column K1-45/50 Ev. +3,60 -
- Concrete Ready Mix K-300 M 3
8.10 2,211,061.94 17,909,601.70 0.342
- Reinforcement Kg 1,804.93 16,006.10 28,889,826.57 0.551
- Column Formwork M2 68.40 275,300.00 18,830,520.00 0.359
2 Column K2-45/45 Ev. +3,60 -
- Concrete Ready Mix K-300 M3 10.94 2,211,061.94 24,177,962.30 0.461
- Reinforcement Kg 2,441.84 16,006.10 39,084,337.74 0.745
- Column Formwork M2 97.20 275,300.00 26,759,160.00 0.510
3 Column K3-30/45 Ev. +3,60 -
- Concrete Ready Mix K-300 M3 1.46 2,211,061.94 3,223,728.31 0.061
- Reinforcement Kg 310.56 16,006.10 4,970,812.26 0.095
- Column Formwork M2 16.20 275,300.00 4,459,860.00 0.085
4 Beam RB1 (200x350) Ev. +7,20 -
- Concrete Ready Mix K-300 M 3
7.83 2,211,061.94 17,315,378.80 0.330
- Reinforcement Kg 1,600.94 16,006.10 25,624,774.94 0.489
- Beam Formwork M2 100.69 282,050.00 28,398,909.37 0.542
5 Beam RB 2 (200x350) Ev. +6,27 -
- Concrete Ready Mix K-300 M3 1.22 2,211,061.94 2,700,812.16 0.052
- Reinforcement Kg 275.72 16,006.10 4,413,175.52 0.084
- Beam Formwork M2 15.70 282,050.00 4,429,595.25 0.084
6 2nd Floor Slab H=12 cm Ev. +3,60 -
- Concrete Ready Mix K-300 M3 29.76 2,211,061.94 65,801,468.61 1.255
- Reinforcement Kg 3,159.12 16,006.10 50,565,251.22 0.964
- Floor Slab Formwork M2 248.00 295,300.00 73,234,695.30 1.397
7 2nd Roof Slab Stair H=10 cm Ev. +6,27 -
- Concrete Ready Mix K-300 M3 2.19 2,211,061.94 4,842,446.75 0.092
- Reinforcement Kg 214.04 16,006.10 3,425,987.82 0.065
- Floor Slab Formwork M2 21.90 295,300.00 6,467,365.30 0.123
Total Structural Cost 1,668,258,669.91 31.820
IV CLASSROOM 8X9 (2 ROOMS)-C
A PREPARATION WORK
1 Site Measurement m' 56.00 22,990.00 1,287,440.00 0.025 28.000 50.000 0.012 28.000 50.000 0.012 56.000 100.000 0.025
PREPARATION 1,287,440.00 0.025 0.012 0.012 0.025
B ARCHITECTURAL WORKS
B.1 1ST LEVEL
I. WALLWORK
1 1/2 Brick Wall 1:5 M2 155.16 139,920.88 21,709,564.06 0.414 93.094 60.000 0.248 93.094 60.000 0.248
2 Mortar Plaster Work M2 469.86 67,316.74 31,629,445.34 0.603
3 Mortar Neat Plaster Work M2 469.86 42,427.00 19,934,750.22 0.380
4 Practical Column & Lintel Beam Work -
- K250 Concrete M3 1.01 1,226,720.35 1,238,987.55 0.024
- Reinforcement Kg 155.36 16,006.10 2,486,772.52 0.047
- Formwork M2 16.83 185,185.00 3,117,280.83 0.059
II. Ceiling Installation Work -
1 Ceiling Hollow frame M 2
240.29 149,919.00 36,023,436.83 0.687
2 6 mm of Calcium Board GRC (Ceiling Interior) M 2
140.18 72,230.40 10,125,257.47 0.193
3 6 mm of Calcium Board GRC (Ceiling Exterior) M2 100.11 72,230.40 7,230,696.42 0.138
III. Floor Installation Work -
1 Tile 40x40 cm (Polished) Rooms M2 135.53 162,962.80 22,086,348.28 0.421
2 Tile 40x40 cm (Unpolished) Hallway M2 35.96 166,262.80 5,979,475.34 0.114
IV. Door and Window Installation Work -
1 Door Alumunium Frame Installation Work (type P1) Unit 2.00 1,082,950.00 2,165,900.00 0.041
2 Leaf Door Instalation Work (type P1) Unit 2.00 2,625,000.00 5,250,000.00 0.100
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

3 Door Alumunium Frame Installation Work (type P2) Unit 2.00 1,533,286.70 3,066,573.40 0.058
4 Leaf Door Instalation Work (type P2) Unit 2.00 5,250,000.00 10,500,000.00 0.200
5 Window Allumunium Frame Installation Work (type J1) Unit 8.00 2,539,878.00 20,319,024.00 0.388
V. Painting Works -
1 Wall Painting; Interior M 2
201.68 40,563.60 8,180,866.85 0.156
2 Wall Painting; Exterior M 2
268.18 54,313.60 14,565,821.25 0.278
3 Ceiling Painting; Interior M2 140.18 40,563.60 5,686,205.45 0.108
4 Ceiling Painting; Exterior M 2
110.22 54,313.60 5,986,553.62 0.114
5 Calsiplank Painting M2 19.28 54,313.60 1,047,383.46 0.020
VI. Other Works -
1 Stair -
- Retaining Wall 1 Pc : 5 Ps M2 6.48 139,920.88 906,687.30 0.017
- Landfill for floor elevation M3 0.97 163,075.00 158,508.90 0.003
- Lean Ramp 1 Pc : 3 Ps : 5 Kr M3 0.18 912,325.16 164,218.53 0.003
- Chevron Works M1 36.00 40,315.00 1,451,340.00 0.028
- Mortar Plaster Work M2 4.86 67,316.74 326,890.11 0.006
- Mortar Neat Plaster Work M2 4.86 42,427.00 206,025.51 0.004
B.2 ROOF WORKS -
Roof Covering Works -
1 Zincalume Spandex h 0,30 mm Installation M 2
324.55 171,306.67 55,597,578.67 1.060
2 Light Steel Frame; including rafter and accessoris M 2
324.55 213,420.90 69,265,753.10 1.321
3 Aluminium Foil Installation M2 324.55 27,087.50 8,791,248.13 0.168
4 Roof Ridges, Zincalum Spandex M1 34.88 73,810.00 2,574,492.80 0.049
5 Calsiplank H. 0,8 mm M1 80.31 59,070.00 4,744,029.84 0.090
6 Roof Jalousie Unit 2.00 1,563,743.50 3,127,487.00 0.060
Total Architectural Cost 385,644,602.77 7.356 0.248 0.248
C STRUCTURAL WORK
1 K1 Column 30/30
- K-250 Concrete Ready Mix M3 6.66 2,161,230.23 14,384,067.81 0.274 6.655 100.000 0.274 6.655 100.000 0.274
- Reinforcement Kg 9.47 16,006.10 151,568.80 0.003 9.469 100.000 0.003 9.469 100.000 0.003
- Column Formwork M2 88.74 275,300.00 24,430,122.00 0.466 88.740 100.000 0.466 88.740 100.000 0.466
2 K2 Column 20/20 -
- K-250 Concrete Ready Mix M 3
1.20 2,161,230.23 2,602,121.20 0.050 1.204 100.000 0.050 1.204 100.000 0.050
- Column Formwork M2 24.08 275,300.00 6,629,224.00 0.126 24.080 100.000 0.126 24.080 100.000 0.126
3 25/30 Tie Beam S1 -
- K-250 Concrete Ready Mix M 3
4.10 2,161,230.23 8,850,237.80 0.169 4.095 100.000 0.169 4.095 100.000 0.169
- Tie Beam Formwork M2 32.76 195,085.00 6,390,984.60 0.122 16.380 50.000 0.061 16.380 50.000 0.061
4 20/25 Tie Beam S2 -
- K-250 Concrete Ready Mix M3 1.10 2,161,230.23 2,382,756.33 0.045 1.102 100.000 0.045 1.102 100.000 0.045
- Tie Beam Formwork M2 11.02 195,085.00 2,150,812.12 0.041 5.512 50.000 0.021 5.512 50.000 0.021
5 20/25 Beam B1 -
- K-250 Concrete Ready Mix M3 3.83 2,161,230.23 8,282,914.86 0.158
- Reinforcement Kg 670.48 16,006.10 10,731,782.56 0.205
- Beam Formwork M2 53.66 282,050.00 15,133,392.75 0.289
6 Floor Slab t=12 cm -
- K-250 Concrete Ready Mix M3 20.10 2,161,230.23 43,440,727.66 0.829 20.100 100.000 0.829 20.100 100.000 0.829
- Floor Formwork M2 6.85 225,800.00 1,547,181.60 0.030 6.852 100.000 0.030 6.852 100.000 0.030
Total Structural Cost 147,107,894.10 2.806 2.073 2.073
D CLASSROOM ELECTRICAL WORKS
D.1 LOW VOLTAGE PANEL WORKS
Procurement and installation of a complete Panel
MCB-BOX of the Classroom unit 4.00 1,124,332.00 4,497,328.00 0.086
D.2 LIGHTING WORKS -
Procurement, installation of lighting and sockets -
a. CLASSROOM A ( 4 ROOMS ) -
1 Roset Led 22 W Type Bulb unit 28.00 143,896.50 4,029,102.00 0.077
2 Single Electrical Switch unit 1.00 34,727.00 34,727.00 0.001
3 Double Electrical Switch unit 4.00 42,350.00 169,400.00 0.003
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

4 100 W Wall Electric Socket unit 8.00 49,929.00 399,432.00 0.008


5 Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 28.00 194,035.42 5,432,991.67 0.104
6 Electrical Socket NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 8.00 218,556.25 1,748,450.00 0.033
b. CLASSROOM B ( 3 ROOMS ) GROUND FLOOR -
1 Roset Led 22 W Type Bulb unit 21.00 143,896.50 3,021,826.50 0.058
2 Single Electrical Switch unit 1.00 34,727.00 34,727.00 0.001
3 Double Electrical Switch unit 3.00 42,350.00 127,050.00 0.002
4 100 W Wall Electric Socket unit 6.00 49,929.00 299,574.00 0.006
5 Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 21.00 194,035.42 4,074,743.75 0.078
6 Electrical Socket NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 6.00 218,556.25 1,311,337.50 0.025
c. CLASSROOM B ( 3 ROOMS ) SECOND FLOOR -
1 Roset Led 22 W Type Bulb unit 21.00 143,896.50 3,021,826.50 0.058
2 Single Electrical Switch unit 1.00 34,727.00 34,727.00 0.001
3 Double Electrical Switch unit 3.00 42,350.00 127,050.00 0.002
4 100 W Wall Electric Socket unit 6.00 49,929.00 299,574.00 0.006
5 Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 21.00 194,035.42 4,074,743.75 0.078
6 Electrical Socket NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 6.00 218,556.25 1,311,337.50 0.025
d. CLASSROOM C ( 2 ROOMS ) -
1 Roset Led 22 W Type Bulb unit 14.00 143,896.50 2,014,551.00 0.038
2 Single Electrical Switch unit 1.00 34,727.00 34,727.00 0.001
3 Double Electrical Switch unit 2.00 42,350.00 84,700.00 0.002
4 100 W Wall Electric Socket unit 4.00 49,929.00 199,716.00 0.004
5 Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 14.00 194,035.42 2,716,495.83 0.052
6 Electrical Socket NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 4.00 218,556.25 874,225.00 0.017
D.3 Lightning Rod Installation -
Procurement, installation of a
-
complete lightning rod
a. CLASSROOM A ( 4 ROOM ) -
1 Ø 3/4 30cm Air Terminal , Completed With Ø 3/4 70cm GIP set 6.00 442,541.00 2,655,246.00 0.051
2 BC 25 mm² Cable Installation m 48.00 75,065.83 3,603,160.00 0.069
3 600mm² x 600mm² c/w Junction Box with Grounding System set 1.00 948,398.00 948,398.00 0.018
4 Auxiliary Materials lot 1.00 366,501.21 366,501.21 0.007
b. CLASSROOM B (3 ROOM TWO FLOOR) -
1 Ø 3/4 30cm Air Terminal , Completed With Ø 3/4 70cm GIP set 4.00 442,541.00 1,770,164.00 0.034
2 BC 25 mm² Cable Installation m 42.00 75,065.83 3,152,765.00 0.060
3 600mm² x 600mm² c/w Junction Box with Grounding System set 1.00 948,398.00 948,398.00 0.018
4 Auxiliary Materials lot 1.00 366,501.21 366,501.21 0.007
c. CLASSROOM C ( 2 ROOM ) -
1 Ø 3/4 30cm Air Terminal , Completed With Ø 3/4 70cm GIP set 3.00 442,541.00 1,327,623.00 0.025
2 BC 25 mm² Cable Installation m 29.00 75,065.83 2,176,909.17 0.042
3 600mm² x 600mm² c/w Junction Box with Grounding System set 1.00 948,398.00 948,398.00 0.018
4 Auxiliary Materials lot 1.00 366,501.21 366,501.21 0.007
Total Electrical Cost 58,604,927.79 1.118
V EXTRA CURRICULLAR BUILDING / GEDUNG UKS-D
A PREPARATION WORK
1 Site Measurement and Bowplank Installation M1 44.00 278,630.00 12,259,720.00 0.234 44.000 100.000 0.234 44.000 100.000 0.234
PREPARATION 12,259,720.00 0.234 0.234 0.234
B ARCHITECTURAL WORKS
B.1 1ST LEVEL
I WALLWORK
1 Brick Wall 1:5 M2 113.15 139,920.88 15,832,467.33 0.302
2 Brick Wall 1:3 M2 50.10 147,363.92 7,382,637.66 0.141
3 Mortar Plaster Work M2 389.88 67,316.74 26,245,721.42 0.501
4 Mortar Neat Plaster Work M2 389.88 42,427.00 16,541,608.47 0.316
5 Practical Column & Lintel Beam Work -
- K250 Concrete M3 1.18 1,226,720.35 1,448,756.73 0.028
- Reinforcement Kg 188.84 16,006.10 3,022,660.44 0.058
- Formwork M2 19.68 185,185.00 3,645,058.08 0.070
6 Wall Tiles Work 25x40 cm (Unpolished) M2 24.67 183,499.80 4,527,674.07 0.086
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

II Floor Installation Work -


1 Tile 40x40 cm (Polished) Rooms M2 65.48 162,962.80 10,670,967.11 0.204
2 Tile 40x40 cm (Unpolished) Hallway M2 9.29 166,262.80 1,544,082.62 0.029
3 Tile 40x40 (Unpolished) Toilet M2 3.92 166,262.80 651,085.12 0.012
4 Waterproofing Coating + Mortar M 2
28.59 119,614.62 3,419,781.87 0.065
III Sanitary Work and Installation -
Sanitary work includes procurement & installation -
1 Sitting closet Unit 2.00 3,699,704.80 7,399,409.60 0.141
2 Shower spray Unit 2.00 960,355.00 1,920,710.00 0.037
3 Floor Drain Unit 2.00 675,235.00 1,350,470.00 0.026
4 Robe Hook Unit 2.00 334,235.00 668,470.00 0.013
5 Tissue Holder Unit 2.00 585,475.00 1,170,950.00 0.022
6 Faucet Unit 2.00 746,652.50 1,493,305.00 0.028
IV Painting Works -
1 Wall Painting; Interior M2 215.56 40,563.60 8,743,930.18 0.167
2 Wall Painting; Exterior M2 174.32 54,313.60 9,468,109.69 0.181
3 Ceiling Painting; Interior M2 68.85 40,563.60 2,792,844.42 0.053
4 Ceiling Painting; Exterior M2 51.42 54,313.60 2,792,588.06 0.053
5 Calsiplank Painting M 2
13.49 54,313.60 732,581.84 0.014
V Door and Window Installation Work -
1 Door Alumunium Frame Installation Work (type P1) Unit 1.00 1,082,950.00 1,082,950.00 0.021
2 Leaf Door Instalation Work (type P1) Unit 1.00 2,625,000.00 2,625,000.00 0.050
3 Door Alumunium Frame Installation Work (type P2) Unit 1.00 1,533,286.70 1,533,286.70 0.029
4 Leaf Door Instalation Work (type P2) Unit 1.00 5,250,000.00 5,250,000.00 0.100
5 Door Allumunium Frame Installation Work (type P3) Unit 2.00 2,368,025.00 4,736,050.00 0.090
6 Window Allumunium Frame Installation Work (type J3) Unit 5.00 3,546,928.00 17,734,640.00 0.338
7 Window Allumunium Frame Installation Work (type V1) Unit 5.00 615,450.00 3,077,250.00 0.059
VI Ceiling Installation Work -
1 Ceiling Hollow frame M2 120.27 149,919.00 18,030,308.37 0.344
2 6 mm of Calcium Board GRC (Ceiling Interior) M2 68.85 72,230.40 4,973,135.27 0.095
3 6 mm of Calcium Board GRC (Ceiling Exterior) M2 51.42 72,230.40 3,713,798.25 0.071
VI Other Works -
1 Railling for Disability access -
- Disability Handrail Ramp work M 1
14.10 760,976.98 10,729,014.37 0.205
- Lean Ramp 1 Pc : 3 Ps : 5 Kr M 3
0.78 912,325.16 711,613.62 0.014
- Chevron Works M1 20.90 40,315.00 842,381.92 0.016
- Retaining Wall Ramp 1 Pc : 5 Ps M 2
5.75 139,920.88 803,985.38 0.015
- Landfill for floor elevation M3 1.25 163,075.00 204,332.97 0.004
- Mortar Plaster Work M2 5.76 67,316.74 387,609.81 0.007
- Mortar Neat Plaster Work M2 5.76 42,427.00 244,294.67 0.005
2 Stair -
- Retaining Wall 1 Pc : 5 Ps M2 6.48 139,920.88 906,687.30 0.017
- Landfill for floor elevation M3 0.97 163,075.00 158,508.90 0.003
- Lean Ramp 1 Pc : 3 Ps : 5 Kr M3 0.18 912,325.16 164,218.53 0.003
- Chevron Works M1 36.00 40,315.00 1,451,340.00 0.028
- Mortar Plaster Work M2 4.86 67,316.74 326,890.11 0.006
- Mortar Neat Plaster Work M2 4.86 42,427.00 206,025.51 0.004
B.2 ROOF WORKS -
A Roof Covering Works -
1 Zincalume Spandex H. 0,30 mm Installation M 2
164.38 171,306.67 28,158,704.64 0.537
2 Light Steel Frame; including rafter and accessoris M 2
164.38 213,420.90 35,081,273.86 0.669
3 Aluminium Foil Installation M2 164.38 27,087.50 4,452,534.90 0.085
4 Roof Ridges, Zincalum Spandex M1 36.63 73,810.00 2,703,512.68 0.052
5 Calsiplank H. 0,8 mm M1 45.62 59,070.00 2,695,009.68 0.051
Total Architectural Cost 286,450,227.18 5.464
C. STRUCTURAL WORK
I FOUNDATION WORK
1 Foundation PD1
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

- Foundation Cutting M3 22.66 105,435.00 2,388,735.36 0.046 22.656 100.000 0.046 22.656 100.000 0.046
- Backfill M3 16.29 62,150.00 1,012,299.20 0.019
- K-250 Concrete Ready Mix M3 4.80 2,161,230.23 10,373,905.11 0.198
- Reinforcement Kg 546.11 16,006.10 8,741,162.36 0.167
- Formwork Foundation M 2
19.20 185,185.00 3,555,552.00 0.068
- Sand Layer T=10 cm M 3
1.60 192,830.00 308,528.00 0.006
- Base Concrete T=5 cm M 3
0.80 912,325.16 729,860.13 0.014
2 PD2 Broken Stone Foundation -
- Foundation Cutting M3 8.54 105,435.00 900,836.64 0.017 8.544 100.000 0.017 8.544 100.000 0.017
- Sand Layer T=10 cm M3 2.10 192,830.00 404,943.00 0.008
- Masonry 1:4 M3 7.94 756,723.00 6,011,407.51 0.115
- Aanstamping Stone T=15 cm M3 3.15 332,739.00 1,048,127.85 0.020
- Backfill M3 2.28 62,150.00 141,702.00 0.003
3 PD3 Broken Stone Foundation -
- Foundation Cutting M3 9.60 105,435.00 1,012,281.44 0.019 9.601 100.000 0.019 9.601 100.000 0.019
- Sand Layer T=10 cm M3 2.27 192,830.00 438,456.85 0.008
- Masonry 1:4 M3 8.32 756,723.00 6,297,448.81 0.120
- Aanstamping Stone T=15 cm M3 3.41 332,739.00 1,134,872.91 0.022
- Backfill M 3
2.42 62,150.00 150,278.70 0.003
4 Tie Beam S1 - 20/25 -
- K-250 Concrete Ready Mix M 3
2.80 2,161,230.23 6,051,444.65 0.115
- Reinforcement Kg 484.44 16,006.10 7,754,007.38 0.148
- Tie Beam Formwork M2 28.00 195,085.00 5,462,380.00 0.104
5 Tie Beam S2 - 15/20 -
- K-250 Concrete Ready Mix M3 0.25 2,161,230.23 546,791.25 0.010
- Reinforcement Kg 57.82 16,006.10 925,432.04 0.018
- Tie Beam Formwork M2 1.69 195,085.00 329,043.37 0.006
II. STRUCTURAL WORK -
1 Column K1- 20/20 -
- K-250 Concrete Ready Mix M3 3.41 2,161,230.23 7,365,472.63 0.140
- Reinforcement Kg 712.36 16,006.10 11,402,079.02 0.217
- Formwork Column M2 68.16 275,300.00 18,764,448.00 0.358
2 Beam B1 - 20/25 -
- K-250 Concrete Ready Mix M 3
2.52 2,161,230.23 5,446,300.18 0.104
- Reinforcement Kg 412.74 16,006.10 6,606,386.81 0.126
- Formwork Column M2 35.28 275,300.00 9,712,584.00 0.185
3 Floor Slab T = 12 cm -
- Base Concrete T=5 cm m3 3.56 912,325.16 3,244,045.80 0.062
- Sand layer T=10 cm m3 7.11 192,830.00 1,371,329.83 0.026
- K-250 Concrete Ready Mix m3 8.56 2,161,230.23 18,495,808.32 0.353
- Reinforcement kg 739.89 16,006.10 11,842,683.30 0.226
- Floor Formwork m2 4.32 225,800.00 975,456.00 0.019
Total Structural Cost 160,946,090.45 3.070 0.082 0.08
D. MECHANICAL AND ELECTRICAL WORKS
1 UKS ROOM PLUMBING WORKS
1.1 CLEAN WATER SYSTEM
Procurement and installation of PVC Pipes including excavation, accessories, and auxiliary equipment
A Toilet and Clean Water Piping and Its Completeness
1 PVC AW Ø 25 mm m 10.00 28,026.63 280,266.25 0.005
2 PVC AW Ø 20 mm m 1.00 23,892.00 23,892.00 0.000
3 Fitting ls 1.00 43,076.83 43,076.83 0.001
4 Gate Valve Ø 32mm unit 1.00 126,610.00 126,610.00 0.002
1.2 VENT AND GREY WATER SYSTEM -
Procurement and installation of PVC Pipes including excavation, accessories, and auxiliary tool -
A Grey Water Piping and Its completeness in toilet to Sepictank.1 -
1 PVC-AW Ø 100 mm; SW (Sewage Water) m 13.00 185,950.88 2,417,361.38 0.046
2 PVC-AW Ø 80 mm; WW (Waste Water) m 12.00 123,292.13 1,479,505.50 0.028
3 Floor Clean Out Ø 80 mm, WW (Waste Water) bh 1.00 230,725.00 230,725.00 0.004
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

4 Floor Clean Out Ø 100 mm, SW (Sewage Water) bh 1.00 340,263.00 340,263.00 0.006
5 Fitting ls 1.00 446,785.49 446,785.49 0.009
D. UKS ELECTRICAL WORKS -
D.1 LOW VOLTAGE PANEL WORKS -
Procurement and installation -
MCB-BOX of The Extra Curricullar Building unit 1.00 930,149.00 930,149.00 0.018
D.2 LIGHTING WORKS -
Procurement and installation -
A UKS ELECTRICAL WORKS -
1 Roset Led 22 W Type Bulb unit 8.00 143,896.50 1,151,172.00 0.022
2 Roset Led 5 W Type Bulb (toilet and antrance) unit 2.00 69,399.00 138,798.00 0.003
3 Single Electrical Switch unit 4.00 34,727.00 138,908.00 0.003
4 Double Electrical Switch unit 1.00 42,350.00 42,350.00 0.001
5 200 W Wall Electric Socket unit 5.00 49,929.00 249,645.00 0.005
6 Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 10.00 194,035.42 1,940,354.17 0.037
7 Electrical Socket NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 5.00 218,556.25 1,092,781.25 0.021
D.3 Lightning Rod Installation -
Procurement and installation -
1 Ø 3/4 30cm Air Terminal , Completed With Ø 3/4 70cm GIP set 1.00 442,541.00 442,541.00 0.008
2 BC 25 mm² Cable Installation m 20.00 75,065.83 1,501,316.67 0.029
3 600mm² x 600mm² c/w Junction Box with Grounding System set 1.00 948,398.00 948,398.00 0.018
4 Auxiliary Materials lot 1.00 366,501.21 366,501.21 0.007
Total Mechanical And Electrical Cost 14,331,399.73 0.273
VI TOILET 6 ROOMS-E
A PREPARATION WORK
1 Site Measurement M1 29.00 22,990.00 666,710.00 0.013 29.000 100.000 0.013 29.000 100.000 0.013
PREPARATION 666,710.00 0.013 0.013 0.013
B ARCHITECTURAL WORKS
A WALLWORK
1 Brick Wall 1:3 M2 73.77 147,363.92 10,871,036.38 0.207
2 Mortar Plaster Work M2 124.71 67,316.74 8,395,071.14 0.160
3 Mortar Neat Plaster Work M2 124.71 42,427.00 5,291,071.17 0.101
4 Practical Column & Lintel Beam Work -
- K250 Concrete M 3
0.39 1,226,720.35 473,514.05 0.009
- Reinforcement Kg 59.38 16,006.10 950,390.29 0.018
- Formwork M2 6.43 185,185.00 1,191,356.83 0.023
5 Wall Tiles Work 25x40 cm (Unpolished) M 2
88.54 183,499.80 16,247,439.29 0.310
B Ceiling Installation Work -
1 Ceiling Hollow frame M2 64.97 149,919.00 9,739,637.75 0.186
2 6 mm of Calcium Board GRC (Ceiling Interior) M2 16.38 72,230.40 1,183,206.18 0.023
3 6 mm of Calcium Board GRC (Ceiling Exterior) M2 48.59 72,230.40 3,509,313.98 0.067
C Floor Installation Work -
1 40x40 cm of Ceramic Tile (Unpolished) Hallway M2 35.80 166,262.80 5,952,041.98 0.114
2 40x40 cm of Ceramic Tile (Unpolished) Rooms M2 15.55 162,962.80 2,534,071.54 0.048
3 Waterproofing Coating + Mortar M2 15.55 119,614.62 1,860,007.28 0.035
D Door and Window Installation Work (complete w. alluminium frame) -
1 Door Allumunium Frame Installation Work (type P4) Difabel Unit 1.00 2,585,000.00 2,585,000.00 0.049
2 Door Allumunium Frame Installation Work (type P3) Unit 5.00 2,368,025.00 11,840,125.00 0.226
E Sanitary Work and Installation -
Sanitary work includes procurement & installation -
1 Squatting Closet Unit 5.00 1,306,646.00 6,533,230.00 0.125
2 Sitting Closet Unit 1.00 3,699,704.80 3,699,704.80 0.071
3 Shower Spray Unit 1.00 960,355.00 960,355.00 0.018
4 Wastafel Hang Unit 5.00 3,723,830.00 18,619,150.00 0.355
5 Floor Drain Unit 6.00 675,235.00 4,051,410.00 0.077
6 Tissue Holder Unit 1.00 585,475.00 585,475.00 0.011
7 Soap Dispenser Unit 3.00 165,275.00 495,825.00 0.009
8 Robe Hook Unit 6.00 334,235.00 2,005,410.00 0.038
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

9 Fibre Basin Unit 5.00 992,670.36 4,963,351.80 0.095


10 5mm; uk 500x700 of mirror work Unit 5.00 126,379.00 631,895.00 0.012
11 Handrail M1 1.20 610,995.00 733,194.00 0.014
12 Faucet Unit 6.00 746,652.50 4,479,915.00 0.085
F Painting Works -
1 Wall Painting; Interior M 2
28.29 40,563.60 1,147,544.24 0.022
2 Wall Painting; Exterior M 2
96.42 54,313.60 5,236,917.31 0.100
3 Ceiling Painting; Interior M2 16.38 40,563.60 664,472.33 0.013
4 Ceiling Painting; Exterior M2 48.59 54,313.60 2,638,826.26 0.050
5 Calsiplank Painting M2 11.37 54,313.60 617,437.00 0.012
G Other Works -
1 Stair -
- Retaining Wall 1 Pc : 5 Ps M2 3.24 139,920.88 453,343.65 0.009
- Landfill for floor elevation M3 0.49 163,075.00 79,254.45 0.002
- Lean Ramp 1 Pc : 3 Ps : 5 Kr M3 0.09 912,325.16 82,109.26 0.002
- Chevron Works M1 18.00 40,315.00 725,670.00 0.014
- Mortar Plaster Work M2 2.43 67,316.74 163,445.05 0.003
- Mortar Neat Plaster Work M2 2.43 42,427.00 103,012.76 0.002
B.2 ROOF WORKS -
A Roof Covering Works -
1 Zincalume Spandex H. 0,30 mm Installation M 2
113.01 171,306.67 19,360,051.63 0.369
2 Light Steel Frame; including rafter and accessoris M 2
113.01 213,420.90 24,119,549.59 0.460
3 Aluminium Foil Installation M2 113.01 27,087.50 3,061,266.73 0.058
4 Roof Ridges, Zincalum Spandex M1 30.09 73,810.00 2,220,795.28 0.042
5 Calsiplank H. 0,8 mm M1 38.50 59,070.00 2,274,195.00 0.043
Total Architectural Cost 193,330,089.03 3.688
C STRUCTURAL WORK
I FOUNDATION WORK
1 Foundation PD1
- Backfill M3 5.80 62,150.00 360,470.00 0.007
II STRUCTURAL WORK -
1 Column K1 - 20/20 -
- K-250 Concrete Ready Mix M 3
2.25 2,161,230.23 4,858,445.56 0.093
- Reinforcement Kg 58.12 16,006.10 930,349.45 0.018
- Column Formwork M2 44.96 275,300.00 12,377,488.00 0.236
2 Column K2 - 15/20 -
- K-250 Concrete Ready Mix M 3
0.52 2,161,230.23 1,115,194.80 0.021
- Reinforcement Kg 17.10 16,006.10 273,628.27 0.005
-Column Formwork M2 12.04 275,300.00 3,314,612.00 0.063
3 20/25 Tie Beam S1 -
- K-250 Concrete Ready Mix M3 2.19 2,161,230.23 4,733,094.21 0.090
- Reinforcement Kg 43.48 16,006.10 695,877.64 0.013
- Tie Beam Formwork M2 21.90 195,085.00 4,272,361.50 0.081
4 15/20 Tie Beam S2 -
- K-250 Concrete Ready Mix M3 0.42 2,161,230.23 902,853.93 0.017
- Reinforcement Kg 21.74 16,006.10 347,938.82 0.007
- Tie Beam Formwork M2 5.57 195,085.00 1,086,623.45 0.021
5 Beam B1-15/20 -
- K-250 Concrete Ready Mix M 3
1.81 2,161,230.23 3,914,528.26 0.075
- Reinforcement Kg 496.92 16,006.10 7,953,819.27 0.152
- Beam Formwork M2 33.21 282,050.00 9,365,822.81 0.179
6 Floor Slab H=12 cm -
- K-250 Concrete Ready Mix M3 5.28 2,161,230.23 11,411,295.62 0.218
- Reinforcement Kg 459.12 16,006.10 7,348,718.71 0.140
- Floor Formwork M2 3.58 225,800.00 807,460.80 0.015
- Sand layer T=10 cm M3 4.40 192,830.00 848,452.00 0.016
- Base Concrete T=5 cm M3 2.20 912,325.16 2,007,115.35 0.038
Total Structural Cost 78,926,150.44 1.505
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

D. MECHANICAL AND ELECTRICAL WORKS


1 TOILET PLUMBING WORKS
1.1 CLEAN WATER SYSTEM
Procurement and installation of PVC Pipes
a Toilet Clean Water Piping and Its Completeness
1 PVC AW Ø 25 mm m 24.00 28,026.63 672,639.00 0.013
2 PVC AW Ø 20 mm m 2.00 23,892.00 47,784.00 0.001
3 Fitting ls 1.00 84,703.30 84,703.30 0.002
4 Gate Valve Ø 32mm unit 1.00 126,610.00 126,610.00 0.002
1.2 VENT AND GREY WATER SYSTEM
Procurement and installation of PVC Pipes
a. Grey Water Piping and Its completeness in toilet to Sepictank
1 PVC-AW Ø 100 mm; SW (Sewage Water) m 17.00 185,950.88 3,161,164.88 0.060
2 PVC-AW Ø 80 mm; WW (Waste Water) m 31.00 123,292.13 3,822,055.88 0.073
3 PVC-AW Ø 65 mm; WW (Waste Water) m 4.00 95,628.50 382,514.00 0.007
4 PVC-AW Ø 50 mm; WW (Waste Water) m 5.00 55,061.88 275,309.38 0.005
5 Floor Clean Out Ø 80 mm, WW (Waste Water) unit 2.00 230,725.00 461,450.00 0.009
6 Floor Clean Out Ø 100 mm, SW (Sewage Water) unit 1.00 340,263.00 340,263.00 0.006
7 Fitting ls 1.00 844,275.71 844,275.71 0.016
2 TOILET ELECTRICAL WORKS
2.1 PANEL WORKS
Procurement & Installation
1 MCB BOX Toilet Unit 1.00 631,939.00 631,939.00 0.012
2 NYM 3x2,5 mm² Lamp Installation in 20 mmi conduit pipe m 29.00 43,081.50 1,249,363.50 0.024
of MCB-BOX from Classroom MCB-BOX to Toilet
2.2 LIGHTING WORKS
Procurement, installation of lighting
A Toilet (6 ROOMS)
Roset Led 5 W Type Bulb (Toilet) unit 10.00 69,399.00 693,990.00 0.013
Single Electrical Switch unit 2.00 34,727.00 69,454.00 0.001
Double Electrical Switch unit 4.00 42,350.00 169,400.00 0.003
Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 10.00 194,035.42 1,940,354.17 0.037
2.3 Lightning Rod Installation
Procurement, installation of a complete lightning rod
A Toilet (6 ROOMS)
1 Air Terminal, Ø 3/4 30cm; Completed with GIP, Ø 3/4 70cm set 1.00 442,541.00 442,541.00 0.008
2 BC Cable Installation, 25 mm² m 18.00 75,065.83 1,351,185.00 0.026
3 Earthing Pit, 600mm² x 600mm² c/w with grounding system set 1.00 948,398.00 948,398.00 0.018
4 Auxiliary Equipments lot 1.00 366,501.21 366,501.21 0.007
Total Mechanical And Electrical Cost 18,081,895.01 0.345
VI. SITE PLAN
A SITEPLAN STRUCTURAL WORKS
1.1 STRUCTURAL FOUNDATION TOWER WATER TANK
a. Foundation Footplat
- Foundation Cutting m3 1.12 105,435.00 117,665.46 0.002
- Backfill m3 0.73 62,150.00 45,493.80 0.001
- Concrete K-250 m3 0.29 1,226,720.35 353,295.46 0.007
- Reinforcement kg 11.54 16,006.10 184,724.48 0.004
- Formwork m 2 1.92 185,185.00 355,555.20 0.007
- Sand layer t=10cm m3 0.07 192,830.00 13,883.76 0.000
- Base Concrete t=5cm m3 0.07 912,325.16 65,687.41 0.001
b. 20/20 Column
- Concrete K-250 m3 0.10 1,226,720.35 117,765.15 0.002
- Reinforcement kg 13.31 16,006.10 213,067.85 0.004
- Formwork Column m2 1.92 275,300.00 528,576.00 0.010
c. 15/20 Tie Beam
- Concrete K-250 m3 0.16 1,226,720.35 191,368.37 0.004
- Reinforcement kg 23.15 16,006.10 370,535.20 0.007
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

- Tie Beam Formwork m 2 2.08 195,085.00 405,776.80 0.008


Total Site Plan Structural Work Cost 2,963,394.95 0.057
B. SITEPLAN PLUMBING WORKS
1.1 MAIN EQUIPMENTS OF CLEAN WATER SYSTEM
Pipeline procurement and installation include excavation, accessories, and auxiliary equipment
a. Piping and accessories (Pump)
1 PVC-AW Ø 32 mm m 40.00 33,610.50 1,344,420.00 0.026
2 PVC-AW Ø 25 mm m 40.00 28,026.63 1,121,065.00 0.021
3 Fitting ls 1.00 123,274.25 123,274.25 0.002
b. CLEAN WATER PUMP
1 Type : Jet Pump ls 1.00 9,729,500.00 9,729,500.00 0.186
Capacity : 35 Lpm
Suction Head : 40 m
Discharge Head : 41 m
Output Power : 1 Kw
Installed complete with WLC (water level control), holder, support etc. according to specifications and drawing
c. Piping from Jet Pump to water tank
1 PVC AW Ø 32 mm m 67.00 33,610.50 2,251,903.50 0.043
2 Gate Valve Ø 32mm unit 1.00 126,610.00 126,610.00 0.002
4 Fitting ls 1.00 237,851.35 237,851.35 0.005
d. Roof Tank
1 Type : Fibreglass unit 1.00 7,812,750.00 7,812,750.00 0.149
2 Capacity : 1 m3
Rooftank work c/w Water Tower 4 meters high
1.2 CLEAN WATER SYSTEM
Procurement and installation of PVC Pipes including excavation, accessories, and auxiliary equipment
a. Piping and accessories from the Tank to UKS
1 PVC AW Ø 40 mm m 4.00 50,373.13 201,492.50 0.004
2 PVC AW Ø 32 mm m 17.00 33,610.50 571,378.50 0.011
3 Fitting ls 1.00 91,061.85 91,061.85 0.002
4 Gate Valve Ø 40mm unit 1.00 137,747.50 137,747.50 0.003
b. Piping and accessories from the Tank to toilet
1 PVC AW Ø 40 mm m 4.00 50,373.13 201,492.50 0.004
2 PVC AW Ø 32 mm m 19.00 33,610.50 638,599.50 0.012
3 Fitting ls 1.00 97,783.95 97,783.95 0.002
4 Gate Valve Ø 40mm unit 1.00 137,747.50 137,747.50 0.003
1.3 VENT AND GREY WATER SYSTEM
Procurement and installation of PVC Pipes including excavation, accessories, and auxiliary tool
a. Grey Water Piping to Sepictank 1 (UKS)
1 PVC-AW Ø 100 mm; SW (Sewage Water) m 5.00 185,950.88 929,754.38 0.018
2 PVC-AW Ø 80 mm; WW (Waste Water) m 6.00 123,292.13 739,752.75 0.014
3 Fitting ls 1.00 166,950.71 166,950.71 0.003
b. Grey Water Piping to Sepictank 2 (Toilet)
1 PVC-AW Ø 100 mm; SW (Sewage Water) m 2.00 185,950.88 371,901.75 0.007
2 PVC-AW Ø 80 mm; WW (Waste Water) m 2.00 123,292.13 246,584.25 0.005
3 Fitting ls 1.00 61,848.60 61,848.60 0.001
1.4 DRAINAGE PIPE SYSTEM TO INFILTRATION WELL
Procurement and installation of PVC Pipes including excavation, accessories, and auxiliary tool
a. PVC-AW Ø 100 mm; PAH m 7.00 185,950.88 1,301,656.13 0.025
Total Site Plan Structural Work Cost 28,643,126.46 0.546
C. SITE PLAN ELECTRICAL WORKS
C.1 LOW VOLTAGE PANEL WORK
Procurement and installation of Panel
School Main Panel unit 1.00 3,173,775.00 3,173,775.00 0.061
New Installation of PLN
Connecting Fee VA 7,700.00 993.33 7,648,666.67 0.146
Deposit Money VA 7,700.00 333.33 2,566,666.67 0.049
SLO (Certificate of Eligibility for Operation) (adjusted for rates from SLO consultants) VA 7,700.00 66.67 513,333.33 0.010
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

C.2 CONNECTOR CABLE PROVISION AND INSTALLATION


The work of procurement, installation and testing
Low Voltage Cable ;
From Main Panel to Classroom 4 Room MCB-BOX, NYY 3 x 4 mm² + BC 6mm² m 99.00 75,967.83 7,520,815.50 0.143
From Main Panel to Classroom 3 Room Lt.1 MCB-BOX, NYY 3 x 4 mm² + BC 6mm² m 8.00 75,967.83 607,742.67 0.012
From Main Panel to Classroom 3 Room Lt.2 MCB-BOX, NYY 3 x 4 mm² + BC 6mm² m 12.00 75,967.83 911,614.00 0.017
From Main Panel to Classroom 2 Room MCB-BOX, NYY 3 x 4 mm² + BC 6mm² m 130.00 75,967.83 9,875,818.33 0.188
From Main Panel to UKS MCB-BOX, NYY 3 x 4 mm² + BC 6mm² m 86.00 75,967.83 6,533,233.67 0.125
From MCB-BOX.UKS to Jet Pump, NYY 3 x 4 mm² + BC 6mm² m 45.00 75,967.83 3,418,552.50 0.065
Total Site Plan Mechanical And Electrical Cost 42,770,218.33 0.816
VII. SEPTIC TANK N25 WORKS -1
A STP
1 Ground Work
- STP Foundation Cutting m3 26.21 105,435.00 2,763,480.64 0.053
- Backfill m3 21.64 62,150.00 1,345,026.55 0.026
2 (120X120) Column
- K-250 Concrete m3 0.12 1,226,720.35 144,851.14 0.003
- Reinforcement kg 30.76 16,006.10 492,358.63 0.009
- Column Formwork m 2
3.94 275,300.00 1,083,580.80 0.021
3 (120X120)Tie Beam
- K-250 Concrete m3 0.08 1,226,720.35 92,210.12 0.002
- Reinforcement kg 19.17 16,006.10 306,882.62 0.006
- Tie Beam Formwork m2 1.25 195,085.00 244,402.49 0.005
4 B1 (120X120) Beam
- K-250 Concrete m3 0.08 1,226,720.35 92,210.12 0.002
- Reinforcement kg 19.17 16,006.10 306,882.62 0.006
- Beam Formwork m2 1.25 282,050.00 353,352.24 0.007
5 B2 (120X120) Beam
- K-250 Concrete m3 0.07 1,226,720.35 81,552.37 0.002
- Reinforcement kg 23.23 16,006.10 371,886.69 0.007
- Beam Formwork m2 1.11 282,050.00 312,511.40 0.006
6 Wall h=12 cm
- K-250 Concrete m 3 1.30 1,226,720.35 1,596,760.54 0.030
- Reinforcement kg 72.51 16,006.10 1,160,547.33 0.022
- Formwork m 2
22.22 282,050.00 6,266,361.26 0.120
7 Slab Top h=12cm
- K-250 Concrete m3 0.10 1,226,720.35 117,421.67 0.002
- Reinforcement kg 16.80 16,006.10 268,896.48 0.005
- Formwork m2 0.81 295,300.00 239,488.30 0.005
8 Floor Slab h=12 cm
- K-250 Concrete m3 0.22 1,226,720.35 265,707.63 0.005
- Reinforcement kg 16.80 16,006.10 268,896.48 0.005
- Floor Formwork m2 0.68 225,800.00 154,447.20 0.003
- Sand layer t=10cm m3 0.24 192,830.00 46,568.45 0.001
- Base Concrete t=5cm m3 0.12 912,325.16 110,163.26 0.002
- Waterproofing Coating m2 18.22 48,213.00 878,537.29 0.017
Total STP-1 Cost 19,364,984.30 0.369
B Infiltration
- Soil Exavation m 3 1.22 105,435.00 128,103.53 0.002
- Brick Wall 1 Pc : 3 Ps m2 5.40 147,363.92 795,765.17 0.015
- Sand Layer m3 0.48 192,830.00 92,558.40 0.002
- Gravel m3 0.48 429,330.00 206,078.40 0.004
Total Infiltration-1 Cost 1,222,505.49 0.023
VIII. SEPTIC TANK N25 WORKS -2
A STP
1 Ground Work
- STP Foundation Cutting m3 26.21 105,435.00 2,763,480.64 0.053
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

- Backfill m 3 21.64 62,150.00 1,345,026.55 0.026


2 (120X120) Column
- K-250 Concrete m3 0.12 1,226,720.35 144,851.14 0.003
- Reinforcement kg 30.76 16,006.10 492,358.63 0.009
- Column Formwork m 2
3.94 275,300.00 1,083,580.80 0.021
3 (120X120)Tie Beam
- K-250 Concrete m3 0.08 1,226,720.35 92,210.12 0.002
- Reinforcement kg 19.17 16,006.10 306,882.62 0.006
- Tie Beam Formwork m2 1.25 195,085.00 244,402.49 0.005
4 B1 (120X120) Beam
- K-250 Concrete m3 0.08 1,226,720.35 92,210.12 0.002
- Reinforcement kg 19.17 16,006.10 306,882.62 0.006
- Beam Formwork m2 1.25 282,050.00 353,352.24 0.007
5 B2 (120X120) Beam
- K-250 Concrete m3 0.07 1,226,720.35 81,552.37 0.002
- Reinforcement kg 23.23 16,006.10 371,886.69 0.007
- Beam Formwork m2 1.11 282,050.00 312,511.40 0.006
6 Wall h=12 cm
- K-250 Concrete m 3 1.30 1,226,720.35 1,596,760.54 0.030
- Reinforcement kg 72.51 16,006.10 1,160,547.33 0.022
- Formwork m 2
22.22 282,050.00 6,266,361.26 0.120
7 Slab Top h=12cm
- K-250 Concrete m3 0.10 1,226,720.35 117,421.67 0.002
- Reinforcement kg 16.80 16,006.10 268,896.48 0.005
- Formwork m2 0.81 295,300.00 239,488.30 0.005
8 Floor Slab h=12 cm
- K-250 Concrete m3 0.22 1,226,720.35 265,707.63 0.005
- Reinforcement kg 16.80 16,006.10 268,896.48 0.005
- Floor Formwork m2 0.68 225,800.00 154,447.20 0.003
- Sand layer t=10cm m3 0.24 192,830.00 46,568.45 0.001
- Base Concrete t=5cm m3 0.12 912,325.16 110,163.26 0.002
- Waterproofing Coating m2 18.22 48,213.00 878,537.29 0.017
Total STP-2 Cost 19,364,984.30 0.369
B Infiltration
- Soil Exavation m3 1.22 105,435.00 128,103.53 0.002
- Brick Wall 1 Pc : 3 Ps m2 5.40 147,363.92 795,765.17 0.015
- Sand Layer m3 0.48 192,830.00 92,558.40 0.002
- Gravel m3 0.48 429,330.00 206,078.40 0.004
Total Infiltration-2 Cost 1,222,505.49 0.023
IX GUTTERS AROUND THE BUILDING AND INFILTRATION
A Gutters Around the Building
- Soil Exavation m3 41.62 105,435.00 4,388,542.09 0.084
- Brick Wall 1 Pc : 3 Ps m2 209.92 147,363.92 30,934,634.09 0.590
- Sand Layer m3 26.81 192,830.00 5,170,543.62 0.099
- Lean Work 1 Pc : 2 Ps : 3 Kr m3 32.03 912,325.16 29,221,044.97 0.557
- Mortar Plaster Work m2 393.60 67,316.74 26,495,870.44 0.505
- Mortar Neat Plaster Work m2 393.60 42,427.00 16,699,267.20 0.319
Total Gutters Around The Building Cost 112,909,902.41 2.154
B Infiltration
- Soil Exavation m3 6.08 105,435.00 640,517.63 0.012
- Brick Wall 1 Pc : 3 Ps m2 27.00 147,363.92 3,978,825.84 0.076
- Sand Layer m3 2.40 192,830.00 462,792.00 0.009
- Gravel m3 2.40 429,330.00 1,030,392.00 0.020
Total Infiltration Cost 6,112,527.47 0.117
X CONNECTING CORRIDOR
- Soil Exavation m3 1.38 105,435.00 145,184.00 0.003
- Brick Wall 1 Pc : 5 Ps m2 26.62 139,920.88 3,724,973.67 0.071
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

- Landfill for floor elevation m 3 7.57 163,075.00 1,235,048.51 0.024


- Sand layer m3 0.84 192,830.00 162,266.45 0.003
- Lean Work 1 Pc : 2 Ps : 3 Kr m3 1.39 912,325.16 1,270,230.32 0.024
- Chevron Works m' 19.89 40,315.00 801,865.35 0.015
- Mortar Plaster Work m2 17.44 67,316.74 1,174,138.65 0.022
- Mortar Neat Plaster Work m2 17.44 42,427.00 740,011.73 0.014
- Canopy (Module 1,4mx3m) Unit 2.00 3,168,440.00 6,336,880.00 0.121
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

- Handrail Corridor Work m 24.60 760,976.98 18,720,033.59 0.357


Total Connecting Corridor Cost 34,310,632.26 0.654
TOTAL 5,242,761,000.00 100.000 4.682 2.021 6.703
Plan 8.442 Realization 6.703 Deviation (1.739)

Acknowledged by ; Approved by ; Submitted by;


UNITED NATIONS DEVELOPMENT PROGRAMME Supervision Consultant Contractor
PT. YODYA KARYA (PERSERO) JV PT. SETIA MULIA ABADI

(Whisnu Yonar Anggono) (Apjelvian Henri) (Faris Mubarok)


Community Mobilization Officer UNDP PETRA Team Leader Site Manager
Assignor : Supervision Consultant : Contractor :

WEEKLY REPORT
Project : CONSTRUCTION OF SCHOOLS FACILITIES IN CENTRAL SULAWESI (LOT 3) Week : 7 (seven)
Contract No. : Ref.: 10057438 Period : 30 July 2023 - 05 August 2023
Location : SD Negeri 21 Palu Weight Until Last Week : 4.452 %
Owner : United Nations Development Programme Weight This Week : 1.323 %
Contract Price : IDR 6,437,917,000 Weight Until This week Week : 5.775 %

UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK


NO. WORK DESCRIPTION VOLUME / UNIT Weight (%)
Physic (%) Weight (%) Physic (%) Weight (%) Physic (%) Weight (%)

1. SD Negeri 21 Palu 18.496


I PREPARATION WORK
A SITE PREPARATION 1.00 0.999 71.957 0.719 71.957 0.719
II CLASSROOM 8X7 (3 ROOMS) A1
A PREPARATION WORK 1.00 0.024 100.000 0.024 100.000 0.024
B ARCHITECTURAL WORKS 1.00 7.622
C STRUCTURAL WORK 1.00 2.882 75.035 2.162 20.862 0.601 95.897 2.763

III CLASSROOM 8X7 (3 ROOMS) A2


A PREPARATION WORK 1.00 0.024
B ARCHITECTURAL WORKS 1.00 7.641
C STRUCTURAL WORK 1.00 3.332 5.624 0.187 1.967 0.066 7.591 0.253
D CLASSROOM ELECTRICAL WORKS 1.00 0.493

IV TEACHER'S OFFICE -B
A PREPARATION WORK 1.00 0.173
B ARCHITECTURAL WORKS 1.00 3.580
C. STRUCTURAL WORK 1.00 2.467
D. MECHANICAL AND ELECTRICAL WORKS 1.00 0.176

V LIBRARY 8x7 -C
A PREPARATION WORK 1.00 0.138
B ARCHITECTURAL WORKS 1.00 3.216
C. STRUCTURAL WORK 1.00 2.490
D. LIBRARY ELECTRICAL WORKS 1.00 0.118
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION VOLUME / UNIT Weight (%)
Physic (%) Weight (%) Physic (%) Weight (%) Physic (%) Weight (%)

VI MUSHOLA 8x7 -D
A PREPARATION WORK 1.00 0.130
B ARCHITECTURAL WORKS 1.00 3.073
C. STRUCTURAL WORK 1.00 2.308
D. MECHANICAL AND ELECTRICAL WORKS 1.00 0.165

VII TOILET 4 ROOMS -E


A PREPARATION WORK 1.00 0.009
B ARCHITECTURAL WORKS 1.00 2.474
C STRUCTURAL WORK 1.00 1.131
D. MECHANICAL AND ELECTRICAL WORKS 1.00 0.244

IX SITE PLAN
A SITEPLAN STRUCTURAL WORKS 1.00 0.046
B SITEPLAN PLUMBING WORKS 1.00 0.551
C. SITE PLAN ELECTRICAL WORKS 1.00 0.450

X SEPTIC TANK N25 WORKS-1


A STP 1.00 0.301
B Infiltration 1.00 0.019

XI SEPTIC TANK N25 WORKS-2


A STP 1.00 0.301
B Infiltration 1.00 0.019

XII GUTTERS AROUND THE BUILDING AND INFILTRATION


A Gutters Around the Building 1.00 1.373
B Infiltration 1.00 0.114

XIII CONNECTING CORRIDOR


A Connecting Corridor 1.00 0.219

TOTAL SDN 21 PALU 48.299 3.069 0.690 3.759

2. SD Negeri Pengawu 19.799


I PREPARATION WORK
A SITE PREPARATION 1.0898 83.726 0.912 1.434 0.016 85.160 0.928
II CLASSROOM 8x7 (5 ROOMS) A1
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION VOLUME / UNIT Weight (%)
Physic (%) Weight (%) Physic (%) Weight (%) Physic (%) Weight (%)

A PREPARATION WORK 0.0674


B ARCHITECTURAL WORKS 11.4224
C STRUCTURAL WORK 1.2361

III CLASSROOM 8x7 (3 ROOMS) A2


A PREPARATION WORK 0.2146 10.981 0.024 10.981 0.024
B ARCHITECTURAL WORKS 7.0801
C STRUCTURAL WORK 0.7482 16.026 0.120 15.346 0.115 31.372 0.235

IV CLASSROOM 10x9 (1 ROOM) B1


A PREPARATION WORK 0.1956
B ARCHITECTURAL WORKS 3.7619
C STRUCTURAL WORK 0.2787 56.313 0.157 56.313 0.157

V CLASSROOM 10x9 (1 ROOM) B2


A PREPARATION WORK 0.0583
B ARCHITECTURAL WORKS 3.8351
C STRUCTURAL WORK 2.0066 14.766 0.296 4.569 0.092 19.335 0.388
D CLASSROOM ELECTRICAL WORKS 1.1076

VI MUSHOLA 10x9-C
A PREPARATION WORK 0.0828
B ARCHITECTURAL WORKS 3.5670
C. STRUCTURAL WORK 1.9898 2.738 0.054 11.570 0.230 14.308 0.285
D. MECHANICAL AND ELECTRICAL WORKS 0.1775

VII TOILET 6 ROOMS-D2


A PREPARATION WORK 0.0203
B ARCHITECTURAL WORKS 3.0030

IX TOILET 6 ROOMS-D1
A PREPARATION WORK 0.1290
B ARCHITECTURAL WORKS 3.3730
C STRUCTURAL WORK 0.9485
D. MECHANICAL AND ELECTRICAL WORKS 0.3793
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION VOLUME / UNIT Weight (%)
Physic (%) Weight (%) Physic (%) Weight (%) Physic (%) Weight (%)

X SITE PLAN
A SITEPLAN STRUCTURAL WORKS 0.0447
B. SITEPLAN PLUMBING WORKS 1.1675
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION VOLUME / UNIT Weight (%)
Physic (%) Weight (%) Physic (%) Weight (%) Physic (%) Weight (%)

XI SEPTIC TANK N25 WORKS 1


A STP 0.2579
B Infiltration 0.0190

XII SEPTIC TANK N25 WORKS 2


A STP 0.2579
B Infiltration 0.0190

XIII GUTTERS AROUND THE BUILDING AND INFILTRATION


A Gutters Around the Building 1.8895
B Infiltration 0.0760

XIV CONNECTING CORRIDOR


A Connecting Corridor 1.1972
TOTAL SDN PENGAWU 51.701 1.383 0.633 2.016
TOTAL LOT 3 100.000 4.452 1.323 5.775

Plan 7.195 Realization 5.775 Deviation (1.420)

Acknowledged by ; Approved by ; Submitted by;


UNITED NATIONS DEVELOPMENT PROGRAMME Supervision Consultant Contractor
PT. YODYA KARYA (PERSERO) JV PT. SETIA MULIA ABADI

(Whisnu Yonar Anggono) (Apjelvian Henri) (Ajeng Listianti)


Community Mobilization Officer UNDP PETRA Team Leader Site Manager
Assignor : Supervision Consultant : Contractor :

WEEKLY REPORT
Project : CONSTRUCTION OF SCHOOLS FACILITIES IN CENTRAL SULAWESI (LOT 3) Week : 7 (seven)
Contract No. : Ref.: 10057438 Period : 30 July 2023 - 05 August 2023
Location : SD Negeri 21 Palu Weight Until Last Week : 6.354 %
Owner : United Nations Development Programme Weight This Week : 1.429 %
Contract Price : IDR 3,109,428,000 Weight Until This week Week : 7.783 %

UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK


UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

I PREPARATION WORK
1 Project Safety Fencing m' 50.00 251,460.00 12,573,000.00 0.404 30.000 60.000 0.243 30.000 60.000 0.243
2 Project Signage Unit 1.00 474,732.50 474,732.50 0.015 1.000 100.000 0.015 1.000 100.000 0.015
3 Renovation Temporary Office Construction; Plaster Floor ls 1.00 18,354,930.00 18,354,930.00 0.590 0.750 75.000 0.443 0.750 75.000 0.443
4 Renovation Storage Construction & Bordinghouse ls 1.00 5,738,238.00 5,738,238.00 0.185 1.000 100.000 0.185 1.000 100.000 0.185
5 Mobilization, Demobilization of Personnel and Tools ls 1.00 5,000,000.00 5,000,000.00 0.161 0.500 50.000 0.080 0.500 50.000 0.080
6 HSE (Safety Net, Hat, Helmet,etc.) ls 1.00 10,175,000.00 10,175,000.00 0.327 0.750 75.000 0.245 0.750 75.000 0.245
7 Site Cleaning m2 1,089.00 4,158.00 4,528,062.00 0.146 816.750 75.000 0.109 816.750 75.000 0.109
8 Rebar Cleaning ls 1.00 7,500,000.00 7,500,000.00 0.241 0.700 70.000 0.169 0.700 70.000 0.169
Total Preparation Work Cost 64,343,962.50 2.069 1.489 1.489

II CLASSROOM 8X7 (3 ROOMS) A1


A PREPARATION WORK
1 Site Measurement m' 66.00 22,990.00 1,517,340.00 0.049 66.000 100.000 0.049 66.000 100.000 0.049
PREPARATION 1,517,340.00 0.049 0.049 0.049
B ARCHITECTURAL WORKS
B.1 1ST LEVEL
I WALLWORK
1 1/2 Brick Wall 1:5 m2 153.06 139,920.88 21,415,870.13 0.689
2 Mortar Plaster Work m2 446.97 67,316.74 30,088,430.43 0.968
3 Mortar Neat Plaster Work m2 446.97 42,427.00 18,963,511.34 0.610
4 Practical Column & Lintel Beam Work
- K250 Concrete m3 1.68 1,226,720.35 2,064,570.35 0.066
- Reinforcement kg 259.62 16,006.10 4,155,491.79 0.134
- Formwork m2 28.05 185,185.00 5,194,439.25 0.167
II Floor Installation Work
1 Tile 40x40 cm (Polished) Rooms m2 163.64 162,962.80 26,667,884.44 0.858
2 Tile 40x40 cm (Unpolished) Hallway m2 49.10 166,262.80 8,162,672.17 0.263
III Painting Works
1 Wall Painting; Interior m2 189.05 40,563.60 7,668,670.27 0.247
2 Wall Painting; Exterior m2 257.92 54,313.60 14,008,292.14 0.451
3 Ceiling Painting; Interior m2 161.65 40,563.60 6,557,187.07 0.211
4 Ceiling Painting; Exterior m2 117.71 54,313.60 6,393,416.80 0.206
5 Calsiplank Painting m2 22.38 54,313.60 1,215,766.49 0.039
6 Partition Painting m2 74.75 40,563.60 3,032,210.23 0.098
IV Door and Window Installation Work (complete w. aluminium frame)
Door Alumunium Frame
1 Unit 3.00 1,082,950.00 3,248,850.00 0.104
Installation Work (typeWork
Leaf Door Instalation P1)
2 Unit 3.00 2,625,000.00 7,875,000.00 0.253
(type P1)
Door Alumunium Frame
3 Unit 3.00 1,533,286.70 4,599,860.10 0.148
Installation Work (typeWork
Leaf Door Instalation P2)
4 Unit 3.00 5,250,000.00 15,750,000.00 0.507
(type P2)
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)
Window Installation Work (type
6 Unit 3.00 3,417,381.00 10,252,143.00 0.330
J2)
Window Installation Work (type
7 Unit 9.00 3,546,928.00 31,922,352.00 1.027
J3)
8 Partition m2 36.61 457,506.50 16,748,397.95 0.539
V Ceiling Installation Work
1 Ceiling Hollow frame m2 279.37 149,919.00 41,882,121.44 1.347
2 6 mm of Calcium Board GRC (Ceiling Interior) m2 161.65 72,230.40 11,676,188.62 0.376
3 6 mm of Calcium Board GRC (Ceiling Exterior) m2 117.71 72,230.40 8,502,457.08 0.273
VI Other Works
1 Railling for Disability access
- Disability Handrail Ramp work m 14.10 760,976.98 10,729,014.37 0.345
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.78 912,325.16 711,613.62 0.023
- Chevron Works m2 20.90 40,315.00 842,381.92 0.027
- Retaining Wall Ramp 1 Pc : 5 Ps m2 5.75 139,920.88 803,985.38 0.026
- Landfill for floor elevation m3 1.25 163,075.00 204,332.97 0.007
- Mortar Plaster Work m2 5.76 67,316.74 387,609.81 0.012
- Mortar Neat Plaster Work m2 5.76 42,427.00 244,294.67 0.008
2 Stair
- Retaining Wall 1 Pc : 5 Ps m2 6.48 139,920.88 906,687.30 0.029
- Landfill for floor elevation m3 0.97 163,075.00 158,508.90 0.005
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.18 912,325.16 164,218.53 0.005
- Chevron Works m1 13.20 40,315.00 532,158.00 0.017
- Mortar Plaster Work m2 4.86 67,316.74 326,890.11 0.011
- Mortar Neat Plaster Work m2 4.86 42,427.00 206,025.51 0.007
B.2 ROOF WORKS
I Roof Covering Works
1 Zincalume Spandex H. 0,30 mm Installation m2 377.00 171,306.67 64,582,270.72 2.077
2 Light Steel Frame; including rafter and accessoris m2 377.00 213,420.90 80,459,252.46 2.588
3 Aluminium Foil Installation m2 377.00 27,087.50 10,211,933.33 0.328
4 Calsiplank 30x0,80 cm m 88.96 59,070.00 5,254,749.06 0.169
5 Roof Ridges, Zincalum Spandex m 37.97 73,810.00 2,802,860.94 0.090
6 Roof Jalousie Unit 2.00 1,563,743.50 3,127,487.00 0.101
Total Architectural Cost 490,702,057.67 15.781

C STRUCTURAL WORK
I FOUNDATION WORK
1 Tie Beam 25/30
- Concrete K-250 m3 5.12 1,226,720.35 6,274,674.59 0.202 5.115 100.000 0.202 5.115 100.000 0.202
- Reinforcement kg 25.15 16,006.10 402,566.74 0.013
- Tie Beam Formwork m2 40.92 195,085.00 7,982,878.20 0.257 18.960 46.334 0.119 18.960 46.334 0.119
2 Tie Beam 20/25
- Concrete K-250 m3 1.46 1,226,720.35 1,791,011.71 0.058 1.460 100.000 0.058 1.460 100.000 0.058
- Reinforcement kg 5.43 16,006.10 86,984.70 0.003
- Tie Beam Formwork m2 14.60 195,085.00 2,848,241.00 0.092 7.075 48.459 0.044 7.075 48.459 0.044
II 1ST LEVEL
1 30/30 Column
- K-250 Concrete m3 9.40 1,226,720.35 11,526,264.40 0.371 9.396 100.000 0.371 9.396 100.000 0.371
- Reinforcement kg 287.34 16,006.10 4,599,254.30 0.148 287.344 100.000 0.148 287.344 100.000 0.148
- Column Formwork m2 125.28 275,300.00 34,489,584.00 1.109 125.280 100.000 1.109 125.280 100.000 1.109
2 20/20 Column
- K-250 Concrete m3 1.72 1,226,720.35 2,109,959.00 0.068 1.720 100.000 0.068 1.720 100.000 0.068
- Reinforcement kg 32.19 16,006.10 515,310.64 0.017 32.195 100.000 0.017 32.195 100.000 0.017
- Column Formwork m2 34.40 275,300.00 9,470,320.00 0.305 34.400 100.000 0.305 34.400 100.000 0.305
3 20/25 Beam
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

- Concrete K-250 m3 4.87 1,226,720.35 5,974,128.10 0.192 4.870 100.000 0.192 4.870 100.000 0.192
- Reinforcement kg 843.36 16,006.10 13,498,938.69 0.434 843.362 100.000 0.434 843.362 100.000 0.434
- Beam Formwork m2 68.18 282,050.00 19,230,169.00 0.618 68.180 100.000 0.618 68.180 100.000 0.618
4 Floor Slab h=12 cm
- Base Concrete t=5cm m3 2.61 912,325.16 2,384,361.80 0.077 2.614 100.000 0.077 2.614 100.000 0.077
- Sand layer t=10cm m3 5.23 192,830.00 1,007,922.41 0.032 5.227 100.000 0.032 5.227 100.000 0.032
- Concrete K-250 m3 23.79 1,226,720.35 29,186,621.24 0.939 23.792 100.000 0.939 23.792 100.000 0.939
- Reinforcement kg 1,894.27 16,006.10 30,319,878.73 0.975 1808.687 95.482 0.931 1808.687 95.482 0.931
- Floor Formwork m2 8.05 225,800.00 1,818,141.60 0.058 8.052 100.000 0.058 8.052 100.000 0.058
Total Structural Cost 185,517,210.85 5.966 4.477 1.245 5.721

III CLASSROOM 8X7 (3 ROOMS) A2


A PREPARATION WORK
1 Site Measurement m' 66.00 22,990.00 1,517,340.00 0.049
PREPARATION 1,517,340.00 0.049
B ARCHITECTURAL WORKS
B.1 1ST LEVEL
I WALLWORK
1 1/2 Brick Wall 1:5 m2 191.59 139,920.88 26,806,741.79 0.862
2 Mortar Plaster Work m2 550.64 67,316.74 37,067,291.92 1.192
3 Mortar Neat Plaster Work m2 550.64 42,427.00 23,362,003.28 0.751
4 Practical Column & Lintel Beam Work
- K250 Concrete m3 1.68 1,226,720.35 2,064,570.35 0.066
- Reinforcement kg 259.62 16,006.10 4,155,491.79 0.134
- Formwork m2 28.05 185,185.00 5,194,439.25 0.167
II Floor Installation Work
1 Tile 40x40 cm (Polished) Rooms m2 163.64 162,962.80 26,667,884.44 0.858
2 Tile 40x40 cm (Unpolished) Hallway m2 49.10 166,262.80 8,162,672.17 0.263
III Painting Works
1 Wall Painting; Interior m2 292.72 40,563.60 11,873,979.81 0.382
2 Wall Painting; Exterior m2 257.92 54,313.60 14,008,292.14 0.451
3 Ceiling Painting; Interior m2 161.65 40,563.60 6,557,187.07 0.211
4 Ceiling Painting; Exterior m2 117.71 54,313.60 6,393,416.80 0.206
5 Calsiplank Painting m2 22.38 54,313.60 1,215,766.49 0.039
IV Door and Window Installation Work (complete w. alluminium frame)
1 Door Alumunium Frame Installation Work (type P1) Unit 3.00 1,082,950.00 3,248,850.00 0.104
2 Leaf Door Instalation Work (type P1) Unit 3.00 2,625,000.00 7,875,000.00 0.253
3 Door Alumunium Frame Installation Work (type P2) Unit 3.00 1,533,286.70 4,599,860.10 0.148
4 Leaf Door Instalation Work (type P2) Unit 3.00 5,250,000.00 15,750,000.00 0.507
6 Window Installation Work (type J2) Unit 3.00 3,417,381.00 10,252,143.00 0.330
7 Window Installation Work (type J3) Unit 9.00 3,546,928.00 31,922,352.00 1.027
V Ceiling Installation Work
1 Ceiling Hollow frame m2 279.37 149,919.00 41,882,121.44 1.347
2 6 mm of Calcium Board GRC (Ceiling Interior) m2 161.65 72,230.40 11,676,188.62 0.376
3 6 mm of Calcium Board GRC (Ceiling Exterior) m2 117.71 72,230.40 8,502,457.08 0.273
VI Other Works
1 Railling for Disability access
- Disability Handrail Ramp work m 14.10 760,976.98 10,729,014.37 0.345
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.78 912,325.16 711,613.62 0.023
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

- Chevron Works m 2
20.90 40,315.00 842,381.92 0.027
- Retaining Wall Ramp 1 Pc : 3 Ps : 5 Kr m2 5.75 139,920.88 803,985.38 0.026
- Landfill for floor elevation m3 1.25 163,075.00 204,332.97 0.007
- Mortar Plaster Work m2 5.76 67,316.74 387,609.81 0.012
- Mortar Neat Plaster Work m2 5.76 42,427.00 244,294.67 0.008
2 Stair
- Retaining Wall 1 Pc : 5 Ps m2 6.48 139,920.88 906,687.30 0.029
- Landfill for floor elevation m3 0.97 163,075.00 158,508.90 0.005
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.18 912,325.16 164,218.53 0.005
- Chevron Works m1 13.20 40,315.00 532,158.00 0.017
- Mortar Plaster Work m2 4.86 67,316.74 326,890.11 0.011
- Mortar Neat Plaster Work m2 4.86 42,427.00 206,025.51 0.007
B.2 ROOF WORKS
I Roof Covering Works
1 Zincalume Spandex H. 0,30 mm Installation m2 377.00 171,306.67 64,582,270.72 2.077
2 Light Steel Frame; including rafter and accessoris m2 377.00 213,420.90 80,459,252.46 2.588
3 Aluminium Foil Installation m2 377.00 27,087.50 10,211,933.33 0.328
4 Calsiplank 30x0,80 cm m 88.96 59,070.00 5,254,749.06 0.169
5 Roof Ridges, Zincalum Spandex m 37.97 73,810.00 2,802,860.94 0.090
6 Roof Jalousie Unit 2.00 1,563,743.50 3,127,487.00 0.101
Total Architectural Cost 491,894,984.12 15.819

C STRUCTURAL WORK
I FOUNDATION WORK
1 PD1 Foundation
- Backfill m3 22.07 62,150.00 1,371,650.50 0.044
2 PD1A Foundation
- Backfill m3 12.55 62,150.00 779,982.50 0.025
3 PD2 Foundation
- Backfill m3 1.61 62,150.00 100,061.50 0.003
4 PD4 Foundation
- Backfill m3 2.11 62,150.00 131,385.10 0.004
5 PD5 Foundation
- Backfill m3 2.69 62,150.00 167,183.50 0.005
6 Tie Beam 25/30
- Concrete K-250 m3 5.12 1,226,720.35 6,274,674.59 0.202
- Reinforcement kg 933.95 16,006.10 14,948,871.12 0.481 753.621 80.692 0.388 753.621 80.692 0.388
- Tie Beam Formwork m2 40.92 195,085.00 7,982,878.20 0.257
7 Tie Beam 20/25
- Concrete K-250 m3 1.46 1,226,720.35 1,791,011.71 0.058
- Reinforcement kg 263.61 16,006.10 4,219,310.78 0.136 263.606 100.000 0.136 263.606 100.000 0.136
- Tie Beam Formwork m2 12.85 195,085.00 2,506,842.25 0.081
II 1ST LEVEL
1 30/30 Column
- K-250 Concrete m3 9.40 1,226,720.35 11,526,264.40 0.371
- Reinforcement kg 118.08 16,006.10 1,889,961.93 0.061
- Column Formwork m2 125.28 275,300.00 34,489,584.00 1.109
2 20/20 Column
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

- K-250 Concrete m 3 1.72 1,226,720.35 2,109,959.00 0.068


- Reinforcement kg 26.86 16,006.10 429,987.28 0.014
- Column Formwork m2 34.40 275,300.00 9,470,320.00 0.305
3 20/25 Beam
- Concrete K-250 m3 4.87 1,226,720.35 5,974,128.10 0.192
- Reinforcement kg 870.53 16,006.10 13,933,862.21 0.448
- Beam Formwork m2 68.18 282,050.00 19,230,169.00 0.618
4 Floor Slab h=12 cm
- Landfill for floor elevation m3 5.95 163,075.00 969,986.41 0.031
- Base Concrete t=5cm m3 9.91 912,325.16 9,044,335.46 0.291
- Sand layer t=10cm m3 19.83 192,830.00 3,823,240.41 0.123
- Concrete K-250 m3 23.79 1,226,720.35 29,186,621.24 0.939
- Reinforcement kg 1,894.27 16,006.10 30,319,878.73 0.975
- Floor Formwork m2 8.05 225,800.00 1,818,141.60 0.058
Total Structural Cost 214,490,291.51 6.898 0.388 0.136 0.524

D CLASSROOM ELECTRICAL WORKS


I. LOW VOLTAGE PANEL WORKS
Procurement and installation of
a complete Panel
1 MCB-BOX of the Classroom unit 2.00 1,124,332.00 2,248,664.00 0.072
D.2 LIGHTING WORKS
Procurement, installation of lighting and sockets
I. CLASSROOM A1 ( 3 UNITS )
1 Roset Led 22 W Type Bulb unit 21.00 143,896.50 3,021,826.50 0.097
2 Single Electrical Switch unit 1.00 34,727.00 34,727.00 0.001
3 Double Electrical Switch unit 3.00 42,350.00 127,050.00 0.004
4 100 W Wall Electric Socket unit 6.00 49,929.00 299,574.00 0.010
5 Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 21.00 194,035.42 4,074,743.75 0.131
6 Electrical Socket NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 6.00 218,556.25 1,311,337.50 0.042
II. CLASSROOM A2 ( 3 UNITS )
1 Roset Led 22 W Type Bulb unit 21.00 143,896.50 3,021,826.50 0.097
2 Single Electrical Switch unit 1.00 34,727.00 34,727.00 0.001
3 Double Electrical Switch unit 3.00 42,350.00 127,050.00 0.004
4 100 W Wall Electric Socket unit 6.00 49,929.00 299,574.00 0.010
5 Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 21.00 194,035.42 4,074,743.75 0.131
6 Electrical Socket NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 6.00 218,556.25 1,311,337.50 0.042
D.3 Lightning Rod Installation
Procurement, installation of a complete lightning rod
I. CLASSROOM A1
1 Ø 3/4 30cm Air Terminal , Completed With Ø 3/4 70cm GIP set 4.00 442,541.00 1,770,164.00 0.057
2 BC 25 mm² Cable Installation m 37.00 75,065.83 2,777,435.83 0.089
3 600mm² x 600mm² c/w Junction Box with Grounding System set 1.00 948,398.00 948,398.00 0.031
4 Auxiliary Materials lot 1.00 366,501.21 366,501.21 0.012
II. CLASSROOM A2
1 Ø 3/4 30cm Air Terminal , Completed With Ø 3/4 70cm GIP set 4.00 442,541.00 1,770,164.00 0.057
2 BC 25 mm² Cable Installation m 37.00 75,065.83 2,777,435.83 0.089
3 600mm² x 600mm² c/w Junction Box with Grounding System set 1.00 948,398.00 948,398.00 0.031
4 Auxiliary Materials lot 1.00 366,501.21 366,501.21 0.012
Total Electrical Cost 31,712,179.58 1.020
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

IV TEACHER'S OFFICE -B
A PREPARATION WORK
1 Site Measurement and Bowplank Intallation m' 40.00 278,630.00 11,145,200.00 0.358
PREPARATION 11,145,200.00 0.358
B ARCHITECTURAL WORKS
B.1 1ST LEVEL
I. WALLWORK
1 Brick Wall 1:5 m2 94.55 139,920.88 13,229,379.28 0.425
2 Brick Wall 1:3 m2 20.69 147,363.92 3,048,664.78 0.098
3 Mortar Plaster Work m2 289.28 67,316.74 19,473,387.70 0.626
4 Mortar Neat Plaster Work m2 289.28 42,427.00 12,273,282.56 0.395
5 Practical Column & Lintel Beam Work
- K250 Concrete m3 1.39 1,226,720.35 1,705,141.29 0.055
- Reinforcement kg 207.79 16,006.10 3,325,827.94 0.107
- Formwork m2 23.17 185,185.00 4,290,119.17 0.138
6 Wall Tiles 25x40cm (Unpolished) m2 16.09 183,499.80 2,952,511.78 0.095
II. Ceiling Installation Work
1 Ceiling Hollow frame m2 102.09 149,919.00 15,305,230.71 0.492
2 6 mm of Calcium Board GRC (Ceiling Interior) m2 46.63 72,230.40 3,368,103.55 0.108
3 6 mm of Calcium Board GRC (Ceiling Exterior) m2 55.46 72,230.40 4,005,897.98 0.129
III. Floor Installation Work
1 Tile 40x40 cm (Polished) Rooms m2 37.99 162,962.80 6,190,956.77 0.199
2 Tile 40x40 cm (Unpolished) Hallway m2 16.63 166,262.80 2,764,950.36 0.089
3 Tile 40x40 cm (Unpolished) Toilet m2 2.40 166,262.80 399,030.72 0.013
4 Waterproofing Coating + mortar m2 2.40 119,614.62 287,075.08 0.009
IV. Door and Window Installation Work (complete w. alluminium frame)
1 Door Alumunium Frame Installation Work (type P1) Unit 4.00 1,082,950.00 4,331,800.00 0.139
2 Leaf Door Instalation Work (type P1) Unit 4.00 2,625,000.00 10,500,000.00 0.338
3 Door Alumunium Frame Installation Work (type P2) Unit 1.00 1,533,286.70 1,533,286.70 0.049
4 Leaf Door Instalation Work (type P2) Unit 1.00 5,250,000.00 5,250,000.00 0.169
5 Door Alumunium Frame Installation Work (type P3) Unit 1.00 2,368,025.00 2,368,025.00 0.076
6 Window Installation Work (type J2) Unit 7.00 3,417,381.00 23,921,667.00 0.769
7 Window Installation Work (type V1) Unit 2.00 615,450.00 1,230,900.00 0.040
V. Sanitary Work and Installation
Sanitary work includes
procurement & installation
1 Sitting Closed Unit 1.00 3,699,704.80 3,699,704.80 0.119
2 Shower spray Unit 1.00 960,355.00 960,355.00 0.031
3 Floor Drain Unit 1.00 675,235.00 675,235.00 0.022
4 Robe hook Unit 1.00 334,235.00 334,235.00 0.011
5 Tissue Holder Unit 1.00 585,475.00 585,475.00 0.019
6 Faucet Unit 1.00 746,652.50 746,652.50 0.024
VI. Painting Works
1 Wall Painting; Interior m2 167.60 40,563.60 6,798,459.36 0.219
2 Wall Painting; Exterior m2 121.68 54,313.60 6,608,878.85 0.213
3 Ceiling Painting; Interior m2 46.63 40,563.60 1,891,480.67 0.061
4 Ceiling Painting; Exterior m2 55.46 54,313.60 3,012,232.26 0.097
5 Calsiplank Painting m2 12.66 54,313.60 687,610.18 0.022
VII Other Works
1 Stair
- Retaining Wall 1 Pc : 5 Ps m2 6.48 139,920.88 906,687.30 0.029
- Landfill for floor elevation m3 0.97 163,075.00 158,508.90 0.005
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.18 912,325.16 164,218.53 0.005
- Chevron Works m1 13.20 40,315.00 532,158.00 0.017
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

- Mortar Plaster Work m2 4.86 67,316.74 326,890.11 0.011


- Mortar Neat Plaster Work m2 4.86 42,427.00 206,025.51 0.007
B.2 ROOF WORKS
I. Roof Covering Works
1 Zincalume Spandex H. 0,30 mm Installation m2 134.73 171,306.67 23,080,147.20 0.742
2 Light Steel Frame; including rafter and accessories m2 134.73 213,420.90 28,754,197.86 0.925
3 Aluminium Foil Installation m2 134.73 27,087.50 3,649,498.87 0.117
4 Roof Ridges, Zincalum Spandex m 33.16 73,810.00 2,447,244.36 0.079
5 Calsiplank 30x0,80 cm m 42.20 59,070.00 2,492,754.00 0.080
Total Architectural Cost 230,473,887.64 7.412

C. STRUCTURAL WORK
I FOUNDATION WORK
1 Foundation PD1
- Foundation Cutting m3 33.30 105,435.00 3,510,985.50 0.113
- Backfill m3 29.84 62,150.00 1,854,804.60 0.060
- Concrete K-250 m3 3.46 1,226,720.35 4,239,545.53 0.136
- Reinforcement kg 395.82 16,006.10 6,335,474.94 0.204
- Formwork m2 11.52 185,185.00 2,133,331.20 0.069
- Sand layer t=10cm m3 1.15 192,830.00 222,140.16 0.007
- Base Concrete t=5cm m3 0.58 912,325.16 525,499.29 0.017
2 Foundation PD1A
- Foundation Cutting m3 9.38 105,435.00 988,927.58 0.032
- Backfill m3 8.48 62,150.00 527,000.93 0.017
- Concrete K-250 m3 0.90 1,226,720.35 1,104,048.31 0.036
- Reinforcement kg 112.37 16,006.10 1,798,662.26 0.058
- Formwork m2 3.60 185,185.00 666,666.00 0.021
- Sand layer t=10cm m3 0.30 192,830.00 57,849.00 0.002
- Base Concrete t=5cm m3 0.15 912,325.16 136,848.77 0.004
3 PD2 Broken Stone Foundation
- Foundation Cutting m3 30.78 105,435.00 3,245,289.30 0.104
- Sand layer t=10cm m3 3.24 192,830.00 624,769.20 0.020
- Masonry 1:4 m3 16.59 756,723.00 12,551,764.40 0.404
- Aanstamping Stone H=15cm m3 4.86 332,739.00 1,617,111.54 0.052
- Backfill m3 10.71 62,150.00 665,626.50 0.021
4 PD3 Broken Stone Foundation
- Foundation Cutting m3 21.80 105,435.00 2,298,483.00 0.074
- Sand layer t=10cm m3 7.59 192,830.00 1,463,579.70 0.047
- Masonry 1:4 m3 5.81 756,723.00 4,399,587.52 0.141
- Aanstamping Stone H=15cm m3 3.44 332,739.00 1,144,622.16 0.037
- Backfill m3 7.59 62,150.00 471,718.50 0.015
5 PD4 Broken Stone Foundation
- Foundation Cutting m3 11.54 105,435.00 1,216,983.49 0.039
- Sand layer t=10cm m3 1.21 192,830.00 234,288.45 0.008
- Masonry 1:4 m3 6.86 756,723.00 5,192,160.27 0.167
- Aanstamping Stone H=15cm m3 1.82 332,739.00 606,416.83 0.020
- Backfill m3 4.02 62,150.00 249,609.94 0.008
6 Soil fill m3 1.20 128,715.71 154,922.23 0.005

II 1ST LEVEL
1 K1 30/30 Column
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

- Concrete K-250 m 3 4.12 1,226,720.35 5,052,125.09 0.162


- Reinforcement kg 679.54 16,006.10 10,876,721.17 0.350
- Formwork Column m2 54.91 275,300.00 15,117,273.60 0.486
2 K2 20/20 Column
- Concrete K-250 m3 0.69 1,226,720.35 842,020.85 0.027
- Reinforcement kg 133.35 16,006.10 2,134,422.68 0.069
- Formwork Column m2 13.73 275,300.00 3,779,318.40 0.122
3 S1 25/30 Tie Beam
- Concrete K-250 m3 2.50 1,226,720.35 3,063,734.07 0.099
- Reinforcement kg 564.46 16,006.10 9,034,861.66 0.291
- Tie Beam Formwork m2 19.98 195,085.00 3,897,798.30 0.125
4 S2 20/25 Tie Beam
- Concrete K-250 m3 0.56 1,226,720.35 680,829.79 0.022
- Reinforcement kg 160.85 16,006.10 2,574,590.33 0.083
- Tie Beam Formwork m2 5.55 195,085.00 1,082,721.75 0.035
5 S3 (150x200) Tie Beam
- Concrete K-250 m3 0.38 1,226,720.35 463,700.29 0.015
- Reinforcement kg 125.96 16,006.10 2,016,188.75 0.065
- Tie Beam Formwork m2 4.92 195,085.00 959,818.20 0.031
6 B1 20/25 Beam
- Concrete K-250 m3 1.85 1,226,720.35 2,263,299.04 0.073
- Reinforcement kg 337.33 16,006.10 5,399,313.39 0.174
- Beam Formwork m2 25.69 282,050.00 7,245,864.50 0.233
7 Floor Slab h=12 cm
- K-250 Concrete m3 6.47 1,226,720.35 7,941,787.54 0.255
- Reinforcement kg 566.59 16,006.10 9,068,965.43 0.292
- Floor Formwork m2 3.97 225,800.00 896,877.60 0.029
- Sand layer t=10cm m3 6.43 192,830.00 1,240,668.22 0.040
- Base Concrete t=5cm m3 3.22 912,325.16 2,934,950.04 0.094
Total Structural Cost 158,806,567.78 5.107

D. MECHANICAL AND ELECTRICAL WORKS


1 PLUMBING WORKS
1.1 CLEAN WATER SYSTEM
Procurement and installation of PVC Pipes including excavation, accessories, and auxiliary equipment
a. Toilet and Clean Water Piping and Its Completeness
1 PVC AW Ø 25 mm m 5.00 28,026.63 140,133.13 0.005
2 PVC AW Ø 20 mm m 1.00 23,892.00 23,892.00 0.001
3 Fitting ls 1.00 29,063.51 29,063.51 0.001
4 Gate Valve Ø 32 mm unit 1.00 126,610.00 126,610.00 0.004
1.2 VENT AND GREY WATER SYSTEM
Procurement and installation of PVC Pipes including excavation, accessories, and auxiliary tool
a. Grey Water Piping and Its completeness in toilet to Sepictank.1
1 PVC-AW Ø 100 mm; SW (Sewage Water) m 2.00 185,950.88 371,901.75 0.012
2 PVC-AW Ø 80 mm; WW (Waste Water) m 2.00 123,292.13 246,584.25 0.008
3 Floor Clean Out Ø 80 mm, WW ( Waste Water) unit 1.00 230,725.00 230,725.00 0.007
4 Floor Clean Out Ø 100 mm, SW (Sewage Water) unit 1.00 340,263.00 340,263.00 0.011
5 Fitting ls 1.00 118,947.40 118,947.40 0.004
D.2 ELECTRICAL WORKS
2.1 PANEL WORKS
Procurement & Installation
1 MCB-BOX of Teacher Room unit 1.00 1,156,969.00 1,156,969.00 0.037
2.2 LIGHTING WORKS
Procurement & Installation
a. Teacher Room
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

1 Roset Led 22 W Type Bulb unit 7.00 143,896.50 1,007,275.50 0.032


2 Roset Led 5 W Type Bulb (Toilet) unit 2.00 69,399.00 138,798.00 0.004
3 Single Switch unit 5.00 34,727.00 173,635.00 0.006
4 Double Switch unit 1.00 42,350.00 42,350.00 0.001
5 200 W Wall Electric Socket unit 6.00 49,929.00 299,574.00 0.010
6 AC Electric Socket unit 2.00 57,783.00 115,566.00 0.004
7 NYM 3x2,5 mm² Lamp Installation in 20 mm of Conduit Pipe point 9.00 194,035.42 1,746,318.75 0.056
8 Electr. Socket NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 8.00 218,556.25 1,748,450.00 0.056
2.3 Lightning Rod Installation
Procurement & Installation
1 Air Terminal, Ø 3/4 30cm; Completed with GIP, Ø 3/4 70cm set 1.00 442,541.00 442,541.00 0.014
2 BC Cable Installation, 25 mm² m 20.00 75,065.83 1,501,316.67 0.048
3 Earthing Pit, 600mm² x 600mm² c/w with grounding system set 1.00 948,398.00 948,398.00 0.031
4 Auxiliary Equipments lot 1.00 366,501.21 366,501.21 0.012
Total Mechanical And Electrical Cost 11,315,813.16 0.364

V LIBRARY 8x7 -C
A PREPARATION WORK
1 Site Measurement and Bowplank Installation m' 32.00 278,630.00 8,916,160.00 0.287
PREPARATION 8,916,160.00 0.287
B ARCHITECTURAL WORKS
B.1 1ST FLOOR
I. WALLWORK
1 Brick Wall 1:5 m2 68.36 139,920.88 9,564,991.36 0.308
2 Mortar Plaster Work m2 213.25 67,316.74 14,355,497.61 0.462
3 Mortar Neat Plaster Work m2 213.25 42,427.00 9,047,685.03 0.291
4 Practical Column & Lintel Beam Work
- K250 Concrete m3 0.88 1,226,720.35 1,073,380.31 0.035
- Reinforcement kg 132.32 16,006.10 2,117,910.89 0.068
- Formwork m2 14.58 185,185.00 2,700,614.58 0.087
II. Ceiling Installation Work
1 Ceiling Hollow frame m 2
108.15 149,919.00 16,213,589.93 0.521
2 6 mm of Calcium Board GRC (Ceiling Interior) m2 53.83 72,230.40 3,888,162.43 0.125
3 6 mm of Calcium Board GRC (Ceiling Exterior) m2 54.32 72,230.40 3,923,483.10 0.126
III. Floor Installation Work
1 Tile 40x40 cm (Polished) Rooms m2 54.46 162,962.80 8,874,465.20 0.285
2 Tile 40x40 cm (Unpolished) Hallway m2 14.46 166,262.80 2,404,326.35 0.077
IV. Door and Window Installation Work (complete w. alluminium frame)
Door Alumunium Frame
1 Unit 1.00 1,533,286.70 1,533,286.70 0.049
Installation Work (typeWork
Leaf Door Instalation P2)
2 Unit 1.00 5,250,000.00 5,250,000.00 0.169
(type P2)
3 Window Installation Work (type J2) Unit 11.00 3,417,381.00 37,591,191.00 1.209
V. Painting Works
1 Wall Painting; Interior m2 89.59 40,563.60 3,634,255.18 0.117
2 Wall Painting; Exterior m2 123.66 54,313.60 6,716,365.46 0.216
3 Ceiling Painting; Interior m2 53.83 40,563.60 2,183,538.59 0.070
4 Ceiling Painting; Exterior m2 54.32 54,313.60 2,950,260.44 0.095
5 Calsiplank Painting m2 15.98 54,313.60 867,877.01 0.028
VI. Other Works
1 Stair
- Retaining Wall 1 Pc : 5 Ps m2 3.24 139,920.88 453,343.65 0.015
- Landfill for floor elevation m3 0.49 163,075.00 79,254.45 0.003
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.09 912,325.16 82,109.26 0.003
- Chevron Works m1 6.60 40,315.00 266,079.00 0.009
- Mortar Plaster Work m2 2.43 67,316.74 163,445.05 0.005
- Mortar Neat Plaster Work m2 2.43 42,427.00 103,012.76 0.003
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

B.2 ROOF WORKS


I. Roof Covering Works
1 Zincalume Spandex H. 0,30 mm Installation m2 152.39 171,306.67 26,105,936.85 0.840
2 Light Steel Frame; including rafter and accessoris m2 152.39 213,420.90 32,523,851.21 1.046
3 Aluminium Foil Installation m2 152.39 27,087.50 4,127,945.39 0.133
4 Calsiplank 30x0,80 cm m 14.69 59,070.00 867,561.09 0.028
5 Roof Ridges, Zincalum Spandex m 57.24 73,810.00 4,225,179.64 0.136
6 Roof Jalousie Unit 2.00 1,563,743.50 3,127,487.00 0.101
Total Architectural Cost 207,016,086.53 6.658

C. STRUCTURAL WORK
I FOUNDATION WORK
1 Foundation PD1
- Foundation Cutting m3 38.25 105,435.00 4,032,888.75 0.130
- Backfill m3 33.93 62,150.00 2,108,749.50 0.068
- Concrete K-250 m3 4.32 1,226,720.35 5,299,431.91 0.170
- Reinforcement kg 494.77 16,006.10 7,919,343.68 0.255
- Formwork m2 14.40 185,185.00 2,666,664.00 0.086
- Sand layer t=10cm m3 1.44 192,830.00 277,675.20 0.009
- Base Concrete t=5cm m3 0.72 912,325.16 656,874.11 0.021
2 Foundation PD1A
- Foundation Cutting m3 11.49 105,435.00 1,211,659.02 0.039
- Backfill m3 10.29 62,150.00 639,647.80 0.021
- Concrete K-250 m3 1.20 1,226,720.35 1,472,064.42 0.047
- Reinforcement kg 149.83 16,006.10 2,398,216.34 0.077
- Formwork m2 4.80 185,185.00 888,888.00 0.029
- Sand layer t=10cm m3 0.40 192,830.00 77,132.00 0.002
- Base Concrete t=5cm m3 0.20 912,325.16 182,465.03 0.006
3 Foundation PD2
- Foundation Cutting m3 25.65 105,435.00 2,704,407.75 0.087
- Sand layer t=10cm m3 2.70 192,830.00 520,641.00 0.017
- Masonry 1:4 m3 13.82 756,723.00 10,459,803.67 0.336
- Aanstamping Stone m3 4.05 332,739.00 1,347,592.95 0.043
- Backfill m3 5.36 62,150.00 333,279.37 0.011
4 Foundation PD3
- Foundation Cutting m3 18.64 105,435.00 1,965,202.96 0.063
- Sand layer t=10cm m3 1.96 192,830.00 378,332.46 0.012
- Masonry 1:4 m3 10.56 756,723.00 7,992,584.00 0.257
- Aanstamping Stone m3 2.94 332,739.00 979,250.88 0.031
- Backfill m3 3.90 62,150.00 242,183.01 0.008
5 Soil fill m3 1.57 128,715.71 201,839.11 0.006

II. 1ST LEVEL


1 K1 30/30 Column
- Concrete K-250 m3 5.15 1,226,720.35 6,315,156.36 0.203
- Reinforcement kg 849.42 16,006.10 13,595,901.46 0.437
- Formwork Column m2 68.64 275,300.00 18,896,592.00 0.608
2 K2 20/20 Column
- Concrete K-250 m3 0.92 1,226,720.35 1,122,694.46 0.036
- Reinforcement kg 177.80 16,006.10 2,845,896.91 0.092
- Formwork Column m2 18.30 275,300.00 5,039,091.20 0.162
3 S1 25/30 Tie Beam
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

- Concrete K-250 m 3 2.03 1,226,720.35 2,484,108.71 0.080


- Reinforcement kg 496.23 16,006.10 7,942,641.07 0.255
- Tie Beam Formwork m2 16.20 195,085.00 3,160,377.00 0.102
4 S2 20/25 Tie Beam
- Concrete K-250 m3 0.47 1,226,720.35 570,424.96 0.018
- Reinforcement kg 107.81 16,006.10 1,725,680.30 0.055
- Tie Beam Formwork m2 4.65 195,085.00 907,145.25 0.029
5 B1 20/25 Beam
- Concrete K-250 m3 1.87 1,226,720.35 2,287,833.45 0.074
- Reinforcement kg 302.53 16,006.10 4,842,339.87 0.156
- Beam Formwork m2 25.69 282,050.00 7,245,864.50 0.233
6 Floor Slab h=12 cm
- K-250 Concrete m3 7.72 1,226,720.35 9,471,262.47 0.305
- Reinforcement kg 610.88 16,006.10 9,777,766.67 0.314
- Floor Formwork m2 4.21 225,800.00 951,069.60 0.031
- Sand layer t=10cm m3 6.43 192,830.00 1,240,668.22 0.040
- Base Concrete t=5cm m3 3.22 912,325.16 2,934,950.04 0.094
Total Structural Cost 160,314,281.43 5.156

D. LIBRARY ELECTRICAL WORKS


D.1 LOW VOLTAGE PANEL WORKS
Procurement and installation
1 MCB-BOX of The Library unit 1.00 930,149.00 930,149.00 0.030
D.2 LIGHTING WORKS
Procurement and installation
a. LIBRARY
1 Roset Led 22 W Type Bulb unit 7.00 143,896.50 1,007,275.50 0.032
2 Single Electrical Switch unit 1.00 34,727.00 34,727.00 0.001
3 Double Electrical Switch unit 1.00 42,350.00 42,350.00 0.001
4 200 W Wall Electric Socket unit 2.00 49,929.00 99,858.00 0.003
5 Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 7.00 194,035.42 1,358,247.92 0.044
6 Electrical Socket NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 2.00 218,556.25 437,112.50 0.014
D.3 Lightning Rod Installation
Procurement and installation
1 Ø 3/4 30cm Air Terminal , Completed With Ø 3/4 70cm GIP set 2.00 442,541.00 885,082.00 0.028
2 BC 25 mm² Cable Installation m 20.00 75,065.83 1,501,316.67 0.048
3 600mm² x 600mm² c/w Junction Box with Grounding System set 1.00 948,398.00 948,398.00 0.031
4 Auxiliary Materials lot 1.00 366,501.21 366,501.21 0.012
Total Mechanical And Electrical Cost 7,611,017.79 0.245

VI MUSHOLA 8x7 -D
A PREPARATION WORK
1 Site Measurement and Bowplank Installation m' 30.00 278,630.00 8,358,900.00 0.269
PREPARATION 8,358,900.00 0.269
B ARCHITECTURAL WORKS
B.1 1ST FLOOR
I. WALLWORK
1 Brick Wall 1:5 m2 62.39 139,920.88 8,729,943.54 0.281
2 Mortar Plaster Work m2 205.78 67,316.74 13,852,372.26 0.445
3 Mortar Neat Plaster Work m2 205.78 42,427.00 8,730,585.63 0.281
4 Practical Column & Lintel Beam Work
- K250 Concrete m3 1.01 1,226,720.35 1,232,853.95 0.040
- Reinforcement kg 162.01 16,006.10 2,593,149.61 0.083
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

- Formwork m2 16.75 185,185.00 3,101,848.75 0.100


5 Wall Tiles 25x40cm (Unpolished) m2 22.92 183,499.80 4,205,448.42 0.135
II. Ceiling Installation Work
1 Ceiling Hollow frame m2 93.93 149,919.00 14,082,491.35 0.453
2 6 mm of Calcium Board GRC (Ceiling Interior) m2 24.65 72,230.40 1,780,262.67 0.057
3 6 mm of Calcium Board GRC (Ceiling Exterior) m2 69.29 72,230.40 5,004,627.72 0.161
III. Floor Installation Work
1 Tiles 40x40 cm (Polished) m2 45.53 162,962.80 7,419,370.36 0.239
2 Tiles 40x40 cm (Unpolished) m3 5.70 166,262.80 947,032.91 0.030
IV. Door and Window Installation Work (complete w. alluminium frame)
1 Door Installation Work (type P2) Unit 1.00 1,533,286.70 1,533,286.70 0.049
2 Leaf Door Instalation Work (type P2) Unit 1.00 5,250,000.00 5,250,000.00 0.169
3 Door Alumunium Frame Installation Work (type P1) Unit 2.00 1,082,950.00 2,165,900.00 0.070
4 Leaf Door Instalation Work (type P1) Unit 2.00 2,625,000.00 5,250,000.00 0.169
5 Window Installation Work (type J1) Unit 2.00 2,539,878.00 5,079,756.00 0.163
6 Window Installation Work (type J2) Unit 4.00 2,928,090.00 11,712,360.00 0.377
V. Sanitary Work and Installation
Sanitary work includes procurement & installation
1 Faucet Unit 4.00 746,652.50 2,986,610.00 0.096
2 Floor Drain Unit 2.00 675,235.00 1,350,470.00 0.043
VI. Painting Works
1 Wall Painting; Interior m2 85.74 40,563.60 3,478,004.19 0.112
2 Wall Painting; Exterior m2 120.04 54,313.60 6,519,641.60 0.210
3 Ceiling Painting; Interior m2 24.65 40,563.60 999,771.05 0.032
4 Ceiling Painting; Exterior m2 69.29 54,313.60 3,763,226.40 0.121
5 Calsiplank Painting m2 14.73 54,313.60 800,147.96 0.026
VII. Other Works
1 Railling for Disability access
- Disability Handrail Ramp work m' 14.10 760,976.98 10,729,014.37 0.345
- Retaining Wall Ramp 1 Pc : 5 Ps m2 5.75 139,920.88 803,985.38 0.026
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.78 912,325.16 711,613.62 0.023
- Chevron Works m1 20.90 40,315.00 842,381.92 0.027
- Landfill for floor elevation m3 1.25 163,075.00 204,332.97 0.007
- Mortar Plaster Work m2 5.76 67,316.74 387,609.81 0.012
- Mortar Neat Plaster Work m2 5.76 42,427.00 244,294.67 0.008
2 Stair
- Retaining Wall 1 Pc : 5 Ps m2 3.24 139,920.88 453,343.65 0.015
- Landfill for floor elevation m3 0.49 163,075.00 79,254.45 0.003
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.09 912,325.16 82,109.26 0.003
- Chevron Works m2 6.60 40,315.00 266,079.00 0.009
- Mortar Plaster Work m2 2.43 67,316.74 163,445.05 0.005
- Mortar Neat Plaster Work m2 2.43 42,427.00 103,012.76 0.003
B.2 ROOF WORKS
I. Roof Covering Works
1 Zincalume Spandex H 0,30 mm Installation m2 128.55 171,306.67 22,021,643.31 0.708
2 Light Steel Frame; including rafter and accessoris m2 128.55 213,420.90 27,435,470.12 0.882
3 Aluminium Foil Installation m2 128.55 27,087.50 3,482,125.21 0.112
4 Calsiplank, 30x0,80 cm m 49.10 59,070.00 2,900,573.28 0.093
5 Crown (Makara) Ø 50 cm unit 1.00 2,238,104.00 2,238,104.00 0.072
6 Roof Ridges, Zincalum Spandex m 28.82 73,810.00 2,127,499.44 0.068
Total Architectural Cost 197,845,053.36 6.363

C. STRUCTURAL WORK
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

I FOUNDATION WORK
1 Foundation PD1
- Foundation Cutting m3 5.40 105,435.00 569,349.00 0.018
- Backfill m3 3.67 62,150.00 228,214.80 0.007
- Concrete K-250 m3 1.73 1,226,720.35 2,119,772.76 0.068
- Reinforcement kg 197.91 16,006.10 3,167,737.47 0.102
- Formwork m2 5.76 185,185.00 1,066,665.60 0.034
- Sand layer t=10cm m3 0.58 192,830.00 111,070.08 0.004
- Base Concrete t=5cm m3 0.29 912,325.16 262,749.65 0.008
2 Foundation PD1A
- Foundation Cutting m3 34.48 105,435.00 3,634,977.06 0.117
- Backfill m3 30.88 62,150.00 1,918,943.40 0.062
- Concrete K-250 m3 3.60 1,226,720.35 4,416,193.26 0.142
- Reinforcement kg 449.49 16,006.10 7,194,649.02 0.231
- Formwork m2 14.40 185,185.00 2,666,664.00 0.086
- Sand layer t=10cm m3 1.20 192,830.00 231,396.00 0.007
- Base Concrete t=5cm m3 0.60 912,325.16 547,395.10 0.018
3 Foundation PD2
- Foundation Cutting m3 16.76 105,435.00 1,766,879.73 0.057
- Sand layer t=10cm m3 1.76 192,830.00 340,152.12 0.011
- Masonry 1:4 m3 9.03 756,723.00 6,833,738.40 0.220
- Aanstamping Stone H=15cm m3 2.65 332,739.00 880,427.39 0.028
- Backfill m3 3.50 62,150.00 217,742.52 0.007
4 Foundation PD3
- Foundation Cutting m3 27.87 105,435.00 2,938,789.76 0.095
- Sand layer t=10cm m3 2.93 192,830.00 565,763.22 0.018
- Masonry 1:4 m3 15.79 756,723.00 11,952,212.77 0.384
- Aanstamping Stone H=15cm m3 4.40 332,739.00 1,464,384.34 0.047
- Backfill m3 5.83 62,150.00 362,163.59 0.012
5 Soil fill m3 1.20 128,715.71 154,922.23 0.005

II. 1ST LEVEL


1 K1 30/30 Column
- Concrete K-250 m3 2.06 1,226,720.35 2,526,062.54 0.081
- Reinforcement kg 339.77 16,006.10 5,438,360.58 0.175
- Formwork Column m2 27.46 275,300.00 7,558,636.80 0.243
2 K2 20/20 Column
- Concrete K-250 m3 2.75 1,226,720.35 3,368,083.39 0.108
- Reinforcement kg 543.39 16,006.10 8,697,518.44 0.280
- Formwork Column m2 54.91 275,300.00 15,117,273.60 0.486
3 S1 25/30 Tie Beam
- Concrete K-250 m3 1.38 1,226,720.35 1,692,874.08 0.054
- Reinforcement kg 318.51 16,006.10 5,098,120.91 0.164
- Tie Beam Formwork m2 11.04 195,085.00 2,153,738.40 0.069
4 S2 20/25 Tie Beam
- Concrete K-250 m3 1.60 1,226,720.35 1,960,299.12 0.063
- Reinforcement kg 309.87 16,006.10 4,959,836.48 0.160
- Tie Beam Formwork m2 15.98 195,085.00 3,117,458.30 0.100
5 B1 20/25 Beam
- Concrete K-250 m3 2.09 1,226,720.35 2,560,778.73 0.082
- Reinforcement kg 389.53 16,006.10 6,234,886.15 0.201
- Beam Formwork m2 25.69 282,050.00 7,245,864.50 0.233
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

6 Floor Slab h=12 cm


- K-250 Concrete m3 4.90 1,226,720.35 6,008,966.96 0.193
- Reinforcement kg 462.28 16,006.10 7,399,241.65 0.238
- Floor Formwork m2 3.70 225,800.00 834,556.80 0.027
- Sand layer t=10cm m3 4.08 192,830.00 787,132.06 0.025
- Base Concrete t=5cm m3 0.20 912,325.16 182,465.03 0.006
Total Structural Cost 148,555,107.79 4.778

D. MECHANICAL AND ELECTRICAL WORKS


D.1 MUSHOLA PLUMBING WORKS
1.1 CLEAN WATER SYSTEM
Procurement and installation of PVC Pipes including excavation, accessories, and auxiliary equipment
a. Toilet and Clean Water Piping and Its Completeness
1 PVC AW Ø 25 mm m 19.00 28,026.63 532,505.88 0.017
2 PVC AW Ø 20 mm m 1.00 23,892.00 23,892.00 0.001
3 Fitting ls 1.00 68,300.79 68,300.79 0.002
4 Gate Valve Ø 32 mm Unit 1.00 126,610.00 126,610.00 0.004
1.2 VENT AND GREY WATER SYSTEM
Procurement and installation of PVC Pipes including excavation, accessories, and auxiliary tool
a. Grey Water Piping and Its completeness in toilet to Sepictank.1
1 PVC-AW Ø 80 mm; WW (Waste Water) m 6.00 123,292.13 739,752.75 0.024
2 Floor Clean Out Ø 80 mm, WW ( Waste Water) unit 1.00 230,725.00 230,725.00 0.007
3 Fitting ls 1.00 97,047.78 97,047.78 0.003
D.2 ELECTRICAL WORKS
2.1 PANEL WORKS
Procurement & Installation
1 MCB-BOX of the Mushola unit 1.00 930,149.00 930,149.00 0.030
2.2 LIGHTING WORKS
Procurement & Installation
a. Mushola
1 Roset Led 22 W Type Bulb unit 8.00 143,896.50 1,151,172.00 0.037
2 Roset Led 5 W Type Bulb (Toilet) unit 2.00 69,399.00 138,798.00 0.004
3 Double Switch unit 3.00 42,350.00 127,050.00 0.004
4 100 W Wall Electric Socket unit 6.00 49,929.00 299,574.00 0.010
5 NYM 3x2,5 mm² Lamp Installation in 20 mm of Conduit Pipe point 10.00 194,035.42 1,940,354.17 0.062
6 Electr. Socket NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 6.00 218,556.25 1,311,337.50 0.042
2.3 Lightning Rod Installation
Procurement & Installation
1 Air Terminal, Ø 3/4 30cm; Completed with GIP, Ø 3/4 70cm set 1.00 442,541.00 442,541.00 0.014
2 BC Cable Installation, 25 mm² m 15.00 75,065.83 1,125,987.50 0.036
3 Earthing Pit, 600mm² x 600mm² c/w with grounding system set 1.00 948,398.00 948,398.00 0.031
4 Auxiliary Equipments lot 1.00 366,501.21 366,501.21 0.012
Total Mechanical And Electrical Cost 10,600,696.56 0.341

VII TOILET 4 ROOMS -E


A PREPARATION WORK
1 Site Measurement m' 26.00 22,990.00 597,740.00 0.019
PREPARATION 597,740.00 0.019
B ARCHITECTURAL WORKS
B.1 1ST FLOOR
I. WALLWORK
1 Brick Wall 1:3 m2 63.10 147,363.92 9,298,073.90 0.299
2 Mortar Plaster Work m2 136.13 67,316.74 9,164,097.63 0.295
3 Mortar Neat Plaster Work m2 136.13 42,427.00 5,775,757.22 0.186
4 Practical Column & Lintel Beam Work
- K250 Concrete m3 0.54 1,226,720.35 657,522.11 0.021
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

- Reinforcement kg 82.45 16,006.10 1,319,712.94 0.042


- Formwork m2 8.93 185,185.00 1,654,319.33 0.053
5 Wall Tiles 25x40cm (Unpolished) m2 46.41 183,499.80 8,515,675.22 0.274
II. Floor Installation Work
1 40x40 cm of Ceramic Tile (Unpolished) Hallway m2 31.24 166,262.80 5,194,049.87 0.167
2 40x40 cm of Ceramic Tile (Unpolished) Rooms m2 12.56 162,962.80 2,046,486.84 0.066
3 Waterproofing Coating + mortar m2 12.56 119,614.62 1,502,120.35 0.048
III. Painting Works
1 Wall ; Interior m2 46.63 40,563.60 1,891,358.98 0.061
2 Wall Painting; Exterior m2 89.51 54,313.60 4,861,447.40 0.156
3 Ceiling Painting; Interior m2 10.78 40,563.60 437,235.04 0.014
4 Ceiling Painting; Exterior m2 58.58 54,313.60 3,181,527.75 0.102
5 Calsiplank Painting m2 10.61 54,313.60 576,370.49 0.019
IV. Sanitary Work and Installation
Sanitary work includes procurement & installation
1 Squatting Closet Unit 3.00 1,306,646.00 3,919,938.00 0.126
2 Sitting Toilet Unit 1.00 3,699,704.80 3,699,704.80 0.119
3 Shower spray Unit 1.00 960,355.00 960,355.00 0.031
4 Wastafel hang Unit 3.00 3,723,830.00 11,171,490.00 0.359
5 Handrail Stainless; Diffable m 1.20 610,995.00 733,194.00 0.024
6 Faucet Unit 4.00 746,652.50 2,986,610.00 0.096
7 Floor Drain Unit 4.00 675,235.00 2,700,940.00 0.087
8 5mm; uk 500x700 of mirror work Unit 3.00 126,296.50 378,889.50 0.012
9 Fibre Basin Unit 3.00 992,670.36 2,978,011.08 0.096
10 Tissue Holder Unit 1.00 585,475.00 585,475.00 0.019
11 Soap Dispenser Unit 3.00 165,275.00 495,825.00 0.016
12 Robe hook Unit 4.00 334,235.00 1,336,940.00 0.043
V. Door and Window Installation Work (complete w. alluminium frame)
1 Door Allumunium Frame Installation Work (type P4) Difabel Unit 1.00 2,585,000.00 2,585,000.00 0.083
2 Door Allumunium Frame Installation Work (type P3) Unit 3.00 2,368,025.00 7,104,075.00 0.228
VI. Ceiling Installation Work
1 Ceiling Hollow frame m2 69.36 149,919.00 10,397,782.16 0.334
2 6 mm of Calcium Board GRC (Ceiling Interior) m2 10.78 72,230.40 778,571.48 0.025
3 6 mm of Calcium Board GRC (Ceiling Exterior) m2 58.58 72,230.40 4,231,040.14 0.136
VII. Other Works
1 Stair
- Retaining Wall 1 Pc : 5 Ps m2 3.24 139,920.88 453,343.65 0.015
- Landfill for floor elevation m3 0.49 163,075.00 79,254.45 0.003
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.09 912,325.16 82,109.26 0.003
- Chevron Works m1 6.60 40,315.00 266,079.00 0.009
- Mortar Plaster Work m2 2.43 67,316.74 163,445.05 0.005
- Mortar Neat Plaster Work m2 2.43 42,427.00 103,012.76 0.003
B.2 ROOF WORKS
I. Roof Covering Works
1 Zincalume Spandex H. 0,30 mm Installation m2 99.18 171,306.67 16,990,366.51 0.546
2 Light Steel Frame; including rafter and accessoris m2 99.18 213,420.90 21,167,298.28 0.681
3 Aluminium Foil Installation m2 99.18 27,087.50 2,686,565.34 0.086
4 Roof Ridges, Zincalum Spandex m 27.94 73,810.00 2,061,956.16 0.066
5 Calsiplank 30x0,80 cm m 35.37 59,070.00 2,089,483.11 0.067
Total Architectural Cost 159,262,509.80 5.122

C STRUCTURAL WORK
I FOUNDATION WORK
1 Foundation PD1
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

- Backfill m 3 5.88 62,150.00 365,442.00 0.012


2 Foundation PD2
- Backfill m3 2.50 62,150.00 155,375.00 0.005
3 Tie Beam 20/25
- Concrete K-250 m3 1.88 1,226,720.35 2,306,234.26 0.074
- Reinforcement kg 334.72 16,006.10 5,357,601.97 0.172
- Tie Beam Formwork m2 18.80 195,085.00 3,667,598.00 0.118
4 Tie Beam 15/20
- Concrete K-250 m3 0.27 1,226,720.35 329,374.41 0.011
- Reinforcement kg 92.22 16,006.10 1,476,134.89 0.047
- Tie Beam Formwork m2 3.58 195,085.00 698,404.30 0.022
II 1ST LEVEL
1 200x200 Column
- K-250 Concrete m3 2.21 1,226,720.35 2,708,598.53 0.087
- Reinforcement kg 488.55 16,006.10 7,819,771.66 0.251
- Column Formwork m2 44.16 275,300.00 12,157,248.00 0.391
2 15/20 Column
- K-250 Concrete m3 0.55 1,226,720.35 677,149.63 0.022
- Reinforcement kg 133.87 16,006.10 2,142,728.97 0.069
-Column Formwork m2 9.66 275,300.00 2,659,398.00 0.086
3 15/20 Beam
- Concrete K-250 m3 1.48 1,226,720.35 1,810,639.24 0.058
- Reinforcement kg 403.54 16,006.10 6,459,156.67 0.208
- Beam Formwork m2 27.06 282,050.00 7,632,273.00 0.245
4 Floor Slab h=12 cm
- Base Concrete t=5cm m3 2.04 912,325.16 1,862,055.65 0.060
- Sand layer t=10cm m3 3.53 192,830.00 680,304.24 0.022
- Concrete K-250 m3 4.23 1,226,720.35 5,193,443.27 0.167
- Reinforcement kg 369.85 16,006.10 5,919,866.97 0.190
- Floor Formwork m2 3.22 225,800.00 726,172.80 0.023
Total Structural Cost 72,804,971.45 2.341

D. MECHANICAL AND ELECTRICAL WORKS


1 TOILET PLUMBING WORKS
1.1 CLEAN WATER SYSTEM
Procurement and installation of PVC Pipes
a. Toilet Clean Water Piping and Its Completeness
1 PVC AW Ø 25 mm m 19.00 28,026.63 532,505.88 0.017
2 PVC AW Ø 20 mm m 2.00 23,892.00 47,784.00 0.002
3 Fitting ls 1.00 70,689.99 70,689.99 0.002
4 Gate Valve Ø 32 mm Unit 1.00 126,610.00 126,610.00 0.004
1.2 VENT AND GREY WATER SYSTEM
Procurement and installation of PVC Pipes
a. Grey Water Piping and Its completeness in toilet 1
1 PVC-AW Ø 100 mm; SW (Sewage Water) m 12.00 185,950.88 2,231,410.50 0.072
2 PVC-AW Ø 80 mm; WW (Waste Water) m 20.00 123,292.13 2,465,842.50 0.079
3 PVC-AW Ø 65 mm; WW (Waste Water) m 4.00 95,628.50 382,514.00 0.012
4 PVC-AW Ø 50 mm; WW (Waste Water) m 5.00 55,061.88 275,309.38 0.009
5 Floor Clean Out Ø 80 mm, WW ( Waste Water) unit 2.00 230,725.00 461,450.00 0.015
6 Floor Clean Out Ø 100 mm, SW (Sewage Water) unit 1.00 340,263.00 340,263.00 0.011
7 Fitting ls 1.00 615,678.94 615,678.94 0.020
D.2 ELECTRICAL WORKS
2.1 PANEL WORKS
Procurement & Installation
1 MCB BOX Toilet Unit 1.00 631,939.00 631,939.00 0.020
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

2 NYM 3x2,5 mm² Lamp Installation in 20 mmi conduit pipe m 53.00 43,081.50 2,283,319.50 0.073
of MCB-BOX from Classroom MCB-BOX to Toilet
2.2 LIGHTING WORKS
Procurement, installation of
lighting
a. Toilet (4 ROOMS)
1 Roset Led 5 W Type Bulb (Toilet) unit 8.00 69,399.00 555,192.00 0.018
2 Double Electrical Switch unit 4.00 42,350.00 169,400.00 0.005
3 Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 8.00 194,035.42 1,552,283.33 0.050
2.3 Lightning Rod Installation
Procurement, installation of a
complete lightning rod
a. Toilet (4 ROOMS)
1 Ø 3/4 30cm Air Terminal , Completed With Ø 3/4 70cm GIP set 1.00 442,541.00 442,541.00 0.014
2 BC 25 mm² Cable Installation m 16.00 75,065.83 1,201,053.33 0.039
3 600mm² x 600mm² c/w Junction Box with Grounding System set 1.00 948,398.00 948,398.00 0.031
4 Auxiliary Materials lot 1.00 366,501.21 366,501.21 0.012
Total Mechanical And Electrical Cost 15,700,685.55 0.505

IX SITE PLAN
A SITEPLAN STRUCTURAL WORKS
1.1 STRUCTURAL FOUNDATION TOWER WATER TANK
a. Foundation Footplat
- Foundation Cutting m3 1.12 105,435.00 117,665.46 0.004
- Backfill m3 0.73 62,150.00 45,493.80 0.001
- Concrete K-250 m3 0.29 1,226,720.35 353,295.46 0.011
- Reinforcement kg 11.54 16,006.10 184,724.48 0.006
- Formwork m2 1.92 185,185.00 355,555.20 0.011
- Sand layer t=5cm m3 0.07 192,830.00 13,883.76 0.0004
- Base Concrete t=5cm m3 0.07 912,325.16 65,687.41 0.002
b. 20/20 Column
- Concrete K-250 m3 0.10 1,226,720.35 117,765.15 0.004
- Reinforcement kg 13.31 16,006.10 213,067.85 0.007
- Formwork Column m2 1.92 275,300.00 528,576.00 0.017
c. 15/20 Tie Beam
- Concrete K-250 m3 0.16 1,226,720.35 191,368.37 0.006
- Reinforcement kg 23.15 16,006.10 370,535.20 0.012
- Tie Beam Formwork m2 2.08 195,085.00 405,776.80 0.013
Total Site Plan Structural Work Cost 2,963,394.95 0.095

B SITEPLAN PLUMBING WORKS


1.1 MAIN EQUIPMENTS OF CLEAN WATER SYSTEM
Pipeline procurement and
installation
a. Piping include excavation,
and accessories (pump)
accessories, and auxiliary
1 PVC-AW
equipmentØ 32 mm m 40.00 33,610.50 1,344,420.00 0.043
2 PVC-AW Ø 25 mm m 40.00 28,026.63 1,121,065.00 0.036
3 Fitting ls 1.00 246,548.50 246,548.50 0.008
b. CLEAN WATER PUMP
1 Type : Jet Pump ls 1.00 9,729,500.00 9,729,500.00 0.313
Capacity : 35 Lpm
Suction Head : 40 m
Discharge Head : 41 m
Output Power : 1 Kw
Installed complete with WLC (water level control), holder, support etc.
according to specifications and drawing
c. Piping from Jet Pump to water tank
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

1 PVC AW Ø 32 mm m 14.00 33,610.50 470,547.00 0.015


2 Gate Valve Ø 32mm unit 1.00 126,610.00 126,610.00 0.004
3 Fitting ls 1.00 59,715.70 59,715.70 0.002
d. Roof Tank
1 Type : Fibreglass Unit 1.00 7,812,750.00 7,812,750.00 0.251
2 Capacity : 1 m3
Rooftank work c/w Water Tower 4 meters high
1.2 CLEAN WATER SYSTEM
Procurement and installation of PVC Pipes including excavation, accessories,
and auxiliary equipment
a. Piping and accessories from the Tank to teacher office
1 PVC AW Ø 40 mm m 4.00 50,373.13 201,492.50 0.006
2 PVC AW Ø 32 mm m 40.00 33,610.50 1,344,420.00 0.043
3 Fitting ls 1.00 168,366.00 168,366.00 0.005
4 Gate Valve Ø 40mm unit 1.00 137,747.50 137,747.50 0.004
b. Piping and accessories from the Tank to mushola
1 PVC AW Ø 40 mm m 4.00 50,373.13 201,492.50 0.006
2 PVC AW Ø 32 mm m 3.00 33,610.50 100,831.50 0.003
3 Fitting ls 1.00 44,007.15 44,007.15 0.001
4 Gate Valve Ø 40mm unit 1.00 137,747.50 137,747.50 0.004
c. Piping and accessories from the Tank to toilet
1 PVC AW Ø 40 mm m 4.00 50,373.13 201,492.50 0.006
2 PVC AW Ø 32 mm m 7.00 33,610.50 235,273.50 0.008
3 Fitting ls 1.00 57,451.35 57,451.35 0.002
4 Gate Valve Ø 40mm unit 1.00 137,747.50 137,747.50 0.004
1.3 VENT AND GREY WATER SYSTEM
Procurement and installation of PVC Pipes including excavation, accessories,
and auxiliary tool
a. Grey Water Piping and accessories Teacher Office And Toilet to Sepictank
1 PVC-AW Ø 100 mm; SW (Sewage Water) m 38.00 185,950.88 7,066,133.25 0.227
2 PVC-AW Ø 80 mm; WW (Waste Water) m 17.00 123,292.13 2,095,966.13 0.067
3 Fitting ls 1.00 916,209.94 916,209.94 0.029
b. Grey Water Piping and accessories Mushola to Infiltration
1 PVC-AW Ø 80 mm; WW (Waste Water) m 7.00 123,292.13 863,044.88 0.028
2 Fitting ls 1.00 86,304.49 86,304.49 0.003
1.4 DRAINAGE PIPE SYSTEM TO INFILTRATION WELL
Procurement and installation of PVC Pipes including excavation, accessories,
and auxiliary tool
a. PVC-AW Ø 100 mm; PAH m 3.00 185,950.88 557,852.63 0.018
Total Site Plan Plumbing Cost 35,464,737.00 1.141
C. SITE PLAN ELECTRICAL WORKS
C.1 LOW VOLTAGE PANEL WORK
Procurement and installation of Panel
School Main Panel unit 1.00 3,173,775.00 3,173,775.00 0.102
New Installation of PLN
Connecting Fee VA 7,700.00 993.33 7,648,666.67 0.246
Deposit Money VA 7,700.00 333.33 2,566,666.67 0.083
SLO (Certificate of Eligibility for Operation ) (adjusted for rates from SLO consultants) VA 7,700.00 66.67 513,333.33 0.017
C.2 CONNECTOR CABLE PROVISION AND INSTALLATION
The work of procurement, installation and testing
Low Voltage Cable ;
From Main Panel to MCB-BOX.1, NYY 3 x 6 mm² + BC 6mm² (Office) m 2.00 80,521.83 161,043.67 0.005
From Main Panel to MCB-BOX.2, NYY 3 x 4 mm² + BC 6mm² (Classroom-1) m 9.00 75,967.83 683,710.50 0.022
From Main Panel to MCB-BOX.3, NYY 3 x 4 mm² + BC 6mm² (Mushola) m 46.00 75,967.83 3,494,520.33 0.112
From Main Panel to MCB-BOX.4, NYY 3 x 4 mm² + BC 6mm² (Library) m 42.00 75,967.83 3,190,649.00 0.103
From Main Panel to MCB-BOX.5, NYY 3 x 4 mm² + BC 6mm² (Classroom-2) m 42.00 75,967.83 3,190,649.00 0.103
From MCB-BOX.1 to Jet Pump, NYY 3 x 4 mm² + BC 6mm² m 57.00 75,967.83 4,330,166.50 0.139
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

Total Site Plan Mechanical And Electrical Cost 28,953,180.67 0.931

X SEPTIC TANK N25 WORKS-1


A STP
1 Ground Work
- STP Foundation Cutting m3 26.21 105,435.00 2,763,480.64 0.089
- Backfill m3 21.64 62,150.00 1,345,026.55 0.043
2 (120X120) Column
- K-250 Concrete m3 0.12 1,226,720.35 144,851.14 0.005
- Reinforcement kg 30.76 16,006.10 492,358.63 0.016
- Column Formwork m2 3.94 275,300.00 1,083,580.80 0.035
3 (120X120)Tie Beam
- K-250 Concrete m3 0.08 1,226,720.35 92,210.12 0.003
- Reinforcement kg 19.17 16,006.10 306,882.62 0.010
- Tie Beam Formwork m2 1.25 195,085.00 244,402.49 0.008
4 B1 (120X120) Beam
- K-250 Concrete m3 0.08 1,226,720.35 92,210.12 0.003
- Reinforcement kg 19.17 16,006.10 306,882.62 0.010
- Beam Formwork m2 1.25 282,050.00 353,352.24 0.011
5 B2 (120X120) Beam
- K-250 Concrete m3 0.07 1,226,720.35 81,552.37 0.003
- Reinforcement kg 23.23 16,006.10 371,886.69 0.012
- Beam Formwork m2 1.11 282,050.00 312,511.40 0.010
6 Wall h=12 cm
- K-250 Concrete m3 1.30 1,226,720.35 1,596,760.54 0.051
- Reinforcement kg 72.51 16,006.10 1,160,547.33 0.037
- Formwork m2 22.22 282,050.00 6,266,361.26 0.202
7 Slab Top h=12cm
- K-250 Concrete m3 0.10 1,226,720.35 117,421.67 0.004
- Reinforcement kg 16.80 16,006.10 268,896.48 0.009
- Formwork m2 0.81 295,300.00 239,488.30 0.008
8 Floor Slab h=12 cm
- K-250 Concrete m3 0.22 1,226,720.35 265,707.63 0.009
- Reinforcement kg 16.80 16,006.10 268,896.48 0.009
- Floor Formwork m2 0.68 225,800.00 154,447.20 0.005
- Sand layer t=10cm m3 0.24 192,830.00 46,568.45 0.001
- Base Concrete t=5cm m3 0.12 912,325.16 110,163.26 0.004
- Waterproofing Coating m2 18.22 48,213.00 878,537.29 0.028
Total STP-1 Cost 19,364,984.30 0.623
B Infiltration
- Soil Exavation m3 1.22 105,435.00 128,103.53 0.004
- Brick Wall 1 Pc : 3 Ps m2 5.40 147,363.92 795,765.17 0.026
- Landfill m3 0.48 192,830.00 92,558.40 0.003
- Gravel m3 0.48 429,330.00 206,078.40 0.007
Total Infiltration-1 Cost 1,222,505.49 0.039

XI SEPTIC TANK N25 WORKS-2


A STP
1 Ground Work
- STP Foundation Cutting m3 26.21 105,435.00 2,763,480.64 0.089
- Backfill m3 21.64 62,150.00 1,345,026.55 0.043
2 (120X120) Column
- K-250 Concrete m3 0.12 1,226,720.35 144,851.14 0.005
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

- Reinforcement kg 30.76 16,006.10 492,358.63 0.016


- Column Formwork m2 3.94 275,300.00 1,083,580.80 0.035
3 (120X120)Tie Beam
- K-250 Concrete m3 0.08 1,226,720.35 92,210.12 0.003
- Reinforcement kg 19.17 16,006.10 306,882.62 0.010
- Tie Beam Formwork m2 1.25 195,085.00 244,402.49 0.008
4 B1 (120X120) Beam
- K-250 Concrete m3 0.08 1,226,720.35 92,210.12 0.003
- Reinforcement kg 19.17 16,006.10 306,882.62 0.010
- Beam Formwork m2 1.25 282,050.00 353,352.24 0.011
5 B2 (120X120) Beam
- K-250 Concrete m3 0.07 1,226,720.35 81,552.37 0.003
- Reinforcement kg 23.23 16,006.10 371,886.69 0.012
- Beam Formwork m2 1.11 282,050.00 312,511.40 0.010
6 Wall h=12 cm
- K-250 Concrete m3 1.30 1,226,720.35 1,596,760.54 0.051
- Reinforcement kg 72.51 16,006.10 1,160,547.33 0.037
- Formwork m2 22.22 282,050.00 6,266,361.26 0.202
7 Slab Top h=12cm
- K-250 Concrete m3 0.10 1,226,720.35 117,421.67 0.004
- Reinforcement kg 16.80 16,006.10 268,896.48 0.009
- Formwork m2 0.81 295,300.00 239,488.30 0.008
8 Floor Slab h=12 cm
- K-250 Concrete m3 0.22 1,226,720.35 265,707.63 0.009
- Reinforcement kg 16.80 16,006.10 268,896.48 0.009
- Floor Formwork m2 0.68 225,800.00 154,447.20 0.005
- Sand layer t=10cm m3 0.24 192,830.00 46,568.45 0.001
- Base Concrete t=5cm m3 0.12 912,325.16 110,163.26 0.004
- Waterproofing Coating m2 18.22 48,213.00 878,537.29 0.028
Total STP-2 Cost 19,364,984.30 0.623
B Infiltration
- Soil Exavation m3 1.22 105,435.00 128,103.53 0.004
- Brick Wall 1 Pc : 3 Ps m2 5.40 147,363.92 795,765.17 0.026
- Landfill m3 0.48 192,830.00 92,558.40 0.003
- Gravel m3 0.48 429,330.00 206,078.40 0.007
Total Infiltration-2 Cost 1,222,505.49 0.039

XII GUTTERS AROUND THE BUILDING AND INFILTRATION


A Gutters Around the Building
- Soil Exavation m3 32.59 105,435.00 3,436,308.74 0.111
- Brick Wall 1 Pc : 3 Ps m2 164.37 147,363.92 24,222,384.37 0.779
- Sand Layer m3 21.00 192,830.00 4,048,630.24 0.130
- Lean Work 1 Pc : 2 Ps : 3 Kr m3 25.08 912,325.16 22,880,612.75 0.736
- Mortar Plaster Work m2 308.20 67,316.74 20,746,751.23 0.667
- Mortar Neat Plaster Work m2 308.20 42,427.00 13,075,831.69 0.421
Total Gutters Around The Building Cost 88,410,519.01 2.843
B Infiltration
- Soil Exavation m3 7.29 105,435.00 768,621.15 0.025
- Brick Wall 1 Pc : 3 Ps m2 32.40 147,363.92 4,774,591.01 0.154
- Landfill m3 2.88 192,830.00 555,350.40 0.018
- Gravel m3 2.88 429,330.00 1,236,470.40 0.040
Total Gutters Around The Building And Infiltration Cost 7,335,032.96 0.236
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
UNIT PRICE TOTAL PRICE
NO. WORK DESCRIPTION UNIT VOLUME Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

XIII CONNECTING CORRIDOR


- Soil Exavation m3 0.52 105,435.00 55,037.07 0.002
- Brick Wall 1 Pc : 5 Ps m2 10.09 139,920.88 1,412,081.52 0.045
- Landfill for floor elevation m3 2.87 163,075.00 468,188.33 0.015
- Sand layer m3 0.32 192,830.00 61,512.77 0.002
- Lean Work 1 Pc : 2 Ps : 3 Kr m3 0.53 912,325.16 481,525.22 0.015
- Chevron Works m' 7.54 40,315.00 303,975.10 0.010
- Mortar Plaster Work m2 6.61 67,316.74 445,098.31 0.014
- Mortar Neat Plaster Work m2 6.61 42,427.00 280,527.32 0.009
- Canopy (Module 1,4x3m) Unit 2.00 3,168,440.00 6,336,880.00 0.204
- Handrail Corridor Work m 5.60 760,976.98 4,261,471.06 0.137
Total Connecting Corridor Cost 14,106,296.70 0.454

TOTAL 3,109,428,000.00 100.000 6.354 1.429 7.783


Plan 5.156 Realization 7.783 Deviation 2.627

Acknowledged by ; Approved by ; Submitted by;


UNITED NATIONS DEVELOPMENT PROGRAMME Supervision Consultant Contractor
PT. YODYA KARYA (PERSERO) JV PT. SETIA MULIA ABADI

(Whisnu Yonar Anggono) (Apjelvian Henri) (Ajeng Listianti)


Community Mobilization Officer UNDP PETRA Team Leader Site Manager
Assignor : Supervision Consultant : Contractor :

WEEKLY REPORT
Project : CONSTRUCTION OF SCHOOLS FACILITIES IN CENTRAL SULAWESI (LOT 3) Week : 7 (seven)
Contract No. : Ref.: 10057438 Period : 30 July 2023 - 05 August 2023
Location : SD Negeri Pengawu Weight Until Last Week : 2.675 %
Owner : United Nations Development Programme Weight This Week : 1.224 %
Contract Price : IDR 3,328,489,000 Weight Until This week Week : 3.899 %

UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK


NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

I PREPARATION WORK
1 Project Safety Fencing M1 80.00 251,460.00 20,116,800.00 0.604 76.000 95.000 0.574 4.000 5.000 0.030 80.000 100.000 0.604
2 Project Signage Unit 1.00 474,732.50 474,732.50 0.014 1.000 100.000 0.014 1.000 100.000 0.014
3 Renovation Temporary Office Construction; Plaster Floor ls 1.00 14,683,944.00 14,683,944.00 0.441 1.000 100.000 0.441 1.000 100.000 0.441
4 Renovation Storage Construction & Bordinghouse ls 1.00 5,738,238.00 5,738,238.00 0.172 1.000 100.000 0.172 1.000 100.000 0.172
5 Mobilization, Demobilization of Personnel and Tools ls 1.00 5,000,000.00 5,000,000.00 0.150 0.500 50.000 0.075 0.500 50.000 0.075
6 HSE (Safety Net, Hat, Helmet,etc.) ls 1.00 10,175,000.00 10,175,000.00 0.306 0.750 75.000 0.229 0.750 75.000 0.229
7 Site Cleaning M2 1,556.98 4,158.00 6,473,922.84 0.195 1167.735 75.000 0.146 1167.735 75.000 0.146
8 Rebar Cleaning ls 1.00 7,500,000.00 7,500,000.00 0.225 0.500 50.000 0.113 0.500 50.000 0.113
Total Preparation Work Cost 70,162,637.34 2.108 1.765 0.030 1.795

II CLASSROOM 8x7 (5 ROOMS) A1


A PREPARATION WORK
1 Site Measurement M1 98.00 22,990.00 2,253,020.00 0.068
2 Brick Wall Demolition M2 8.97 232,870.00 2,088,843.90 0.063
PREPARATION 4,341,863.90 0.130

B ARCHITECTURAL WORKS
B.1 1ST FLOOR
I WALLWORK
1 1/2 Brick Wall 1:5 M2 43.54 139,920.88 6,092,183.10 0.183
2 Mortar Plaster Work M2 863.31 67,316.74 58,115,218.26 1.746
3 Mortar Neat Plaster Work M 2
863.31 42,427.00 36,627,653.37 1.100
4 Practical Column & Lintel Beam Work
- K250 Concrete M3 0.30 1,226,720.35 370,285.54 0.011
- Reinforcement Kg 46.56 16,006.10 745,297.20 0.022
- Formwork M2 5.03 185,185.00 931,634.87 0.028
II Floor Installation Work
1 Tile 40x40 cm (Polished) Rooms M2 272.74 162,962.80 44,446,474.07 1.335
2 Tile 40x40 cm (Unpolished) Hallway M2 81.82 166,262.80 13,604,453.61 0.409
III Painting Works
1 Wall Painting; Interior M 2
487.88 40,563.60 19,789,966.35 0.595
2 Wall Painting; Exterior M2 375.43 54,313.60 20,391,226.42 0.613
3 Ceiling Painting; Interior M2 269.42 40,563.60 10,928,645.11 0.328
4 Ceiling Painting; Exterior M2 197.57 54,313.60 10,730,737.95 0.322
5 Calsiplank Painting M2 36.02 54,313.60 1,956,625.71 0.059
IV Door and Window Installation Work (complete w. aluminiumframe)
Door Alumunium Frame Installation
1 Unit 5.00 1,082,950.00 5,414,750.00 0.163
Work (type P1)
2 Leaf Door Instalation Work (type P1) Unit 5.00 2,625,000.00 13,125,000.00 0.394
Door Alumunium Frame Installation
3 Unit 5.00 1,533,286.70 7,666,433.50 0.230
Work (type P2)
4 Leaf Door Instalation Work (type P2) Unit 5.00 5,250,000.00 26,250,000.00 0.789
5 Window Installation Work (type J2) Unit 5.00 3,417,381.00 17,086,905.00 0.513
6 Window Installation Work (type J3) Unit 15.00 3,546,928.00 53,203,920.00 1.598
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

V Ceiling Installation Work


1 Ceiling Hollow frame M2 466.99 149,919.00 70,010,673.81 2.103
2 6 mm of Calcium Board GRC (Ceiling Interior) M2 269.42 72,230.40 19,460,314.37 0.585
3 6 mm of Calcium Board GRC (Ceiling Exterior) M2 197.57 72,230.40 14,270,560.13 0.429
VI Other Works
1 Railling for Disability access
- Disability Handrail Ramp work M1 14.10 760,976.98 10,729,014.37 0.322
- Lean Ramp 1 Pc : 3 Ps : 5 Kr M3 0.78 912,325.16 711,613.62 0.021
- Chevron Works M 2
20.90 40,315.00 842,381.92 0.025
- Retaining Wall Ramp 1 Pc : 5 Ps M 2
5.75 139,920.88 803,985.38 0.024
- Landfill for floor elevation M2 1.25 163,075.00 204,332.97 0.006
- Mortar Plaster Work M2 5.76 67,316.74 387,609.81 0.012
- Mortar Neat Plaster Work M2 5.76 42,427.00 244,294.67 0.007
2 Stair
- Retaining Wall 1 Pc : 5 Ps M2 12.96 139,920.88 1,813,374.60 0.054
- Landfill for floor elevation M3 1.94 163,075.00 317,017.80 0.010
- Lean Ramp 1 Pc : 3 Ps : 5 Kr M 3
0.36 912,325.16 328,437.06 0.010
- Chevron Works M 2
26.40 40,315.00 1,064,316.00 0.032
- Mortar Plaster Work M2 9.71 67,316.74 653,780.22 0.020
- Mortar Neat Plaster Work M2 9.71 42,427.00 412,051.02 0.012
B.2 ROOF WORKS
I Roof Covering Works
1 Zincalume Spandex H. 0,30 mm Installation M2 610.06 171,306.67 104,507,002.45 3.140
2 Light Steel Frame; including rafter and accessoris M2 610.06 213,420.90 130,199,127.41 3.912
3 Aluminium Foil Installation M2 610.06 27,087.50 16,524,946.08 0.496
4 Calsiplank 30x0,8 cm M 1
120.08 59,070.00 7,093,243.74 0.213
5 Roof Ridges, Zincalum Spandex M 1
56.64 73,810.00 4,180,598.40 0.126
6 Roof Jalousie Unit 2.00 1,563,743.50 3,127,487.00 0.094
Total Architectural Cost 735,363,572.91 22.093

C STRUCTURAL WORK
I 1ST LEVEL
1 30/30 Column
- K-250 Concrete m3 2.22 1,226,720.35 2,726,999.34 0.082
- Reinforcement kg 12.35 16,006.10 197,645.72 0.006
- Column Formwork m2 29.64 275,300.00 8,159,892.00 0.245
2 20/20 Column
- K-250 Concrete m3 0.43 1,226,720.35 526,017.69 0.016
- Reinforcement kg 7.33 16,006.10 117,269.26 0.004
- Column Formwork m2 8.58 275,300.00 2,360,972.80 0.071
3 20/25 Beam
- Concrete K-250 m3 7.85 1,226,720.35 9,623,621.14 0.289
- Reinforcement kg 1,554.99 16,006.10 24,889,320.06 0.748
- Beam Formwork m2 109.83 282,050.00 30,977,551.50 0.931
Total Structural Cost 79,579,289.50 2.391

III CLASSROOM 8x7 (3 ROOMS) A2


A PREPARATION WORK
1 Site Measurement m' 66.00 22,990.00 1,517,340.00 0.046 66.000 100.000 0.046 66.000 100.000 0.046
2 Brick Wall Demolition m2 44.19 232,870.00 10,291,410.21 0.309
3 Beam Formwork Demolition m2 80.45 24,970.00 2,008,836.50 0.060
PREPARATION 13,817,586.71 0.415 0.046 0.046

B ARCHITECTURAL WORKS
B.1 1ST FLOOR
I WALLWORK
1 1/2 Brick Wall 1:5 m2 29.56 139,920.88 4,135,781.37 0.124
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

2 Mortar Plaster Work m2 435.33 67,316.74 29,305,132.80 0.880


3 Mortar Neat Plaster Work m2 435.33 42,427.00 18,469,830.76 0.555
4 Practical Column & Lintel Beam Work
- K250 Concrete m3 0.22 1,226,720.35 271,411.88 0.008
- Reinforcement kg 34.13 16,006.10 546,287.91 0.016
- Formwork m2 3.69 185,185.00 682,869.69 0.021
II Floor Installation Work
1 Tile 40x40 cm (Polished) Rooms m2 163.64 162,962.80 26,667,884.44 0.801
2 Tile 40x40 cm (Unpolished) Hallway m2 49.10 166,262.80 8,162,672.17 0.245
III Painting Works
1 Wall Painting; Interior m2 177.42 40,563.60 7,196,672.22 0.216
2 Wall Painting; Exterior m2 257.92 54,313.60 14,008,292.14 0.421
3 Ceiling Painting; Interior m2 161.65 40,563.60 6,557,187.07 0.197
4 Ceiling Painting; Exterior m2 131.89 54,313.60 7,163,420.70 0.215
5 Calsiplank Painting m2 26.26 54,313.60 1,426,416.35 0.043
6 Partition Painting m3 74.75 40,563.60 3,032,210.23 0.091
IV Door and Window Installation Work (complete w. aluminium frame)
1 Door Alumunium Frame Installation Work (type P1) Unit 3.00 1,082,950.00 3,248,850.00 0.098
2 Leaf Door Instalation Work (type P1) Unit 3.00 2,625,000.00 7,875,000.00 0.237
3 Door Alumunium Frame Installation Work (type P2) Unit 3.00 1,533,286.70 4,599,860.10 0.138
4 Leaf Door Instalation Work (type P2) Unit 3.00 5,250,000.00 15,750,000.00 0.473
5 Window Installation Work (type J2) Unit 3.00 3,417,381.00 10,252,143.00 0.308
6 Window Installation Work (type J3) Unit 9.00 3,546,928.00 31,922,352.00 0.959
7 Partition m2 36.61 457,506.50 16,748,397.95 0.503
V Ceiling Installation Work
1 Ceiling Hollow frame m 2
293.54 149,919.00 44,007,523.10 1.322
2 6 mm of Calcium Board GRC (Ceiling Interior) M2 161.65 72,230.40 11,676,188.62 0.351
3 6 mm of Calcium Board GRC (Ceiling Exterior) M2 131.89 72,230.40 9,526,467.46 0.286
VI Other Works
1 Stair
- Retaining Wall 1 Pc : 5 Ps m2 6.48 139,920.88 906,687.30 0.027
- Landfill for floor elevation m3 0.97 163,075.00 158,508.90 0.005
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.18 912,325.16 164,218.53 0.005
- Chevron Works m 13.20 40,315.00 532,158.00 0.016
- Mortar Plaster Work m 2
4.86 67,316.74 326,890.11 0.010
- Mortar Neat Plaster Work m 2
4.86 42,427.00 206,025.51 0.006
B.2 ROOF WORKS
I Roof Covering Works
1 Zincalume Spandex h 0,30mm Installation m2 385.99 171,306.67 66,121,975.04 1.987
2 Light Steel Frame; including rafter and accessoris m2 385.99 213,420.90 82,377,479.51 2.475
3 Aluminium Foil Installation m2 385.99 27,087.50 10,455,395.78 0.314
4 Calsiplank 30x0,8 cm m 88.08 59,070.00 5,203,003.74 0.156
5 Roof Ridges, Zincalum Spandex m 40.64 73,810.00 2,999,638.40 0.090
6 Roof Jalousie Unit 2.00 1,563,743.50 3,127,487.00 0.094
Total Architectural Cost 455,812,319.78 13.694

C STRUCTURAL WORK
I 1ST LEVEL
1 30/30 Column
- K-250 Concrete m3 2.05 1,077,138.88 2,210,288.98 0.066 2.052 100.000 0.066 2.052 100.000 0.066
- Column Formwork m2 27.36 327,500.00 8,960,400.00 0.269
2 20/20 Column
- K-250 Concrete m3 0.39 1,077,138.88 417,929.88 0.013 0.388 100.000 0.013 0.388 100.000 0.013
- Column Formwork m2 7.60 327,500.00 2,489,000.00 0.075
3 25/30 Beam
- Concrete K-250 m3 5.12 1,077,138.88 5,509,565.36 0.166 5.115 100.000 0.166 5.115 100.000 0.166
- Beam Formwork m2 60.01 335,750.00 20,148,357.50 0.605 12.000 19.997 0.121 12.000 19.997 0.121
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

4 20/25 Beam
- Concrete K-250 m3 1.46 1,077,138.88 1,572,622.76 0.047 1.460 100.000 0.047 1.460 100.000 0.047
- Beam Formwork m2 20.44 335,750.00 6,862,730.00 0.206 4.088 20.000 0.041 4.088 20.000 0.041
Total Structural Cost 48,170,894.49 1.447 0.232 0.222 0.454

IV CLASSROOM 10x9 (1 ROOM) B1


A PREPARATION WORK
1 Site Measurement And Bouwplank m' 42.00 278,630.00 11,702,460.00 0.352
2 Brick Wall Demolition m2 2.88 232,870.00 671,131.34 0.020
3 Beam Formwork Demolition m2 8.80 24,970.00 219,736.00 0.007
PREPARATION 12,593,327.34 0.378

B ARCHITECTURAL WORKS
B.1 1ST FLOOR
I WALLWORK
1 1/2 Brick Wall 1:5 m2 9.13 139,920.88 1,277,127.83 0.038
2 Mortar Plaster Work m2 302.43 67,316.74 20,358,670.20 0.612
3 Mortar Neat Plaster Work m 2
302.43 42,427.00 12,831,240.04 0.385
4 Practical Column & Lintel Beam Work
- K250 Concrete m3 0.07 1,226,720.35 81,883.58 0.002
- Reinforcement kg 10.09 16,006.10 161,566.35 0.005
- Formwork m2 1.11 185,185.00 206,018.31 0.006
B Ceiling Installation Work
1 Ceiling Hollow frame m2 135.10 149,919.00 20,254,506.66 0.609
2 6 mm of Calcium Board GRC (Ceiling Interior) M2 57.89 72,230.40 4,181,417.86 0.126
3 6 mm of Calcium Board GRC (Ceiling Exterior) M 2
77.21 72,230.40 5,577,125.88 0.168
C Floor Installation Work
1 Tile 40x40 cm (Polished) Rooms m2 88.34 162,962.80 14,395,644.86 0.432
2 Tile 40x40 cm (Unpolished) Hallway m2 19.96 166,262.80 3,318,106.70 0.100
D Door and Window Installation Work (complete w. aluminium frame)
Door Alumunium Frame Installation
1 Unit 1.00 1,082,950.00 1,082,950.00 0.033
Work (type P1)
2 Leaf Door Instalation Work (type P1) Unit 1.00 2,625,000.00 2,625,000.00 0.079
Door Alumunium Frame Installation
3 Unit 1.00 1,533,286.70 1,533,286.70 0.046
Work (type P2)
4 Leaf Door Instalation Work (type P2) Unit 1.00 5,250,000.00 5,250,000.00 0.158
5 Window Installation Work (type J3) Unit 4.00 3,546,928.00 14,187,712.00 0.426
E Painting Works
1 Wall Painting; Interior m2 125.88 40,563.60 5,106,348.79 0.153
2 Wall Painting; Exterior m2 176.55 54,313.60 9,588,848.83 0.288
3 Ceiling Painting; Interior m2 57.89 40,563.60 2,348,226.80 0.071
4 Ceiling Painting; Exterior m2 77.21 54,313.60 4,193,716.00 0.126
5 Calsiplank Painting m2 19.96 54,313.60 1,084,338.44 0.033
F Other Works
1 Railling for Disability access
- Disability Handrail Ramp work m 14.10 760,976.98 10,729,014.37 0.322
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.78 912,325.16 711,613.62 0.021
- Chevron Works m 20.90 40,315.00 842,381.92 0.025
- Retaining Wall Ramp 1 Pc : 5 Ps m2 5.75 139,920.88 803,985.38 0.024
- Landfill for floor elevation m3 1.25 163,075.00 204,332.97 0.006
- Mortar Plaster Work m2 5.76 67,316.74 387,609.81 0.012
- Mortar Neat Plaster Work m2 5.76 42,427.00 244,294.67 0.007
2 Stair
- Retaining Wall 1 Pc : 5 Ps m 2
3.24 139,920.88 453,343.65 0.014
- Landfill for floor elevation m3 0.49 163,075.00 79,254.45 0.002
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.09 912,325.16 82,109.26 0.002
- Chevron Works m 6.60 40,315.00 266,079.00 0.008
- Mortar Plaster Work m2 2.43 67,316.74 163,445.05 0.005
- Mortar Neat Plaster Work m2 2.43 42,427.00 103,012.76 0.003
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

B.2 ROOF WORKS


I Roof Covering Works
1 Zincalume Spandex h 0,30mm Installation m2 214.65 171,306.67 36,771,147.31 1.105
2 Light Steel Frame; including rafter and accessoris m2 214.65 213,420.90 45,811,009.61 1.376
3 Aluminium Foil Installation m2 214.65 27,087.50 5,814,358.96 0.175
4 Roof Ridges, Zincalum Spandex m 27.40 73,810.00 2,022,394.00 0.061
5 Calsiplank, fin. Paint m 66.50 59,070.00 3,927,918.72 0.118
6 Roof Jalousie Unit 2.00 1,563,743.50 3,127,487.00 0.094
Total Architectural Cost 242,188,528.33 7.276

C STRUCTURAL WORK
I 1ST LEVEL
1 K1 30/30 Column
- K-250 Concrete m3 0.27 1,226,720.35 331,214.49 0.010
- Reinforcement kg 21.09 16,006.10 337,493.20 0.010 21.085 100.000 0.010 21.085 100.000 0.010
- Column Formwork m2 3.60 275,300.00 991,080.00 0.030 3.600 100.000 0.030 3.600 100.000 0.030
2 K2 20/20 Column
- K-250 Concrete m3 0.03 1,226,720.35 39,255.05 0.001
- Reinforcement kg 9.99 16,006.10 159,827.72 0.005 9.985 100.000 0.005 9.985 100.000 0.005
- Column Formwork m2 0.64 275,300.00 176,192.00 0.005 0.640 100.000 0.005 0.640 100.000 0.005
3 B1 25/30 Beam
- Concrete K-250 m3 2.63 1,226,720.35 3,220,140.92 0.097
- Reinforcement kg 16.77 16,006.10 268,377.83 0.008
- Beam Formwork m2 29.92 282,050.00 8,438,936.00 0.254 29.920 100.000 0.254 29.920 100.000 0.254
4 B2 20/25 Beam
- Concrete K-250 m 3 0.64 1,226,720.35 778,967.42 0.023
- Reinforcement kg 43.28 16,006.10 692,693.12 0.021
- Beam Formwork m2 8.89 282,050.00 2,507,424.50 0.075
Total Structural Cost 17,941,602.25 0.539 0.304 0.304

V CLASSROOM 10x9 (1 ROOM) B2


A PREPARATION WORK
1 Site Measurement m' 42.00 22,990.00 965,580.00 0.029
2 Bouwplank Intallation m' 10.00 278,630.00 2,786,300.00 0.084
PREPARATION 3,751,880.00 0.113

B ARCHITECTURAL WORKS
B.1 1ST FLOOR
I WALLWORK
1 1/2 Brick Wall 1:5 m2 105.50 139,920.88 14,762,212.52 0.444
2 Mortar Plaster Work m2 302.43 67,316.74 20,358,670.20 0.612
3 Mortar Neat Plaster Work m2 302.43 42,427.00 12,831,240.04 0.385
4 Practical Column & Lintel Beam Work
- K250 Concrete m3 0.77 1,226,720.35 949,481.55 0.029
- Reinforcement kg 117.05 16,006.10 1,873,443.46 0.056
- Formwork m2 12.90 185,185.00 2,388,886.50 0.072
B Ceiling Installation Work
1 Ceiling Hollow frame m2 135.10 149,919.00 20,254,506.66 0.609
2 6 mm of Calcium Board GRC (Ceiling Interior) M2 57.89 72,230.40 4,181,417.86 0.126
3 6 mm of Calcium Board GRC (Ceiling Exterior) M2 77.21 72,230.40 5,577,125.88 0.168
C Floor Installation Work
1 Tile 40x40 cm (Polished) Rooms m 2
88.34 162,962.80 14,395,644.86 0.432
2 Tile 40x40 cm (Unpolished) Hallway m2 19.96 166,262.80 3,318,106.70 0.100
D Door and Window Installation Work (complete w. aluminium frame)
1 Door Alumunium Frame Installation Work (type P1) Unit 1.00 1,082,950.00 1,082,950.00 0.033
2 Leaf Door Instalation Work (type P1) Unit 1.00 2,625,000.00 2,625,000.00 0.079
3 Door Alumunium Frame Installation Work (type P2) Unit 1.00 1,533,286.70 1,533,286.70 0.046
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

4 Leaf Door Instalation Work (type P2) Unit 1.00 5,250,000.00 5,250,000.00 0.158
5 Window Installation Work (type J3) Unit 4.00 3,546,928.00 14,187,712.00 0.426
E Painting Works
1 Wall ; Interior m2 125.88 40,563.60 5,106,348.79 0.153
2 Wall Painting; Exterior m2 176.55 54,313.60 9,588,848.83 0.288
3 Ceiling Painting Interior m2 57.89 40,563.60 2,348,226.80 0.071
4 Ceiling Painting; Exterior m2 77.21 54,313.60 4,193,716.00 0.126
5 Calsiplank Painting m2 19.96 54,313.60 1,084,338.44 0.033
F Other Works
1 Stair
- Retaining Wall 1 Pc : 5 Ps m2 3.24 139,920.88 453,343.65 0.014
- Landfill for floor elevation m3 0.49 163,075.00 79,254.45 0.002
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.09 912,325.16 82,109.26 0.002
- Chevron Works m2 6.60 40,315.00 266,079.00 0.008
- Mortar Plaster Work m2 2.43 67,316.74 163,445.05 0.005
- Mortar Neat Plaster Work m2 2.43 42,427.00 103,012.76 0.003
B.2 ROOF WORKS
I Roof Covering Works
1 Zincalume Spandex H. 0,30 mm Installation m2 214.65 171,306.67 36,771,147.31 1.105
2 Light Steel Frame; including rafter and accessoris m2 214.65 213,420.90 45,811,009.61 1.376
3 Insulation Layer m2 214.65 27,087.50 5,814,358.96 0.175
4 Roof Ridges, Zincalum Spandex m 27.40 73,810.00 2,022,394.00 0.061
5 Calsiplank 30x0,80 cm m 66.50 58,520.00 3,891,345.92 0.117
6 Roof Jalousie Unit 2.00 1,776,981.25 3,553,962.50 0.107
Total Architectural Cost 246,902,626.25 7.418

C STRUCTURAL WORK
I FOUNDATION WORK
1 PD1 Foundation
- Backfill m3 36.18 62,150.00 2,248,587.00 0.068 28.944 80.000 0.054 7.236 20.000 0.014 36.180 100.000 0.068
2 PD1A Foundation
- Backfill m3 10.29 62,150.00 639,647.80 0.019 8.234 80.000 0.015 2.058 20.000 0.004 10.292 100.000 0.019
3 PD2 Broken Stone Foundation
- Foundation Cutting m3 0.86 105,435.00 90,146.93 0.003 0.855 100.000 0.003 0.855 100.000 0.003
- Masonry 1:4 m3 4.41 756,723.00 3,339,796.96 0.100 4.414 100.000 0.100 4.414 100.000 0.100
- Aanstamping Stone H=15cm m3 1.23 332,739.00 408,769.86 0.012 1.229 100.000 0.012 1.229 100.000 0.012
- Sand layer t=10cm m3 0.82 192,830.00 157,927.77 0.005 0.819 100.000 0.005 0.819 100.000 0.005
- Backfill m3 2.97 62,150.00 184,896.25 0.006 2.380 80.000 0.004 0.595 20.000 0.001 2.975 100.000 0.006
4 PD3 Broken Stone Foundation
- Foundation Cutting m3 5.02 105,435.00 528,861.96 0.016 5.016 100.000 0.016 5.016 100.000 0.016
- Masonry 1:4 m3 8.49 756,723.00 6,422,686.46 0.193 8.488 100.000 0.193 8.488 100.000 0.193
- Aanstamping Stone H=15cm m3 1.01 332,739.00 335,400.91 0.010 1.008 100.000 0.010 1.008 100.000 0.010
- Sand layer t=10cm m3 0.67 192,830.00 129,581.76 0.004 0.672 100.000 0.004 0.672 100.000 0.004
- Backfill m3 8.33 62,150.00 517,709.50 0.016 6.664 80.000 0.012 1.666 20.000 0.003 8.330 100.000 0.016
5 PD4 Broken Stone Foundation
- Foundation Cutting m3 0.76 105,435.00 80,130.60 0.002 0.760 100.000 0.002 0.760 100.000 0.002
- Masonry 1:4 m3 5.41 756,723.00 4,092,168.80 0.123 5.408 100.000 0.123 5.408 100.000 0.123
- Aanstamping Stone H=15cm m3 1.34 332,739.00 445,204.78 0.013 1.338 100.000 0.013 1.338 100.000 0.013
- Sand layer t=10cm m3 0.89 192,830.00 172,004.36 0.005 0.892 100.000 0.005 0.892 100.000 0.005
- Backfill m3 4.17 62,150.00 258,854.75 0.008 4.165 100.000 0.008 4.165 100.000 0.008
6 Soil fill m3 2.53 128,715.71 325,869.57 0.010 2.532 100.000 0.010 2.532 100.000 0.010
II 1ST LEVEL
1 K1 30/30 Column
- K-250 Concrete m3 3.91 1,077,138.88 4,216,998.71 0.127
- Reinforcement kg 64.14 16,006.10 1,026,676.55 0.031
- Column Formwork m2 52.20 275,300.00 14,370,660.00 0.432
2 K2 20/20 Column
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

- K-250 Concrete m3 0.69 1,077,138.88 741,071.55 0.022


- Reinforcement kg 17.09 16,006.10 273,504.33 0.008
- Column Formwork m2 13.76 275,300.00 3,788,128.00 0.114
3 S1 25/30 Tie Beam
- Concrete K-250 m3 2.64 1,077,138.88 2,843,646.64 0.085
- Reinforcement kg 587.98 16,006.10 9,411,333.30 0.283 287.382 48.876 0.138 287.382 48.876 0.138
- Tie Beam Formwork m2 21.12 195,085.00 4,120,195.20 0.124
4 S2 20/25 Tie Beam
- Concrete K-250 m3 0.64 1,077,138.88 683,983.19 0.021
- Reinforcement kg 116.63 16,006.10 1,866,776.64 0.056
- Tie Beam Formwork m2 6.35 195,085.00 1,238,789.75 0.037
5 B1 20/25 Beam
- Concrete K-250 m3 2.41 1,077,138.88 2,590,519.00 0.078
- Reinforcement kg 550.81 16,006.10 8,816,351.54 0.265
- Beam Formwork m2 49.56 335,750.00 16,639,770.00 0.500
6 Floor Slab h=12 cm
- K-250 Concrete m 3 12.18 1,077,138.88 13,124,721.81 0.394
- Reinforcement kg 961.91 16,006.10 15,396,370.91 0.463
- Floor Formwork m2 5.17 225,800.00 1,167,837.60 0.035
- Sand layer t=10cm m3 10.14 183,637.14 1,862,172.45 0.056
- Base Concrete t=5cm m3 5.07 912,325.16 4,625,716.64 0.139
Total Structural Cost 129,183,469.83 3.881 0.573 0.177 0.750

D CLASSROOM ELECTRICAL WORKS


D.1 LOW VOLTAGE PANEL WORKS
Procurement and installation of a
complete
MCB-BOXPanel
of the Classroom unit 4 0.135
1,124,332.00 4,497,328.00
D.2 LIGHTING WORKS
Procurement, installation of lighting and sockets
A CLASSROOM A1 ( 5 CLASS UNIT )
Roset Led 22 W Type Bulb unit 35 143,896.50 5,036,377.50 0.151
Single Electrical Switch unit 1 34,727.00 34,727.00 0.001
Double Electrical Switch unit 3 42,350.00 127,050.00 0.004
100 W Wall Electric Socket unit 6 49,929.00 299,574.00 0.009
Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 35 194,035.42 6,791,239.58 0.204
Electrical Socket NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 6 218,556.25 1,311,337.50 0.039
B CLASSROOM A2 ( 3 CLASS UNIT )
Roset Led 22 W Type Bulb unit 21 143,896.50 3,021,826.50 0.091
Single Electrical Switch unit 1 34,727.00 34,727.00 0.001
Double Electrical Switch unit 3 42,350.00 127,050.00 0.004
100 W Wall Electric Socket unit 6 49,929.00 299,574.00 0.009
Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 21 194,035.42 4,074,743.75 0.122
Electrical Socket NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 6 218,556.25 1,311,337.50 0.039
C CLASSROOM B1 ( 1 CLASS UNIT )
Roset Led 22 W Type Bulb unit 7 143,896.50 1,007,275.50 0.030
Single Electrical Switch unit 1 34,727.00 34,727.00 0.001
Double Electrical Switch unit 1 42,350.00 42,350.00 0.001
100 W Wall Electric Socket unit 2 49,929.00 99,858.00 0.003
Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 7 194,035.42 1,358,247.92 0.041
Electrical Socket NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 2 218,556.25 437,112.50 0.013
D CLASSROOM A1 ( 5 CLASS UNIT )
Roset Led 22 W Type Bulb unit 35 143,896.50 5,036,377.50 0.151
Single Electrical Switch unit 1 34,727.00 34,727.00 0.001
Double Electrical Switch unit 3 42,350.00 127,050.00 0.004
100 W Wall Electric Socket unit 6 49,929.00 299,574.00 0.009
Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 35 194,035.42 6,791,239.58 0.204
Electrical Socket NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 6 218,556.25 1,311,337.50 0.039
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

D.3 Lightning Rod Installation


Procurement, installation of a complete lightning rod
A CLASSROOM A1 (5 CLASS UNIT)
1 Ø 3/4 30cm Air Terminal , Completed With Ø 3/4 70cm GIP set 8 442,541.00 3,540,328.00 0.106
2 BC 25 mm² Cable Installation m 56 75,065.83 4,203,686.67 0.126
3 Earthing Pit, 600mm² x 600mm² c/w with grounding system set 1 948,398.00 948,398.00 0.028
4 Auxiliary Materials lot 1 366,501.21 366,501.21 0.011
B CLASSROOM A2 (3 CLASS UNIT)
1 Ø 3/4 30cm Air Terminal , Completed With Ø 3/4 70cm GIP set 4 442,541.00 1,770,164.00 0.053
2 BC 25 mm² Cable Installation m 37 75,065.83 2,777,435.83 0.083
3 Earthing Pit, 600mm² x 600mm² c/w with grounding system set 1 948,398.00 948,398.00 0.028
4 Auxiliary Materials lot 1 366,501.21 366,501.21 0.011
C CLASSROOM B1 (1 CLASS UNIT)
1 Ø 3/4 30cm Air Terminal , Completed With Ø 3/4 70cm GIP set 2 442,541.00 885,082.00 0.027
2 BC 25 mm² Cable Installation m 21 75,065.83 1,576,382.50 0.047
3 Earthing Pit, 600mm² x 600mm² c/w with grounding system set 1 948,398.00 948,398.00 0.028
4 Auxiliary Materials lot 1 366,501.21 366,501.21 0.011
D.4 CLASSROOM A1 (5 CLASS UNIT)
1 Ø 3/4 30cm Air Terminal , Completed With Ø 3/4 70cm GIP set 8 442,541.00 3,540,328.00 0.106
2 BC 25 mm² Cable Installation m 56 75,065.83 4,203,686.67 0.126
3 Earthing Pit, 600mm² x 600mm² c/w with grounding system set 1 948,398.00 948,398.00 0.028
4 Auxiliary Materials lot 1 366,501.21 366,501.21 0.011
Total Electrical Cost 71,303,459.33 2.142

VI MUSHOLA 10x9-C
A PREPARATION WORK
1 Site Measurement m' 38.00 22,990.00 873,620.00 0.026
2 Bowplank Installation m' 16.00 278,630.00 4,458,080.00 0.134
PREPARATION 5,331,700.00 0.160

B ARCHITECTURAL WORKS
B.1 1ST FLOOR
A WALLWORK
1 Brick Wall 1:5 m2 80.95 139,920.88 11,326,455.32 0.340
2 Mortar Plaster Work m2 253.08 67,316.74 17,036,790.84 0.512
3 Mortar Neat Plaster Work m 2
253.08 42,427.00 10,737,594.87 0.323
4 Practical Column & Lintel Beam Work
- K250 Concrete m3 1.12 1,226,720.35 1,372,700.07 0.041
- Reinforcement kg 179.42 16,006.10 2,871,750.75 0.086
- Formwork m2 18.65 185,185.00 3,453,700.25 0.104
B Ceiling Installation Work
1 Ceiling Hollow frame m2 101.41 149,919.00 15,202,836.03 0.457
2 6 mm of Calcium Board GRC (Ceiling Interior) M2 48.42 72,230.40 3,497,323.74 0.105
3 6 mm of Calcium Board GRC (Ceiling Exterior) M 2
52.99 72,230.40 3,827,344.44 0.115
C Floor Installation Work
1 Tile 40x40 cm (Polished) Rooms m2 80.16 162,962.80 13,063,586.94 0.392
2 Tile 40x40 cm (Unpolished) Hallway m2 8.43 166,262.80 1,400,930.35 0.042
D Door and Window Installation Work (complete w. aluminium frame)
1 Door Alumunium Frame Installation Work (type P2) Unit 3.00 1,533,286.70 4,599,860.10 0.138
2 Leaf Door Instalation Work (type P2) Unit 3.00 5,250,000.00 15,750,000.00 0.473
3 Window Installation Work (type J2) Unit 6.00 2,928,090.00 17,568,540.00 0.528
E Sanitary Work and Installation
Sanitary work includes procurement & installation
1 Faucet Unit 8.00 746,652.50 5,973,220.00 0.179
2 Floordrain Unit 2.00 675,235.00 1,350,470.00 0.041
F Painting Works
1 Wall Painting; Interior m2 93.02 40,563.60 3,773,226.07 0.113
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

2 Wall Painting; Exterior m2 160.06 54,313.60 8,693,652.07 0.261


3 Ceiling Painting; Interior m2 48.42 40,563.60 1,964,048.95 0.059
4 Ceiling Painting; Exterior m2 52.99 54,313.60 2,877,969.04 0.086
5 Calsiplank Painting m2 17.06 54,313.60 926,416.21 0.028
G Other Works
1 Stair
- Retaining Wall 1 Pc : 5 Ps m2 3.24 139,920.88 453,343.65 0.014
- Landfill for floor elevation m3 0.49 163,075.00 79,254.45 0.002
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m 3
0.09 912,325.16 82,109.26 0.002
- Chevron Works m 6.60 40,315.00 266,079.00 0.008
- Mortar Plaster Work m2 2.43 67,316.74 163,445.05 0.005
- Mortar Neat Plaster Work m2 2.43 42,427.00 103,012.76 0.003
B.2 ROOF WORKS
A Roof Covering Works
1 Zincalume Spandex h 0,30mm Installation m2 177.36 171,306.67 30,382,607.79 0.913
2 Light Steel Frame; including rafter and accessoris m2 177.36 213,420.90 37,851,903.98 1.137
3 Insulation Layer m 2
177.36 27,087.50 4,804,184.82 0.144
4 Roof Ridges, Zincalum Spandex m 35.09 73,810.00 2,589,845.28 0.078
5 Calsiplank m 56.86 59,070.00 3,358,483.92 0.101
6 Crown (Makara) Ø 50 cm unit 1.00 2,238,104.00 2,238,104.00 0.067
Total Architectural Cost 229,640,790.00 6.899

C. STRUCTURAL WORK
I FOUNDATION WORK
1 Foundation PD1
- Backfill m3 14.47 62,150.00 899,434.80 0.027
2 Foundation PD1A
- Backfill m3 30.88 62,150.00 1,918,943.40 0.058
3 PD2 Broken Stone Foundation
- Foundation Cutting m3 2.57 105,435.00 270,440.78 0.008 2.565 100.000 0.008 2.565 100.000 0.008
- Sand layer t=10cm m3 2.38 192,830.00 458,164.08 0.014 2.376 100.000 0.014 2.376 100.000 0.014
- Masonry 1:4 m3 6.40 756,723.00 4,844,540.65 0.146 6.402 100.000 0.146 6.402 100.000 0.146
- Aanstamping Stone H=15 cm m3 1.78 332,739.00 592,940.90 0.018 1.782 100.000 0.018 1.782 100.000 0.018
- Backfill m3 8.21 62,150.00 510,313.65 0.015
4 PD3 Broken Stone Foundation
- Foundation Cutting m3 2.57 105,435.00 270,440.78 0.008 2.565 100.000 0.008 2.565 100.000 0.008
- Sand layer t=10cm m3 1.94 192,830.00 373,126.05 0.011 1.935 100.000 0.011 1.935 100.000 0.011
- Masonry 1:4 m3 9.43 756,723.00 7,138,357.24 0.214 9.433 100.000 0.214 9.433 100.000 0.214
- Aanstamping Stone H=15 cm m3 2.63 332,739.00 873,689.43 0.026 2.626 100.000 0.026 2.626 100.000 0.026
- Backfill m3 12.08 62,150.00 750,678.77 0.023
5 Soil fill m3 2.59 128,715.71 333,013.30 0.010
II. 1ST LEVEL
1 K1 30/30 Column
- Concrete K-250 m3 1.81 1,077,138.88 1,952,421.93 0.059 0.234 12.910 0.008 0.234 12.910 0.008
- Reinforcement kg 34.62 16,006.10 554,186.07 0.017
- Formwork Column m2 24.17 275,300.00 6,653,450.40 0.200 3.120 12.910 0.026 3.120 12.910 0.026
2 K2 20/20 Column
- Concrete K-250 m3 2.47 1,077,138.88 2,662,256.45 0.080 0.364 14.727 0.012 0.364 14.727 0.012
- Reinforcement kg 16.87 16,006.10 269,994.56 0.008
- Formwork Column m2 49.23 275,300.00 13,553,569.60 0.407 7.280 14.787 0.060 7.280 14.787 0.060
3 S1 25/30 Tie Beam
- Concrete K-250 m 3 1.98 1,077,138.88 2,132,734.98 0.064
- Reinforcement kg 432.54 16,006.10 6,923,274.55 0.208
- Tie Beam Formwork m2 15.84 195,085.00 3,090,146.40 0.093
4 S2 20/25 Tie Beam
- Concrete K-250 m3 1.88 1,077,138.88 2,030,406.79 0.061
- Reinforcement kg 352.14 16,006.10 5,636,368.57 0.169
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

- Tie Beam Formwork m2 18.85 195,085.00 3,677,352.25 0.110


5 B1 20/25 Beam
- Concrete K-250 m3 3.54 1,077,138.88 3,813,071.63 0.115
- Reinforcement kg 576.75 16,006.10 9,231,550.60 0.277
- Beam Formwork m2 49.56 335,750.00 16,639,770.00 0.500
6 Floor Slab h=12 cm
- K-250 Concrete m3 9.19 1,077,138.88 9,900,414.29 0.297
- Reinforcement kg 775.63 16,006.10 12,414,827.03 0.373
- Floor Formwork m2 4.66 225,800.00 1,051,324.80 0.032
- Sand layer t=10cm m3 10.44 183,637.14 1,917,381.12 0.058
- Base Concrete t=5cm m3 5.22 912,325.16 4,762,857.35 0.143
Total Structural Cost 128,101,443.18 3.849 0.105 0.445 0.551

D. MECHANICAL AND ELECTRICAL WORKS


1 MUSHOLA PLUMBING WORKS
1.1 CLEAN WATER SYSTEM
Procurement and installation of PVC Pipes including excavation, accessories, and auxiliary equipment
A Toilet and Clean Water Piping and Its Completeness
1 PVC AW Ø 25 mm m 17 33,610.50 571,378.50 0.017
2 PVC AW Ø 20 mm m 1 28,026.63 28,026.63 0.001
3 Fitting ls 1 72,601.51 72,601.51 0.002
4 Gate Valve Ø 32 mm Unit 1 126,610.00 126,610.00 0.004
1.2 VENT AND GREY WATER SYSTEM
Procurement and installation of PVC Pipes including excavation, accessories, and auxiliary tool
A Grey Water Piping and Its completeness in Mushola to Infiltration
1 PVC-AW Ø 80 mm; WW (Waste Water) m 12 123,292.13 1,479,505.50 0.044
2 Floor Clean Out Ø 80 mm, WW ( Waste Water) unit 2 230,725.00 461,450.00 0.014
3 Fitting ls 1 194,095.55 194,095.55 0.006
2 MUSHOLA ELECTRICAL WORKS
2.1 PANEL WORKS
Procurement & Installation
MCB-BOX of the Mushola unit 1.000 930,149.00 930,149.00 0.028
2.2 LIGHTING WORKS
Procurement & Installation
A Mushola
Roset Led 22 W Type Bulb unit 10 143,896.50 1,438,965.00 0.043
Roset Led 5 W Type Bulb (Toilet) unit 2 69,399.00 138,798.00 0.004
Single Switch unit 1 34,727.00 34,727.00 0.001
Double Switch unit 3 42,350.00 127,050.00 0.004
100 W Wall Electric Socket unit 2 49,929.00 99,858.00 0.003
NYM 3x2,5 mm² Lamp Installation in 20 mm of Conduit Pipe point 12 194,035.42 2,328,425.00 0.070
Electr. Socket NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 2 218,556.25 437,112.50 0.013
2.3 Lightning Rod Installation
Procurement & Installation
1 Air Terminal, Ø 3/4 30cm; Completed with GIP, Ø 3/4 70cm set 1 442,541.00 442,541.00 0.013
2 BC Cable Installation, 25 mm² m 16 75,065.83 1,201,053.33 0.036
3 Earthing Pit, 600mm² x 600mm² c/w with grounding system set 1 948,398.00 948,398.00 0.028
4 Auxiliary Equipments lot 1 366,501.21 366,501.21 0.011
Total Mechanical And Electrical Cost 11,427,245.73 0.343

VII TOILET 6 ROOMS-D2


A PREPARATION WORK
1 Site Measurement m' 29.00 22,990.00 666,710.00 0.020
2 Formwork Beam Demolition m2 25.55 24,970.00 637,983.50 0.019
PREPARATION 1,304,693.50 0.039

B ARCHITECTURAL WORKS
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

B.1 1ST FLOOR


A WALLWORK
1 Brick Wall 1:3 m2 73.77 147,363.92 10,871,036.38 0.327
2 Mortar Plaster Work m2 124.71 67,316.74 8,395,071.14 0.252
3 Mortar Neat Plaster Work m2 124.71 42,427.00 5,291,071.17 0.159
4 Practical Column & Lintel Beam Work
- K250 Concrete m3 0.39 1,226,720.35 473,514.05 0.014
- Reinforcement kg 59.38 16,006.10 950,390.29 0.029
- Formwork m 2
6.43 185,185.00 1,191,356.83 0.036
5 Wall Tiles 25x40cm (Unpolished) m 2
88.54 183,499.80 16,247,439.29 0.488
B Ceiling Installation Work
1 Ceiling Hollow frame m2 64.97 149,919.00 9,739,637.75 0.293
2 6 mm of Calcium Board GRC (Ceiling Interior) M2 16.38 72,230.40 1,183,206.18 0.036
3 6 mm of Calcium Board GRC (Ceiling Exterior) M2 48.59 72,230.40 3,509,313.98 0.105
C Floor Installation Work
1 40x40 cm of Ceramic Tile (Unpolished) Hallway m2 35.80 166,262.80 5,952,041.98 0.179
2 40x40 cm of Ceramic Tile (Unpolished) Rooms m2 15.55 162,962.80 2,534,071.54 0.076
3 Waterproofing Coating + mortar m 2
15.55 119,614.62 1,860,007.28 0.056
D Door and Window Installation Work (complete w. alluminium frame)
Door Allumunium Frame Installation
1 Unit 1.00 2,585,000.00 2,585,000.00 0.078
Work Allumunium
Door (type P4) Difabel
Frame Installation
2 Unit 5.00 2,368,025.00 11,840,125.00 0.356
Work (type P3)
E Sanitary Work and Installation
Sanitary work includes procurement & installation
1 Sitting Closet Unit 1.00 3,699,704.80 3,699,704.80 0.111
2 Squatting Closet Unit 5.00 1,306,646.00 6,533,230.00 0.196
3 Shower spray Unit 1.00 960,355.00 960,355.00 0.029
4 Wastafel hang Unit 5.00 3,723,830.00 18,619,150.00 0.559
5 Floor Drain Unit 6.00 675,235.00 4,051,410.00 0.122
6 Tissue Holder Unit 1.00 585,475.00 585,475.00 0.018
7 Soap Dispenser Unit 3.00 165,275.00 495,825.00 0.015
8 Robe hook Unit 6.00 334,235.00 2,005,410.00 0.060
9 Fibre Basin Unit 5.00 992,670.36 4,963,351.80 0.149
10 5mm; uk 500x700 of mirror work Unit 5.00 126,379.00 631,895.00 0.019
11 Handrail Stainless;Difabel m 1.20 610,995.00 733,194.00 0.022
12 Faucet Unit 6.00 746,652.50 4,479,915.00 0.135
F Painting Works
1 Wall Painting; Interior m2 28.29 40,563.60 1,147,544.24 0.034
2 Wall Painting; Exterior m2 96.42 54,313.60 5,236,917.31 0.157
3 Ceiling Painting; Interior m2 16.38 40,563.60 664,472.33 0.020
4 Ceiling Painting; Exterior m3 48.59 54,313.60 2,638,826.26 0.079
5 Calsiplank Painting m2 11.37 54,313.60 617,437.00 0.019
G Other Works
1 Stair
- Retaining Wall 1 Pc : 5 Ps m2 3.24 139,920.88 453,343.65 0.014
- Landfill for floor elevation m3 0.49 163,075.00 79,254.45 0.002
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.09 912,325.16 82,109.26 0.002
- Chevron Works m 18.00 40,315.00 725,670.00 0.022
- Mortar Plaster Work m2 2.43 67,316.74 163,445.05 0.005
- Mortar Neat Plaster Work m2 2.43 42,427.00 103,012.76 0.003
B.2 ROOF WORKS
A Roof Covering Works
1 Zincalume Spandex H 0,30 mm Installation m2 113.01 171,306.67 19,360,051.63 0.582
2 Light Steel Frame; including rafter and accessoris m2 113.01 213,420.90 24,119,549.59 0.725
3 Aluminium Foil Installation m2 113.01 27,087.50 3,061,266.73 0.092
4 Roof Ridges, Zincalum Spandex m 30.09 73,810.00 2,220,795.28 0.067
5 Calsiplank 30x0,80 cm m 38.50 59,070.00 2,274,195.00 0.068
Total Architectural Cost 193,330,089.03 5.808
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

IX TOILET 6 ROOMS-D1
A PREPARATION WORK
1 Site Measurement and Bowplank Installation m' 29.80 278,630.00 8,303,174.00 0.249
PREPARATION 8,303,174.00 0.249

B ARCHITECTURAL WORKS
B.1 1ST FLOOR
A WALLWORK
1 Brick Wall 1:3 m2 130.24 147,363.92 19,192,676.94 0.577
2 Mortar Plaster Work m2 190.62 67,316.74 12,831,648.47 0.386
3 Mortar Neat Plaster Work m2 190.62 42,427.00 8,087,265.03 0.243
4 Practical Column & Lintel Beam Work
- K250 Concrete m3 0.62 1,226,720.35 761,793.34 0.023
- Reinforcement kg 98.22 16,006.10 1,572,136.05 0.047
- Formwork m2 10.35 185,185.00 1,916,664.75 0.058
5 Wall Tiles 25x40cm (Unpolished) m 2
91.78 183,499.80 16,841,061.14 0.506
B Ceiling Installation Work
1 Ceiling Hollow frame m2 52.57 149,919.00 7,881,841.51 0.237
2 6 mm of Calcium Board GRC (Ceiling Interior) m2 15.33 72,230.40 1,107,147.57 0.033
3 6 mm of Calcium Board GRC (Ceiling Exterior) m2 37.25 72,230.40 2,690,293.48 0.081
C Floor Installation Work
1 40x40 cm of Ceramic Tile (Unpolished) Hallway m2 20.53 166,262.80 3,412,876.50 0.103
2 40x40 cm of Ceramic Tile (Unpolished) Rooms m2 16.99 162,962.80 2,768,900.93 0.083
3 Waterproofing Coating + mortar m2 16.99 119,614.62 2,032,371.94 0.061
D Door and Window Installation Work (complete w. alluminium frame)
1 Door Allumunium Frame Installation Work (type P4) Difabel Unit 1.00 2,585,000.00 2,585,000.00 0.078
2 Door Allumunium Frame Installation Work (type P3) Unit 5.00 2,368,025.00 11,840,125.00 0.356
E Sanitary Work and Installation
Sanitary work includes procurement & installation
1 Sitting Closet Unit 1.00 3,699,704.80 3,699,704.80 0.111
2 Squatting Closet Unit 5.00 1,306,646.00 6,533,230.00 0.196
3 Shower spray Unit 1.00 960,355.00 960,355.00 0.029
4 Wastafel hang Unit 5.00 3,723,830.00 18,619,150.00 0.559
5 Floor Drain Unit 6.00 675,235.00 4,051,410.00 0.122
6 Tissue Holder Unit 1.00 585,475.00 585,475.00 0.018
7 Soap Dispenser Unit 3.00 165,275.00 495,825.00 0.015
8 Robe hook Unit 6.00 334,235.00 2,005,410.00 0.060
9 Fibre Basin Unit 5.00 992,670.36 4,963,351.80 0.149
10 5mm; uk 500x700 of mirror work Unit 5.00 126,379.00 631,895.00 0.019
11 Handrail Stainless;Difabel m 1.20 610,995.00 733,194.00 0.022
12 Faucet Unit 6.00 746,652.50 4,479,915.00 0.135
F Painting Works
1 Wall Painting; Interior m 2
44.21 40,563.60 1,793,195.07 0.054
2 Wall Painting; Exterior m2 146.41 54,313.60 7,951,999.86 0.239
3 Ceiling Painting; Interior m2 15.33 40,563.60 621,758.86 0.019
4 Ceiling Painting; Exterior m3 37.25 54,313.60 2,022,964.35 0.061
5 Calsiplank Painting m2 7.59 54,313.60 412,044.70 0.012
G Other Works
1 Disability Ramp Work
- Disability Handrail Ramp work m 14.10 760,976.98 10,729,014.37 0.322
- Chevron Work m 0.78 40,315.00 31,445.70 0.001
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m 3
20.90 912,325.16 19,063,034.19 0.573
- Retaining Wall Ramp 1 Pc : 5 Ps m2 5.75 139,920.88 803,985.38 0.024
- Landfill for floor elevation m3 1.25 163,075.00 204,332.97 0.006
- Mortar Plaster Work m2 5.76 67,316.74 387,609.81 0.012
- Mortar Neat Plaster Work m2 5.76 42,427.00 244,294.67 0.007
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

2 Stair
- Retaining Wall 1 Pc : 5 Ps m2 3.24 139,920.88 453,343.65 0.014
- Landfill for floor elevation m3 0.49 163,075.00 79,254.45 0.002
- Lean Ramp 1 Pc : 3 Ps : 5 Kr m3 0.09 912,325.16 82,109.26 0.002
- Chevron Works m 6.60 40,315.00 266,079.00 0.008
- Mortar Plaster Work m2 2.43 67,316.74 163,445.05 0.005
- Mortar Neat Plaster Work m2 2.43 42,427.00 103,012.76 0.003
B.2 ROOF WORKS
A Roof Covering Works
1 Zincalume Spandex h 0,30mm Installation m2 65.47 171,306.67 11,215,447.47 0.337
2 Light Steel Frame; including rafter and accessoris m2 65.47 213,420.90 13,972,666.32 0.420
3 Aluminium Foil Installation m2 65.47 27,087.50 1,773,418.63 0.053
4 Calsiplank 30x0,80 cm m 25.29 59,070.00 1,493,762.16 0.045
Total Architectural Cost 217,148,936.92 6.524

C STRUCTURAL WORK
I FOUNDATION WORK
1 Foundation PD1 Broken Stone
- Backfill m2 1.46 62,150.00 90,707.92 0.003
2 Foundation PD2 Broken Stone
- Backfill m3 1.48 62,150.00 91,733.40 0.003
II 1ST LEVEL
1 K1 200x200 Column
- K-250 Concrete m3 1.72 1,077,138.88 1,852,678.87 0.056
- Reinforcement kg 32.45 16,006.10 519,440.10 0.016
- Column Formwork m 2 34.40 275,300.00 9,470,320.00 0.285
2 K2 150x200 Column
- K-250 Concrete m3 0.90 1,077,138.88 972,656.41 0.029
- Reinforcement kg 149.77 16,006.10 2,397,236.67 0.072
-Column Formwork m2 21.07 275,300.00 5,800,571.00 0.174
3 S1 (200x250) Tie Beam
- Concrete K-250 m3 1.37 1,077,138.88 1,474,333.84 0.044
- Reinforcement kg 43.48 16,006.10 695,877.64 0.021
- Tie Beam Formwork m2 13.69 195,085.00 2,670,225.94 0.080
4 S2 (150x200) Tie Beam
- Concrete K-250 m3 0.79 1,077,138.88 851,478.28 0.026
- Reinforcement kg 39.94 16,006.10 639,310.90 0.019
- Tie Beam Formwork m2 10.54 195,085.00 2,056,195.90 0.062
5 B1 (150x200) Beam
- Concrete K-250 m3 1.58 1,077,138.88 1,706,187.98 0.051
- Reinforcement kg 472.93 16,006.10 7,569,753.39 0.227
- Beam Formwork m2 29.04 335,750.00 9,750,180.00 0.293
6 Floor Slab h=12 cm
- Concrete K-250 m3 3.72 1,077,138.88 4,006,067.99 0.120
- Reinforcement kg 352.34 16,006.10 5,639,622.57 0.169
- Floor Formwork m2 3.67 225,800.00 829,137.60 0.025
- Sand Layer t=10cm m3 3.10 183,637.14 569,148.89 0.017
- Base Concrete t=5cm m3 1.55 912,325.16 1,413,790.38 0.042
Total Structural Cost 61,066,655.68 1.835

D. MECHANICAL AND ELECTRICAL WORKS


1 TOILET PLUMBING WORKS
1.1 CLEAN WATER SYSTEM
Procurement and installation of PVC
a. Pipes
Toilet D2 Clean Water Piping and Its Completeness
1 PVC AW Ø 25 mm m 24 33,610.50 806,652.00 0.024
2 PVC AW Ø 20 mm m 2 28,026.63 56,053.25 0.002
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

3 Fitting ls 1 98,931.53 98,931.53 0.003


4 Gate Valve Ø 32 mm Unit 1 126,610.00 126,610.00 0.004
c. Toilet D1 Clean Water Piping and Its Completeness
1 PVC AW Ø 25 mm m 27 33,610.50 907,483.50 0.027
2 PVC AW Ø 20 mm m 2 28,026.63 56,053.25 0.002
3 Fitting ls 1 109,014.68 109,014.68 0.003
4 Gate Valve Ø 32 mm Unit 1 126,610.00 126,610.00 0.004
1.2 VENT AND GREY WATER SYSTEM
Procurement and installation of PVC
a. Pipes
Grey Water Piping and Its completeness in toilet D2 to Sepictank.2
1 PVC-AW Ø 65 mm; WW (Waste Water) m 4 95,628.50 382,514.00 0.011
2 PVC-AW Ø 50 mm; WW (Waste Water) m 5 55,061.88 275,309.38 0.008
3 Floor Clean Out Ø 80 mm, WW ( Waste Water) unit 2 230,725.00 461,450.00 0.014
4 Floor Clean Out Ø 100 mm, SW (Sewage Water) unit 2 340,263.00 680,526.00 0.020
5 Fitting ls 1 179,979.94 179,979.94 0.005
c. Grey Water Piping and Its completeness in toilet D1 to Sepictank.1
1 PVC-AW Ø 100 mm; SW (Sewage Water) m 4 185,950.88 743,803.50 0.022
2 PVC-AW Ø 80 mm; WW (Waste Water) m 20 123,292.13 2,465,842.50 0.074
3 PVC-AW Ø 65 mm; WW (Waste Water) m 4 95,628.50 382,514.00 0.011
4 PVC-AW Ø 50 mm; WW (Waste Water) m 5 55,061.88 275,309.38 0.008
5 Floor Clean Out Ø 80 mm, WW ( Waste Water) unit 2 230,725.00 461,450.00 0.014
6 Floor Clean Out Ø 100 mm, SW (Sewage Water) unit 1 340,263.00 340,263.00 0.010
7 Fitting ls 1 466,918.24 466,918.24 0.014
2 TOILET ELECTRICAL WORKS
2.1 PANEL WORKS
Procurement & Installation
1 MCB BOX Toilet Unit 2 631,939.00 1,263,878.00 0.038
2 NYM 3x2,5 mm² Lamp Installation in 20 mmi conduit pipe m 38 43,081.50 1,637,097.00 0.049
of MCB-BOX from Classroom MCB-BOX to Toilet
2.2 LIGHTING WORKS
Procurement, installation of lighting
A Toilet D2 (6 ROOMS)
Roset Led 5 W Type Bulb (Toilet) unit 10 69,399.00 693,990.00 0.021
Single Electrical Switch unit 2 34,727.00 69,454.00 0.002
Double Electrical Switch unit 4 42,350.00 169,400.00 0.005
Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 10 194,035.42 1,940,354.17 0.058
C Toilet.D1 (6 ROOMS)
Roset Led 5 W Type Bulb (Toilet) unit 10 69,399.00 693,990.00 0.021
Single Electrical Switch unit 2 34,727.00 69,454.00 0.002
Double Electrical Switch unit 4 42,350.00 169,400.00 0.005
Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pipe point 10 194,035.42 1,940,354.17 0.058
2.3 Lightning Rod Installation
Procurement, installation of a complete lightning rod
A Toilet.D2 (6 ROOMS)
1 Ø 3/4 30cm Air Terminal , Completed With Ø 3/4 70cm GIP set 1 442,541.00 442,541.00 0.013
2 BC 25 mm² Cable Installation m 18 75,065.83 1,351,185.00 0.041
3 600mm² x 600mm² c/w Junction Box with Grounding System set 1 948,398.00 948,398.00 0.028
4 Auxiliary Materials lot 1 366,501.21 366,501.21 0.011
C Toilet.D1 (6 ROOMS)
1 Ø 3/4 30cm Air Terminal , Completed With Ø 3/4 70cm GIP set 1 442,541.00 442,541.00 0.013
2 BC 25 mm² Cable Installation m 20 75,065.83 1,501,316.67 0.045
3 600mm² x 600mm² c/w Junction Box with Grounding System set 1 948,398.00 948,398.00 0.028
4 Auxiliary Materials lot 1 366,501.21 366,501.21 0.011
Total Mechanical And Electrical Cost 24,418,041.54 0.734

X SITE PLAN
A SITEPLAN STRUCTURAL WORKS
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

1.1 STRUCTURAL FOUNDATION TOWER WATER TANK


a. Foundation Footplat
- Foundation Cutting m3 1.12 27,610.00 30,812.76 0.001
- Backfill m3 0.73 62,150.00 45,493.80 0.001
- Concrete K-250 m3 0.29 1,226,720.35 353,295.46 0.011
- Reinforcement kg 11.54 16,006.10 184,724.48 0.006
- Formwork m2 1.92 185,185.00 355,555.20 0.011
- Sand layer t=10cm m3 0.07 192,830.00 13,883.76 0.000
- Base Concrete t=5cm m3 0.07 912,325.16 65,687.41 0.002
b. 20/20 Column
- Concrete K-250 m3 0.10 1,226,720.35 117,765.15 0.004
- Reinforcement kg 13.31 16,006.10 213,067.85 0.006
- Formwork Column m2 1.92 275,300.00 528,576.00 0.016
c. 15/20 Tie Beam
- Concrete K-250 m3 0.16 1,226,720.35 191,368.37 0.006
- Reinforcement kg 23.15 16,006.10 370,535.20 0.011
- Tie Beam Formwork m 2 2.08 195,085.00 405,776.80 0.012
Total Site Plan Structural Work Cost 2,876,542.25 0.086

B. SITEPLAN PLUMBING WORKS


1.1 MAIN EQUIPMENTS OF CLEAN WATER SYSTEM
Pipeline procurement and installation
a. include excavation,
CLEAN WATER PUMP accessories, and
auxiliary equipment
1 Type : Jet Pump ls 1 9,729,500.00 9,729,500.00 0.292
Capacity : 35 Lpm
Suction Head : 40 m
Discharge Head : 41 m
Output Power : 1 Kw
Installed complete with WLC (water
b. level control),
Piping from Jetholder,
Pumpsupport
to wateretc.
tank
according to specifications and
1 PVC AW Ø 32 mm
drawing m 56 33,610.50 1,882,188.00 0.057
2 Gate Valve Ø 32mm unit 1 126,610.00 126,610.00 0.004
3 Fitting ls 1 200,879.80 200,879.80 0.006
d. Roof Tank
1 Type : Fibreglass Unit 1 10,671,375.00 10,671,375.00 0.321
2 Capacity : 2 m3
Rooftank work c/w Water Tower 4 meters high
1.2 CLEAN WATER SYSTEM
Procurement and installation of PVC
a. Pipes including
Piping excavation,
and accessories from the Tank to mushola
accessories, and auxiliary equipment
1 PVC AW Ø 40 mm m 4 50,373.13 201,492.50 0.006
2 PVC AW Ø 32 mm m 77 33,610.50 2,588,008.50 0.078
2 Fitting ls 1 292,724.85 292,724.85 0.009
3 Gate Valve Ø 40mm unit 1 137,747.50 137,747.50 0.004
b. Piping and accessories from the Tank to toilet D2
1 PVC AW Ø 40 mm m 4 50,373.13 201,492.50 0.006
2 PVC AW Ø 32 mm m 12 33,610.50 403,326.00 0.012
2 Fitting ls 1 74,256.60 74,256.60 0.002
3 Gate Valve Ø 40mm unit 1 137,747.50 137,747.50 0.004
d. Piping and accessories from the Tank to toilet D1
1 PVC AW Ø 40 mm m 4 50,373.13 201,492.50 0.006
2 PVC AW Ø 32 mm m 29 33,610.50 974,704.50 0.029
2 Fitting ls 1 172,718.70 172,718.70 0.005
3 Gate Valve Ø 40mm unit 4 137,747.50 550,990.00 0.017
VENT AND GREY WATER SYSTEM
1.3 Procurement and installation of PVC
a. PipesWater
Grey including excavation,
Piping toilet D2 to Sepictank.1
accessories, and auxiliary tool
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

1 PVC-AW Ø 100 mm; SW (Sewage Water) m 11 185,950.88 2,045,459.63 0.061


2 PVC-AW Ø 80 mm; WW (Waste Water) m 2 123,292.13 246,584.25 0.007
3 Fitting ls 1 229,204.39 229,204.39 0.007
b. Grey Water Piping toilet D1 to Sepictank.2
1 PVC-AW Ø 100 mm; SW (Sewage Water) m 16 185,950.88 2,975,214.00 0.089
2 PVC-AW Ø 80 mm; WW (Waste Water) m 5 123,292.13 616,460.63 0.019
3 Fitting ls 1 359,167.46 359,167.46 0.011
c. Grey Water Piping mushola to Infiltration
1 PVC-AW Ø 80 mm; WW (Waste Water) m 13 123,292.13 1,602,797.63 0.048
2 Fitting ls 1 160,279.76 160,279.76 0.005
1.4 DRAINAGE PIPE SYSTEM TO INFILTRATION WELL
Procurement and installation of PVC
a. Pipes including
PVC-AW Ø 100excavation,
mm; PAH m 5 0.028
185,950.88 929,754.38
accessories, and auxiliary tool
B. SITE PLAN ELECTRICAL WORKS
B.1 LOW VOLTAGE PANEL WORK
Procurement and installation of Panel
1 School Main Panel unit 1 3,173,775.00 3,173,775.00 0.095
New Installation of PLN
1 Connecting Fee VA 7700 993.33 7,648,666.67 0.230
2 Deposit Money VA 7700 333.33 2,566,666.67 0.077
3 SLO (Certificate of Eligibility for Operation ) (adjusted for rates from SLO consultants) VA 7700 66.67 513,333.33 0.015
B.2 CONNECTOR CABLE PROVISION AND INSTALLATION
The work of procurement, installation
and
Low testing
Voltage Cable ;
1 From Main Panel to MCB-BOX.1, NYY 3 x 4 mm² + BC 6mm² (Classroom 1 room-1) m 15 75,967.83 1,139,517.50 0.034
2 From Main Panel to MCB-BOX.2, NYY 3 x 4 mm² + BC 6mm²(Classroom 1 room-2) m 46 75,967.83 3,494,520.33 0.105
3 From Main Panel to MCB-BOX.3, NYY 3 x 4 mm² + BC 6mm²(Classroom 5 room) m 32 75,967.83 2,430,970.67 0.073
4 From Main Panel to MCB-BOX.4, NYY 3 x 4 mm² + BC 6mm(Mushola) m 68 75,967.83 5,165,812.67 0.155
5 From Main Panel to MCB-BOX.5, NYY 3 x 4 mm² + BC 6mm(Classroom 3 room) m 87 75,967.83 6,609,201.50 0.199
6 From MCB-BOX.1 to Jet Pump, NYY 3 x 4 mm² + BC 6mm² m 62 75,967.83 4,710,005.67 0.142
Total Site Plan Cost 75,164,646.56 2.258

XI SEPTIC TANK N25 WORKS 1


A STP
1 Ground Work
- Backfill m3 21.64 62,150.00 1,345,026.55 0.040
2 (120X120) Column
- K-250 Concrete m3 0.12 1,226,720.35 144,851.14 0.004
- Reinforcement kg 30.76 16,006.10 492,358.63 0.015
- Column Formwork m2 3.94 275,300.00 1,083,580.80 0.033
3 (120X120)Tie Beam
- K-250 Concrete m3 0.08 1,226,720.35 92,210.12 0.003
- Reinforcement kg 19.17 16,006.10 306,882.62 0.009
- Tie Beam Formwork m2 1.25 195,085.00 244,402.49 0.007
4 B1 (120X120) Beam
- K-250 Concrete m3 0.08 1,226,720.35 92,210.12 0.003
- Reinforcement kg 19.17 16,006.10 306,882.62 0.009
- Beam Formwork m2 1.25 282,050.00 353,352.24 0.011
5 B2 (120X120) Beam
- K-250 Concrete m3 0.07 1,226,720.35 81,552.37 0.002
- Reinforcement kg 23.23 16,006.10 371,886.69 0.011
- Beam Formwork m 2 1.11 282,050.00 312,511.40 0.009
6 Wall h=12 cm
- K-250 Concrete m3 1.30 1,226,720.35 1,596,760.54 0.048
- Reinforcement kg 72.51 16,006.10 1,160,547.33 0.035
- Formwork m2 22.22 282,050.00 6,266,361.26 0.188
7 Slab Top h=12cm
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

- K-250 Concrete m3 0.10 1,226,720.35 117,421.67 0.004


- Reinforcement kg 16.80 16,006.10 268,896.48 0.008
- Formwork m2 0.81 295,300.00 239,488.30 0.007
8 Floor Slab h=12 cm
- K-250 Concrete m3 0.22 1,226,720.35 265,707.63 0.008
- Reinforcement kg 16.80 16,006.10 268,896.48 0.008
- Floor Formwork m2 0.68 225,800.00 154,447.20 0.005
- Sand layer t=10cm m3 0.24 192,830.00 46,568.45 0.001
- Base Concrete t=5cm m3 0.12 912,325.16 110,163.26 0.003
- Waterproofing Coating m2 18.22 48,213.00 878,537.29 0.026
Total STP-1 Cost 16,601,503.65 0.499
B Infiltration
- Soil Exavation m3 1.22 105,435.00 128,103.53 0.004
- Brick Wall 1 Pc : 3 Ps m2 5.40 147,363.92 795,765.17 0.024
- Landfill m3 0.48 192,830.00 92,558.40 0.003
- Gravel m3 0.48 429,330.00 206,078.40 0.006
Total Infiltration-1 Cost 1,222,505.49 0.037

XII SEPTIC TANK N25 WORKS 2


A STP
1 Ground Work
- Backfill m3 21.64 62,150.00 1,345,026.55 0.040
2 (120X120) Column
- K-250 Concrete m3 0.12 1,226,720.35 144,851.14 0.004
- Reinforcement kg 30.76 16,006.10 492,358.63 0.015
- Column Formwork m 2 3.94 275,300.00 1,083,580.80 0.033
3 (120X120)Tie Beam
- K-250 Concrete m3 0.08 1,226,720.35 92,210.12 0.003
- Reinforcement kg 19.17 16,006.10 306,882.62 0.009
- Tie Beam Formwork m2 1.25 195,085.00 244,402.49 0.007
4 B1 (120X120) Beam
- K-250 Concrete m3 0.08 1,226,720.35 92,210.12 0.003
- Reinforcement kg 19.17 16,006.10 306,882.62 0.009
- Beam Formwork m2 1.25 282,050.00 353,352.24 0.011
5 B2 (120X120) Beam
- K-250 Concrete m3 0.07 1,226,720.35 81,552.37 0.002
- Reinforcement kg 23.23 16,006.10 371,886.69 0.011
- Beam Formwork m2 1.11 282,050.00 312,511.40 0.009
6 Wall h=12 cm
- K-250 Concrete m3 1.30 1,226,720.35 1,596,760.54 0.048
- Reinforcement kg 72.51 16,006.10 1,160,547.33 0.035
- Formwork m2 22.22 282,050.00 6,266,361.26 0.188
7 Slab Top h=12cm
- K-250 Concrete m3 0.10 1,226,720.35 117,421.67 0.004
- Reinforcement kg 16.80 16,006.10 268,896.48 0.008
- Formwork m2 0.81 295,300.00 239,488.30 0.007
8 Floor Slab h=12 cm
- K-250 Concrete m3 0.22 1,226,720.35 265,707.63 0.008
- Reinforcement kg 16.80 16,006.10 268,896.48 0.008
- Floor Formwork m2 0.68 225,800.00 154,447.20 0.005
- Sand layer t=10cm m3 0.24 192,830.00 46,568.45 0.001
- Base Concrete t=5cm m3 0.12 912,325.16 110,163.26 0.003
- Waterproofing Coating m2 18.22 48,213.00 878,537.29 0.026
Total STP-2 Cost 16,601,503.65 0.499
B Infiltration
- Soil Exavation m3 1.22 105,435.00 128,103.53 0.004
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

- Brick Wall 1 Pc : 3 Ps m2 5.40 147,363.92 795,765.17 0.024


- Landfill m3 0.48 192,830.00 92,558.40 0.003
- Gravel m3 0.48 429,330.00 206,078.40 0.006
Total Infiltration-2 Cost 1,222,505.49 0.037

XIII GUTTERS AROUND THE BUILDING AND INFILTRATION


A Gutters Around the Building
- Soil Exavation m3 44.84 105,435.00 4,728,118.92 0.142
- Brick Wall 1 Pc : 3 Ps m2 226.16 147,363.92 33,328,295.71 1.001
- Sand Layer m3 28.89 192,830.00 5,570,630.20 0.167
- Lean Work 1 Pc : 2 Ps : 3 Kr m3 34.51 912,325.16 31,482,112.42 0.946
- Mortar Plaster Work m2 424.06 67,316.74 28,546,069.19 0.858
- Mortar Neat Plaster Work m2 424.06 42,427.00 17,991,423.91 0.541
Total Gutters Around The Building Cost 121,646,650.35 3.655
B Infiltration
- Soil Exavation m3 4.86 105,435.00 512,414.10 0.015
- Brick Wall 1 Pc : 3 Ps m2 21.60 147,363.92 3,183,060.67 0.096
- Landfill m3 1.92 192,830.00 370,233.60 0.011
- Gravel m3 1.92 429,330.00 824,313.60 0.025
Total Infiltration Cost 4,890,021.97 0.147

XIV CONNECTING CORRIDOR


- Soil Exavation m3 3.05 105,435.00 321,862.48 0.010
- Brick Wall 1 Pc : 5 Ps m2 59.02 139,920.88 8,257,998.81 0.248
- Landfill for floor elevation m3 16.79 163,075.00 2,738,013.76 0.082
- Sand layer m3 1.87 192,830.00 359,733.04 0.011
- Lean Work 1 Pc : 2 Ps : 3 Kr m3 3.09 912,325.16 2,816,009.29 0.085
- Chevron Works m' 44.09 40,315.00 1,777,677.83 0.053
- Mortar Plaster Work m2 38.67 67,316.74 2,602,980.97 0.078
- Mortar Neat Plaster Work m2 38.67 42,427.00 1,640,552.81 0.049
- Canopy (Module 1,4mx3m) Unit 3.00 3,168,440.00 9,505,320.00 0.286
UNTIL LAST WEEK THIS WEEK UNTIL THIS WEEK
NO. WORK DESCRIPTION UNIT VOLUME UNIT PRICE TOTAL PRICE Weight (%)
Volume Physic (%) Weight (%) Volume Physic (%) Weight (%) Volume Physic (%) Weight (%)

- Handrail Corridor Work m 61.84 760,976.98 47,057,294.18 1.414


Total Connecting Corridor Cost 77,077,443.17 2.316
TOTAL 3,328,489,000.00 100.00 2.675 1.224 3.899
Plan 9.099 Realization 3.899 Deviation (5.200)

Acknowledged by ; Approved by ; Submitted by;


UNITED NATIONS DEVELOPMENT PROGRAMME Supervision Consultant Contractor
PT. YODYA KARYA (PERSERO) JV PT. SETIA MULIA ABADI

(Whisnu Yonar Anggono) (Apjelvian Henri) (Ajeng Listianti)


Community Mobilization Officer UNDP PETRA Team Leader Site Manager

You might also like