Professional Documents
Culture Documents
$ Hours
Variable overhead
Bonding department 45,000 30,000
Finishing department 25,000 25,000
Fixed overhead apportioned to this product:
Production $36,000
Selling, distribution and administration $27,000
Required:
1 prime cost
2 marginal cost
KAPLAN PUBLISHING
343
Standard costing
Solution
Direct labour:
Variable overhead:
.•!V.-..\--.,,-
. - ^ The following statement shows budgeted and actual costs for the month
' of October for Department X.
.•':.;:•. -
: . :
Direct materials 150,000 130,000
Direct labour 200,000 189,000
I' - 86 ;
Production overhead
mi
'•'••.:. "-"l-'r
Variable with direct labour 50,000 46,000
Fixed 25,000 29,000
(a)' Calculate the standard cost per unit under absorption costing.
(b) Calculate standard cost per unit under marginal costing.
KAPLAN PUBLISHING
345
Standard costing
3 Safes variances
Introduction
There are two causes of sales variances: a difference in the selling price,
and a difference in the sales volume, giving:
The sales volume variance calculates the effect on profit of the actual sales
volume being different from that budgeted. The effect on profit will differ
depending upon whether a marginal or absorption costing system is being
used.
The Standard Margin equals the Contribution per unit (marginal costing), or
the Profit per unit (absorption costing).
The sales price variance shows the effect on profit of selling at a different
price from that expected.
(Actual Quantity Sold x Actual Price) - (Actual Quantity sold x Budget Price)
••-
Budgeted profit per unit: $205
Required:
CD Solution
if
i:-*v2
Budgeted sales 900 units
imm
t V'f-!"-:
= $24,500 (F) (more sold so higher profit).
••••:'•••
': •:
: i
Hi
$50
Radek Ltd has budgeted sales of 400 units at $2.50 each. The variable
costs are expected to be $1.80 per unit, and there are no fixed costs.
The actual sales were 500 units at $2each and costs were as expected.
Calculate the sales price and sales volume variances (using marginal
costing).
WLtd budgeted sales of 6,500 units but actually sold only 6,000 units. Its
standard cost card is as follows:
Direct materials 25
Direct wages 8
Variable overhead 4
Fixed overhead 18
—WW WW
chapter 14
&;.-:• ;: ;,
The actual selling price for the period was $61.
Calculate the sales price and sales volume variances for the period
(using absorption costing).
There are three different materials variances that you need to know about:
s'.V •••,.•-•'.
>j:m:£
'.'• -''.J
(a) the standard material cost ofthe actual production (flexed budget) and
(b) the actual cost of direct material.
• It can be analysed into two sub-variances: a materials price variance
and a materials usage variance.
A materials price variance analyses whether the company paid more or
less than expected for materials.
Material variances
Direct materials (40 square metres x $5.30 per square metre) $212
Actual results for direct materials in the period: 1,000 units were
produced and 39,000 square metres of material costing $210,600 in
total were used.
Required:
Calculate the materials total, price and usage variances for Product X in
the period.
I'.JI i i p i . ^ i u w i
'_•• : ••:•.
ffj Solution
ProoLThe materials total variance is the sum of the price and usage
variances.i.e. $5,300 (F) + $3,900 (A) = $1,400 (F).
Actual details:
m
m Output 1,000 units
. •••
?/;
m. Material purchased and used 2,200 kg
m
m
m
:.i,r Possible causes of materials variances
i-
KAPLAN PUBLISHING
351
Standard costing
There are three different labour variances that you need to know about:
(a) the standard direct labour cost of the actual production (flexed budget);
and
chapter 14
Direct labour:
Required:
•t m
mm*
• . :
. •••:".
i :.
CD Solution
(a) the standard direct labour cost of the actual production (flexed
budget) $120,000 and
(b) the actual cost of direct labour $131,450.
chapter 14
\m* The labour total variance in the Finishing department is the sum
r-'...C"-.--i.!v
of the rate and efficiency variances, i.e.
(a) the standard direct labour cost of the actual production (flexed
budget) $72,000 and
(b) the actual cost of direct labour $69,750.
•••-•; C-'fli Difference = $(72,000 - 69,750) = $2,250 (F) which is what was
:.•'•'•'--
calculated above.
•s-:;:^:-':;
' ;V:-r-v-'v
-.•-•S.Vi-:
.'•n^.:V-
•:• :;:.V.i;
v •' :^- -J
:•.'•••••;'•:
/•,.:••'..;-•
•V; v:
V '. ^
mm
mm
my&
• • V-.;
••\i-ts
..-;.:; '.;
••'.>: "
•-'':'•
KAPLAN PUBLISHING
355
Standard costing
Roseberry Ltd makes a single product and has the following budgeted
information:
Actual results:
Variable overhead variances are very similar to those for materials and
labour because, like these direct costs, the variable overhead cost also
changes when activity levels change.
KAPLAN PUBLISHING
356
chapter 14
mm ••:•':••
-'-"•'
VARIABLE OVERHEAD TOTAL VARIANCE
• •-.•, ..:*'-
.•-•:•. .•-'.:.v>
It is normally assumed that variable overheads vary with direct labour hours
of input and the variable overhead total variance will therefore be due to cne
of the following:
• • the variable overhead cost per hour was different to that expected (an
expenditure variance)
working more or fewer hours than expected for the actual production (an
efficiency variance)
: v, - •
.
Actual Hours X - Standard Rate } Expenditure Variance
mm
mm
'•?v-: '•
iiv:- -'•;:•>.
•-;/;-::•••:
.,.:'•:.•'
-•:•• •-'•..",-•'
v . •,:•
''••.: • •' •
.::•.-. -^;
••' :-
The following information relates to the production of Product X.
m
Extract from the standard cost card of Product X
Direct labour:
Variable overhead:
Required:
KAPLAN PUBLISHING
358
hS m chapter 14
•:;;«v ';•:•:-.
m
PT^ r
f-Ll Solution
Expenditure $2,390
variance (A)
Actual quantity x Standard
mm.
mm price
l$$5> 23,900 hours x $1.50 $35,850
Efficiency $150 (F)
variance
: ' •
(a) the standard variable overhead of the actual production (flexed
j••;/• budget) $36,000 and
m:~: (b) the actual cost ofthe variable overhead $38,240.
mm,
mm
j.'.-::7 :••;'-:
:•••••.- v,
•r-'-K:'.'
mi
mrnm
KAPLAN PUBLISHING
359
Standard costi
variance
The budgeted output for Carr Ltd for May was 1,000 units of product A
Each unit requires two direct labour hours. Variable overheads are
budgeted at $3/labour hour.
Actual results:
-
KAPLAN PUBLISHING
361
""7 • By definition, actual and expected fixed overheads do not change when
there is a change in the level of activity, consequently many of the
variances calculated are based upon budgets.
• However, the effect on profit depends upon whether a marginal or
absorption costing system is being used.
Fixed overhead variances in a marginal costing system
As you know, marginal costing does not relate fixed overheads to cost units.
There is no under- orover-absorption and thefixed overhead incurred is the
amount shown in the income statement (as a period cost).
• Since fixed overhead costs are fixed, they are not expected to change
when there is a change in the level of activity.
Fixed overhead variances in a marginal costing system are as follows:
Actual Expenditure x