Plant Parameters – Part 1

Request for a Distribution Impact Study

Section 1: General Connection Information


Note: All of the information in “Section 1: General Connection Information” must be
completed in full. Failure to provide complete information may delay the processing of
the study. Any revision of technical information already provided below should be
submitted within three (3) days upon payment of Distribution Impact Study (DIS) fee
otherwise, additional fees will be charged to the account of the Applicant.

Date: 11/04/2021 (mm/dd /yyyy)

DIS Applicant’s Name: EDWARD LIWANAG Signature:____________________

1. Project Name: 747.6 kWp PV POWER PLANT – DENSO PHILIPPINES

2. Project Dates: For New Facilities


Proposed Start of Construction: 08/16/2021 (mm/dd/yyyy)
Target Energization: 02/05/2021 (mm/dd/yyyy)
For Energized Facilities
Date Constructed: __________ (mm/dd/yyyy)
Dated Energized: __________ (mm/dd/yyyy)

3. Project Size: Proposed Total Capacity 747.6kWp / 840kWac (kW)

4. Project Location: City/Town/Province: CANLUBANG, CALAMBA, LAGUNA

*Attach a vicinity map of the project

Distribution Utility Plant Parameters for Embedded Generators DIS Version 14.0 – Part 1 Page 1 of 12
5. Project Information:

Generator Owner* Consultant/Contractor


Company/Person: DENSO PHILIPPINES DENSO SUSTENA, INC.
COORPORATION PHILIPPINES
CORPORATION

Contact Person: EDWARD LIWANAG EDWARD LIWANAG PERRY RYAN


CATABAY

Mailing Address:
UNITY AVENUE, UNITY AVENUE, UNIT 208 VICENTE
CARMELRAY CARMELRAY MADRIGAL BLDG.
INDUSTRIAL PARK, INDUSTRIAL PARK, 6793 AYALA AVENUE,
CALAMBA, LAGUNA CALAMBA, LAGUNA MAKATI CITY

Telephone: (+6349) 549-3030 loc. (+6349) 549-3030 0998 957 7796


2520 loc. 2520
Fax:
E-mail: edward.liwanag.a8a@ edward.liwanag.a8a catabay@sustena.jp
ap.denso.com @ap.denso.com

*Note: The Owner is required to submit a letter authorizing a Third Party DIS Applicant to file and submit
this Plant Parameters in his/her behalf.

Distribution Utility Plant Parameters for Embedded Generators DIS Version 14.0 – Part 1 Page 2 of 12
6. Intent of Generation (check all that applies):

Export of Power only


For Export to Distribution Utility:
Total: ______ kVA ______ kW (initial) Target Date _________
Total: ______ kVA ______ kW (ultimate) Target Date _________
Auxiliary Power to be Drawn (Import) from Distribution Utility:
Total: ______ kVA ______ kW (initial) Target Date _________
Total: ______ kVA ______ kW (ultimate) Target Date _________

Load Displacement only


Installed Load of Applicant:
Total: _3,300__ kVA _3,135_ kW (initial) Target Date _________
Total: _3,300 _ kVA _3,135_ kW (ultimate)Target Date _________
Total Power to be Drawn from Distribution Utility:
Total: _3,300_ kVA _3,135_ kW (initial) Target Date _________
Total: _3,300_ kVA _3,135_ kW (ultimate) Target Date _________

Load Displacement and Export of Power


Installed Load of Applicant:
Total: ______ kVA ______ kW (initial) Target Date _________
Total: ______ kVA ______ kW (ultimate) Target Date _________
For Export to Distribution Utility:
Total: ______ kVA ______ kW (initial) Target Date _________
Total: ______ kVA ______ kW (ultimate) Target Date _________
Total Power to be Drawn (Import) from Distribution Utility:
Total: ______ kVA ______ kW (initial) Target Date _________
Total: ______ kVA ______ kW (ultimate) Target Date _________

7. Project Type:

Wind Turbine Hydraulic Turbine Steam Turbine Solar

Diesel Engine Gas Turbine Fuel Cell Biomass

Co-generation/CHP (Combined Heat & Power) Microgrid

Other (Please Specify) ___________________

8. Generator Facility Type(s):

Generation Facility Voltage: __230___ Volts AC DC

Type: Rotating Generators: Synchronous Induction N/A

Other (Please Specify) _____________

Distribution Utility Plant Parameters for Embedded Generators DIS Version 14.0 – Part 1 Page 3 of 12
Non-Rotating DC generation: Photovoltaic Arrays Fuel Cells Batteries

N/A Other (Please Specify) _______

9. Service Identification Number (SIN), if an existing Distribution Utility Customer:


SIN No. 200396580102__________________

10. Location and Site Plan

Site plan with approximate line routings for connection to nearby Distribution
Utility facilities. The Site Plan include roads (with street names), concession and
lot numbers and nearby power lines. It is preferred to submit a Google Map of the
site with coordinates.

11. Proposed Connection voltage to Distribution Utility’s distribution system:


______230__ V

Section 2: Impact Assessment Information


Note:
(a) It is important that the requesting Generator provide ALL the information
requested below, if applicable. Indicate N/A (Not Applicable) where
appropriate.
(b) In certain circumstances, Distribution Utility may require additional
information to conduct the Impact Assessment. Should this be the case, the
requesting Generator should be duly advised and ready to provide the
additional information.

1. Single Line Diagram (“SLD”):

Provide a SLD of the Applicant’s facilities including the Connection Point to Distribution
Utility’s Distribution System. The diagram/drawing shall indicate the quantities, ratings,
and operating parameters of the following:
 Equipment (e.g. generators, motors, furnaces, power transformers,
emergency/standby systems, back-up generators, circuit breaker, disconnecting
means, remote disconnecting means, etc.)
 Substation bus arrangements and switching facilities
 Conductor ratings from connection point to major loads, transformers and
generators (indicate the type, wire size and estimated lengths)
 Phasing arrangements

Distribution Utility Plant Parameters for Embedded Generators DIS Version 14.0 – Part 1 Page 4 of 12
 For multiple generators, please indicate the bus number or label where each
generator is connected.

2. Generator Facility Fault Contribution for Faults at the Point of Common


Coupling
All values to be at the nominal connection voltage to Distribution Utility’s
Distribution System, i.e. the high voltage side of the Facility Interface (step-up)
transformer.

Maximum Symmetrical (all generators online)


- Three Phase Fault ____21__ kA
- Phase to Phase Fault ____18__ kA
- Single Phase to ground Fault ____2.24 kA

3. Generator Facility Characteristics:

a. Number of generating units: ____1705 PV units_________________________


b. Manufacturer/Type of model No. ________________________________________
c. Rated Capacity of each unit:
Gross : __________ kW _________ kVA
Net : __________ kW _________ kVA

If unit outputs are not identical, please fill additional sheets to provide individual
information.

d. Type of Generating Unit(s): Synchronous Induction

Static Power Converters (SPC)

Other, please specify:_______________________

e. Rated Frequency: 60 Hz

f. Number of phases: One Three

g. For Synchronous Units (please provide on a separate sheet if the units are not
identical):

i) Generation facility voltage: ____ kV


ii) Rated Current: _____ A
iii) Machine model: ______________
iv) Rated Power Factor of generating unit(s): ____ p.u.
v) Power factor operating range. (Specify lag or lead):
from ____ p.u. to ____ p.u.
vi) Sequence Impedances

Distribution Utility Plant Parameters for Embedded Generators DIS Version 14.0 – Part 1 Page 5 of 12
Positive sequence ____ p.u. ___ohms
Negative sequence ____ p.u. ___ohms
Zero sequence ____ p.u. ___ohms
vii) Unsaturated reactances on:________ kVA base, ______ kV base
Direct axis synchronous Reactance, Xd _____ p.u. _____ohms
Direct axis transient Reactance, Xd’ _____ p.u. ______ohms
Direct axis subtransient Reactance, Xd” _____p.u. _____ohms
Quadrature synchronous Reactance, Xq ______ p.u. ______ ohms
Quadrature transient Reactance, Xq’ _____ p.u. ______ohms
Quadrature subtransient Reactance, Xq” _____ p.u. ______ohms
viii) Time Constants:
Direct axis open circuit transient, T’do ______ second
Direct axis open circuit subtransient, T”do ______ second
Quadrature open circuit transient, T’qo ______ second
Quadrature open circuit subtransient, T”qo ______ second
ix) Exciter PT Ratio ________
x) Earth Resistivity ________ ohms-meters
xi) Leakage reactance, XL __ _ p.u. ______ohms
xii) Armature resistance, RA __ _ p.u. ______ohms
xiii) Provide a plot of generator capability curve (MW output vs MVAR)
xiv) Generator Inertia constant (on machine base).
H = ______ kW-sec/kVA(generator only)
H = ______ kW-sec/kVA (generator and turbine)
xv) Ground reactor details, if any:
Solid Ungrounded Impedance: R ______ X ______ ohms

h. For Induction Units:

i) Generation Facility Voltage: ____kV


ii) Rated Current: _____ A
iii) Rated Design power factor: ______ p.u.
iv) Power factor operating range if applicable (specify Lag or Lead): ___p.u
to ____p.u.
v) Unsaturated reactances on:______ kVA base, ______ kV base
Direct Axis synchronous Reactance, Xd ____ p.u.
Direct Axis transient Reactance, Xd’ _____ p.u.
Direct Axis subtransient reactance, Xd” _____ p.u.
vi) Time constants:
Direct axis open circuit transient, T’ _____ second
Direct axis open circuit subtransient, T” _____ second
vii) Actual Power factor at Connection Point (after p.f. correction):
Full Output: _________ p.u.
No Output: _________ p.u.
viii) Generator full reactive power requirements:
Full Output: _________ kVAR

Distribution Utility Plant Parameters for Embedded Generators DIS Version 14.0 – Part 1 Page 6 of 12
No Output: _________ kVAR
ix) Total power correction installed: ________ kVAR
Number of regulating steps: _______
Power factor correction switched per step: ________ kVAR
Power factor correction capacitors are automatically switched off
when generator breaker open: __________
x) Maximum starting inrush current (multiple of full load current): ____ p.u.
xi) Generator inertia constant (on machine base).
H = ______ kW-sec/kVA(generator only)
H = ______ kW-sec/kVA (generator and turbine)
xii) Ground reactor details, if any:
Solid Ungrounded Impedance: R ______ X ______ ohms

i. For Static Power Converters/Inverter type units: (Please provide additional


sheets for multiple models)

i) Manufacturer/Type or Model No.: _HUAWEI_/ SUN2000-100KTL-M1


ii) Technology/Type: Grid Tie Off-Grid
iii) Rated Capacity per unit: __100____kW
iv) Number of units: __6___
v) Efficiency per unit: _98.6__%
vi) Inverter AC output voltage: _480__ volts
vii) Inverter AC output current: _133.7_ Amps
viii) Inverter DC input voltage: _1100_ volts
ix) Inverter DC input current: _40 _ Amps
x) Number of phases: One Three
xi) Inverter output frequency: _60__ Hz
xii) Type of inverter: Self-Commutated Line Commutated
Other (Please Specify) _______

xiii) Inverter type: Central String

xiv) Control scheme: Voltage control Current control


xv) Power source for inverter control circuit:
DC side AC side Both (AC and DC side)
xvi) Total harmonic distortion: _<3__% (Please attach harmonic data
plot/graph)
xvii) Inverter rated power factor: _______ %
xviii) Inverter power factor adjustments range, if applicable (specify lag or lead)
from: _0.8 leading__ p.u. to _0.8 lagging__ p.u.
xix) Are power factor correction capacitors used? No
xx) If yes, total power correction installed: _______ kVAR
xxi) Number of capacitors steps: _______
xxii) Grounding: System Equipment

Distribution Utility Plant Parameters for Embedded Generators DIS Version 14.0 – Part 1 Page 7 of 12
xxiii) Are power factor correction capacitors automatically switched off when
inverter breaker opens?
Yes No
xxiv) Does the inverter have an available surge protection?
Yes No
xxv) Does the inverter have short-circuit shutdown capability?
Yes No
xxvi) Does the inverter have an anti-islanding protection?
Yes No
xxvii) Is the inverter paralleling equipment and/or design pre-certified?
Yes No
xxviii) If yes, to which standard(s), e.g. CSA c22.2 NO. 107.1-01, UL1741:
UL1741
xxix) Maximum inrush current upon inverter start-up (multiple of full-load
current): _1.02_ p.u.
xxx) Is the inverter test certified to comply with the Philippine Grid Code
(PGC) or Philippine Distribution Code (PDC)? If yes, please attached the
test certificate
Yes No

j. PV Panel / Module Data

i) Manufacturer : SHARP
ii) Technology : ______________
iii) Model No. : NU-JD445L
iv) Total Plant Capacity : 747.6 kWp DC
v) Rated Output/Panel : 445 kW
vi) Operating Current : _Amp
vii) Open Circuit Voltage : 49.04_volts
viii) Short Circuit Current : 11.55_Amp
ix) Maximum Power Current : 10.77 Amp
x) Maximum Power Voltage : 41.32 volts
xi) Maximum Power : 445 kW
xii) Number of Units Installed: __1705
xiii) Total PV Array Area : _______________
xiv) Solar Panel Technology
monocrystalline silicon
polycrystalline silicon
thin film
xv) Is there lightning protection system available?

Distribution Utility Plant Parameters for Embedded Generators DIS Version 14.0 – Part 1 Page 8 of 12
Yes No
xvi) For solar rooftop installations, is the facility equipped with a Rapid
Shutdown Device required by the latest Philippine Electrical Code?
Yes No
xvii) Grounding
System Equipment

k. Battery Storage Data

i) Manufacturer : _______________
ii) Battery type : _______________
iii) Power : _______________ kW
iv) Connection Voltage : _______________ volts (AC)
v) Energy : _____________ kWh
vi) Efficiency (charge) : _____________ %
vii) Efficiency (discharge) : _____________ %
viii) Interface Transformer Data:
Number of phases: One Three
Nominal voltage of high voltage winding: ______ kV
Nominal voltage of low voltage winding: _______ kV
Guaranteed Core Loss: ________kW
Guaranteed Full Load Copper Loss: _________kW
Impedances on: _______ kVA base _______ kV base
R: ______ p.u. X: ______ p.u. Tolerance: _______ %

l. Other Information for Wind Farms

i) Please provide the following information for Wind Farms:

a. Rated Wind Speed: _____________ m/sec


b. Cut-in Wind Speed: _____________ m/sec
c. Cut-off Wind Speed: ____________ m/sec
d. Synchronous Speed: _____________rpm
e. Type: fixed speed variable speed
continuous seasonal

4. Interface (Step-Up) Transformer Characteristics:

a. Transformer rating: ______ kVA

Distribution Utility Plant Parameters for Embedded Generators DIS Version 14.0 – Part 1 Page 9 of 12
b. Manufacturer (if known ): _______
c. Rated Frequency: ________ Hz
d. Number of phases: One Three
e. Nominal voltage of high voltage winding: ______ kV
f. Nominal voltage of low voltage winding: _______ kV
g. High voltage winding connection: ________ (Distribution Utility prefers Delta-
connected high voltage winding)
h. Low voltage winding connection: _______ (Distribution Utility prefers Wye-
grounded-connected low voltage winding)
i. Guaranteed Core Loss: ________kW
j. Guaranteed Full Load Copper Loss: _________kW
k. Grounding method of star connected low voltage winding neutral; if applicable
Solid Ungrounded Impedance: R ______ X ______ ohms
l. Impedances on: _______ kVA base _______ kV base
R: ______ p.u. X: ______ p.u. Tolerance: _______ %
l. Sequence Impedances:
positive sequence: __ _ p.u. ______ohms
negative sequence: __ _ p.u. ______ohms
zero sequence: __ _ p.u. ______ohms
m. Information on On-Load Tap Changer:
Number of steps/taps: above nominal tap ______ below nominal tap______
Tap-Changing Operation: (Ganged, Unganged) ___________
Minimum Tap: ________ (volts; p.u.)
Maximum Tap: ________ (volts; p.u.)

5. Intermediate Transformer Characteristics (for ratings 2,000 KVA and above


only), please provide on a separate sheet if the units are not identical:

a. Transformer rating: ______ kVA


b. Manufacturer ( if known ): _______
c. Rated Frequency: ________ Hz
d. Number of phases: One Three
e. Nominal voltage of high voltage winding: ______ kV
f. Nominal voltage of low voltage winding: _______ kV
g. High voltage winding connection: ________
h. Grounding method of star connected high voltage winding neutral; if applicable
Solid Ungrounded Impedance: R ______ X ______ ohms
i. Low voltage winding connection: _________
j. Grounding method of star connected low voltage winding neutral; if applicable
Solid Ungrounded Impedance: R ______ X ______ ohms
k. Impedances on: _______ kVA base _______ kV base
R: ______ p.u. X: ______ p.u. Tolerance: _______ %
l. Sequence Impedances:
positive sequence: __ _ p.u. ______ohms
negative sequence: __ _ p.u. ______ohms

Distribution Utility Plant Parameters for Embedded Generators DIS Version 14.0 – Part 1 Page 10 of 12
zero sequence: __ _ p.u. ______ohms

6. Existing Service Transformer Characteristics (if an existing Distribution Utility


Customer), please provide on a separate sheet if the units are not identical:

a. Transformer rating: 2000 kVA


b. Number of Units : 1
c. Manufacturer (if known): Shihlin Electric & Engineering Corp.
d. Rated Frequency: 60 Hz
e. Number of phases: One Three
f. Nominal voltage of high voltage winding: 4160 kV
g. Nominal voltage of low voltage winding: 220 kV
h. High voltage winding connection: Delta
i. Grounding method of star connected high voltage winding neutral; if applicable
Solid Ungrounded Impedance: R _____ X _____ ohms
j. Low voltage winding connection: Wye
k. Grounding method of star connected low voltage winding neutral; if applicable
Solid Ungrounded Impedance: R _____ X _____ ohms
l. Impedances on: _______ kVA base _______ kV base
R: ______ p.u. X: ______ p.u. Tolerance: ______ %
l. Sequence Impedances:
positive sequence: __ _ p.u. ______ohms
negative sequence: __ _ p.u. ______ohms
zero sequence: __ _ p.u. ______ohms

7. Generator Facility Type(s):

Generation Facility Voltage: _____ Volts AC DC

Type: Rotating Generators: Synchronous Induction N/A

Other (Please Specify) _____________

Non-Rotating DC generation: Photovoltaic Arrays Fuel Cells Batteries

N/A Other (Please Specify) _______

8. Information on Installed Load (for Load Displacement only)

a. Maximum continuous load:


Total: _3,017_ kVA _2,867_ kW (initial) _0.95_ p.f. Year expected _________
Total: _3,017_ kVA _2,867_ kW (ultimate) _0.95 p.f. Year expected _________

b. Maximum start up load: _3,300__ kVA _3,135_ kW

Distribution Utility Plant Parameters for Embedded Generators DIS Version 14.0 – Part 1 Page 11 of 12
c. Motor Loads:
Highest Motor Load _637_Hp
No. of Phases__3___
Voltage __460__ volts
Rated Full Load Current ________amperes
Rated Locked Rotor KVA Code _______ KVA/Hp _______
Service Factor _60%_
Method of Starting ____Inverter___________
Frequency of Starting the Motor __60Hz______
Rated p.f._0.92_ %
Starting p.f.____ %
If started by Variable Frequency Drive (VFD) or Soft Starter, please indicate the
following:
Total Harmonic Distortion (THD)-Voltage_25.1__ %
Total Harmonic Distortion (THD)-Current__5.9_ %
Total Demand Distortion (TDD) ______ %

9. Operation Information:

a. Mode of Plant Operation: Base-Load Peak-Load Off-Peak


For peak or off-peak operation, indicate the number of hours of on-line
operation: _________ hours
Time of operation: ___________ (i.e. 1100H to 1400H)

b. Indicate the means by which injection of power into Distribution Utility’s system will
be prevented during unintentional islanding.
___________________________________

c. Annual capacity factor: ______ %

10. Expected/Actual Hourly Generation, Consumption and Output (Energy and


Demand) from the facility (24-hour period). Please provide this information
using the Table for Plant Parameter Item_Hourly.xls file.

11. Expected/Actual Monthly Generation, Consumption and Output (Energy and


Demand) from the facility (12-month period) for the first year and annually for
the remaining four years. Please provide this information using the Table for
Plant Parameter Item.xls file.

Distribution Utility Plant Parameters for Embedded Generators DIS Version 14.0 – Part 1 Page 12 of 12