NO ITEM PEKERJAAN (Job Description ) PAYMENT VOLUME SATUAN HARGA SATUAN TOTAL

A. PEKERJAAN PERSIAPAN (PREPARATION WORK)


1 PENGURUGAN/PERATAAN LAHAN (LAND EMBROIDERY / LEVELING ) 600 M2 393,496 236,097,877
2 PEMBUATAN AKSES JALAN (CONSTRUCTION OF ACCESS ROAD ) 138 M2 232,211 32,045,097
3 PEKERJAAN BOWPLANK (BOWPLANK WORK ) 171.96 M1 151,006 25,967,036
4 PEK. SEPTICTANK & PERESAPAN (SEPTIC TANK AND ABSTRACT WORK ) 6 TITIK 3,000,000 18,000,000
5 PEK. GROUNDTANK (GROUNDTANK ) UNIT -
6 PEK. LISTRIK PROYEK (ELECTRICITY ) 1 UNIT -

B. BUILDING -

1. STEP PERTAMA (FIRST STEP) -


a. GALIAN PONDASI (FOUNDATION EXCAVATION ) 112.41 M3 114,287 12,847,031
b. GALIAN KOLAM (POOL EXCAVATION ) 75.6 M3 188,379 14,241,435
c. PEK. PONDASI FOOTPLATE (FOOTPLATE FOUNDATION ) 36 TITIK 3,147,698 113,317,124
d. PEK. PONDASI BATU KALI (RIVER STONE FOUNDATION ) 187.35 M1 1,489,535 279,064,386
e. PEK. URUGAN PONDASI (FOUNDATION BURNING ) 103 M3 393,496 40,530,136
f. PEK. SLOOF (SLOOF WORK) 187.35 M1 -
- Bekisting Sloof (Sloof Formwork) I 224.82 M2 158,685 35,675,481
g. - Pembesian Sloof (Sloof Beginning) 131.2 KG 174,416 22,883,331
- Cor Sloof (Cast Sloop) 13.1145 M3 1,447,109 18,978,112
h. PEK. URUGAN SLOOF (SLOOF FILLING WORK) 56.205 M3 299,896 16,855,641
PEK. PLAT GROUND FLOOR (GROUND FLOOR PLATE WORK) 30.9 M3 1,588,952 49,098,601
- Bekisting Plat Lantai (Floor Plate Formwork) -
i.
- Pembesian Plat Lantai (Floor Plate Formwork) -
- Cor Plat Lantai/Rabat Lantai (Cast Floor Plate / Floor Rebate) -
PEK. kolom/tiang GROUND FLOOR (Ground floor column/pole work) 36 TITIK 5,500,000 198,000,000
- Bekisting kolom/tiang (Column/pole formwork) -
j.
- Pembesian kolom/tiang (Column/pole reinforcement) -
- Cor kolom/tiang ground floor (Cast ground floor columns/poles) -
PEK. BALOK & PEK. PLAT FIRST FLOOR (BEAM WORK AND FIRST
-
c. FLOOR PLATE WORK)
- Bekisting Balok first floor (Beam formwork first floor) 295.95 M1 158,685 46,962,719
- Bekisting Plat first floor (formwork first floor plate) 309 M2 158,685 49,033,554
2. STEP KEDUA (SECOND STEP) - -
- Pembesian Balok first floor (Reinforcing ironing first floor) 132.9 174,416 23,179,838
a. - Pembesian Plat first floor (Plate ironing first floor) -
- Cor Balok & Plat first floor (Cast Beams and Plate first floor) -
PEK. BOUNDARY WALL (Boundary Wall Work) -
- Pek. Pondasi (Foundation Work) -
- Pek. Sloof (Sloof Work) -
b.
- Pasang Batako (Install bricks) II -
- Pasang kolom/tiang Praktis & Ring Balok (Install Practical
-
columns/poles and Beam Rings)
PEK. kolom/tiang first floor (first floor column/pole work) -
- Bekisting kolom/tiang first floor (First floor column/pillar formwork) -
c.
- Pembesian kolom/tiang first floor (reinforcing columns or pillars of
-
the first floor)
TOTAL 1,232,777,397