500 Case Study 4 – Execution and Control
Background
The project started on 5-Mar-18 as planned and has been updated at weekly intervals to 23-Apr-18. So far,
Please note: Although Actual Units are automatically calculated based on the Percent Complete of an
activity, you will manually update the Actual Units of some activities below to account for changes in the
project plan.
Objectives
1. Open a project, RENO-4 RENO – Project Execution and Control. In the Activities window, open a
layout, Classic WBS.
a. Activate the Progress Spotlight, and confirm the status updating period, 23-Apr-18 to 30-Apr-
18.
b. On the Status and Resources tabs in Activity Details, update or confirm activity data as
specified in the following table:
3. Next you will update the project for the status period from 30-Apr-18 to 7-May-18. During this
period, it was discovered that vandals had gained access to the work site over the weekend and
caused damage to several floor structures and to the hydraulic equipment being used to repair
them. Work on activity A1120 was suspended to enable an inspection by insurance adjusters
and an investigation by local police. Replacement parts for the damaged hydraulic equipment
were ordered through suppliers.
b. On the Status and Resources tabs in Activity Details, update or confirm activity data as
specified in the following table:
c. The vandalism to the work site must be documented. On the Notebook tab for activity A1120,
add a Notebook topic, Problems Encountered, and type a description <Work site vandalized
during the weekend of April 28/29. Work on A1120 suspended on April 30. New parts
ordered for hydraulic jacks.>.
d. On the Expenses tab, enter a new expense for activity A1120 as specified in the table below:
4. Next you will update the project for the status period 7-May-18 to 14-May-18. During this time,
work resumed on activity A1120.
b. On the Status and Resources tabs in Activity Details, update or confirm activity data as
specified in the following table:
c. On the Notebook tab for activity A1120, update the Problems Encountered topic to reflect that
work resumed on the activity on 10-May-18.
5. Due to the vandalism and the suspension of activity A1120, the project has slipped significantly
behind schedule. You will add a second laborer to the activity, enabling the activity to be
completed in half the time: 5 days instead of 10 days. Show the addition of a second laborer by
doubling the Remaining Units/Time from 8h/d to 16 h/d. This reflects two laborers, each
working 8 h/d.
a. Select activity A1120. On the Status tab in Activity Details, change Remaining Duration to 5d.
When you changed the Remaining Duration to 5 days above, P6 Professional calculated that 10
days of work have already been done: Original Duration (15d) – Remaining Duration (5d) = 10d.
However, in reality, only 5 days of work have been completed.
THESE eKIT MATERIALS ARE FOR YOUR USE IN THIS CLASSROOM ONLY. COPYING eKIT MATERIALS FROM THIS COMPUTER IS STRICTLY PROHIBITED
Case Study 4 – Execution and Control 503
You will manually change values on the Resources tab in Activity Details to reflect the revised
Remaining Duration and the addition of a second laborer.
b. On the Resources tab, customize columns and update resource data as indicated in the table
below:
6. To put the project fully back on schedule, you will make a change to the relationship between two
successors to activity A1120, which were all affected when A1120 was suspended. There is a
Finish to Start relationship between activity A1130 – Install subflooring and its successor,
A1370 – Build new interior non-bearing walls. Instead of waiting for the subflooring to be
completed, however, there should be enough subflooring installed after a couple of days to
begin building the interior walls
a. Select activity A1130. Change the Finish to Start relationship with its successor, A1370, to a
Start to Start relationship with 2 days of lag.
b. Add a Finish to Start relationship between A1130 and its successor, A1280, to close the open
end on A1130.
7. Now that the project is back on track to meet its Must Finish By date, use the Resource Usage
Profile to check the project’s resources for overallocation. (On the Resource Usage Profile left-
pane Display Options bar, click Filter By, Current Project’s Resources and on the right-pane
Display Options bar, click to remove the check mark in front of Show All Projects.)
8. After analyzing the schedule and resources and re-optimizing the project plan, check for the impact
of the changes on the project’s budget.
a. Open a layout, Analyzing the Budget, and add an At Completion Total Cost column to the
layout.