274 Case Study 2 – Scheduling the Project
Objectives
1. Open a project, RENO-2 – RENO Scheduling the Project, and open a layout, Creating
Relationships. Create relationships between activities as indicated in the table below. Some
relationships have already been created for you.
a. Schedule the project with a data date of 05-Mar-18. What is the scheduled Finish date?
THESE eKIT MATERIALS ARE FOR YOUR USE IN THIS CLASSROOM ONLY. COPYING eKIT MATERIALS FROM THIS COMPUTER IS STRICTLY PROHIBITED
Case Study 2 – Scheduling the Project 275
2. The building owner has indicated that she plans to hold a building dedication and ribbon-cutting
ceremony on Wednesday, 25-Jul-2018.
b. Schedule the project with a data date of 05-Mar-18. What is the Total Float on the project?
(You may have to drag the vertical split bar to the right to expose the Total Float column in
3. As time for the project to start draws near, you receive notice from one of your suppliers that, due
to retooling by the manufacturer, the special architectural shingles you ordered will not be
available until 15-Jun-2018. The supplier asks if you would prefer to substitute different
shingles, but you decide to keep the original order intact.
a. Does the constrained activity affect the finish date of the project? If no, why not?