1

UN RESTRICTED

TO Engineering Section, U-8

FROM PER ENG COY

DATE 14 Set 2023


ASSESMENT REPORT - MAINTENANCE AND IMPROVEMENT OF
SUBJECT
ROUTES1 - BOUAR

NATIONS UNIES
UNITED NATIONS
Mission Multidimensionnelle
United Nations Multidimensional
MINUSCA Intégrée des Nations Unies pour la
Integrated stabilization Mission in the
Stabilisation en
Central African Republic
République Centrafricaine

ASSESSMENT REPORT– MAINTENANCE AND IMPROVEMENT OF ROUTES1 -


BOUAR
1. Gen. The works on Route N°1 that extends from Bouar-Maigaro with a distance of
11.5 kilometers, these works facilitate transitability for the minusca force and are also used
for commerce in the region, this work during the date was affected by the rainy season,
which caused a delay in the works, as 8 kilometers of the total route were not repaired, for
which an extension of the deadline for the completion of the works is requested.
Assessment is proffered for extending of route for which is as follows:

RUTA N°1

2. Aim. grass cleaning, leveling, water outlet and formation of the Bouar route.
UN RESTRICTED
2
UN RESTRICTED

3. Existing Dimensions
a. Length - 11.5 km.
b. Width - 6m.
4. Quantum of Work. Following works have been identified as shown in
Annexure A: -
a.Cleaning, removal and disposal of organic material.
b. Extraction and hauling of quarry material.
c. Humidification and scarification of the ground.
d. Leveling of the sub-grade.
e. Conformation of pumping, ditches and superelevations.
f. Compaction of the road surface.

5. Execution Plan. Following option is available to improving and Clearing Grass on


all Sides of Runway.
a. Composition of Manpower for Work
(a) Officers - 01
(b) Junior Commissioned Officer - 13
(c) Security - 02
Total - 16
b. Machinery Required
(a) Road Roller - 2 (Req to be moved from Peruvian camp)
(b) Front loader - 1 (Req to be moved from Peruvian camp)
(c) Motor Grader - 2 (Req to be moved from Peruvian camp)
(d) Dump Truck - 4 (Req to be moved from Peruvian camp)
(e) Wheel tractor - 1 (Req to be moved from Peruvian camp)
(f) Crawler tractor - 1 (Req to be moved from Peruvian camp)
(g) Water tank - 1 (Req to be moved from Peruvian camp)
(h) Utility vehicle - 1 (Req to be moved from Peruvian camp)
c. Engineer Stores Required
(a) Stone ½” - 10 Cft.

d. Fuel Required. (Staff check of diesel is attached at Annexure B).


e. Time required. Approximately 45 working days (depending on weather
conditions, material supply and security availability). Star time: 16 August
2023 and final time: 16 October 2023.
6. Prerequisites
a. It is necessary to have the municipality for the civilian vehicles that travel.
7. Recommendations.
a. Fuel approval should as quickly as possible to continue with the work.
UN RESTRICTED
3
UN RESTRICTED

ANNEXURE - A
TASKS TO PERFORM IN THE ROUTE N° 1

UN RESTRICTED
4
UN RESTRICTED

Annex B
FUEL REQUIRED
Carburant (diesel)
QUANTIT HOUR TOTAL
MECHANICAL EQUIPMENT LTS/H DAYS
Y S (LITERS)
01 Front Loader 20 LT/H 5 HRS 45 4,500 LT
02 Motor Grader 16 LT/H 6 HRS 35 6,220 LT
02 Roller 14 LT/H 5 HRS 30 4,200 LT
04 Dump truck 16 LT/H 7 HRS 45 20,160 LT

01 Wheel Tractor 24 LT/H 6 HRS 30 4,320 LT

01 Crawler Tractor 24 LT/H 7 HRS 35 5,880 LT

01 Water Tank 16 LT/H 5 HRS 45 19,050 LT

01 Low bed truck 16 LT/H 3 HRS 45 2,160 LT

01 Utility vehicle 8 LT/H 3 HRS 45 1,080 LT


TOTAL, LTS 67,570 LTS

Motor oil
CANTIDAD EQUIPMENT TOTAL, LT
01 Bulldozer 90 LT

Grease
CANTIDAD EQUIPMENT TOTAL, LT
01 Bulldozer 180 LT

UN RESTRICTED