Professional Documents
Culture Documents
v010t10a013 omae2020 18784拔桩
v010t10a013 omae2020 18784拔桩
OMAE2020-18784
1
Contact author: p.lehn@tu-braunschweig.de
Modell Set up
The following input parameters were selected for the model
pile and the model soil:
Pile Set-up
The pile set-up takes into account the increase in load
capacity over time. For this preliminary dimensioning, the pile
setup is taken into account with an increase in Fs of 30%. During
the 25-year life cycle of a monopile, it is constantly stressed by
cyclical loads. How these effects influence each other has not yet
been fully demonstrated. In addition, not enough data is available
yet, e.g. from test loads of monopiles after 25 years. It can be
assumed that the increase of pile setup will decrease over time.
The value used must be adjusted to the current state of
knowledge for further, more detailed calculations.
Decom methods
In this paper two concepts of dismantling methods are
presented. On the one hand the dismantling by buoyancy bodies
and on the other hand the dismantling by a press construction. In
the following, execution options are described and roughly
calculated. Further methods such as vibratory extraction, internal
dredging, external jet drilling and decommissioning with
overpressure are described in [21].
This method has some advantages: on the one hand it has a FIGURE 7: STRESS DISTRIBUTION UNDER THE PRESS-
CONSTRUCTION
high flexibility. Furthermore, it can be reused for several
projects. It can be assembled on land and requires just a little
additional work offshore. Smaller boats are sufficient to pull the
pile. The entire construction and the pile are also floatable. 150000
Furthermore, a scour protection on the site has not to be
125000
Additional force [kN]
10
Depth [m]
15
20
25
30
2
35
FIGURE 10: THE PILE IS PUSHED OUT BY PRESSES
FIGURE 9: STRESS ON PILE CAUSED BY A SINGLE LOAD (3,5
m DISTANCE)
The advantages of the design are that any high press forces
can be used and the speed can be easily regulated. The entire
From the calculations results that two additional presses are
construction has very large dimensions. Due to the small stroke
required for the force transfer. A foundation is also required to
of the presses, many individual lifting operations are necessary
transfer the press force into the soil. Deep foundations and
until the pile is completely lifted out, which will take a lot of
heavyweight foundations are excluded as they require additional
time. All in all, this method is to be classified as rather unsuitable
work on site for construction and dismantling. Flat foundations
compared to other decommissioning methods.
offer the advantage of being prefabricated and easy to dismantle.
However, the press force cannot be transferred into the soil
CONCLUSION
through individual flat foundations under each press, as the
In a few years more and more offshore foundations will have
required dimensions are too big. Therefore, a ring-shaped strip
to be dismantled. The currently preferred method, in which a
foundation around the pile is chosen. The press forces should be
large part of the foundation remains in the ground, has some
distributed over the entire foundation area if possible.
disadvantages, such as the fact that the site can no longer be used.
A steel framework construction similar to a jacket has to be
For this reason, research is being carried out on further methods
made for the transfer of force, including further presses which
for dismantling the foundations. In this paper two alternative
brace the structure to the pile.
methods have been shown and roughly calculated for a model
First, the presses on the seabed are extended and the pile is
pile.
pushed out with the height of the stroke. Then the brace on the
The first approach is to use buoyancy bodies which are non-
pile is released and the presses on the seabed are retracted. The
positively connected to the pile by a truss construction.
bracing with the pile is re-established. The process is then
Advantage of this method is that no large installation vessels are
repeated until the pile is completely pushed out of the ground
required. Furthermore, the construction is floating and can be
(Figure 10).
towed to its destination by tugboats. In addition, the construction
can be used for different pile diameters and Ft, as it is modularly
expandable.
The second approach is the possibility to overcome Ft by a
press design. Due to the greater distance between the presses and
the pile, which is required to avoid a sharp increase in the pile
skin friction, and due to the time required for the entire process,
this approach has economic weaknesses compared to other
methods.