MATERIAL INSPECTION REQUEST

Project name : JORDAN SCHOOLS EXPANSION PROJECT MIR No.: Contract No.:13\2019\USAID\JESP\5\7

Project location : IBN ALAMEED Package No. 7 Date:29\05\2021

Contractor : C.G.C

Architectural Structural MEP Testing Others (Specify…)

Inspection Requested at: RIBS (3000) PIECES Time : Date

Location: GROUND SLAB Material Ref. No.:

Item :
Material ready for inspection Time: Date:
Contractor personnel Name Signature Date
Project Manager

Site Engineer

Surveyor

MEP

ENGINEER'S INSPECTION REPORT

A B C D

Approved as Submitted Approved As Noted Revise & Re-submit Rejected


before work proceed
Inspection Carried Out: Time: Date:
Engineer's Comments:

Inspected By Name & Signature

Structural Engineer

MEP Engineer

Architectural Engineer
Name: Signature: Date: