Abstract— Black start in power system basically means restoring need to be tested through carrying out black start exercises.
a generating unit with its auxiliaries supplied by DG set or These exercises apart from validating effectiveness of existing
battery and extending power supply to loads after dead bus black start generators also boost the confidence level of grid
charging and energizing a transmission line to seek loads. This is operators to deal with the crisis during a real black out
the first step in system restoration post a partial or total black
scenario. Therefore it is mandated by the regulators in India to
out in any part of an electrical power grid. In view of growing
complexity in power system with addition of new generation, conduct such exercises twice a year for power system
transmission and distribution network the need for a well-tested reliability [2].
plan for system restoration has gained currency across system
operators round the globe. Going forward, with gradual The black start strategy can be broadly classified into two
development of a mature power market in India the black start categories viz. the ‘bottom-up strategy’ where in a generator is
facility of existing and upcoming generating stations can be black started from a standalone source of power and an island
commoditized and possibly traded as an ancillary service to the is created around that generator by charging some short length
power system users for which each black start capable generator
transmission lines up to a nearest load point followed by
would be required to get its black start capability validated and
certified on a regular basis. Black start mock drills are planned
gradual connection of load; or the ‘top-down strategy’ where
grid restoration exercises carried out by the system operators on start-up power is extended from a surviving sub-system to a
a live power system to test the capability of existing black start nearest generating unit in the area affected during blackout.
sources like hydro / gas turbine generators and validate the This paper describes the system operator experience in
existing grid restoration strategies. These exercises do also play a black start mock drill activities carried out in western grid of
vital role in boosting confidence of the system operators to deal India. Section II gives an insight into the worldwide practices
with a real black out scenario. This paper describes four black on black start. While section III describes the bottom-up
start exercises, various lessons learnt and experience gained approach of black start activity. The black start approach is
during black start exercises carried out at three black start western grid has been explained in section IV. Section V-VIII
capable hydro stations and one black start capable gas turbine comprises of 4 mock drill activity carried out in western
based generating station in Western Regional Power grid of regional black start capable generating station. The experience
India. of all these mock drill activity have been summarized in
section IX.
Keywords— Black Out; Black Start; Islanding; Ancillary II. LITERATURE SURVEY ON WORLDWIDE PRACTICES ON
Services; Restoration. BLACK START
A lot of literatures are available related with various
I. INTRODUCTION
blackout scenarios and black start followed to restore the
The blackout in electrical power system is a condition of system. A method of black start based on VSC-HVDC
total loss of power supply in an area due to failure of (Voltage Source Converter – High Voltage Direct Current) has
associated generation or transmission facilities [1]. It is one of been proposed by Li Li Mingxia Zhou Sheng Li Yinhui Li,
the worst case scenarios for power system operators and all Hunan Inst. of Eng., Xiangtan, [3]. This paper provides an
efforts are made by the operators to restore the system in the analysis on the advantages of VSC-HVDC as black start
least possible time since the overall economic loss due to power source and discusses the control strategies of VSC-
system black out multiplies with every minute delay in HVDC in different operating conditions. Northern Region of
recovery. Restoration of large power grids post black out India has conducted several black start exercises mainly from
requires meticulous planning and coordination among system available hydroelectric power stations at Bhakra(BBMB),
operators. Hence the operators of integrated electrical power Chamera, Bairasiul, Tehri, Jhakri, Salal etc. [4]. They have
grids worldwide devise restoration procedures and validate it followed basically bottom-up approach of restoration during
regularly. The strategy for restoration post a black out depends those exercises.
upon the nature of blackout which may be either a partial
black out where part of from a standalone source of power like Kris Koellner of Salt River Project(SRP), Central Arizona,
a local DG set and energize the transmission system to a USA, Chris Anderson and Roy Moxley of Schweitzer
nearest load point with least reactive support from any Engineering Laboratories(SEL), Inc. have shared their
external source. This capability of the black start sources experience during a black start exercise conducted in an area
30Km 54.00
220 kV Main Bus-I 220/132/33 kV Is-landed operation
F re q u e n c y (H z )
Jaitpura sub-station of ISP unit #5 At 12:15 the first load (0.7MW
160 MVA, 53.00 approx.)connected on 33 kV
220/132 kV Jetpura 10:12:48 hrs : Jetpura bus
ICT-I 132 kV Jetpura Bus 400 kV ISP B/C Is-land Frequency 13:12:37 hrs:
52.00 opened creating Subsystem was
the is-land.The is- synchronized with
LEGEND: 63 MVA,220/33 kV
land collapsed at the main grid
BBL make transforme
400 kV : 51.00 10:13:58 hrs Grid Frequency through 400 kV
at Jetpura
220 kV : B/C at Indore.
132 kV :
33 kV : 50.00
Transformer: Radial Load at Jetpura( feeding BPCL,Rama-
Generator: Phosphate,Dharampuri,Dhaturia,Sanwer) Indore220_Bus-I_Frq(Hz)
49.00
ISP_400 BusA_Frq(Hz)
Fig. 4. Frequency plots during black start exercise at Bargi Fig. 5. Schematic Diagram of the SSP