Professional Documents
Culture Documents
net/publication/241635950
CITATIONS READS
2 128
6 authors, including:
Aditya Das
POSOCO
4 PUBLICATIONS 6 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by S. R. Narasimhan on 30 December 2017.
instead of Nagda (Fig. 2). The schematic diagram of the is- LEGEND:
Rama Phosphate
400 kV :
land is given in Fig. 1. The transmission and distribution 220 kV :
Dharampuri
132 kV :
operators involved in the black start exercise were kept in
Dhaturia
33 kV :
Sanwer
BPCL
Transformer:
started unit
Indira Sagar Island 400/220 kV
during Black Start Main Bus-B Indira Sagar
North Zone-I&II Ujjain-I&II Depalpur-I&II
Mock Drill Substation(ISP)
Is-landed operation
53.00
of ISP unit #5 At 12:15 the first load (0.7MW
approx.)connected on 33 kV
to test include the ability of switch gear to charge dead bus,
10:12:48 hrs : Jetpura bus
52.00
400 kV ISP B/C
opened creating
Is-land Frequency 13:12:37 hrs:
Subsystem was
healthiness of bus coupler breakers, capability of reactive
the is-land.The is-
land collapsed at
synchronized with
the main grid
resources (line reactor etc.), flexibility available in protection
51.00 10:13:58 hrs Grid Frequency through 400 kV
B/C at Indore. systems in terms of operating at other than normal settings for
50.00 a temporary period, healthiness of synchronizing facilities
49.00
Indore220_Bus-I_Frq(Hz)
ISP_400 BusA_Frq(Hz)
available at important substations etc.
48.00
Total duration of 220 kV bus dead at During the exercise it was observed that the restoration of
Jetpura on account of mock exercise
was from 10:15 to 11:52 [1hr & 27mins]
Time(hh:mm:ss)
power supply at Jetpura post the blackout took almost two
47.00
:0
0 00 00 :0
0
:0
0 0 0 00 00 00 00 0 0
hours. This helped in identifying the constraints that need to be
00 0: 0: 30 00 0: 0: 0: 0: 0: 0:
9: 9 :3
10
:0
10
:
11
:
11
:3
12
:0
12
:3
13
:0
13
:3
14
:0
removed to expedite the restoration process in real time. One
of the reason for longer restoration time was the apprehension
Fig. 4. Frequency plots during black start exercise at ISP. of tripping and collapse of the is-land on high voltage during
energization for which the 400 kV system was energized at
The generator took 24 minutes to start with local DG set
very lower level (160 kV approximately) and the voltages
after its auxiliary supply from the grid was cut-off. It took 16
were raised close to nominal levels just before connection of
minutes to check-synchronize the 400kV bus coupler at Indore
load at 33 kV Jetpura bus. Since a 50 MVAR, L/R was
S/S and thus integrate the is-land with rest of the grid after
available for the 400kV ISP-Indore line at Indore S/S, later it
instruction for the same was passed from WRLDC.
was felt that the restoration time could be considerably
reduced if the 400 kV system was charged in the range of 360-
10:13:58 hrs : The is-
land collapsed due to
Indore_Bus-I_Voltage(400kV) 370 kV. The SCADA / EMS facilities, the healthiness of
Voltage(kV)
110
VI. CONCLUSION
Time(hh:mm:ss) Blackout in real time power grid is the worst kind of
10
contingency and brings new surprises every time it occurs.
0
00
00
00
00
00
00
00
00
00
:0
:0
0:
0:
0:
0:
0:
0:
0:
0:
00
30
:0
:3
:0
:3
:0
:3
:0
:3
:0
9:
9:
10
10
11
11
12
12
13
13
14
VIII. BIOGRAPHIES