FIDIC DM etc Nakheel DCA Yours

Notices :-
EOT (44.2) 28 28 7 7 ?

(12.2)
Costs (53.1) 28 28 7 7 ?
Varied (52.2)
Rates/Prices 14 14 14 14 ?
Detailed Particulars :-
EOT (44.2) 28+ 28+ 21 28 ?
(44.3) 28 28 28 14 ?

(12.2)
(12.2)
Costs (53.3) 28+ 28+ 28+ 28+ ?
If the requirement is not complied with
Green Contractor doesn’t lose right (not condition precedent)
Black Engineer is prevented from determining
Blue Contractor may lose part of the entitlement
Pink Valuation may be at BOQ rates/prices
Red Contractor is likely to lose the right