You are on page 1of 2

Al Naboodah MEP & Engineering Group (AMEG)

Integrated Management System (IMS)


Propasals Form Pricing Sheet
Material Mandays
Sl.No Description Points Avearge Cabling PVC Conduit GI Conduit Cabling PVC Conduit GI Conduit Remarks

Total no of Points - 41090


Total no of DDC - 822 (Considered @ avg for every 50 points)
Points as per : Supplier & Make -

Field Devices

1 PVC Conduits (FCU, MSFD, KEF etc.) 28,763 5 345,156 345,156 1,726 5,992

GI Conduits (AHU, FAHU, Heat Exc,


2 LV Room, Pump Room, Elec Room, 12,327 5 147,924 862,890 740 10,273
SEF etc. )

DDC

DDC Looping Cable 112.00 25 14,000 6,720 28 117

Total Material & Labour 1,721,846 18,875

2551-Proposed Media City Hotel 1of2


Al Naboodah MEP & Engineering Group (AMEG)
Integrated Management System (IMS)
Propasals Form Pricing Sheet
Material Mandays
Sl.No Description Points Avearge Cabling PVC Conduit GI Conduit Cabling PVC Conduit GI Conduit Remarks

Total no of Points - 41090


Total no of DDC - 822 (Considered @ avg for every 50 points)
Points as per : Supplier & Make -

Field Devices

1 PVC Conduits (FCU, MSFD, KEF etc.) 8,363 5 100,350 100,350 502 1,742

GI Conduits (AHU, FAHU, Heat Exc,


2 LV Room, Pump Room, Elec Room, 8,363 5 100,350 585,375 502 6,969
SEF etc. )

3 GI Conduits (FCU, DERV units. ) 24,365 3 243,650 1,023,330 1,462 12,183

DDC

DDC Looping Cable 112.00 25 14,000 6,720 28 117

Total Material & Labour 2,174,125 23,504

2551-Proposed Media City Hotel 2of2