GANTT CHART

PERT/CPM
ACTIVITY TASK DURATION ( WEEKS)
PREDECESSORS
A PLANNING 2 ~
B MOBILATION 1 A
C EARTHWORK 2 B
D STRUCTURAL 4 C
E ARCHITECTURAL 6 D
F PLUMBING 3 E
G ELECTRICAL 2 F
H CLOSEOUT 1 G

2 1 2 4 6
A B C D E

3
F
2
G H

1
PDM
0 A 2 2 B 3 3
0 2 2 2 1 3 3
C 5 5 D 9 9 E 15
2 5 5 4 9 9 6 15

9 F 12
14 3 17
15 G 17
15 2 17
17 H 18
17 1 18