RQG 237 ASSIGNMENT

MEASUREMENT II
SEMESTER I
ACADEMIC SESSION 20/21

TITLE: EARTHWORK
LECTURER: Associate Professor Dr NAZIRAH ZAINUL ABIDIN
DUE DATE: 27 NOVEMBER 2020

NO. NAME MATRIC NO.

1. MUHAMMAD AZIM BIN MOHD ASRI 147759

2. MUHAMMAD ILHAM BIN IZARUDIN 145861

0
1) DETERMINE CUT AND FILL LINE

Grid no. Diagram Calculation Distance from


lowest point
D2-D3 𝑋 20
0.2
= 0.6
(75.0 – 75.6) 75.2
0.2 0.6 20 𝑋 0.2 X is 6.67 from D2
X= = 6.67
20 0.6

D1-E1 𝑋 20
=
0.5 1.9
(74.7 – 76.6)
20 0.5 75.20 20 𝑋 0.5 X is 5.26 from D1
X= 1.9
= 5.26
1.9
D2-E2 𝑋 20
0.2
= 2.0
(75.0 – 77.0)
20 0.2 20 𝑋 0.2 X is 2.00 from D2
75.20
X= = 2.00
2.0
2

C3-D3 𝑋 20
0.9
= 1.3
(74.3 – 75.6)
20 0.9 75.20 20 𝑋 0.9 X is 13.85 from C3
X= 1.3
= 13.85
1.3
C4-D4 𝑋 20
0.7
= 1.2
(74.5 – 75.7)
20 𝑋 0.7 X is 11.67 from C4
20 0.7 75.20 X= 1.2
= 11.67

1.2
C5-D5 𝑋 20
0.6
= 1.3
(74.6 – 75.7)
20 0.6 75.20 20 𝑋 0.6 X is 9.23 m from C5
X= 1.3
= 9.23

1.3
C6-D6 𝑋 20
0.8
= 1.3
(74.4 – 75.6)
20 0.8 75.2 20 𝑋 0.8 X is 12.31 from C6
X= 1.3
= 12.31
1.3

1
i. FILL CALCULATION FOR PERFECT SQUARE USING WEIGHTAGE METHOD
a) Schedule of perfect square for fill area (weightage method)
b) 11 perfect square

Grid Point Commence on Height ( Finish – 75.20) Weightage Height x Weight


surface
1 2.70
A1 72.50 75.20 – 72.50 = 2.70
2 4.40
A2 73.00 75.20 – 73.00 = 2.20
2 4.80
A3 72.80 75.20 – 72.80 = 2.40
2 4.80
A4 72.80 75.20 – 72.80 = 2.40
2 4.80
A5 72.80 75.20 – 72.80 = 2.40
1 2.70
A6 72.50 75.20 – 72.50 = 2.70
2 4.80
B1 72.80 75.20 – 72.80 = 2.40
4 7.60
B2 73.30 75.20 – 73.30 = 1.90
4 7.60
B3 73.30 75.20 – 73.30 = 1.90
4 8.00
B4 73.20 75.20 – 73.20 = 2.00
4 8.80
B5 73.00 75.20 – 73.00 = 2.20
2 4.00
B6 73.20 75.20 – 73.20 = 2.00
2 3.80
C1 73.30 75.20 – 73.30 = 1.90
3 4.50
C2 73.70 75.20 – 73.70 = 1.50
2 1.80
C3 74.30 75.20 – 74.30 = 0.90
2 1.40
C4 74.50 75.20 – 74.50 = 0.70
2 1.20
C5 74.60 75.20 – 74.60 = 0.60
1 0.80
C6 74.40 75.20 – 74.40 = 0.80
1 0.50
D1 74.70 75.20 – 74.70 = 0.50
D2 75.00 75.20 – 75.00 = 0.20 1 0.20

2
TOTAL: 44 79.20

VOLUME OF PERFECT SQUARE TO FILL = (79.20/44) x 20 x 20 x 11


= 7920 m3

i. FILL CALCULATION FOR UN-PERFECT SQUARE


a) Schedule for un-perfect square
b) 6 un perfect square

Grid No. Diagram Height Volume

20
74.7+ 75.0+75.2+75.2 ½ (2.00 + 5.26) x 20 x 0.175
2.0 =
5.26 4
0
D1-D2- =75.20 – 75.025 = 12.705
1*-21*
= 0.175

75.2+ 75.2+75.0
= = ½ x 20 x 2.00 x 0.067
3
D2-2*-D*
2.0
=75.13 =1.34

=75.2 – 75.13= 0.067

3
73.7+ 74.3+75.2+75.2+95.0
= a) 20 x 13.85 x 0.52 = 144.04
5
20 b)1/2 x (20 + 6.67) x 6.15 x
=74.68
0.52 = 42.64533
13.85 13.85 =75.20 – 74.68= 0.52
D2-D*- =144.04 + 42.64533
3*-C*- =186.68533
C2
6.15

6.67

½ x ( 11.67 + 13.85) x 20 x
74.3+ 74.5+75.2+75.2
= 0.4
20 4
=74.80
=102.08
C3-C4- 11.67
13.85 =75.20- 74.80
4*-3*
=0.4

74.5+ 74.6+75.2+75.2
= 1/2 x ( 11.67 + 13.85 ) x 20 x
4
0.4 x 0.325
20 =74.875
=67.925
C4-C5- 11.67 9.23 =75.20 – 74.875
4*-5* =0.325

4
74.6+ 74.4+75.2+75.2
= 1/2 x ( 12.31 + 9.23 ) x 20 x
4
0.325
20 =74.85
= 75.39
9.23 =75.20- 74.85
C5-C6- =0.35
5*-6* 12.31

Total Volume of Un-Perfect Square to Fill : =446.125 m3

5
ii. SLOPE @ FILL FOR BOUNDARY LINE

Perimeter: 100 + 60 + 40 + 12.31 +5.26


=217.57m

Commencing level =
(75.2 + 74.7 + 73.3 + 72.8 + 72.5 + 73.0 + 72.8 + 72.8 +
72.8 + 72.5 + 73.2 + 74.4 + 75.2)
13
=73.480

Average level :75.20 – 73.480 =

=17.23

Form of slope 2:1 at the edge


1=1.723 of the boundary line

2=3.44

Volume: ½ x 215.57 x 1.72 x 3.44 = 637.742288 m3

TOTAL OF FILL
i) Total volume perfect square = 7920 m3

ii) Total volume unperfect square = 446.125 m3

iii) Total volume fill for slope = 637.742 m3

TOTAL VOLUME TO FILL = 9003.867 m3

6
i. CUT CALCULATION FOR PERFECT SQUARE USING WEIGHTAGE METHOD
c) Schedule of perfect square for cut area (weightage method)
d) 8 perfect square

Grid Point Commence Height (Finish – 75.20) Weightage Height x weight


Surface

D3 75.60 75.60 - 75.20 = 0.40 1 0.40

D4 75.70 75.70 - 75.20 = 0.50 2 1.00

D5 75.90 75.90 – 75.20 = 0.70 2 1.40

D6 75.70 75.70 – 75.20 = 0.50 1 0.50

E1 76.60 76.60 – 75.20 = 1.40 1 1.40

E2 77.00 77.00 – 75.20 = 1.80 2 3.60

E3 77.40 77.40 – 75.20 = 2.20 3 6.60

E4 77.70 77.70 – 75.20 = 2.50 4 10.00

E5 77.80 77.80 – 75.20 = 2.60 4 10.40

E6 77.60 77.60 – 75.20 = 2.40 2 4.80

F1 79.40 79.40 – 75.20 = 4.20 1 4.20

F2 79.40 79.40 – 75.20 = 4.20 2 8.40

F3 79.60 79.60 – 75.20 = 4.40 2 8.80

F4 79.90 79.90 – 75.20 = 4.70 2 9.40

F5 80.40 80.40 – 75.20 = 5.20 2 10.40

F6 79.80 79.80 – 75.20 = 4.60 1 4.60


TOTAL: 32 85.90

Total Volume of Perfect Square to Cut: (85.90 / 32) x 20 x 20 x 8


= 8590 m3

7
ii. CUT CALCULATION FOR UN-PERFECT SQUARE
c) Schedule for un-perfect square
d) 6 un perfect square

Grid No. Diagram Height Volume

(75.2+75.2+76.6+77.0) /4 1/2 x (18+14.74) x 20 x 0.80


1*- 2*- 18
E1- E2 14.74 = 76.00 – 75.20 = 261.92
= 0.80

20

13.33
2 (75.2+75.2+75.6+77.4 ½ x (13.33+20) x 2 x 0.88
2*-D*-D3 +77.0) / 5
-E2-E3 = 29.3304
= 76.08 – 75.2
18 20 x 18 x 0.88
= 0.88
= 316.80

29.3304 + 316.80
20
= 346.1304

(75.2+75.2+75.6) / 3 ½ x 13.33 x 6.15 x 0.13

= 75.33 – 75.20 = 5.329


D*-D3-3*
6.15 = 0.13

13.33

8
3*-4*- (75.2+75.2+75.6+75.7) /4 ½ x (8.33+6.15) x 20 x 0.225
D3- D4 8.33
6.15 =75.425 – 75.20 = 32.58
= 0.225

20

(75.2+75.2+75.9+75.7) / 4 ½ X (8.33+10.77) x 20 x 0.30

4*-5*- = 75.5 – 75.2 = 57.30


D4-D5 10.77 = 0.30
8.33

20

(75.2+75.2+75.9+75.7) / 4 ½ x (10.77 + 7.69) x 20 x 0.3

5*-6*- = 75.5 – 75.2 = 55.38


D5-D6 = 0.3
10.77 7.69

20

Total Volume of Un-Perfect Square to Cut : =758.640 m3

9
iii. SLOPE @ CUT FOR BOUNDARY LINE

Perimeter: 100 + 40 + 20 + 14.74 + 7.69


= 182.43 m

Commencing Level: (79.4+79.4+79.6+79.9+80.4+79.8+77.6+75.7+75.2+76.6+75.2)


11
= 78.073
Average Level: 78.073- 75.20
= 2.873

Volume= ½ x 182.43 x 2.873 x 5.746 = 1505.801 m3

2.873 Form of slope 2:1 at the edge of the boundary line


5.746

TOTAL OF CUT

i. Total Volume of Perfect Square to Cut = 8590 m3


ii. Total Volume of Un-Perfect Square to Cut =758.640 m3
iii. Total Volume of Cut for Slope = 1505.801 m3

TOTAL VOLUME OF CUT: =10,854.441 m3

10
2) TOTAL OF CUT TO DISPOSE

i. Total volume of cut = 10,854.441 m3


ii. Total volume of fill = 9003.867 m3
iii. Balance (to dispose) = 1850.574 m3

Filing (general area) = (7920 + 446.125) = 8366.125 m3

Filing (Slope / embankment) = 637.742 m3

11
3) TRANSFER AMOUNT TO TAKING OFF PAPER

(Cut is more than fill)

F 121
9003.87 Excavation, cut to gill , earth max depth exceeding
1.00 3.00m from commencing surface
1.00 ( F5: 80.4 – 75.2 = 5.2)

9003.87

F 131
1850.58
Excavation, cut to dispose, earth max depth exceeding
1.00
3.00 from commencing surface
1.00

1850.58

8366.13 F 311
1.00 Filing, general, excavated material
1.00
8366.13

F 321
637.74 Filing, embankment, excavated material
1.00
1.00

637.74

12
13