You are on page 1of 29

International

Project Management
Dr. Thomas Grisham
www.thomasgrisham.com

NOTE: Photos have been omitted respecting copyright restrictions, but


suggested locations for graphics are shown.

©2009 Dr. Thomas Grisham www.thomasgrisham.com 1


Introduction

Chapters
– 1 Introduction
– 2 Framework
– 3 Project Basics
– 4 Leading Diversity (HR & Communications)
– 5 Integration Management
– 6 Scope Management
– 7 Cost & Progress Management
– 8 Risk Management
– 9 Time Management
– 10 Quality Management – Customer Satisfaction
– 11 Procurement Management
– 12 CPE’S In the Future
(Collaborative Project Environment)

©2009 Dr. Thomas Grisham www.thomasgrisham.com 2


Introduction

• International project management is


the leadership of projects conducted in
multiple countries and cultures

Photo

©2009 Dr. Thomas Grisham www.thomasgrisham.com 3


Introduction

• International business and project


management practice have converged:
– The need for leaner and flatter
organizations
– The need for leadership skills throughout
the organizational food-chain
– The need for knowledge workers
– Globalization, need to improve quality
while reducing cost
– Kaizen
– Diversity
©2009 Dr. Thomas Grisham www.thomasgrisham.com 4
Introduction

Chapters
– 1 Introduction
– 2 Framework
– 3 Project Basics
– 4 Leading Diversity (HR & Communications)
– 5 Integration Management
– 6 Scope Management
– 7 Cost & Progress Management
– 8 Risk Management
– 9 Time Management
– 10 Quality Management – Customer Satisfaction
– 11 Procurement Management
– 12 CPE’S In the Future

©2009 Dr. Thomas Grisham www.thomasgrisham.com 5


Introduction

Scope Management
– 6.1 Developing a Project Scope
– 6.2 Developing a WBS
• 6.2.1 Step 1 – Organizational WBS
• 6.2.2 Step 2 – Value Chain WBS
• 6.2.3 Step 3 – Partner WBS
• 6.2.4 Step 4 – CPE WBS
– 6.3 Scope Change Control

©2009 Dr. Thomas Grisham www.thomasgrisham.com 6


6.1 Developing a Project Scope - Specifications

Level of
Detail & Cost

Technical
Equal-to
Performance

©2009 Dr. Thomas Grisham www.thomasgrisham.com 7


Figure 28 – Developing Scope

High Negotiated Bid


Performance Spec
Cost Reimbursable

Blended Bid
Equal -to Spec
Incentives
Risk To Customer
Competitive Bid
Technical Spec
Fixed Price
Low

Low High

Participation Of Customer

Go Green
©2009 Dr. Thomas Grisham www.thomasgrisham.com 8
Figure 29 – CPE WBS

Mumbai London All Together


Customer
(Buyer/Seller)
User
(Buyer)
a CPE
- Sponsor
- Project Manager
- Sponsor
- Project Manager
In this Book
- Stakeholders - Stakeholders

Mumbai New York


Service Provider A Service Provider B
(Seller/Buyer) (Seller/Buyer)
Alliance
- Lead Sponsor Partnership - Sponsor
- Lead Project Manager Joint Venture - Project Manager
- Stakeholders Consortium - Stakeholders

SupplyChain
Value ChainA.1
A.1 SupplyChain
Value ChainA.2
A.2 SupplyChain
Value ChainB.1
B.1 SupplyChain
Value ChainB.2
B.2
(Seller/Buyer) (Seller/Buyer) (Seller/Buyer) (Seller/Buyer)
One Participant
- Sponsor - Sponsor - Sponsor - Sponsor
- Project Manager - Project Manager - Project Manager - Project Manager A Project According to
- Stakeholders - Stakeholders
- Stakeholders - Stakeholders IPMA, PRINCE2, PMI, APM
Bangalore Beijing Kuala Lumpur St. Petersburg

Text

©2009 Dr. Thomas Grisham www.thomasgrisham.com 9


6.2 Developing a WBS

Creating a CPE WBS


– All key organizations
– Collaborative
– Open and honest
– Mutual respect
– May be iterative

CPE collaborative project enterprise

Practice XLQ
©2009 Dr. Thomas Grisham www.thomasgrisham.com 10
6.2 Developing a WBS

Work package
– Lowest level detail of WBS
– Lowest level of activity in schedule
– One-for-one with chart of account
– Duration not longer than a month
– Duration not shorter than a week

Not Too Much Detail


©2009 Dr. Thomas Grisham www.thomasgrisham.com 11
Figure 30 - WBS & Chart of Accounts

Project WBS

Project Level 1

Software Hardware Level 2

Engineering Manufacturing Testing Level 3

Computer Router Phones Text Level 4


Vilnius
Chart of Accounts

Engineering
Organization

London

Design

Manufacture Work Package


&
Cost Account
Testing
Tokyo

PMO

©2009 Dr. Thomas Grisham www.thomasgrisham.com 12


6.2 Developing a WBS

Program Evaluation Review Technique


PERT

Best Case + (4 x Most Likely Case) + Worst Case


6

Reduces Bias
©2009 Dr. Thomas Grisham www.thomasgrisham.com 13
Step 1 – Your organization

Mumbai London
Customer User
(Buyer/Seller) (Buyer)
- Sponsor - Sponsor
- Project Manager - Project Manager
- Stakeholders - Stakeholders

Mumbai New York


Service Provider A Service Provider B
(Seller/Buyer) (Seller/Buyer)
Alliance
- Lead Sponsor Partnership - Sponsor
- Lead Project Manager Joint Venture - Project Manager
- Stakeholders Consortium - Stakeholders

SupplyChain
Value ChainA.1
A.1 SupplyChain
Value ChainA.2
A.2 SupplyChain
Value ChainB.1
B.1 SupplyChain
Value ChainB.2
B.2
(Seller/Buyer) (Seller/Buyer) (Seller/Buyer) (Seller/Buyer)
- Sponsor - Sponsor - Sponsor - Sponsor
- Project Manager - Project Manager - Project Manager - Project Manager
- Stakeholders - Stakeholders - Stakeholders - Stakeholders
Bangalore Beijing Kuala Lumpur St. Petersburg

You’re the lead project manager

©2009 Dr. Thomas Grisham www.thomasgrisham.com 14


Figure 31 - Organizational WBS (first section)
WBS Dictionary

Amount Office,
from from Analagous or Brainstorm # of people management,
corporate PMO Bottom-up or Top/down Resources PERT calc'd are paid support, etc. calc'd

Corporate Hours Best Most Worst PERT Base Burdened


Chart of # of per Case Likely Case Work Person Hourly Overhead & Personnel
Accounts WBS # Work Packages People Day Days Days Days Days Hours Rate Profit Factor Cost
$ 100 3.10

Joint Planning Meeting


07.01.03.01 01.01.10 (Service Provider A) 8.0 8.0 2.0 3.0 5.0 3.2 203 $100 3.10 $ 62,827

01.01.20 Medical Mentoring 10.0 4.0 20.0 35.0 60.0 36.7 1,467 $100 3.10 $ 454,667
SC.A.1 - Medical Training
01.30.10 Facilities & Documents - - $100 3.10 $ -
SC.A.1 - Prepare Medical
01.30.11 Training Documents - - $100 3.10 $ -

02.01.10 Deliver Drugs to Hospitals - - $100 3.10 $ -


- - $100 3.10 $ -
- - $100 3.10 $ -

Acceleration (Risk of
07.01.03.02 01.01.90 Liquidated Damages) - - $100 3.10 $ -
- - $100 3.10 $ -
Subtotals 1,669 $ 517,493
Project BAC
Contingency Reserves

©2009 Dr. Thomas Grisham www.thomasgrisham.com 15


Figure 32 - Organizational WBS (second section)

WBS Dictionary
Amount to
Cost for cover
material, estimate
equipment, being less
from from Analagous or Brainstorm subcontractors, than 100% from risk from Chart
corporate PMO Bottom-up or Top/down vendors, travel accurate register calc'd of Acounts

Corporate Total
Chart of Contingency Budgeted
Accounts WBS # Work Packages Fixed Cost Amount Risk Fund Cost Actual Cost
80%

Joint Planning Meeting


07.01.03.01 01.01.10 (Service Provider A) $ 4,750 $ 13,515 $ - $ 81,092 $ 84,000

$ - $ -
$ - $ -
$ - $ -

$ - $ -
$ - $ - $ -
$ - $ - $ -

Acceleration (Risk of
07.01.03.02 01.01.90 Liquidated Damages) $ - $ 40,000 $ 40,000
$ - $ - $ -
Subtotals $ 4,750 $ 13,515 $ 40,000 $ 121,092 $ 84,000
Project BAC $ 121,092
Contingency Reserves $ 53,515

©2009 Dr. Thomas Grisham www.thomasgrisham.com 16


Figure 33 - Organizational WBS (third section)

WBS Dictionary
checks if
actual cost is Software tech,
total cost outside programmers, Assumed no resourse
from from Analagous or Brainstorm from Chart minus actual control designers, iron constraints, or assume from
corporate PMO Bottom-up or Top/down of Acounts costs limits workers, etc. resource availabilit, etc. schedule

Corporate
Chart of Schedule
Accounts WBS # Work Packages Actual Cost Delta Variance Resource Category Assumptions Activity #
10%
Sponsor, PM,
Joint Planning Meeting Planner, Estimator, Fixed cost based on
07.01.03.01 01.01.10 (Service Provider A) $ 84,000 $ (2,908) $ - Technical (4) food for 30 people
$ - $ -
$ - $ -
$ - $ -

$ - $ -
$ - $ -
$ - $ -

Acceleration (Risk of
07.01.03.02 01.01.90 Liquidated Damages) $ - $ -
$ - $ -
Subtotals $ 84,000 $ (2,908) $ -
Project BAC $ 121,092
Contingency Reserves $ 118,184

©2009 Dr. Thomas Grisham www.thomasgrisham.com 17


Step 1 - Contingency

• You have done a PERT on each work


package
• You have checked with experts
• Your due diligence estimate of costs is
20% under the customer’s budget

Do You Divulge Contingency?


©2009 Dr. Thomas Grisham www.thomasgrisham.com 18
Step 2– The Value Chain

Mumbai London
Customer User
(Buyer/Seller) (Buyer)
- Sponsor - Sponsor
- Project Manager - Project Manager
- Stakeholders - Stakeholders

Mumbai New York


Service Provider A Service Provider B
(Seller/Buyer) (Seller/Buyer)
Alliance
- Lead Sponsor Partnership - Sponsor
- Lead Project Manager Joint Venture - Project Manager
- Stakeholders Consortium - Stakeholders

SupplyChain
Value ChainA.1
A.1 SupplyChain
Value ChainA.2
A.2 SupplyChain
Value ChainB.1
B.1 SupplyChain
Value ChainB.2
B.2
(Seller/Buyer) (Seller/Buyer) (Seller/Buyer) (Seller/Buyer)
- Sponsor - Sponsor - Sponsor - Sponsor
- Project Manager - Project Manager - Project Manager - Project Manager
- Stakeholders - Stakeholders - Stakeholders - Stakeholders
Bangalore Beijing Kuala Lumpur St. Petersburg

You’re the lead project manager

©2009 Dr. Thomas Grisham www.thomasgrisham.com 19


Figure 34 - Value chain WBS (first section)

WBS Dictionary

Amount Office,
from from Analagous or Brainstorm # of people management,
corporate PMO Bottom-up or Top/down Resources PERT calc'd are paid support, etc. calc'd

Corporate Hours Best Most Worst PERT Base Burdened


Chart of # of per Case Likely Case Work Person Hourly Overhead & Personnel
Accounts WBS # Work Packages People Day Days Days Days Days Hours Rate Profit Factor Cost
$ 100 3.10

Joint Planning Meeting


07.01.03.01 01.01.10 (Service Provider A) 8.0 8.0 2.0 3.0 5.0 3.2 203 $100 3.10 $ 62,827

01.01.20 Medical Mentoring 10.0 4.0 20.0 35.0 60.0 36.7 1,467 $100 3.10 $ 454,667
SC.A.1 - Medical Training
01.30.10 Facilities & Documents - - $100 3.10 $ -
SC.A.1 - Prepare Medical
01.30.11 Training Documents - - $100 3.10 $ -

02.01.10 Deliver Drugs to Hospitals - - $100 3.10 $ -


- - $100 3.10 $ -
- - $100 3.10 $ -

Acceleration (Risk of
07.01.03.02 01.01.90 Liquidated Damages) - - $100 3.10 $ -
- - $100 3.10 $ -
Subtotals 1,669 $ 517,493
Project BAC
Contingency Reserves

©2009 Dr. Thomas Grisham www.thomasgrisham.com 20


Figure 35 - Value chain WBS (second section)
WBS Dictionary
Amount to
Cost for cover
material, estimate
equipment, being less
from from Analagous or Brainstorm subcontractors, than 100% from risk from Chart
corporate PMO Bottom-up or Top/down vendors, travel accurate register calc'd of Acounts

Corporate Total
Chart of Contingency Budgeted
Accounts WBS # Work Packages Fixed Cost Amount Risk Fund Cost Actual Cost
80%

Joint Planning Meeting


07.01.03.01 01.01.10 (Service Provider A) $ 4,750 $ 13,515 $ - $ 81,092 $ 84,000

01.01.20 Medical Mentoring $ 90,933 $ - $ 545,600 $ 550,000


SC.A.1 - Medical Training
01.30.10 Facilities & Documents $ 20,000 $ 4,000 $ - $ 24,000 $ 40,000
SC.A.1 - Prepare Medical
01.30.11 Training Documents $ - $ - $ -

$ - $ - $ -
$ - $ - $ -

Acceleration (Risk of
07.01.03.02 01.01.90 Liquidated Damages) $ - $ 40,000 $ 40,000
$ - $ - $ -
Subtotals $ 24,750 $ 108,449 $ 40,000 $ 690,692 $ 674,000
Project BAC $ 690,692
Contingency Reserves $ 148,449

©2009 Dr. Thomas Grisham www.thomasgrisham.com 21


Figure 36 - Value chain WBS (third section)

WBS Dictionary
checks if
actual cost is Software tech,
total cost outside programmers, Assumed no resourse
from from Analagous or Brainstorm minus actual control designers, iron constraints, or assume from
corporate PMO Bottom-up or Top/down costs limits workers, etc. resource availabilit, etc. schedule

Corporate
Chart of Schedule
Accounts WBS # Work Packages Delta Variance Resource Category Assumptions Activity #
10%
Sponsor, PM,
Joint Planning Meeting Planner, Estimator, Fixed cost based on
07.01.03.01 01.01.10 (Service Provider A) $ (2,908) $ - Technical (4) food for 30 people
Equipment &
facilities by Supply
01.01.20 Medical Mentoring $ (4,400) $ (4,400) Doctors, Nurses Chain A.1
SC.A.1 - Medical Training
01.30.10 Facilities & Documents $ (16,000) $ (16,000) Supply Chain A.1
SC.A.1 - Prepare Medical
01.30.11 Training Documents $ - $ - Supply Chain A.1

$ - $ -
$ - $ -

Acceleration (Risk of
07.01.03.02 01.01.90 Liquidated Damages) $ -
$ - $ -
Subtotals $ (23,308) $ (20,400)
Project BAC $ 690,692
Contingency Reserves $ 125,141

©2009 Dr. Thomas Grisham www.thomasgrisham.com 22


Step 3– The Partner WBS

Mumbai London
Customer User
(Buyer/Seller) (Buyer)
- Sponsor - Sponsor
- Project Manager - Project Manager
- Stakeholders - Stakeholders

Mumbai New York


Service Provider A Service Provider B
(Seller/Buyer) (Seller/Buyer)
Alliance
- Lead Sponsor Partnership - Sponsor
- Lead Project Manager Joint Venture - Project Manager
- Stakeholders Consortium - Stakeholders

SupplyChain
Value ChainA.1
A.1 SupplyChain
Value ChainA.2
A.2 SupplyChain
Value ChainB.1
B.1 SupplyChain
Value ChainB.2
B.2
(Seller/Buyer) (Seller/Buyer) (Seller/Buyer) (Seller/Buyer)
- Sponsor - Sponsor - Sponsor - Sponsor
- Project Manager - Project Manager - Project Manager - Project Manager
- Stakeholders - Stakeholders - Stakeholders - Stakeholders
Bangalore Beijing Kuala Lumpur St. Petersburg

You’re the lead project manager

©2009 Dr. Thomas Grisham www.thomasgrisham.com 23


Figure 37 - CPE Structure of WBS

User Customer
Level 1 Minister of Health Cambodia Government

Minister of
Consortium
Level 2 Education Level 1

Provincial Provincial Medical Service Provider A Service Provider B Level 2


Level 3
Facility Management Staff

Added Medical Project Facility Mentors & Medical Mentors &


Level 4 Management Trainers Trainers Level 3
Staff Employment

Integration Supply Chain A.1


Level 5 Scope Treatment Level 4
Management Training Program
Management

Level 6 Funding Stakeholder


Analysis
Training Assessment of Staff Level 5
Advertisement
Joint Planning
Selection Sessions

Level 7 Step 1 - Organizational Level 6


Work Package Step 2 - Supply Chain Work Package
Step 3 - Partner

©2009 Dr. Thomas Grisham www.thomasgrisham.com 24


Figure 38 - Partner WBS
WBS Dictionary
checks if
actual cost is Software tech,
total cost outside programmers, Assumed no resourse
from from Analagous or Brainstorm from risk from Chart minus actual control designers, iron constraints, or assume from
corporate PMO Bottom-up or Top/down register calc'd of Acounts costs limits workers, etc. resource availabilit, etc. schedule

Corporate Total
Chart of Budgeted Schedule
Accounts WBS # Work Packages Risk Fund Cost Actual Cost Delta Variance Resource Category Assumptions Activity #
10%
Sponsor, PM,
Joint Planning Meeting Planner, Estimator, Fixed cost based on
07.01.03.01 01.01.10 (Service Provider A) $ - $ 81,092 $ 84,000 $ (2,908) $ - Technical (4) food for 30 people
Equipment &
facilities by Supply
01.01.20 Medical Mentoring $ - $ 545,600 $ 550,000 $ (4,400) $ (4,400) Doctors, Nurses Chain A.1
SC.A.1 - Medical Training
01.30.10 Facilities & Documents $ - $ 24,000 $ 40,000 $ (16,000) $ (16,000) Supply Chain A.1
SC.A.1 - Prepare Medical
01.30.11 Training Documents $ - $ - $ - $ - Supply Chain A.1

02.01.10 Deliver Drugs to Hospitals $ 40,000 $ 52,000 $ 60,000 $ (8,000) $ (8,000) Supply Chain B.1
$ - $ - $ - $ -
$ - $ - $ - $ -

Acceleration (Risk of
07.01.03.02 01.01.90 Liquidated Damages) $ 40,000 $ 40,000 $ 40,000 $ -
$ - $ - $ - $ -
Subtotals $ 80,000 $ 742,692 $ 734,000 $ (28,400)
Project BAC $ 742,692 $ 742,692
Contingency Reserves $ 190,449 $ 162,049

©2009 Dr. Thomas Grisham www.thomasgrisham.com 25


Step 4– The CPE WBS

Mumbai London
Customer User
(Buyer/Seller) (Buyer)
- Sponsor - Sponsor
- Project Manager - Project Manager
- Stakeholders - Stakeholders

Mumbai New York


Service Provider A Service Provider B
(Seller/Buyer) (Seller/Buyer)
Alliance
- Lead Sponsor Partnership - Sponsor
- Lead Project Manager Joint Venture - Project Manager
- Stakeholders Consortium - Stakeholders

SupplyChain
Value ChainA.1
A.1 SupplyChain
Value ChainA.2
A.2 SupplyChain
Value ChainB.1
B.1 SupplyChain
Value ChainB.2
B.2
(Seller/Buyer) (Seller/Buyer) (Seller/Buyer) (Seller/Buyer)
- Sponsor - Sponsor - Sponsor - Sponsor
- Project Manager - Project Manager - Project Manager - Project Manager
- Stakeholders - Stakeholders - Stakeholders - Stakeholders
Bangalore Beijing Kuala Lumpur St. Petersburg

You’re the lead project manager

©2009 Dr. Thomas Grisham www.thomasgrisham.com 26


Step 4 – Joint Planning Meeting

Plan for
– Attendees
– Lead project manager
leads
– Duration
– Venue
– Deliverables
WBS Template
– Support
– Fun

©2009 Dr. Thomas Grisham www.thomasgrisham.com 27


6.3 Scope Change Control

Imagine
You are the lead PM on a €50 million project to build
a new hospital in Nigeria, and you are meeting the
PM for the customer for the first time at the joint
planning meeting.
Over tea he introduces himself and tells you that his
team has overlooked the need for a new sign to tell
the public that the hospital is to be constructed. He
asks you if you can “take care of this for him.”
You are thinking that the cost is about €500. What do
you tell him?

©2009 Dr. Thomas Grisham www.thomasgrisham.com 28


6.3 Scope Change Control

Evaluate ALL Changes


– Description Photo
– Requested by
– Impact on time
– Impact on cost
– Impact on quality
– Impact on risk
– Written approval
– Dispute process
No Matter How Small
©2009 Dr. Thomas Grisham www.thomasgrisham.com 29

You might also like