Professional Documents
Culture Documents
IPM Scope Management
IPM Scope Management
Project Management
Dr. Thomas Grisham
www.thomasgrisham.com
Chapters
– 1 Introduction
– 2 Framework
– 3 Project Basics
– 4 Leading Diversity (HR & Communications)
– 5 Integration Management
– 6 Scope Management
– 7 Cost & Progress Management
– 8 Risk Management
– 9 Time Management
– 10 Quality Management – Customer Satisfaction
– 11 Procurement Management
– 12 CPE’S In the Future
(Collaborative Project Environment)
Photo
Chapters
– 1 Introduction
– 2 Framework
– 3 Project Basics
– 4 Leading Diversity (HR & Communications)
– 5 Integration Management
– 6 Scope Management
– 7 Cost & Progress Management
– 8 Risk Management
– 9 Time Management
– 10 Quality Management – Customer Satisfaction
– 11 Procurement Management
– 12 CPE’S In the Future
Scope Management
– 6.1 Developing a Project Scope
– 6.2 Developing a WBS
• 6.2.1 Step 1 – Organizational WBS
• 6.2.2 Step 2 – Value Chain WBS
• 6.2.3 Step 3 – Partner WBS
• 6.2.4 Step 4 – CPE WBS
– 6.3 Scope Change Control
Level of
Detail & Cost
Technical
Equal-to
Performance
Blended Bid
Equal -to Spec
Incentives
Risk To Customer
Competitive Bid
Technical Spec
Fixed Price
Low
Low High
Participation Of Customer
Go Green
©2009 Dr. Thomas Grisham www.thomasgrisham.com 8
Figure 29 – CPE WBS
SupplyChain
Value ChainA.1
A.1 SupplyChain
Value ChainA.2
A.2 SupplyChain
Value ChainB.1
B.1 SupplyChain
Value ChainB.2
B.2
(Seller/Buyer) (Seller/Buyer) (Seller/Buyer) (Seller/Buyer)
One Participant
- Sponsor - Sponsor - Sponsor - Sponsor
- Project Manager - Project Manager - Project Manager - Project Manager A Project According to
- Stakeholders - Stakeholders
- Stakeholders - Stakeholders IPMA, PRINCE2, PMI, APM
Bangalore Beijing Kuala Lumpur St. Petersburg
Text
Practice XLQ
©2009 Dr. Thomas Grisham www.thomasgrisham.com 10
6.2 Developing a WBS
Work package
– Lowest level detail of WBS
– Lowest level of activity in schedule
– One-for-one with chart of account
– Duration not longer than a month
– Duration not shorter than a week
Project WBS
Project Level 1
Engineering
Organization
London
Design
PMO
Reduces Bias
©2009 Dr. Thomas Grisham www.thomasgrisham.com 13
Step 1 – Your organization
Mumbai London
Customer User
(Buyer/Seller) (Buyer)
- Sponsor - Sponsor
- Project Manager - Project Manager
- Stakeholders - Stakeholders
SupplyChain
Value ChainA.1
A.1 SupplyChain
Value ChainA.2
A.2 SupplyChain
Value ChainB.1
B.1 SupplyChain
Value ChainB.2
B.2
(Seller/Buyer) (Seller/Buyer) (Seller/Buyer) (Seller/Buyer)
- Sponsor - Sponsor - Sponsor - Sponsor
- Project Manager - Project Manager - Project Manager - Project Manager
- Stakeholders - Stakeholders - Stakeholders - Stakeholders
Bangalore Beijing Kuala Lumpur St. Petersburg
Amount Office,
from from Analagous or Brainstorm # of people management,
corporate PMO Bottom-up or Top/down Resources PERT calc'd are paid support, etc. calc'd
01.01.20 Medical Mentoring 10.0 4.0 20.0 35.0 60.0 36.7 1,467 $100 3.10 $ 454,667
SC.A.1 - Medical Training
01.30.10 Facilities & Documents - - $100 3.10 $ -
SC.A.1 - Prepare Medical
01.30.11 Training Documents - - $100 3.10 $ -
Acceleration (Risk of
07.01.03.02 01.01.90 Liquidated Damages) - - $100 3.10 $ -
- - $100 3.10 $ -
Subtotals 1,669 $ 517,493
Project BAC
Contingency Reserves
WBS Dictionary
Amount to
Cost for cover
material, estimate
equipment, being less
from from Analagous or Brainstorm subcontractors, than 100% from risk from Chart
corporate PMO Bottom-up or Top/down vendors, travel accurate register calc'd of Acounts
Corporate Total
Chart of Contingency Budgeted
Accounts WBS # Work Packages Fixed Cost Amount Risk Fund Cost Actual Cost
80%
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ - $ -
$ - $ - $ -
Acceleration (Risk of
07.01.03.02 01.01.90 Liquidated Damages) $ - $ 40,000 $ 40,000
$ - $ - $ -
Subtotals $ 4,750 $ 13,515 $ 40,000 $ 121,092 $ 84,000
Project BAC $ 121,092
Contingency Reserves $ 53,515
WBS Dictionary
checks if
actual cost is Software tech,
total cost outside programmers, Assumed no resourse
from from Analagous or Brainstorm from Chart minus actual control designers, iron constraints, or assume from
corporate PMO Bottom-up or Top/down of Acounts costs limits workers, etc. resource availabilit, etc. schedule
Corporate
Chart of Schedule
Accounts WBS # Work Packages Actual Cost Delta Variance Resource Category Assumptions Activity #
10%
Sponsor, PM,
Joint Planning Meeting Planner, Estimator, Fixed cost based on
07.01.03.01 01.01.10 (Service Provider A) $ 84,000 $ (2,908) $ - Technical (4) food for 30 people
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
Acceleration (Risk of
07.01.03.02 01.01.90 Liquidated Damages) $ - $ -
$ - $ -
Subtotals $ 84,000 $ (2,908) $ -
Project BAC $ 121,092
Contingency Reserves $ 118,184
Mumbai London
Customer User
(Buyer/Seller) (Buyer)
- Sponsor - Sponsor
- Project Manager - Project Manager
- Stakeholders - Stakeholders
SupplyChain
Value ChainA.1
A.1 SupplyChain
Value ChainA.2
A.2 SupplyChain
Value ChainB.1
B.1 SupplyChain
Value ChainB.2
B.2
(Seller/Buyer) (Seller/Buyer) (Seller/Buyer) (Seller/Buyer)
- Sponsor - Sponsor - Sponsor - Sponsor
- Project Manager - Project Manager - Project Manager - Project Manager
- Stakeholders - Stakeholders - Stakeholders - Stakeholders
Bangalore Beijing Kuala Lumpur St. Petersburg
WBS Dictionary
Amount Office,
from from Analagous or Brainstorm # of people management,
corporate PMO Bottom-up or Top/down Resources PERT calc'd are paid support, etc. calc'd
01.01.20 Medical Mentoring 10.0 4.0 20.0 35.0 60.0 36.7 1,467 $100 3.10 $ 454,667
SC.A.1 - Medical Training
01.30.10 Facilities & Documents - - $100 3.10 $ -
SC.A.1 - Prepare Medical
01.30.11 Training Documents - - $100 3.10 $ -
Acceleration (Risk of
07.01.03.02 01.01.90 Liquidated Damages) - - $100 3.10 $ -
- - $100 3.10 $ -
Subtotals 1,669 $ 517,493
Project BAC
Contingency Reserves
Corporate Total
Chart of Contingency Budgeted
Accounts WBS # Work Packages Fixed Cost Amount Risk Fund Cost Actual Cost
80%
$ - $ - $ -
$ - $ - $ -
Acceleration (Risk of
07.01.03.02 01.01.90 Liquidated Damages) $ - $ 40,000 $ 40,000
$ - $ - $ -
Subtotals $ 24,750 $ 108,449 $ 40,000 $ 690,692 $ 674,000
Project BAC $ 690,692
Contingency Reserves $ 148,449
WBS Dictionary
checks if
actual cost is Software tech,
total cost outside programmers, Assumed no resourse
from from Analagous or Brainstorm minus actual control designers, iron constraints, or assume from
corporate PMO Bottom-up or Top/down costs limits workers, etc. resource availabilit, etc. schedule
Corporate
Chart of Schedule
Accounts WBS # Work Packages Delta Variance Resource Category Assumptions Activity #
10%
Sponsor, PM,
Joint Planning Meeting Planner, Estimator, Fixed cost based on
07.01.03.01 01.01.10 (Service Provider A) $ (2,908) $ - Technical (4) food for 30 people
Equipment &
facilities by Supply
01.01.20 Medical Mentoring $ (4,400) $ (4,400) Doctors, Nurses Chain A.1
SC.A.1 - Medical Training
01.30.10 Facilities & Documents $ (16,000) $ (16,000) Supply Chain A.1
SC.A.1 - Prepare Medical
01.30.11 Training Documents $ - $ - Supply Chain A.1
$ - $ -
$ - $ -
Acceleration (Risk of
07.01.03.02 01.01.90 Liquidated Damages) $ -
$ - $ -
Subtotals $ (23,308) $ (20,400)
Project BAC $ 690,692
Contingency Reserves $ 125,141
Mumbai London
Customer User
(Buyer/Seller) (Buyer)
- Sponsor - Sponsor
- Project Manager - Project Manager
- Stakeholders - Stakeholders
SupplyChain
Value ChainA.1
A.1 SupplyChain
Value ChainA.2
A.2 SupplyChain
Value ChainB.1
B.1 SupplyChain
Value ChainB.2
B.2
(Seller/Buyer) (Seller/Buyer) (Seller/Buyer) (Seller/Buyer)
- Sponsor - Sponsor - Sponsor - Sponsor
- Project Manager - Project Manager - Project Manager - Project Manager
- Stakeholders - Stakeholders - Stakeholders - Stakeholders
Bangalore Beijing Kuala Lumpur St. Petersburg
User Customer
Level 1 Minister of Health Cambodia Government
Minister of
Consortium
Level 2 Education Level 1
Corporate Total
Chart of Budgeted Schedule
Accounts WBS # Work Packages Risk Fund Cost Actual Cost Delta Variance Resource Category Assumptions Activity #
10%
Sponsor, PM,
Joint Planning Meeting Planner, Estimator, Fixed cost based on
07.01.03.01 01.01.10 (Service Provider A) $ - $ 81,092 $ 84,000 $ (2,908) $ - Technical (4) food for 30 people
Equipment &
facilities by Supply
01.01.20 Medical Mentoring $ - $ 545,600 $ 550,000 $ (4,400) $ (4,400) Doctors, Nurses Chain A.1
SC.A.1 - Medical Training
01.30.10 Facilities & Documents $ - $ 24,000 $ 40,000 $ (16,000) $ (16,000) Supply Chain A.1
SC.A.1 - Prepare Medical
01.30.11 Training Documents $ - $ - $ - $ - Supply Chain A.1
02.01.10 Deliver Drugs to Hospitals $ 40,000 $ 52,000 $ 60,000 $ (8,000) $ (8,000) Supply Chain B.1
$ - $ - $ - $ -
$ - $ - $ - $ -
Acceleration (Risk of
07.01.03.02 01.01.90 Liquidated Damages) $ 40,000 $ 40,000 $ 40,000 $ -
$ - $ - $ - $ -
Subtotals $ 80,000 $ 742,692 $ 734,000 $ (28,400)
Project BAC $ 742,692 $ 742,692
Contingency Reserves $ 190,449 $ 162,049
Mumbai London
Customer User
(Buyer/Seller) (Buyer)
- Sponsor - Sponsor
- Project Manager - Project Manager
- Stakeholders - Stakeholders
SupplyChain
Value ChainA.1
A.1 SupplyChain
Value ChainA.2
A.2 SupplyChain
Value ChainB.1
B.1 SupplyChain
Value ChainB.2
B.2
(Seller/Buyer) (Seller/Buyer) (Seller/Buyer) (Seller/Buyer)
- Sponsor - Sponsor - Sponsor - Sponsor
- Project Manager - Project Manager - Project Manager - Project Manager
- Stakeholders - Stakeholders - Stakeholders - Stakeholders
Bangalore Beijing Kuala Lumpur St. Petersburg
Plan for
– Attendees
– Lead project manager
leads
– Duration
– Venue
– Deliverables
WBS Template
– Support
– Fun
Imagine
You are the lead PM on a €50 million project to build
a new hospital in Nigeria, and you are meeting the
PM for the customer for the first time at the joint
planning meeting.
Over tea he introduces himself and tells you that his
team has overlooked the need for a new sign to tell
the public that the hospital is to be constructed. He
asks you if you can “take care of this for him.”
You are thinking that the cost is about €500. What do
you tell him?