MAGNO, JAN ARVYN V.

SCOPE OF WORK DURATION WEEKS


DIVISION QUANTITY UNIT AMOUNT
ACTIVITY WEEKS 1 2 3 4 5 6 7 8 9
1 GENERAL REQUIREMENT 1 LOT 57500 9 6389 6389 6389 6389 6389 6389 6389 6389 6389
2 SITEWORKS 1 LOT 13500 5 2700 2700 2700 2700 2700
3 CONCRETE WORKS
3.1 CONCRETE 1 LOT 54500 2 27250 27250
3.2 REINFORCEMENT 1 LOT 73000 2 36500 36500
3.3 FORMWORKS 1 LOT 70500 4 17625 17625 17625 17625
4 METAL WORKS 1 LOT 41000 1 41000
5 MASONRY WORKS 1 LOT 45000 3 15000 15000 15000
6 THERMAL AND MOISTURE PROTECTION 1 LOT 41000 1 41000
7 DOORS AND WINDOWS 1 LOT 64000 1 64000
8 FINISHING
8.1 FLOOR FINISH 1 LOT 40000 1 40000
8.2 WALL FINISH 1 LOT 55000 1 55000
8.3 CEILING FINISH 1 LOT 17000 1 17000
8.4 PAINTING 1 LOT 23000 1 23000
9 PLUMBING AND SANITARY 1 LOT 25000 1 25000
10 ELECTRICAL WORKS 1 LOT 58700 5 11740 11740 11740 11740 11740
TOTAL 678700

TOTAL 6389 9089 38454 149454 258954 158204 45379 6389 6389
ACCUMULATED AMOUNT 6389 15478 53932 203386 462340 620544 665923 672312 678701