You are on page 1of 51

PROJECT : PROPOSED ONE STORY RESIDENTIAL BUILDING

LOCATION: Lumbia, Cagayan de Oro City

Duration OCTOBER
Item Description Qty Unit Total Amount Weight %
(Days) WEEK 1 WEEK 2 WEEK 3 WEEK 4
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
DIV. 01 GENERAL REQUIREMENTS
1.1 Mobilization 1.00 lot 2,500.00 0.12% 157
1.2 Temporary Facilities 1.00 lot 7,200.00 0.34% 4
1.3 Temporary Power & water 1.00 lot 3,000.00 0.14% 3
1.4 Zoning Permit 1.00 lot 800.00 0.04% 2
1.5 Fire Permit 1.00 lot 800.00 0.04% 2
1.6 Building Permits 1.00 lot 2,000.00 0.09% 4
1.7 Occupancy Permits 1.00 lot 800.00 0.04% 2
1.8 As-built drawings 1.00 lot 800.00 0.04% 5
1.9 Hauling and disposal of debris 1.00 lot 1,800.00 0.08% 3
1.10 Subdivision Fees Not Applicable -
1.11 Insurances and Bonds 1.00 lot 5,000.00 0.23% 5
1.11.1 Performance Bond 1.00 lot
1.11.2 Surety Bond 1.00 lot
1.11.3 Guarantee Bond 1.00 lot
1.11.4 Contractors All-risk Insurance (CARI) 1.00 lot
1.12 Construction Safety 1.00 lot 7,500.00 0.35% 164
1.13 Construction Security 1.00 lot 5,500.00 0.26% 164
1.14 Design Fee 1.00 lot 2,500.00 0.12% 1
1.15 Taxes (VAT-EVAT) 1.00 lot
1.16 Demobilization 1.00 lot 2,000.00 0.09% 7

SUBTOTAL 42,200.00 1.98%

DIV. 02 SITE WORKS


2.1 Clearing and grubbing 75.00 sq.m. 1,875.00 0.09% 1
2.2 Layout and staking 1.00 lot 2,200.00 0.10% 1
2.3 Excavation 26.36 cu.m. 13,182.00 0.62% 9
2.4 Gravel bedding/ Lean concrete 7.76 cu.m. 20,176.00 0.95% 2
2.5 Backfilling and compaction 19.53 cu.m. 7,812.00 0.37% 5
2.6 Soil poisoining 48.00 sq.m. 4,080.00 0.19% 1
2.7 Polyethylene vapour barrier 48.00 sq.m. 6,000.00 0.28% 4
2.8 Disposal of waste materials 6.83 cu.m. 6,834.00 0.32% 1

SUBTOTAL 62,159.00 2.92%

DIV. 03 CONCRETE WORKS


3.1 Reinforcement
3.1.1 Footing 192.24 kg 11,342.16 0.53% 2
3.1.2 Column 1135.16 kg 66,974.44 3.14% 10
3.1.3 Roof beam 884.61 kg 52,191.99 2.45% 13
3.1.4 Slab on fill 169.02 kg 9,972.18 0.47% 3
3.1.5 Wall footing 150.00 kg 8,850.00 0.42% 3
3.1.6 Septic tank 500.00 kg 29,500.00 1.38% 8
3.1.7 Tie wire 82.00 kg 5,576.00 0.26% 2

3.2 Formworks
3.2.1 Footing 18.72 sq.m. 21,528.00 1.01% 3
3.2.2 Column 54.00 sq.m. 62,100.00 2.91% 10
3.2.3 Roof beam 38.40 sq.m. 44,160.00 2.07% 7
3.2.4 Slab on fill 2.80 sq.m. 3,220.00 0.15% 4
3.2.5 Wall footing 14.01 sq.m. 16,111.50 0.76% 3
3.2.6 Septic tank 45.05 sq.m. 54,060.00 2.54% 5

3.3 Concrete, 4000 psi


3.3.1 Footing 6.08 cu.m. 35,264.00 1.65% 5
3.3.2 Column 3.15 cu.m. 18,270.00 0.86% 4
3.3.3 Roof beam 2.88 cu.m. 16,704.00 0.78% 4
3.3.4 Slab on fill 48.00 cu.m. 278,400.00 13.06% 9
3.3.5 Wall footing 2.80 cu.m. 16,240.00 0.76% 3
3.3.6 Septic tank 9.20 cu.m. 53,360.00 2.50% 3

SUBTOTAL 803,824.27 37.71%

DIV. 04 MASONRY WORKS


4.1 4" thk CMU wall 25.52 sq.m. 25,520.00 1.20% 4
4.2 6" thk CMU wall 45.39 sq.m. 49,929.00 2.34% 7

SUBTOTAL 75,449.00 3.54%

DIV. 05 THERMAL & MOISTURE PROTECTION


5.1 Preformed metal roofing, gage 24 81.96 sq.m. 67,207.00 3.15% 1
5.2 Metal gutter and supports 13.40 lm 4,020.00 0.19% 2
5.3 Roof insulation 81.96 sq.m. 10,245.00 0.48% 2
5.4 Waterproofing at toilets 3.00 sq.m. 900.00 0.04% 1

SUBTOTAL 82,372.00 3.86%

DIV. 06 WOOD & PLASTICS


6.1 Built-In Closet for BR 1 and BR 2 1.00 lot 10,450.00 0.49% 2

SUBTOTAL 10,450.00 0.49%

DIV. 07 METAL WORKS


7.1 Roof truss 1.00 lot 105,600.00 4.95% 1
7.1.1 Top chord included lm
7.1.2 Bottom chord included lm
7.1.3 Web member included lm
7.1.4 Cleats included pcs
7.1.5 Hexagonal bolts included pcs
7.1.6 Anchor bolts included pcs
7.2 Fascia board metal frame on ficemboard 34.60 lm

SUBTOTAL 105,600.00 4.95%

DIV. 08 DOORS and WINDOWS


8.1 Doors
8.1.1 D-1: 1.05 x 2.1 m Wooden Panel Door on Wooden Jamb 1.00 set 9,999.16 0.47% 1
8.1.2 D-2: 0.80 x 2.1 m Wooden Panel Door on Wooden Jamb 3.00 set 23,398.08 1.10% 1
8.1.3 D-3: 0.70 x 2.1 m Wooden Flush Door on Wooden Jamb 1.00 set 7,399.44 0.35% 1

8.2 Windows
W-1: 0.45 x 2.1 m Fixed Glass Window on Aluminum Analok
2.00 set 3,610.47 0.17% 1
8.2.1 Framing
W-2: 0.30 x 1.8 m Fixed Glass Window on Aluminum Analok
2.00 set 2,848.84 0.13% 1
8.2.2 Framing
W-3:1.6 x 1.9 m Sliding Glass Window on Aluminum Analok
2.00 set 12,963.84 0.61% 1
8.2.3 Framing
W-4: 1.6 x 1.2 m Sliding Glass Window on Aluminum Analok
1.00 set 5,031.92 0.24% 1
8.2.4 Framing
W-5: 1.8 x 1 m Jaloplus System Window on Aluminum Analok
1.00 set 4,581.40 0.21% 1
8.2.5. Framing
W-6: 0.7 x 0.7 m Jaloplus System Window on Aluminum
1.00 set 2,658.27 0.12% 1
8.2.6. Analok Framing

SUBTOTAL 72,491.42 3.40%


DIV. 09 FINISHES
9.1 Floor finish
9.1.1 Plain cement finish 48.00 sq.m. 39,168.00 1.84% 3
9.1.2 Ceramic tiles, 600x600 (including installation cost) 45.00 sq.m. 220,241.25 10.33% 10
9.1.3 Ceramic tiles, 300x300 (including installation cost) 3.00 sq.m. 2,988.00 0.14% 2

9.2 Wall finish


9.2.1 Plain cement finish, interior walls 135.15 sq.m. 67,575.00 3.17% 9
9.2.2 Plain cement finish, exterior walls 83.47 sq.m. 41,735.00 1.96% 5
9.2.3 Ceramic tiles, 300x300 14.00 sq.m. 13,944.00 0.65% 8
9.2.4 Sandstone Finish 7.36 sq.m. 10,672.00 0.50% 3

9.3 Ceiling finish


9.3.1 9mm thick Gypsumboard ceiling on metal framing 48.00 sq.m. 62,400.00 2.93% 5

9.4 Painting
9.4.1 Wall paint 218.62 sq.m. 48,096.40 2.26% 8
9.4.2 Ceiling Paint 48.00 sq.m. 10,560.00 0.50% 6
9.4.3 Door paint 8.72 sq.m. 1,917.30 0.09% 4

SUBTOTAL 519,296.95 24.36%

DIV. 10 PLUMBING WORKS


10.1 Plumbing and Sanitary Works
10.1.1 Waterline
10.1.1.1 Gate Valve, Check Valve 1.00 lot 2,000.00 0.09% 1
10.1.1.2 Water Meter 1.00 set 4,900.00 0.23% 1
10.1.1.3 PVC Pipe & fittings 20.00 lm 15,000.00 0.70% 2
10.1.2 Sewerline
10.1.2.1 100 mm dia, PVC Pipe S1000 incl. fittings 80.16 lm 90,580.80 4.25% 3
10.1.2.2 50 mm dia, PVC Pipe incl. fittings 65.67 lm 50,565.90 2.37% 2
10.1.3 Drainage line
10.1.3.1 Catch basin 4.00 set 11,200.00 0.53% 1
10.1.3.2 PVC pipe, 150mmø 16.00 lm 27,200.00 1.28% 1
10.1.3.3 Downspout, 75mmø PVC pipe 5.00 lm 3,900.00 0.18% 2
10.1.3.4 Floor drain 1.00 pcs 900.00 0.04% 1
10.2 Plumbing Fixtures
Water Closet 1.00 set 14,000.00 0.66% 1
Lavatory, wall hung 1.00 set 11,800.00 0.55% 1
Shower head & accessories 1.00 set 1,450.00 0.07% 2
Faucets 4.00 set 2,800.00 0.13% 2
Kitchen Sink 2.00 pcs 17,600.00 0.83% 1
Fittings and consumables 1.00 lot 5,450.00 0.26% 2

SUBTOTAL 259,346.70 12.17%

DIV. 11 MECHANICAL WORKS


Airconditioning
Window type, 1.5Hp 2.00 sets 19,000.00 0.89% 1
Exhaust fan 1.00 set 1,700.00 0.08% 2

SUBTOTAL 20,700.00 0.97%

DIV. 12 ELECTRICAL WORKS


Power System
Entrance power supply 1.00 lot 16,000.00 0.75% 1
Convenience outlets 8.00 pcs 4,960.00 0.23% 1
Aircon outlet 1.00 set 650.00 0.03% 1

Main power panel


Panelboard 1.00 set 7,900.00 0.37% 1

Lighting system
Dimmable Flush Mount LED Ceiling (24inch) 2.00 set 4,600.00 0.22% 1
Dimmable Flush Mount LED Ceiling (12inch) 2.00 set 3,600.00 0.17% 1
Round Recessed Pinlight w/ Lens Cover 4.00 sets 6,800.00 0.32% 1
Decorative Pendant Light 1.00 pc. 1,900.00 0.09% 1
LED Strip Light (Warm White) 24.00 lm 9,494.40 0.45% 1

Wiring and devices


5.5mm2 THHN 80.23 lm 6,097.48 0.29% 4
3.5mm2 THHN 120.50 lm 9,158.00 0.43% 4
Flexible pipes, 13mmø 1.00 roll 1,780.00 0.08% 4
Utility box 15.00 pcs 1,200.00 0.06% 3
Junction box with cover 10.00 pcs 750.00 0.04% 4
Switch - 1 gang 3.00 set 1,020.00 0.05% 5
Switch - 2 gang 3.00 sets 1,170.00 0.05% 5
Switch - 3 gang 1.00 sets 460.00 0.02% 2

SUBTOTAL 77,539.88 3.64%

GRAND TOTAL AMOUNT 2,131,429.22 100.00%


NOVEMBER
WEEK 4 WEEK 5 WEEK 6 WEEK 7
23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46
NOVEMBER DECEMBER JANUARY
WEEK 7 WEEK 8 WEEK 9 WEEK 10 WEEK 11 WEEK 12 WEEK 13 WEEK 14 WEEK 15 WEEK 16 WEEK 17
47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117
PROJECT : PROPOSED ONE STORY RESIDENTIAL BUILDING
LOCATION: Lumbia, Cagayan de Oro City

Item Description Qty Unit

DIV. 01 GENERAL REQUIREMENTS 1.00 lot


1.1 Mobilization 1.00 lot
1.2 Temporary Facilities 1.00 lot
1.3 Temporary Power & water 1.00 lot
1.4 Zoning Permit 1.00 lot
1.5 Fire Permit 1.00 lot
1.6 Building Permits 1.00 lot
1.7 Occupancy Permits 1.00 lot
1.8 As-built drawings 1.00 lot
1.9 Hauling and disposal of debris 1.00 lot
1.10 Subdivision Fees Not Applicable
1.11 Insurances and Bonds 1.00 lot
1.11.1 Performance Bond 1.00 lot
1.11.2 Surety Bond 1.00 lot
1.11.3 Guarantee Bond 1.00 lot
1.11.4 Contractors All-risk Insurance (CARI) 1.00 lot
1.12 Construction Safety 1.00 lot
1.13 Construction Security 1.00 lot
1.14 Design Fee 1.00 lot
1.15 Taxes (VAT-EVAT) 1.00 lot
1.16 Demobilization 1.00 lot

SUBTOTAL

DIV. 02 SITE WORKS 1.00 lot


2.1 Clearing and grubbing 75.00 sq.m.
2.2 Layout and staking 1.00 lot
2.3 Excavation 26.36 cu.m.
2.4 Gravel bedding/ Lean concrete 7.76 cu.m.
2.5 Backfilling and compaction 19.53 cu.m.
2.6 Soil poisoining 48.00 sq.m.
2.7 Polyethylene vapour barrier 48.00 sq.m.
2.8 Disposal of waste materials 6.83 cu.m.

SUBTOTAL

DIV. 03 CONCRETE WORKS


Reinforcement 1.00 lot
Formworks 1.00 lot
Concreting 1.00 lot
3.1 Reinforcement
3.1.1 Footing 192.24 kg
3.1.2 Column 1135.16 kg
3.1.3 Roof beam 884.61 kg
3.1.4 Slab on fill 169.02 kg
3.1.5 Wall footing 150.00 kg
3.1.6 Septic tank 500.00 kg
3.1.7 Tie wire 82.00 kg

3.2 Formworks
3.2.1 Footing 18.72 sq.m.
3.2.2 Column 54.00 sq.m.
3.2.3 Roof beam 38.40 sq.m.
3.2.4 Slab on fill 2.80 sq.m.
3.2.5 Wall footing 14.01 sq.m.
3.2.6 Septic tank 45.05 sq.m.

3.3 Concrete, 4000 psi


3.3.1 Footing 6.08 cu.m.
3.3.2 Column 3.15 cu.m.
3.3.3 Roof beam 2.88 cu.m.
3.3.4 Slab on fill 48.00 cu.m.
3.3.5 Wall footing 2.80 cu.m.
3.3.6 Septic tank 9.20 cu.m.

SUBTOTAL

DIV. 04 MASONRY WORKS 1.00 lot


4.1 4" thk CMU wall 25.52 sq.m.
4.2 6" thk CMU wall 45.39 sq.m.

SUBTOTAL

DIV. 05 THERMAL & MOISTURE PROTECTION 1.00 lot


5.1 Preformed metal roofing, gage 24 81.96 sq.m.
5.2 Metal gutter and supports 13.40 lm
5.3 Roof insulation 81.96 sq.m.
5.4 Waterproofing at toilets 3.00 sq.m.

SUBTOTAL

DIV. 06 WOOD & PLASTICS 1.00 lot


6.1 Built-In Closet for BR 1 and BR 2 1.00 lot

SUBTOTAL

DIV. 07 METAL WORKS 1.00 lot


7.1 Roof truss 1.00 lot
7.1.1 Top chord included lm
7.1.2 Bottom chord included lm
7.1.3 Web member included lm
7.1.4 Cleats included pcs
7.1.5 Hexagonal bolts included pcs
7.1.6 Anchor bolts included pcs
7.2 Fascia board metal frame on ficemboard 34.60 lm

SUBTOTAL

DIV. 08 DOORS and WINDOWS 1.00 lot


8.1 Doors
8.1.1 D-1: 1.05 x 2.1 m Wooden Panel Door on Wooden Jamb 1.00 set
8.1.2 D-2: 0.80 x 2.1 m Wooden Panel Door on Wooden Jamb 3.00 set
8.1.3 D-3: 0.70 x 2.1 m Wooden Flush Door on Wooden Jamb 1.00 set

8.2 Windows
W-1: 0.45 x 2.1 m Fixed Glass Window on Aluminum Analok
2.00 set
8.2.1 Framing
W-2: 0.30 x 1.8 m Fixed Glass Window on Aluminum Analok
2.00 set
8.2.2 Framing
W-3:1.6 x 1.9 m Sliding Glass Window on Aluminum Analok
2.00 set
8.2.3 Framing
W-4: 1.6 x 1.2 m Sliding Glass Window on Aluminum Analok
1.00 set
8.2.4 Framing
W-5: 1.8 x 1 m Jaloplus System Window on Aluminum Analok
1.00 set
8.2.5. Framing
W-6: 0.7 x 0.7 m Jaloplus System Window on Aluminum
1.00 set
8.2.6. Analok Framing

SUBTOTAL

DIV. 09 FINISHES
Floor Finishes 1.00 lot
Wall Finishes 1.00 lot
Ceiling Finishes 1.00 lot
Painting Finishes 1.00 lot
9.1 Floor finish
9.1.1 Plain cement finish 48.00 sq.m.
9.1.2 Ceramic tiles, 600x600 (including installation cost) 45.00 sq.m.
9.1.3 Ceramic tiles, 300x300 (including installation cost) 3.00 sq.m.

9.2 Wall finish


9.2.1 Plain cement finish, interior walls 135.15 sq.m.
9.2.2 Plain cement finish, exterior walls 83.47 sq.m.
9.2.3 Ceramic tiles, 300x300 14.00 sq.m.
9.2.4 Sandstone Finish 7.36 sq.m.
9.3 Ceiling finish
9.3.1 9mm thick Gypsumboard ceiling on metal framing 48.00 sq.m.

9.4 Painting
9.4.1 Wall paint 218.62 sq.m.
9.4.2 Ceiling Paint 48.00 sq.m.
9.4.3 Door paint 8.72 sq.m.

SUBTOTAL

DIV. 10 PLUMBING WORKS 1.00 lot


10.1 Plumbing and Sanitary Works
10.1.1 Waterline
10.1.1.1 Gate Valve, Check Valve 1.00 lot
10.1.1.2 Water Meter 1.00 set
10.1.1.3 PVC Pipe & fittings 20.00 lm
10.1.2 Sewerline
10.1.2.1 100 mm dia, PVC Pipe S1000 incl. fittings 80.16 lm
10.1.2.2 50 mm dia, PVC Pipe incl. fittings 65.67 lm
10.1.3 Drainage line
10.1.3.1 Catch basin 4.00 set
10.1.3.2 PVC pipe, 150mmø 16.00 lm
10.1.3.3 Downspout, 75mmø PVC pipe 5.00 lm
10.1.3.4 Floor drain 1.00 pcs
10.2 Plumbing Fixtures
Water Closet 1.00 set
Lavatory, wall hung 1.00 set
Shower head & accessories 1.00 set
Faucets 4.00 set
Kitchen Sink 2.00 pcs
Fittings and consumables 1.00 lot

SUBTOTAL

DIV. 11 MECHANICAL WORKS 1.00 lot


Airconditioning
Window type, 1.5Hp 2.00 sets
Exhaust fan 1.00 set

SUBTOTAL

DIV. 12 ELECTRICAL WORKS 1.00 lot


Power System
Entrance power supply 1.00 lot
Convenience outlets 8.00 pcs
Aircon outlet 1.00 set
Main power panel
Panelboard 1.00 set

Lighting system
Dimmable Flush Mount LED Ceiling (24inch) 2.00 set
Dimmable Flush Mount LED Ceiling (12inch) 2.00 set
Round Recessed Pinlight w/ Lens Cover 4.00 sets
Decorative Pendant Light 1.00 pc.
LED Strip Light (Warm White) 24.00 lm

Wiring and devices


5.5mm2 THHN 80.23 lm
3.5mm2 THHN 120.50 lm
Flexible pipes, 13mmø 1.00 roll
Utility box 15.00 pcs
Junction box with cover 10.00 pcs
Switch - 1 gang 3.00 set
Switch - 2 gang 3.00 sets
Switch - 3 gang 1.00 sets

SUBTOTAL

GRAND TOTAL AMOUNT


Duration OCTOBER
Total Amount Weight %
(Days) WEEK 1 WEEK 2 WEEK
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

42,200.00 1.940% 164


2,500.00 0.115% 157
7,200.00 0.331% 4
3,000.00 0.138% 3
800.00 0.037% 2
800.00 0.037% 2
2,000.00 0.092% 4
800.00 0.037% 2
800.00 0.037% 5
1,800.00 0.083% 3
-
5,000.00 0.230% 5

7,500.00 0.345% 164


5,500.00 0.253% 164
2,500.00 0.115% 1

2,000.00 0.092% 7

42,200.00 1.940%

62,159.00 2.860% 23
1,875.00 0.086% 1
2,200.00 0.101% 1
13,182.00 0.606% 9
20,176.00 0.927% 2
7,812.00 0.359% 5
4,080.00 0.188% 1
6,000.00 0.276% 4
6,834.00 0.314% 1

62,159.00 2.857%

184,406.77 8.398% 29
201,179.50 9.247% 27
418,238.00 19.225% 22
11,342.16 0.521% 2
66,974.44 3.000% 10
52,191.99 2.399% 13
9,972.18 0.458% 3
8,850.00 0.407% 3
29,500.00 1.356% 8
5,576.00 0.256% 2

21,528.00 0.990% 3
62,100.00 2.854% 10
44,160.00 2.030% 7
3,220.00 0.148% 4
16,111.50 0.741% 3
54,060.00 2.485% 5

35,264.00 1.621% 5
18,270.00 0.840% 4
16,704.00 0.768% 4
278,400.00 12.797% 9
16,240.00 0.746% 3
53,360.00 2.453% 3

803,824.27 36.948%

75,449.00 3.480% 10
25,520.00 1.173% 4
49,929.00 2.295% 7

75,449.00 3.468%

126,472.00 5.813%
67,207.00 3.089% 1
4,020.00 0.185% 2
10,245.00 0.471% 2
45,000.00 2.068% 1

126,472.00 5.813%

10,459.00 0.490% 2
10,450.00 0.480% 2

10,450.00 0.480%

105,600.00 4.854% 1
105,600.00 4.854% 1
105,600.00 4.854%

72,491.42 3.400% 5

9,999.16 0.460% 1
23,398.08 1.076% 1
7,399.44 0.340% 1

3,610.47 0.166% 1

2,848.84 0.131% 1

12,963.84 0.596% 1

5,031.92 0.231% 1

4,581.40 0.211% 1

2,658.27 0.122% 1

72,491.42 3.332%

262,397.25 12.061% 14
133,926.00 6.156% 25
62,400.00 2.930% 5
60,573.70 2.784% 20

39,168.00 1.800% 3
220,241.25 10.124% 10
2,988.00 0.137% 2

67,575.00 3.106% 9
41,735.00 1.918% 5
13,944.00 0.641% 8
10,672.00 0.491% 3
62,400.00 2.868% 5

48,096.40 2.211% 8
10,560.00 0.485% 6
1,917.30 0.088% 4

519,296.95 23.870%

259,246.70 12.775% 15

2,000.00 0.092% 1
4,900.00 0.225% 1
15,000.00 0.689% 2

90,580.80 4.164% 3
50,565.90 2.324% 2

11,200.00 0.515% 1
27,200.00 1.250% 1
3,900.00 0.179% 2
900.00 0.041% 1

14,000.00 0.644% 1
11,800.00 0.542% 1
1,450.00 0.067% 2
2,800.00 0.129% 2
17,600.00 0.809% 1
5,450.00 0.251% 2

259,346.70 11.921%

20,700.00 1.018% 3

19,000.00 0.873% 1
1,700.00 0.078% 2

20,700.00 0.951%

77,539.88 3.570% 26

16,000.00 0.735% 1
4,960.00 0.228% 1
650.00 0.030% 1
7,900.00 0.363% 1

4,600.00 0.211% 1
3,600.00 0.165% 1
6,800.00 0.313% 1
1,900.00 0.087% 1
9,494.40 0.436% 1

6,097.48 0.280% 4
9,158.00 0.421% 4
1,780.00 0.082% 4
1,200.00 0.055% 3
750.00 0.034% 4
1,020.00 0.047% 5
1,170.00 0.054% 5
460.00 0.021% 2

77,539.88 3.564%

2,175,529.22 100.000%
OCTOBER
WEEK 3 WEEK 4 WEEK 5 WEEK 6
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
NOVEMBER
WEEK 6 WEEK 7 WEEK 8 WEEK 9
39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61
DECEMBER
WEEK 9 WEEK 10 WEEK 11 WEEK 12
62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83

70 71 72 73 74 75 76 77 78 79 80 81 82
K 12 WEEK 13 WEEK 14 WEEK 15
84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105

83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100
JANUARY
WEEK 16 WEEK 17 WEEK 18
106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126

101 102 103 104 105 106 107 108 109 110 111 112 113 114
FEBRUARY
WEEK 19 WEEK 20 WEEK 21
127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143 144 145
MARCH
EEK 21 WEEK 22 WEEK 23 WEEK 24
146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163 164

You might also like