Professional Documents
Culture Documents
INTRODUCTION
such as manpower, material, money, equipment, time or space Hisman (2015). The
depends on the quality and quantity of work, but also largely depends on
amount of resources. Each activity is allocated with a specific resource and must be
completed within the time limit, otherwise it may adversely affect the overall
duration of the project. The main objective of any construction project organization
is to utilize the resources to the optimum level. The availability of certain resources
may fluctuate due to various reasons. The intention is not to waste the resources
properly planned and executed to avoid the negative impacts of material shortage or
present era impose numerous financial, legal, ethical, environmental and logistic
1
projects employ voluminous resources. But they have in-built difficulties,
uncertainties and risks. These pose series of problems concerning resources, like
how much they are required, ‘where they are going to come from’, ‘when they
should be inducted at site’, where they should be housed’, ‘how to optimise their
utilisation’ and ‘when to demobilise’ .In general, construction projects are of high
value, and they employ huge resources of men, materials and machines. Major
works involve heavy investments- say from a hundreds of cores of rupees to a few
thousands of rupees, the use of high level technology and need an open ended
really a difficult task. The construction manager must develop a plan of action for
coordinated and timely manner in order to deliver a project within the frame of
limited funding and time. Hence, aside from a technology and process focus, a
development. (ESTIJ AUG 2012). It embraces the process by which the said
2
persons which include companies, firm and individuals, working as consultants,
main contractors and sub- contractors, material and component producers, plant and
In general, construction projects are of high value, and they employ huge resources
of men, materials and machines. But they have in built difficulties, uncertainties
and risks. These pose series of problems concerning resource, like how they should
be inducted to site, where they should be housed, how to optimise their utilization
construction site due to ineffective managing of site during planning and execution
in every phase of the project life cycle. In fact a state – of –the art resource
project objectives.
The aim of this study is to assess the impact of effective management of resource
on project delivery in Imo State using selected projects. To achieve this aim, the
3
i. To examine the extent to which human resources management affects
project delivery
delivery
delivery
delivery
1.4Research Questions
Imo State?
project delivery?
delivery?
delivery?
H01: Human resources management does not have significant effect on project
4
H02: Financial resources management does not have significant effect on project
Findings from the study would inform these officials on the necessary measures
that to need to be taken to ensure that county project resources are well managed
and push for identification of loopholes in the management of these resources. The
study was crucial in emphasizing the need for established and formalized project
resource plans, schedules and frameworks and systems for ensuring that the
performance.
The findings would be crucial in highlighting how poor and delayed project
resource allocation has influenced the success of road projects within the county
especially when there are delays in disbursements from the national government.
This could guide in the development of adequate project mobilization plans. The
findings could also form a basis for carrying out assessments of project resource
5
optimization in the county in order to identify the areas of resource wastage or
underutilization and how the county can deploy its project resources to attain
The study findings could also assist the policy makers in the national government
such as the Ministry of works that could assist in tightening the prudence
utilization of project resources at the county level in order to seal the loopholes for
The findings from the study would be a point of reference to other researchers who
delivery and approved the variables are Human resources management, financial
6
1.7.2. Geographical Scope
The study covered the period two months, from September, 2023 to October, 2023
units
The major limitation in this study that could be addressed in future research is the
Limited Access to Data; It was difficult to get respondents from our primary
source of data. This involves the personal interview through questionnaire with
most of the contractors and managers of the three organizations. Most of the times,
when you want to see them. The will either not available or the protocol which you
will pass through before you will be given access to see them. This limitation can
way.
7
CHAPTER TWO
LITERATURE REVIEW
effectively and efficiently at the time they are required (Watt, 2007).On basis of
internal resources that are prerequisite for project delivery. Its major focus is
resources of a project is often inclusive, but not limited to, costs of materials, labor
and equipment within the work of the project (Kerzner & Kerzner, 2017).
8
individual tasks (Westland, 2007).Thus, managing of resources is a vital part in
accordance with overview and scope ascertained during the phase of planning.
Resource planning is the act of allocating and utilizing resources that include
people, machinery and equipment and its aim is to maximize resource efficiency,
(Monk & Wagner, 2012). According to Umble, Haft and Umble (2015) resource
planning involves assigning the right tasks to the right team members at the right
time, so that your project delivers the required outputs, without any delays and
conflicts. Therefore, a proper resource plan will help in reducing budgeting and
help forecasting accurately project expenses and lead to better project performance.
efficiently assign the resources they have to jobs, tasks or projects they need to
complete, and schedule start and end dates for each task or project based on
resource availability (Gordon & Tulip, 2017). Chan, Chua and Kannan (2018)
observe that resource scheduling makes for better time estimates, as it provides one
more metric by which to measure your project schedule. With resource scheduling
comes superior organization for projects, teams, sites, equipment and any other
resource associated with the project. All this sets the stage for an intelligent
distribution of resources among your project tasks. Schwindt (2016) observe that
9
resource allocation is the process of assigning and scheduling available resources
in the most effective and economical manner. Projects will always need resources
and resources are scarce. The task therefore lies with the project manager to
determine the proper timing of those resources within the project schedule.
that has to be done and allows to plan and prepare for the project’s implementation
or achieving goals which makes it possible to analyze existing threats and risks to
corrective actions necessary to ensure that the project is within scope, on budget
and meets the specified deadlines (Elonen & Artto, 2019). Lyons, Runge,
Laskowski and Kendall (2019) observe that resource monitoring plays a pivotal
Therefore, resource monitoring helps project managers to track, analyse and report
10
2.1.2 Effective Implementation of projects
good practices information and lessons learned from previous projects to guide
effectively and transfer past experiences of past projects for the effectiveness of
new projects. Measuring the effectiveness of such past projects depends on the
existence of a method for measuring their degree of success. The concept appears
simple and straightforward, however many researchers over the years have
attempted to define and measure project success, a difficult and elusive concept
with many definitions (Thomas and Fernandez, 2008). The definition of project
success is ambiguous (Salleh, 2009). Pinto et al (1998) offer two main reasons for
project success ambiguity. First it is still not clear how to measure project success
because project stakeholders perceive project success or failure differently and thus
the outcome differently. Second is that the list of success or failure factors vary in
between project success and project management success. They defined project
success to be long-termed in nature oriented towards the expected total life span of
and control in the context of the short term life of the project development and
11
delivery. PMBOK (2008) stated that a project is successful if it achieves the triple
objective outcome of within time, scope, and quality. This is the traditional view of
successful achievement of time, cost and quality objectives, as well as the quality
of the project process (Erling et al, 2006). Turner (2004) identifies on time, within
standard for judging success. Erling et al (2006) stated that overall project success
deals with the wider and longer term impact of the project, which means both
project management success and project product success. They noted that project
success can be determined at the end of the project, which means in many cases,
success criteria will be determined months or years after finishing the project,
especially public projects. Baccarini (1999) used the concept project success in a
different approach, viewing it as product success, which implies the quality and
impact of the end product to the end user (in terms of satisfaction of user(s) needs,
staff and subcontract labour. It also means ensuring that they know what needs to
be done, when and how. According to Werner & DeSimone (2006), Human
12
Resource Management can be defined as the effective selection and utilization of
employees to achieve the goals and strategies of the organization, and also the
goals and needs of employees. Human Resources is said to be effective when the
contribute to the creation and realization of the mission, vision, strategy, and goals
of the organization. Thus, human resources could enable the company to create
more value (Hill and Jones, 2004). This is the result why it is vital to manage and
Investigations on the link between HRM and project performance has extensively
been done in the US and the UK. Several authors point out that research needs to
be conducted in others contexts (Ericksen & Dyer, 2005; Wright et al., 2005).
Research on HR practices and their link to firm’s performance in most cases do not
address the issue of horizontal integration and vertical alignment. This is centrally
and contribution to project performance should be explored. Koca & Uysal (2009)
13
researched on HRM practices and firms performance and found out that HRM
practices have a strong relationship with project performance but weak relationship
HRM practices and found a positive significant relationship between practices and
organizational performance. Uysal and Koca (2009) found out that recruitment,
training and performance based pay all have a significant positive relationship with
These are the costs associated with the project, they include costs for labour hours,
purchase of software and purchase price for material and equipment required for
the project among others. Project budget is the third constraint included in the iron
triangle of constraints, and one that receives a lot of attention in relation to failed
projects. If the project scope and schedule cannot be altered, then this constraint
will usually need to be altered to allow for project completion (Turner, 2004). The
budget will often be the determining factor in deciding exactly how a project will
be executed, as one of the decisions that may need to be made is whether to buy or
build the solution. Depending on available internal resources and the available
14
external offerings, this decision will influence whether a certain service is supplied
(PMI, 2008). Managing the budgetary constraint also involves calculating the
an accurate project cost estimate that takes into account the risks and uncertainties
potential negative effects. This is usually designated in the budget in the form of a
contingency reserve. The pro ect’s cost management processes are: resource
planning, cost estimation, cost budgeting and cost control (Schwalbe, 2007).
well as personnel. Cost estimation deals with approximations of all the costs for
carrying out all anticipated activities. Once approximations have been made for the
total costs, cost allocation is then made for individual activities through the process
of cost budgeting. After the project has started, it is necessary to control the cost
changes that occur during deployment. There is however a strong interaction and
overlapping of the processes among themselves. One of the most popular methods
survey is the Activity-Based Costing (White & Fortune, 2002). This is however yet
15
to take effect in Africa and Kenya as well. The purpose of ActivityBased Costing
(ABC) is to measure costs and therefore profitability based on the cost of time.
profitability. The costs of risk mitigation are attributed to appropriate project tasks
and subtracted from project margins (Barkley, 2004). As the name suggests, Cost-
Benefit Analysis identifies, specifies and evaluates a proposal’s costs and benefits
Field & Keller, 1998). It is a typical financial measurement tool, which is also used
Analysis is a tool which is directly related to choosing the best project or finding
the best solution to the project mission. According to Besner & Hobbs (2006) 37%
of respondents of White’s and Fortune’s empirical survey answered that they make
Ren et al., 2011 did a survey on material handling in mining the physical
that a lot of Just-In Time benefits on cost are derived during high inflation
resulting to great rise in the cost of holding stock of materials. It suggested that
companies should be able to focus on planning of materials required, and the time
they are required. The study didn’t show evidently the level of association that
16
exist between material consumption and the performance of a project. The study
agricultural projects that have taken long to be completed in London. This survey
discovered that the management of a project has the main objective attaining the
level of materials the financiers had projected towards that project. With this study,
performance with least anomalies, projects producing desired outcome within the
time. Nonetheless, the study failed to contemplate a lot of other factors prevailing
construction projects. They further explored the ICT techniques presently being
17
sector on the basis of productivity, project duration, cost and quality. Wastage of
constraints that limit it from achieving its objectives. Some of these limiting factors
which might impact on performance. In this theory, constraints define the output of
a given system whether or not they are recognized. The aim of the top management
organization. This way the organization can effectively be able to realize its goals
and maximize profits. This theory describes the causes of the system constraints
and also sheds light on the best ways to deal with these constraints (Goldratt,
18
together in generating outputs from inputs when pursuing certain goals. The
limitation for this system is a constraint which prevents the system from its efforts
constraints is applicable in this study since the planning, scheduling, allocation and
monitoring of project resources are constraints that face project teams in counties
when carrying out road infrastructure projects. The best way to handle such kind of
success of projects are inadequate resources that are poorly allocated to project
into inefficiencies and delays which might result in increased costs of projects.
This is a theory by Barney (1991) which indicates that the possession of resources
which are strategic provides a given organization with a superb chance of creating
a competitive advantage over their rivals. This competitive edge can aid the
are made available throughout the cycle stages of a project in ensuring their
19
success as compared to implementation of projects of other institutions as follows;
of capabilities of the firm, assessing the ability of resources to generate rent and
how capable they are in terms of maintaining sustainability, selection of a the best
resource exploitation strategy within the firm in relation to its rivals and
Brenman,1996). This theory is an exploration of the desire for the right form of
Based on this, management makes use of the readily obtainable resources and
utilizing them for maximum success of projects in place. This theory is thus
and monitoring of project resources towards ensuring that projects are successful.
This study was based on resource dependence theory by Pfeffer and Salancik
(1978). The theory describes projects as being exposed not only to internal but also
resources of its environment which are necessary for the project organization to
exist and excel in successful completion of projects. External factors are able to
20
control these resources to a certain degree which can influence the behaviour of
project team members and build external dependence. To increase control of power
themselves (Ulrich & Barney, 2014). In doing so, resource dependence theory
on resources which are critical for their long term survival. A good portion of the
and exploit raw materials faster than competitors can be fundamental to success.
was used. There was a positive link between financial monitoring and programme
performance for INGOs. The study underscored that the programme performance
for INGOs could be greatly improved if on site visits, financial desk reviews and
21
periodic financial review meetings were conducted. Financial monitoring needed
misallocated as they were utilized for the core business of the programs existence.
However, the contextual setting of this study varies as it focuses on projects which
Kenya. Study relied upon the design of descriptive survey. Investigations revealed
that enough efforts to monitor and control the project resources ensured that
project funds were spent appropriately as planned and with proper authorization.
The study noted that the tools for monitoring progress and how often financial
auditing and reporting were undertaken helped to eliminate waste and served as a
assessing the process and system used in capturing and reporting project costs.
communications firms which are different from public road projects undertaken by
22
Kamwana and Muturi (2014) evaluated the level of success of projects which were
monitoring. A descriptive study design was applied. It was established that the
the funds enhanced their wise usage for the envisioned purposes and enhanced the
creation of value for the beneficiaries. Financial resource monitoring ensured that
cases of diversion of project resources to other purposes and interests outside the
project scope and work plans were minimized. Monitoring how the resources were
used ensured that projects were implemented in accordance to the set budget and
time frames. The study underlined the role of unexpected audits where there was
study varies and focuses on different projects from the ones considered in this
current study.
Jha and Iyer (2016) assessed the significant dynamics that affected the quality
projects in the industry of construction within India. The study made use of the
projects which improved their quality. Ensuring that all cases of inappropriate use
23
of project resources, whether material, labor, plant and machinery or finances were
monitored well and reporting done on time, the anticipated project quality was
attained. However, the study was carried out in a different setting and focuses on
different projects from those considered in this study hence a contextual gap.
While it would be true to say that quite a number of authors have addressed the
issue of resource management, the author feels that the subject of the impact of
projects is not well covered. This is due to a number of reasons which create a gap
to be researched on. Many models have been formulated for both resource
planning and leveling and cited by different authors such as Abeyasinghe et al.
(2001); Ballard, (2000); Bandelloni et al. (1994); Easa (1989); Fathi and Afshar
(2008); Garmsiri and Abassi (2012); Hegazy, (1999); Hussain et al. (2014);
Iranagh and Sonmez (2012); Jun (2010); Kastor and Sirakoulis (2009); Leu and
Yang (1999); MacKenzie (2013); Mattila and Abraham (1998a); Mattila and
Abraham (1998b); Yesugey (2014); Reddy and Nagaraju (2015); Schweiz (2014);
Senouci and Adeli (2001); Senouci and Eldin (2004); Son and Mattila (2004); and
Son and Skibniewski (1999). However, all these models have been postulated by
authors from developed countries for their construction industries. This means that
using these models for the Nigeria industry would therefore be misleading. The
24
same argument holds for the challenges, barriers and benefits associated with
literature review have been based on the manufacturing sector in the developed
countries.
25
CHAPTER THREE
METHODOLOGY
The study adopted a descriptive survey design. This design was preferred because
it was more effective and enabled the researcher to collect relevant data that
and report on the situation as it exists and also helps a researcher in describing the
According to Mugenda (2008), the target population is the entire set of similar
items or objects that a researcher identifies in his or her research. The study
26
3.4 Sample Size and Sampling Technique
Sampling is the process through which a researcher identifies the people, places or
things to be studied (Kombo & Tromp, 2006). The study employed random
purposive sampling and snow balling sampling in reaching respondents for the
to large size of the target population, the researcher used the Taro Yamani formula
n= N
1+N(e)2
n= 178
1+ 178(0.05)2
= 178
1+ 178(0.0025)
= 123
3.5.1 Questionnaire
Both quantitative and qualitative data were collected in this study. The
questionnaire was the instrument for used in collecting primary data from the
the objectives of this study. The questionnaire entailed both close-ended and open
27
ended questions. The questionnaire was divided into two sections, the background
questions section was divided into sections according to the research objectives on
questionnaires is that they are easier to analyse and also permit greater depth of
In social sciences, measurement issues differ in that they are related to the
instances, then, the meaning of quantities is only inferred. Most concepts in the
behavioral sciences have meaning within the context of the theory that they are a
part of. Therefore, the research instruments chosen must be able to measure the
inferences made from the research results are accurate and meaningful. The
research instruments were validated in terms of content and face validity. The
28
researcher sought experts‟ opinion in assessing validity of the instrument. The
questionnaire of the pilot study was assessed and weakness identified for example
few blank spaces, inaccurate responses, and in consistency on the instrument. The
questionnaire was then modified accordingly and pretested on subjects who were
not the actual sample. The subjects were encouraged to write comments and
Reliability refers to the consistency of data arising from the use of a particular
research method. Mugenda and Mugenda (2008), states that reliability is the
measure of the extent to which a research instrument will give the same result
consistently after repeated trials over a period. In this study, split-half method was
used to test the reliability of the research instruments. Tests were divided into two
halves of odd and even items. The sets were then separated into two different
groups. Correlation coefficient for the two sets of scores was calculated to show
the extent to which the two sets of the test provided the same results for internal
Because both closed-end and open-end questionnaires were used in the study, both
quantitative and qualitative data was collected. For content analysis, data was
29
Package for Social Sciences (IBM SPSS Version 23) software was used for this
analysis.
statistical technique that uses several explanatory variables to predict the outcome
of a response variable. The goal of multiple linear regression is to model the linear
variable.
Multiple regressions is the most widely used technique in the social sciences for
generally assumes that the dependent variable is continuous. Yet many of the
dependent variables social scientists wish to study are not continuous. Indeed,
many have only two possible values (an event did, or did not, occur), and are
30
Where
Yi = dependent variable
B0 = intercept
Before data collection, the researcher sought authorization from the various project
to carry out research. The researcher also assured the respondents of confidentiality
of the information obtained and farther that the information was solely be used for
the purpose of the study. Individuals will be given the option to refuse to
participate if the so wish. The dignity, privacy and interest of the participants were
treated with utmost respect. Research data from this study was confidential and all
credit was given to parties contributing to the research. Bryman (2011) states that it
is the researcher bears the responsibility of carefully assessing the possibility that
the research may cause harm to the participants, and to the extent that it is possible,
31
CHAPTER FOUR
The chart above shows the distribution of the age from the responses of our
respondents, from the chart we can see that we have few respondents who are
within the age group of 31 – 40 years, with most of our respondents being above
40, this shows that our sample is mainly made up experienced and matures
persons.
32
Fig 2: Gender
The chart above showed us the gender distributions from the responses of our
respondents, from the chart we can see that we have more male respondent when
compared to the female respondents, this could be as a result of more men taking
up management opportunities.
33
The chart above shows us the level of education our respondents have attend, from
their responses we can see that most of our respondents have acquired their
bachelor’s degree, followed by those who have their Diploma, then those who have
The chart above shows the field where our respondents are currently working in,
the charts shows us that most of our respondents are working in the business
management unit, this is followed by those who works in the project management
unit, this is closes followed by those who are in the building construction unit and
then those who are not working in any of the sectors listed.
34
Fig 5: Years of Experience
The chart above shows us the number of years of experience which our
respondents have in their specific industries, from our respondents we can see that
most of our respondents have 11 -15 years of experience in their industry, this is
followed by those who have less than 5 years of experience, then those who have 6
This section shows the presentation of data from our respondents, the table shows
questions asked.
35
Our respondents were asked to tick against their choice. e.g “SA-STRONGLY
DISAGREE”
SA A N D SD
There are qualified and competent employees Working in this
project 28 22 25 23 25
The number of employees for this project are Enough to carry out
all the activities required 30 25 21 27 20
The method used to recruit employees is Effective 23 29 22 34 15
The workers in this project are very much Cooperative 24 28 22 23 26
The management sometimes delegate Authority to the workers 25 21 23 30 24
The workers are competent enough to receive Delegation of
authority 28 25 20 27 23
The employees are trustworthy and can carry Out duties without
close supervision 22 26 34 21 20
The employees are motivated through various Means like better
remuneration, paid Holidays, promotions etc. 31 17 29 23 23
Employees are paid their salaries and wages Promptly 23 16 40 17 27
Internal training of the employees is carried Out from time to
time. 28 34 21 20 20
The table above shows the responses of our respondents on the effect of human
Our respondents were asked to tick against their choices SA, A, N, D, SD.
36
From the table we can see that most of our respondents (28), strongly agreed that
there are qualified and competent employees Working in this project, they also
strongly agreed (30) that the number of employees for this project are Enough to
carry out all the activities required, but they disagreed (34) that the method used to
recruit employees is Effective and agree (28) that the workers in this project are
Authority to the workers, but were not sure (34) whether the employees are
trustworthy and can carry Out duties without close supervision and finally agreed
(34) that Internal training of the employees is carried Out from time to time.
SA A N D SD
Records that relate to finances are kept well 28 32 18 20 25
Financial records are safe from manipulation by unauthorized
persons 21 17 32 21 32
Keeping of records bring about efficiency in Management of
Finances 19 32 26 19 27
There is a budget made for this project 23 24 30 34 12
We have strictly stuck to the budget to this far 25 26 19 30 23
The budget has been helpful in management of finances 23 28 18 27 27
The suppliers and employees are paid their dues in time 24 23 25 25 26
We have not received any complaints from suppliers and
employees as regards payments 27 21 30 24 21
The payments for any transaction is done by IFMIS 20 26 26 27 24
The use of IFMIS for payment is efficient in managing finances 24 27 22 25 25
37
The table above shows the responses of our respondents on the effect of financial
Our respondents were asked to tick against their choices SA, A, N, D, SD.
From the responses of our respondents most of them agreed (32) that records that
relate to finances are kept well, most of them strongly disagreed (32) that financial
records are safe from manipulation by unauthorized persons, they also disagreed
From the responses of our respondents they also strongly disagree (26) that
suppliers and employees are paid their dues in time, and they agree (27) that the
SA A N D SD
Training and Sensitization of officers on procurement act 2005 and
2006 28 18 18 31 28
Officers participation in tendering processes 23 26 21 24 29
Public entities comply with the public procurement procedure 35 19 26 24 19
Procurement entities apply appropriate procurement methods 23 18 29 25 28
Entities use standard tender documents from PPOA 22 28 28 18 27
Procurement staff are qualified and experienced to handle
procurement process 19 28 27 20 29
Procurement officers make informed decisions 22 22 28 27 24
Tender evaluation is conducted by competent persons 25 23 17 26 32
Procurement opportunities are advertised using appropriate medium 27 22 32 23 19
38
There is effective monitoring and auditing 34 14 22 30 23
The table above shows the responses of our respondents on the effect of
Our respondents were asked to tick against their choices SA, A, N, D, SD.
The results from our respondents shows us that most of them strongly disagree (29)
that officers participation in tendering processes, but they strongly agree (35) that
public entities comply with the public procurement procedure, most of them (29)
were not sure when asked if procurement entities apply appropriate procurement
methods.
From the responses of our respondents we can see that most of them strongly
disagree (29) that procurement staff are qualified and experienced to handle
procurement process, most of our respondents also strongly disagreed (32) that
SA A N D SD
Communication between management and workers is done through
internal memos 20 28 18 33 24
Use of internal memos to communicate to the workers is found to be
effective 24 33 20 23 23
Information is exchanged between the project managers, county
government managers and other concerned parties through e-mails 25 26 14 28 30
Use of e-mails, texts and telephone calls to communicate to the county 25 33 22 23 20
39
officials and other concerned parties in project management found to
be effective
Both vertical and horizontal channels of communications are employed
while passing information 16 29 30 16 32
Use of both vertical and horizontal channels of communication is
effective in exchanging information among the project team. 19 39 20 23 22
The languages that are being used to communicate is English which
are understood by all and never vernacular 16 28 23 26 30
The use of English has brought about clear understanding of the
information being passed hence effective in Communication 28 25 25 25 20
There has been freedom for everybody in the team to exchange
information without any limitation 33 20 16 26 28
All the recipients of the information do give feedback to ensure
communication process is complete 24 22 22 29 26
The table above shows the responses of our respondents on the effect of
Our respondents were asked to tick against their choices SA, A, N, D, SD.
The responses from our respondents show that most of them disagree (28) that
memos, but they agree (39) Use of internal memos to communicate to the workers
is found to be effective, they also agree (33) that the use of e-mails, texts and
telephone calls to communicate to the county officials and other concerned parties
40
They also strongly disagree (32) that both vertical and horizontal channels of
communications are employed while passing information but most of them agree
(39) that the use of both vertical and horizontal channels of communication is
effective in exchanging information among the project team, they also strongly
agreed (28) that the use of English has brought about clear understanding of the
Finally they disagree (29) that all the recipients of the information do give
REGRESSION ANALYSIS
The regression analysis was used to test for any significant impact of our
Human Resources
Table 1: Descriptive Statistics for the Human resource Management
Descriptive Statistics
Std.
Mean Deviation N
Human Resource
3.15 1.401 123
management
There are qualified and
competent employees 2.96 1.451 123
Working in this project
41
The number of
employees for this
project are Enough to 2.85 1.430 123
carry out all the
activities required
The method used to
recruit employees is 2.91 1.324 123
Effective
The workers in this
project are very much 2.99 1.434 123
Cooperative
The management
sometimes delegate
3.06 1.422 123
Authority to the
workers
The workers are
competent enough to
2.93 1.447 123
receive Delegation of
authority
The employees are
trustworthy and can
carry Out duties 2.93 1.325 123
without close
supervision
The employees are
motivated through
various Means like
2.92 1.446 123
better remuneration,
paid Holidays,
promotions etc.
42
Employees are paid
their salaries and wages 3.07 1.380 123
Promptly
Internal training of the
employees is carried 2.76 1.399 123
Out from time to time.
The table above shows us the descriptive analysis from our respondents on the
effect of human resources on the delivery of projects, the table shows us the mean,
H0: Human resources management does not have significant effect on project
H1: Human resources management has significant effect on project delivery in Imo
State
The table above shows us the model summary for the responses of our respondents
43
The R, in the model is the correlation Statistic which is used to test for the strength
correlation between our dependent variable (Project delivery) and our independent
variable (human resources), this shows us that better human resources management
The R square in the model is the test statistic to check how well the independent
variable can predict the variations in the dependent variable, it is used to check if
have an R square value of 0.962 which is 96.2% this shows us that the quality of
human resources can predict the project delivery 96.2% with 96.2% accuracy
Conclusion
The results from our analysis show us that human resource significantly affects
44
Table 3: the ANOVA table for human resources
ANOVA
Sum of
Model Squares df Mean Square F Sig.
1 Regression 23.058 10 2.306 1.194 .003
Residual 216.307 112 1.931
Total 239.366 122
The table above is the ANOVA analysis for the significance of the regression
model
Decision Rule
If the p –value is < 0.05 we reject the null hypothesis
Conclusion
Since the p-value = 0.003 < 0.05 we reject the null and therefore conclude that the
regression model is significant and human resource management significantly
affect project delivery in Imo state.
Table 4: the coefficients of the regression model for Human Resources
Coefficientsa
Unstandardized Standardized
Coefficients Coefficients
Model B Std. Error Beta t Sig.
1 (Constant) 4.361 .908 4.803 .000
There are qualified and competent
-.087 .091 -.090 -.956 .341
employees Working in this project
The number of employees for this -.094 .091 -.096 -1.031 .305
project are Enough to carry out all
the activities required
45
The method used to recruit
.183 .101 .173 1.819 .072
employees is Effective
The workers in this project are very
-.087 .092 -.089 -.946 .346
much Cooperative
The management sometimes
-.223 .093 -.226 -2.386 .019
delegate Authority to the workers
The workers are competent enough
-.001 .088 -.001 -.007 .994
to receive Delegation of authority
The employees are trustworthy and
can carry Out duties without close .024 .100 .023 .240 .811
supervision
The employees are motivated
through various Means like better
-.030 .089 -.031 -.341 .733
remuneration, paid Holidays,
promotions etc.
Employees are paid their salaries
-.136 .097 -.134 -1.404 .163
and wages Promptly
Internal training of the employees is
.057 .094 .057 .603 .548
carried Out from time to time.
a. Dependent Variable: Human Resource management
The table above shows the coefficients of the regression model for the impact of
human resources management on project delivery.
It shows us the independent variables in the model that significantly affects the
dependent variable.
46
Financial Management
47
We have not received
any complaints from
suppliers and 2.93 1.392 123
employees as regards
payments
The payments for any
transaction is done by 3.07 1.368 123
IFMIS
The use of IFMIS for
payment is efficient in 3.00 1.426 123
managing finances
The table above shows us the descriptive analysis from our respondents on the
effect of financial resources on the delivery of projects; the table shows us the
mean, standard deviation and number of respondents.
H0: Financial resources management does not have significant effect on project
delivery in Imo State
H1: Financial resources management has significant effect on project delivery in
Imo State
The table above shows us the model summary for the responses of our respondents
on the significant impact of financial resources management on the delivery of
projects.
48
The R in the model is the correlation Statistic which is used to test for the strength
of the relation, sine we have an R value of 0.779 we have a strong positive
correlation between our dependent variable (Project delivery) and our independent
variable (financial resources management), this shows us that better financial
resources management leads to better project delivery.
The R square in the model is the test statistic to check how well the independent
variable can predict the variations in the dependent variable, it is used to check if
there exist a relationship between the dependent and independent variables, we
have an R square value of 0.878 which is 96.2% this shows us that the quality of
financial resources management can predict the project delivery with 87.8%
accuracy
Conclusion
The results from our analysis show us that financial resource management
significantly affects project delivery in Imo State.
H0: the regression model is not significant
H1: the regression model is significant
Table 7: the ANOVA table for financial resources management
ANOVAa
Sum of
Model Squares df Mean Square F Sig.
1 Regression 18.364 10 1.836 .946 .005b
Residual 217.506 112 1.942
Total 235.870 122
a. Dependent Variable: Financial Management
The table above is the ANOVA analysis for the significance of the regression
model
Decision Rule
49
If the p –value is < 0.05 we reject the null hypothesis
Conclusion
Since the p-value = 0.005 < 0.05 we reject the null and therefore conclude that the
50
The budget has been
helpful in management -.088 .092 -.092 -.961 .339
of finances
The suppliers and
employees are paid -.037 .093 -.038 -.401 .689
their dues in time
We have not received
any complaints from
suppliers and .057 .094 .058 .611 .543
employees as regards
payments
The payments for any
transaction is done by .210 .101 .206 2.085 .039
IFMIS
The use of IFMIS for
payment is efficient in -.045 .094 -.046 -.481 .632
managing finances
a. Dependent Variable: Financial Management
The table above shows the coefficients of the regression model for the impact of
financial resources management on project delivery.
It shows us the independent variables in the model that significantly affects the
dependent variable.
51
Procurement Management
Descriptive Statistics
Std.
Mean Deviation N
Procurement
2.98 1.385 123
Management
Training and
Sensitization of officers
3.11 1.492 123
on procurement act
2005 and 2006
Officers participation in
3.08 1.452 123
tendering processes
Public entities comply
with the public 2.78 1.440 123
procurement procedure
Procurement entities
apply appropriate 3.14 1.416 123
procurement methods
Entities use standard
tender documents from 3.00 1.408 123
PPOA
Procurement staff are
qualified and
3.10 1.399 123
experienced to handle
procurement process
Procurement officers
make informed 3.07 1.380 123
decisions
52
Tender evaluation is
conducted by 3.14 1.500 123
competent persons
Procurement
opportunities are
2.88 1.365 123
advertised using
appropriate medium
There is effective
2.95 1.492 123
monitoring and auditing
The table above shows us the descriptive analysis from our respondents on the
effect of procurement management on the delivery of projects; the table shows us
the mean, standard deviation and number of respondents.
H0: Procurement management does not have significant effect on project delivery
in Imo State
The table above shows us the model summary for the responses of our respondents
53
The R, in the model is the correlation Statistic which is used to test for the strength
correlation between our dependent variable (Project delivery) and our independent
The R square in the model is the test statistic to check how well the independent
variable can predict the variations in the dependent variable, it is used to check if
have an R square value of 0.872 which is 87.2% this shows us that the quality of
procurement management can predict the project delivery with 87.2% accuracy
Conclusion
The result from our analysis shows us that procurement management significantly
54
a. Dependent Variable: Procurement Management
The table above is the ANOVA analysis for the significance of the regression
model
Decision Rule
Conclusion
Since the p-value = 0.003 < 0.05 we reject the null and therefore conclude that the
Table 12: the coefficients of the regression model for Procurement management
Coefficientsa
Unstandardized Standardized
Coefficients Coefficients
Model B Std. Error Beta t Sig.
1 (Constant) 4.868 .987 4.931 .000
Training and
Sensitization of officers
.044 .087 .047 .508 .612
on procurement act
2005 and 2006
Officers participation in
-.032 .089 -.033 -.353 .725
tendering processes
Public entities comply -.100 .090 -.104 -1.108 .270
with the public
procurement procedure
55
Procurement entities
apply appropriate -.076 .092 -.078 -.833 .407
procurement methods
Entities use standard
tender documents from -.177 .093 -.180 -1.902 .060
PPOA
Procurement staff are
qualified and
-.151 .095 -.153 -1.591 .114
experienced to handle
procurement process
Procurement officers
make informed -.125 .093 -.124 -1.336 .184
decisions
Tender evaluation is
conducted by -.026 .087 -.029 -.305 .761
competent persons
Procurement
opportunities are
.033 .096 .033 .349 .728
advertised using
appropriate medium
There is effective
-.012 .086 -.013 -.143 .887
monitoring and auditing
a. Dependent Variable: Procurement Management
The table above shows the coefficients of the regression model for the impact of
It shows us the independent variables in the model that significantly affects the
dependent variable.
Communication Management
56
Table 13: Descriptive Statistics for the Communication management
Descriptive Statistics
Std.
Mean Deviation N
Communication
2.85 1.353 123
Management
Communication
between management
3.11 1.390 123
and workers is done
through internal memos
Use of internal memos
to communicate to the
2.90 1.411 123
workers is found to be
effective
Information is
exchanged between the
project managers,
county government 3.10 1.495 123
managers and other
concerned parties
through e-mails
Use of e-mails, texts
and telephone calls to
communicate to the
county officials and 2.84 1.381 123
other concerned parties
in project management
found to be effective
57
Both vertical and
horizontal channels of
communications are 3.15 1.385 123
employed while passing
information
Use of both vertical and
horizontal channels of
communication is
2.92 1.359 123
effective in exchanging
information among the
project team.
The languages that are
being used to
communicate is English
3.21 1.380 123
which are understood
by all and never
vernacular
The use of English has
brought about clear
understanding of the
2.87 1.402 123
information being
passed hence effective
in Communication
There has been freedom
for everybody in the
team to exchange 2.97 1.541 123
information without
any limitation
58
All the recipients of the
information do give
feedback to ensure 3.09 1.432 123
communication process
is complete
The table above shows us the descriptive analysis from our respondents on the
effect of communication management on the delivery of projects, the table shows
us the mean, standard deviation and number of respondents.
H0: Communication management does not have significant effect on project
delivery in Imo State
H1: Communication management has significant effect on project delivery in Imo
State
Table 14: Model Summary for Communication Management.
Model Summaryb
Adjusted R Std. Error of Durbin-
Model R R Square Square the Estimate Watson
1 .801 .961 .886 1.294 1.753
b. Dependent Variable: Communication Management
The table above shows us the model summary for the responses of our respondents
on the significant impact of communication management on the delivery of
projects.
The R in the model is the correlation Statistic which is used to test for the strength
of the relation, sine we have an R value of 0.801 we have a strong positive
correlation between our dependent variable (Project delivery) and our independent
variable (communication management), this shows us that better communication
management leads to better project delivery.
59
The R square in the model is the test statistic to check how well the independent
variable can predict the variations in the dependent variable, it is used to check if
there exist a relationship between the dependent and independent variables, we
have an R square value of 0.886 which is 88.6% this shows us that the quality of
communication management can predict the project delivery with 88.6% accuracy
Conclusion
The results from our analysis show us that communication management
significantly affects project delivery in Imo State.
H0: the regression model is not significant
The table above is the ANOVA analysis for the significance of the regression
model
Decision Rule
If the p –value is < 0.05 we reject the null hypothesis
Conclusion
Since the p-value = 0.006 < 0.05 we reject the null and therefore conclude that the
regression model is significant and communication management significantly
affect project delivery in Imo state.
60
Table 16: the coefficients of the regression model for Communication management
Coefficientsa
Unstandardized Standardized
Coefficients Coefficients
Model B Std. Error Beta t Sig.
1 (Constant) 2.262 .826 2.739 .007
Communication
between management
-.128 .091 -.131 -1.402 .164
and workers is done
through internal memos
Use of internal memos
to communicate to the
.164 .084 .171 1.955 .053
workers is found to be
effective
Information is
exchanged between the
project managers,
county government -.043 .080 -.048 -.540 .591
managers and other
concerned parties
through e-mails
Use of e-mails, texts .128 .089 .130 1.440 .153
and telephone calls to
communicate to the
county officials and
other concerned parties
in project management
found to be effective
61
Both vertical and
horizontal channels of
communications are -.147 .086 -.151 -1.707 .091
employed while passing
information
Use of both vertical and
horizontal channels of
communication is
.029 .089 .029 .323 .747
effective in exchanging
information among the
project team.
The languages that are
being used to
communicate are
.189 .095 .193 1.991 .049
English which are
understood by all and
never vernacular
The use of English has
brought about clear
understanding of the
-.152 .085 -.157 -1.794 .076
information being
passed hence effective
in Communication
There has been freedom -.056 .081 -.064 -.691 .491
for everybody in the
team to exchange
information without
any limitation
62
All the recipients of the
information do give
feedback to ensure .213 .086 .226 2.479 .015
communication process
is complete
a. Dependent Variable: Communication Management
The table above shows the coefficients of the regression model for the impact of
communication management on project delivery.
It shows us the independent variables in the model that significantly affects the
dependent variable.
63
CHAPTER FIVE
5.1 Introduction
This chapter gives the summary of the study findings, discussions of the research
findings where the findings are compared with the findings of other relevant
studies which were earlier carried out, conclusions that were drawn by the
researcher according to the findings of the study and the recommendations made
by the researcher for the status improvement. The study further illustrates the
The study was conducted to assess the influence of effective management practices
64
5.3 Conclusion
From the responses gathered from project team, there was a strong appreciation of
management practices and its effect on project performance within the industry.
With regards to the specific project management practice issues, there was
respondents indicated that there was no effective regular monitoring and auditing
Majority of the respondents cited that there were failures in project delivery time
lines. For example many noted that this was as a result of delays in getting
overrun. Proper project planning and budgeting with regular project review
From the above findings it was concluded that qualified and competent employees,
adequate number of staff, cooperation amongst staff was good and delegation of
give equal opportunity for selection on merit and ability; on level of motivation
they should show staff clear expectations, valued, trusted, encouraged and
motivated to give their best including paying their salary and wages promptly.
65
The findings indicate that people who are managed well will give their best to
and use of IFMIS in financial transactions. However, a lot need to be done in terms
means to reach the project team such as internal memos, vertical and horizontal
5.4 Recommendation
As a result of these study findings, the researcher put forward the following
66
authority to staff should be encouraged. The organizations to improve on
to public scrutiny, give equal opportunity for selection on merit and ability.
value, trust and encourage them so as to enhance motivation and overcome delay
supply should also be improved to overcome project delivery timelines and cost
67
clearly understood by everybody in the project team. Staff should be facilitated to
influences project performance since the study findings on each and every research
68
References
69
Dansoh, A., Frimpong, S., & Oteng, D. (2017). Industry environment features
influencing construction innovation in a developing country: a case study of
four projects in Ghana. International Journal of Technological Learning,
Innovation and Development. https://doi.org/10.1504/ijtlid.2017.082756
Donaldson, L. (2014). The Contingency Theory of Organizations. In The
Contingency Theory of Organizations.
Garcia-Torres, S., Albareda, L., Rey-Garcia, M., & Seuring, S. (2019). Traceability
for sustainability – literature review and conceptual framework. In Supply
Chain Management.
Goldratt, E. M. (1990). What Is This Thing Called Theory of Constraints and How
Should It Be Implemented? Great Barrington: North River Press.
Günhan, S., & Arditi, D. (2007). Budgeting owner’s construction contingency.
Journal of Construction Engineering and Management.
https://doi.org/10.1061/(ASCE)0733- 9364(2007)133:7(492)
Hintze, S. (2015). Pilot study. In Contributions to Management Science.
Homayounfard, H., & Safakish, G. (2016). A Human Resource Evaluation Toolkit
for Mega Size Industrial Projects. Procedia - Social and Behavioral
Sciences.
Iacovidou, E., & Purnell, P. (2016). Mining the physical infrastructure:
Opportunities, barriers and interventions in promoting structural components
reuse. In Science of the Total Environment.
Institute, P. M., & PMI. (2016). Construction Extension to the PMBOK® Guide.
In Project Management Institute.
Jin, H., Shen, L., & Wang, Z. (2018). Mapping the Influence of Project
Management on Project Cost. KSCE Journal of Civil Engineering.
Kaarsholm, P., & Frederiksen, B. F. (2019). Amaoti and Pumwani: Studying urban
informality in South Africa and Kenya. African Studies.
70
Kerzner, H. (2017a). Project management case studies. In Project Management
Case Studies.
Kerzner, H. (2017b). Project Management Organizational Structures. In Project
Management Case Studies.
Khan, A. S., & Rasheed, F. (2015). Human resource management practices and
project success, a moderating role of Islamic Work Ethics in Pakistani
project-based organizations. International Journal of Project Management.
Khodakarami, V., & Abdi, A. (2014). Project cost risk analysis: A Bayesian
networks approach for modeling dependencies between cost items.
International Journal of Project Management.
Kimmons, & Kimmons, R. L. (2018). The Project Manager. In PROJECT
MANAGEMENT.
Lam, T. Y. M., & Siwingwa, N. (2017). Risk management and contingency sum of
construction projects. Journal of Financial Management of Property and
Construction.
Marcelino-Sádaba, S., González-Jaen, L. F., & Pérez-Ezcurdia, A. (2015). Using
project management as a way to sustainability. from a comprehensive review
to a framework definition. In Journal of Cleaner Production.
Mian, A., Sufi, A., & Verner, E. (2017). Household debt and business cycles
worldwide. Quarterly Journal of Economics.
Pritchard, C. L., & Pritchard, C. L. (2019). Work Breakdown Structure. In The
Project Management Drill Book.
Project Management Institute. (2017). The Standard for Program Management. In
PMI.
Ren, Z., Anumba, C. J., & Tah, J. (2011). RFID-facilitated construction materials
management (RFID-CMM) - A case study of water-supply project.
Advanced Engineering Informatics.
71
Rhodes, C. (2015). Construction Industry: Statistics and policy. House of
Commons Library.
Rodnyansky, A., & Darmouni, O. M. (2017). The effects of quantitative easing on
bank lending behavior. Review of Financial Studies.
Rugenyi, F., & Bwisa, P. H. (2016). Effects of triple constraints on the
management of projects in Nairobi: the project managers’ perspective. The
Strategic Journal Ob Business & Change Management.
Sanchez, B., & Haas, C. (2018). Capital project planning for a circular economy.
Construction Management and Economics.
Shahzad, K., Bajwa, S. U., Ansted, R. B., Mamoon, D., & Khaliq-ur-Rehman.
(2016). Evaluating human resource management capacity for effective
implementation of advanced metering infrastructure by electricity
distribution companies in Pakistan. Utilities Policy.
Shash, A. A., & Qarra, A. Al. (2018). Cash Flow Management of Construction
Projects in Saudi Arabia. Project Management Journal.
Shipworth, D., & Huebner, G. M. (2017). Designing research. In Exploring
Occupant Behavior in Buildings: Methods and Challenges.
Skinner, H. (2016). Action research. In Formative Research in Social Marketing:
Innovative Methods to Gain Consumer Insights.
Skulmoski, G., T. Hartman, F., & Krahn, J. (2017). The Delphi Method for
Graduate Research. Journal of Information Technology Education:
Research.
Smith, P. (2016). Project Cost Management with 5D BIM. Procedia - Social and
Behavioral Sciences.
Taherdoost, H. (2018). Validity and Reliability of the Research Instrument; How to
Test the Validation of a Questionnaire/Survey in a Research. SSRN
Electronic Journal. https://doi.org/10.2139/ssrn.3205040
72
Tansley, C., Kirk, S., Williams, H., & Barton, H. (2014). Tipping the scales:
Ambidexterity practices on e-HRM projects. Employee Relations.
Tasevska, F., Damij, T., & Damij, N. (2014). Project planning practices based on
enterprise resource planning systems in small and medium enterprises - A
case study from the Republic of Macedonia. International Journal of Project
Management.
Team, C. R. (2018). Affordable Housing in Kenya. In cytonnreport.com.
Todorović, M. L., Petrović, D. T., Mihić, M. M., Obradović, V. L., & Bushuyev, S.
D. (2015). Project success analysis framework: A knowledge-based
approach in project management. International Journal of Project
Management.
Transparency International. (2017). Transparency international - what is
corruption? In Transparency International.
UNCTAD. (2016). Second generation biofuel markets: satet of play, trade and
developing country perspectives. United Nations Conference on Trade and
Development.
Viechtbauer, W., Smits, L., Kotz, D., Budé, L., Spigt, M., Serroyen, J., & Crutzen,
R. (2015). A simple formula for the calculation of sample size in pilot
studies. Journal of Clinical Epidemiology.
Wanjala, P. N., Abednego, G., & Stephen, D. (2017). Integration of Management
Information Systems for Effective Construction Projects Monitoring and
Control in Kenya.
Zwikael, O., & Unger-Aviram, E. (2010). HRM in project groups: The effect of
project duration on team development effectiveness. International Journal of
Project Management.
73
Appendix
Yours faithfully
…………………………………….
74
Questionnaires
1. Age Group
31-40
41-50
Above 50
2. Gender
Male
Female
3. Level of Education
Diploma
Bachelor’s degree
Master’s degree
Doctorate degree
4. Field of training
Business management
Project management
Building construction
5. Years of Experience
1-5 yrs
6.10 yrs
11-15 yrs
16-20 yrs
75
Above 20 yrs
76
The budget has been helpful in management of finances
The suppliers and employees are paid their dues in time
We have not received any complaints from suppliers and
employees as regards payments
The payments for any transaction is done by IFMIS
The use of IFMIS for payment is efficient in managing finances
SA A N D SD
Training and Sensitization of officers on procurement act 2005 and
2006
Officers participation in tendering processes
Public entities comply with the public procurement procedure
Procurement entities apply appropriate procurement methods
Entities use standard tender documents from PPOA
Procurement staff are qualified and experienced to handle
procurement process
Procurement officers make informed decisions
Tender evaluation is conducted by competent persons
Procurement opportunities are advertised using appropriate medium
There is effective monitoring and auditing
77
government managers and other concerned parties through e-mails
Use of e-mails, texts and telephone calls to communicate to the county
officials and other concerned parties in project management found to
be effective
Both vertical and horizontal channels of communications are employed
while passing information
Use of both vertical and horizontal channels of communication is
effective in exchanging information among the project team.
The languages that are being used to communicate is English which
are understood by all and never vernacular
The use of English has brought about clear understanding of the
information being passed hence effective in Communication
There has been freedom for everybody in the team to exchange
information without any limitation
All the recipients of the information do give feedback to ensure
communication process is complete
78