Professional Documents
Culture Documents
INTERNSHIP
ON
“To study Bridges, retaining wall, Pipe culverts, Various types of roads,
Buildings and Various development works in Public Work Division (PWD),
Amravati”
SUBMITTED BY
PRATHAMESH. N. SONPARATE
SUBMITTED TO
THROUGH
2020-24
1|Page
CERTIFICATE
This is to certify that the internship report on titled “To study Bridges,
retaining wall, Pipe culverts, Various types of roads, Buildings and
Various development works in Public Work Division (PWD), Amravati”
Submitted By
PRATHAMESH. N. SONPARATE
2|Page
DECLARATION
I the undersigned, hereby declare that the industry internship titled “To study
Bridges, retaining wall, Pipe culverts, Various types of roads, Buildings and Various
development works in Public Work Division (PWD), Amravati” is an original piece
of research work carried out by me under the guidance and supervision of Prof. Vikas
Varekar. The information has been collected from genuine & authentic sources. The
work has been submitted in partial fulfillment of the requirement of MHRD to
Amravati University.
3|Page
INTERNSHIP CERTIFICATE
4|Page
STATEMENT OF CANDIDATE
5|Page
ACKNOWLEDGEMENT
I also appreciate the support from the head of the department Dr. A.S. WAVYAL,
Department of Civil and Environmental Engineering, Mumbai.
I am grateful to all those who have directly or indirectly have been a help for the
completion of this internship work.
6|Page
TABLE OF CONTENTS
3 Declaration 3
4 Internship Certificate 4
5 Statement of Candidate 5
6 Acknowledgement 6
7|Page
INTRODUCTION
8|Page
PUBLIC WORKS DEPARTMENT OF GOVT. OF
MAHARASHTRA PRIMARILY EXECUTES THE FOLLOWING
DIFFERENT VIVID DEVELOPMENT WORKS.
Construction of New Roads & Bridges.
9|Page
Reservation of Govt. Rest Houses and Circuit Houses.
To undertake auction sale of fruit trees along the roadsides.
To permit construction of approaches on both sides of roads to the
private individual, other institutions, factories, Petrol Pumps etc.
To allow irrigation drains, electricity lines, telephone duct cables etc.
along and across the roads.
To evacuate the encroachment coming along the roadsides
The issue of certificates periodically to Cinema Houses about the stability
of structures/arrangement related to electrical fittings conforming to
Cinema Regulation Act.
Issues of certificate for lift operating in Private Buildings.
To lease out the Govt. land for Exhibition/Circus or other purposes etc.
temporarily.
Plantation of trees along both sides of the road.
At field level the wings as mentioned here under work together to accelerate
the execution of the works: -
10 | P a g e
1 The Civil Constructions Wing:
2. Electrical Wing:
This Wing is headed by the Chief Engineer (Electrical) Mumbai who controls
the Superintending Engineers stationed at Bombay /Pune /Nagpur and
Aurangabad. The Executive Engineers/Deputy Engineers/Sectional Engineers
are deployed under each Superintending Engineer according to necessity.
3. Mechanical Wing:
This Wing is headed by the Chief Engineer (Mechanical) and under his control
Superintending Engineers /Executive Engineers / Deputy Engineers
/Sectional Engineers are deployed according to requirement. The
upkeep/New Purchase, maintenance Repairs of machinery is looked after by
this Wing.
4. Architectural Wing:
This Wing is headed by the Chief Architect, Mumbai under whom, at Regional
level Deputy chief Architect works. This wing looks after the architectural
aspects and sorting out the architectural problems for buildings.
11 | P a g e
ORGANIZATION STRUCTURE COLLECTED
FROM PWD OFFICE
12 | P a g e
CHAPTER 2: - EQUIPMENTS
The Company owns wide range of machinery and equipment's some of them are
listed below:
JCB MACHINE
APPROXIMATE COST: 30 lakhs Rs.
SPECIFICATION:
Hrs. 400 Hrs. 400 Hrs. First oil change 100 Hrs. / 30 days* and then every 400
Hrs./90 days*. Engine Oil Filter 4R 1040 400 Hrs. First oil change 100 Hrs. /
30 days* and then every 400 Hrs./90 days* and Oil filter change in 100 hrs.
TRANSIT MIXER
APPROXIMATE COST: Rs. 33.98 Lakh - 34.98 Lakh
SPECIFICATION:
DUMP TRUCK
APPROXIMATE COST: Rs.18 lakh - 21.43 lakh
SPECIFICATION:
• GVW - 28000 kg
• Max. Power - 206 kW @ 2200 r/min
• Max. Torque - 1050 Nm @ 1200-1700 r/min
SPECIFIC USE: A dump truck, known also as a dumping truck, dump trailer,
dumper trailer, is used for transporting materials (such as dirt, gravel, or
demolition waste) for construction as well as coal.
SPECIFICATION:
SPECIFIC USE: A paver (road paver finisher, asphalt finisher, road paving
machine) is a piece of construction equipment used to lay asphalt on roads,
bridges, parking lots and other such places. It lays the asphalt flat and
provides minor compaction before it is compacted by a roller.
15 | P a g e
ROUTINE MAINTENANCE: Repair of surface failures. Repair of complete
slab failures by concrete replacement. Repair of buckled pavement. Repair of
sunken slabs by patching or mud jacking.
Preventive maintenance by sealing joints and cracks.
RAMMERS
APPROXIMATE COST: 59,000 Rs
SPECIFICATION:
• Minimum working weight 1360 kg
• Impact rate (frequency) 430 - 790 bpm
• Operating pressure 2030 - 2320 psi
• Oil flow range 120 - 180 l/min
SPECIFIC USE: Rammers are most often used in construction, road and
paving works, and wherever there is a need for strong soil compaction. The
principle of operation seems to be very simple; however, in the case of the
latest generation equipment, advanced drive and safety systems are behind
everything.
Daily. Make routine visual checks to make sure everything is sound and in
place Weekly: these checks should be made every week or every 25 working
hours.
Annually: Care of plate compactors.
SPECIFICATION:
SPECIFIC USE: They can be used to delineate traffic lanes, inform motorists
and pedestrians or serve as noise generators when run across a road, or
attempt to wake a sleeping driver when installed in the shoulders of a road.
Road surface marking can also indicate regulation for parking and stopping.
SPECIFIC USE: The dumpy level is an optical instrument used for surveying
and levelling operations. It comprises of a telescope tube, firmly held between
two collars and adjusting screws. Relative elevation of survey points on the
land can be determined through the dumpy level.
ROUTINE MAINTENANCE: Be sure to take good care of the tripod that the
dumpy level sits on. Keep your equipment dry. Moisture can blur the lens
from the inside and cause other damage. clean by closing them even when
they are empty to avoid scratches. When your dumpy levelling is done, be sure
to put it back safely into its container.
17 | P a g e
18 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
PROJECT NO: - 1
• Purpose of Project: -
At Anjangaon Bari the height of existing rigid pavement
i.e., the height of embankment was more than 3m. So, there were more chances
of road accident, also there was demand from MLAs and people residing over
there. Another problem was of more surface runoff. This project was also
proposed for the provision of side drains.
19 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
20 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
Ready Mix Concrete of M10 Grade was used for laying of PCC bed for foundation.
Cement:
Portland Pozzolana cement (P.P.C) is normally used for Plain cement concrete.
It should conform to the specifications and tests.
Sand:
Sand to be used for concrete work should be clean, well graded, hard, strong,
durable, and should meet the requirements specified for its use.
Aggregate:
21 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
Aggregate shall be of an inert material and should be clean, dense, hard, Sound,
Durable, Non-absorbent and capable of developing a good bond with mortar.
Coarse Aggregate:
The size of the aggregate used for PCC varies from 10-12 mm to 40 mm depending
on where they are to be used.
If the size of the aggregate is more, it results in the reduction of cement
consumption.
Coarse aggregate shall be clean and free from elongated, flaky or laminated pieces.
It should be free from adhering coat, clay lump, coal residue, clinkers, slag, alkali,
mica, organic matter or other substances
Coarse aggregate shall be of hard broken stone of granite or similar stone, which is
free from dust, dirt and other foreign matters. The smaller size of the stone is 6.3
mm. All the course material should be retained in a 6.3 mm square mesh and should
be well graded such that the void does not exceed 42%.
Fine Aggregate:
Fine aggregate shall be of coarse sand consisting of hard, sharp and angular grains
and shall pass through a screen of 4.75mm square mesh.
Sand for PCC work shall be clean and free from dust, dirt and organic matter or
based on standard specifications. Never used sea sand in foundation work.
Water:
Water shall be clean and free from alkaline and substances should be suitable for
drinking purposes.
Hand Mixing:
Mixing should be done on a masonry platform or sheet iron tray
22 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
Machine Mixing:
Stone ballast, sand and cement shall be poured/ mixed in a concrete mixer to
maintain the required proportions. Machine mixing is always preferred, but under
unavoidable circumstances, hand mixing can be done but all quality check needs to
be assured.
Slump:
For maintaining the required consistency and control the addition of water, the
slump test should be carried out regularly. A slump of 7.5cm to 10cm may be
allowed for foundation work.
Formwork:
Formwork centering and shuttering shall be provided as per the standard
specification before laying concrete to confine to support or to keep the concrete in
position. To prevent sticking of concrete, the inner surface of shuttering shall be
oiled.
Curing Method:
• After two hours of laying of concrete, when the concrete has begun to harden, it
shall be kept damp by covering with wet gunny bags for 24 hours.
• After 24 hours of placing PCC, keep the concrete surface moist by flooding with
water or by covering with moist gunny bags.
• Curing of PCC may be done by either pouring water with buckets or with pipes.
• Curing should be carried out for a minimum 14 days.
23 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
• The Thickness of Raft is 0.45m, Width of the raft is 3.3m and the
overall Length of retaining wall is 300m on both sides of road.
• As per design of retaining wall, the diameter of main steel used is
16mm and provided with a spacing of 150mm Centre to Centre.
• Distribution Bars were provided for overall length of 300m having
diameter of 10mm with Centre to Centre spacing of 200mm.
• Quantity of Steel used for stem was 200kg/cum and total concreting
of stem was 588 cum.
• So, total steel used in stem is 117.6 MT.
• 50mm clear cover of concrete is provided from bottom, top and
side.
• M20 Grade of concrete was used for concreting of raft which has
ratio 1:1.5:3, with the water-cement ratio being kept between 0.4
and 0.6. It is composed of a mixture of cement, sand (fine
aggregates), and coarse aggregate.
24 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
25 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
26 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
Concreting of Raft
27 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
28 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
29 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
30 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
31 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
32 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
33 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
34 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
35 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
expansion joints
36 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
Backfilling: -
37 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
PROJECT NO. 2
BRIDGE CONSTRUCTION AT MASOD VILLAGE i.e., R.C.C. SOLID SLAB
• Purpose of Project: -
This bridge is proposed to connect Masod village
road to Mardi village road as there was no structure connecting these
two villages.
• Foundation Details: -
38 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
Introduction of Structure
39 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
SECTION OF BRIDGE
40 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
1.) Excavation: -
41 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
42 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
43 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
The mixture of cement, fine aggregate (sand) and coarse aggregate are
generally called plain cement concrete (PCC). Before starting any R.C.C or
masonry work directly on the excavated soil, PCC is done to form a levelled
surface and to avoid laying concrete on soil directly so as to avoid mixing/
with soil and also to prevent soil extracting water from PCC thereby
weakening it.
M10 mix have ratio of 1:3:6 = cement: sand: aggregate with required water
cement ratio (say 0.60) and the strength achieved after 28 days of curing
is 10N/mm2
M10 generally used for levelling course and also as bedding for footing etc.
Here M10 PCC bed was provided for two abutments and four solid returns.
For provision of four solid returns, separate PCC bed was provided
Length: - 4.3m
Width: - 3.3m3
Height: - 0.3m
Corresponding quantity of concrete was used for laying of PCC bed for four
solid returns.
44 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
45 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
• M15 grade of concrete was laid for first lift of abutment wall
from top level of the footing to neck level of abutment.
• Offset of 0.3m was left from both sides of abutment wall
from the edge of PCC bed of each abutment.
• Slope of 1:1 was provided for front batter for the first lift of
concrete for abutment wall up to neck level.
• This process was repeated for both abutment walls.
• M15 concrete has cement: sand: aggregate in a ratio
1:2:4 respectively.
• Here the M stands for mix and 15 stands for 15N/mm2
characteristic compressive strength of the concrete in
28 days.
46 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
47 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
1
1.4m 6
x=0.233m
• To achieve the slope of Back Batter i.e., 1:8 corresponding horizontal distance
to be moved from edge of the footing was calculated.
1 x 1 x
• = = x=0.175m
𝑛1 1.4 8 1.4
1
6
1. 4m
x=0.175m
• Same process was repeated for the concreting of second Abutment
48 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
49 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
50 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
51 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
• Following is the Steel reinforcing used for Abutment Cap and Dirt
Wall.
• 1584 kg of steel was used for 12.00 m as per SEDC DRW.
• As per the Design Circle of P.W.D., Government of Maharashtra for
the Road Bridges, Steel bars that should be used for this
corresponding road bridge for the dirt wall and abutment cap is as
follows: -
Figure: - Reinforcement of
Abutment Cap and Dirt Wall
52 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
Front View
Side View
53 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
54 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
55 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
• The GSB material shall be crushed stone aggregate free from organic
and other deleterious constituents or natural river bed material having
proper gradation.
• The material shall have four days of soaked CBR of a minimum of
30%. spread in layers of uniform thickness of 200 mm compacted
thickness for new flexible pavement, and 150 mm compacted thickness
for Service Roads and rigid pavement. A grader shall be used for this
activity.
• The moisture content of the material should have OMC +1.0% or –
2.0%; if not, either a mixing or drying process must be adopted. Water
can be added to raise the moisture content to the required limits. After
spraying water with the browser, the material shall be properly mixed
to obtain a homogeneous mix. The mixing can continue with the help
of a grader. The grader shall then carry out the final well-defined
grading.
• Compaction of Granular Sub Base shall start immediately after
achieving the required moisture content.
• The compaction shall be done with a vibratory compactor.
• The surface of GSB layer shall have a suitable cross fall to enable
efficient surface drainage.
• Depth of granular sub base provided is 150mm.
• For this structure two approaches were provided as per the site
condition.
56 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
The foundation supporting the layer of WBM is either the subgrade or sub-
base course. It is prepared to the required grade and camber. It is cleaned of
all the dust particles and loose materials present on it. The foundation,
supporting the WBM, should be dried.
3. Rolling
Once the aggregates are spread evenly, the rollers are deployed to carry out
the process of compaction. The rollers used shall be of 6 to 10 tonnes
capacity. The compaction of aggregates should start from the edge of the
surface. The aggregates are compacted partially then the compaction is
paused to permit the application of screenings
57 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
5. Application of screenings
The surface is sprinkled with water after applying the screenings. The
surface is then swept and rolled so that the voids are completely filled. If any
voids are left empty, additional screenings may be applied.
Schedule of Reinforcement: -
• Minimum Clear cover to Reinforcement is 40mm.
• Grade of steel used is Fe 415.
• Bar Bending Schedule is based on minimum bearing width of
375mm on both sides.
• Depth of the RCC slab is 450mm.
• Length and Width of slab is 10m and 5m respectively.
58 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
59 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
Section at A-A
60 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
61 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
62 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
63 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
64 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
65 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
PROJECT NO. 3
Pipe Culvert at Pimpalkutha Village, Taluka, district
Amravati.
Construction Site Details: -
• Purpose of Project: -
Slab Drain of Span 8 meter and 5 meters.
Were proposed on this location as the width of the nalla gauge were
8 & 5 meter respectively but due to less availability of funds Hume
pipe culvert was constructed so that the purposed of the villagers was
achieved.
• Foundation Details: -
Being Hard Strata Available at
shallow depth with soil bearing capacity of 20T/sqm. So, the
levelling course of M10 (15cm) thick for bed concrete was proposed.
66 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
Introduction of Structure
Meaning of Culvert: -
• A small bridge may be of 3 to 4 spans with the length of span not more
than 3 m is known as culvert.
• In case of highway where culverts are constructed to cross the small
distributary etc., the span length may be about 4.5 m.
• Similarly, in case of railway track the maximum span length can be
about 6 m and should not exceed this limit.
• The culvert mainly consists of abutment, wingwalls, arches or desk
slab, parapet and foundation.
• Floor pitching from inside the culvert in the bed of drain may or may
not be provided, it depends on the soil condition and flow velocity of
the stream water.
Pipe Culverts: -
• The pipe culverts are used for very small drainage works, passing
through the embankment of road or railway.
• It consists of one or more pipes placed side by side each other.
• The pipes are generally made of steel, R.C.C., cast iron etc.
• To retain the pipes and embankment at their proper position against the
action of spring water etc., they are laid with masonry work in the form
of arches at both the ends.
67 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
Hume Pipe: -
• A Hume pipe is a concrete tube with reinforced bar. It was invented by
the Hume brothers in Australia in 1910.
• A hume pipe is formed by pouring concrete into a formwork, and axially
rotating it, and allowing it to compact using centrifugal force.
• A hume pipe can withstand internal and external pressure well, and is
primarily used for sewer pipes, agricultural waterways, and residential
construction.
• Anti-bacterial concrete is commonly used in hume pipes.
• Class
Light duty- NP2, Medium Duty- NP3, Heavy Duty- NP4
• Density
Optimum water cement ratio and High density.
• Length
2 & 2.5 meter and as per requirement
• Diameter Of RCC Hume Pipe
80, 100, 150. 200, 225, 250, 300, 350, 400, 450, 500, 600, 700, 800,
900, 1000,1100, 1200, 1400, 1600 & 1800.
68 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
69 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
1)Excavation: -
70 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
71 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
72 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
• The process of hand packing the rubble stones over the earth
surface or on the sand bed is called as rubble soling
73 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
soil and also to prevent soil extracting water from PCC thereby
weakening it.
74 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
No of Head L B H Quantity
Walls
75 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
Introduction: -
• Concrete pipe is a rigid pipe having very good strength and high
longevity.
• They are suitable for various loading conditions
• Concrete pipes are structures made of concrete and steel which is a
combination of properties that allows a designer to specify any level of
strength required in a project.
• The manufacturing of precast concrete pipes takes place at a controlled
factory setting with rigid production standards and quality control
requirements.
• Hume pipes are available in three grades NP2, NP3, and NP4.
• The major difference between NP2, NP3, and NP4 RCC pipes is the load-
bearing quality and flow.
• NP 2 RCC pipes are used for low duty load.
• NP 3 RCC pipes are used for medium-duty load.
• NP 4 RCC pipes are used for heavy-duty load.
• Instead of the thickness, these are differentiated on the basis of grades and
reinforcement.
• On the basis of shape and size, different types of RCC pipes are collar joint
type, Spigot and Socket type pipe
76 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
77 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
78 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
79 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
80 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
Strength
Precast concrete pipe is the strongest pipe available. It can be designed and
plant tested to resist any load required. Unlike flexible pipe, it has minimal
reliance on installation to support loads; it relies primarily on its inherent
brute strength manufactured into the pipe.
Resilience
As the strongest pipe available, precast concrete pipe is designed and tested
to resist any load required. With the ability to withstand almost any disaster,
concrete pipe is the most product in its class and it will not burn, rust, tear,
buckle, deflect, and it’s immune to the attack of most elements, whether the
pipe is buried or exposed. Projects that use concrete pipe can prepare and
plan to absorb, recover from, or more successfully adapt to adverse events.
Dependability
Concrete pipe’s long-term performance is proven, not theoretical. Innovation
has made concrete pipe more reliable and dependable than ever. This
innovation includes improvements to concrete mixes, pipe design,
manufacturing processes and more.
Disaster-Resilient
Concrete pipe will not burn, corrode prematurely, or collapse under loads
81 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
Life-Cycle Cost
Concrete pipe has lower installed costs, less ongoing maintenance, and
reduced likelihood of future problems. This adds up to a lower total cost over
the life cycle of your project. That’s the definition of real value.
Environmentally Friendly
Concrete is produced with benign, natural materials. What’s more,
manufacturing of concrete consumes less energy than fabrication of
alternative pipes. It is also recyclable and has little if any environmental
impact. Because it’s a local resource, concrete can provide lower fuel cost
for delivery.
Lower-Risk Installation
Concrete’s strength facilitates successful installation. This lessens the
liability on the owner, engineer, and contractor. When proper installation is
specified and inspected, concrete pipe has the lowest installed cost and risk,
compared to alternative products.
82 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
Joint Performance
Concrete pipe offers the design engineer several different joint types,
depending on the application, to meet the utmost demanding project
specifications. Soil-tight, water-tight, and pressure-rated joints can be
designed to meet different sealing requirements.
Hydraulic Performance
Precast concrete pipe’s rigidity and mass allow it to greatly outperform
flexible pipe systems in this critical area, which in turn helps to improve
hydraulic efficiency by minimizing the resistance to water flow that often
occurs when the shape or integrity of a flexible pipe is compromised.
• M20 Grade of Concrete was used for concreting of 4 wing walls and 2
head walls.
• For a depth of 0.7m, second lift of concreting was done.
• As per the design of wall, section of wall is tapered so average width
of wall was considered for the purpose of calculating the quantity of
concrete to be used.
• As bottom width is 1.2m, so for overall depth of 2.2m the
corresponding top width is 0.45m.
• Same procedure was repeated for the second head wall.
• With this slope of 1:3 was also maintained for both the head walls.
83 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
84 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
85 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
86 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
87 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
• Then hard murum was supplied in between the cement concrete pipes
and also for the approaches on both sides of culvert.
• It was supplied below the rigid pavement having span of 7m in length
and 6m in width.
• It was also provided for approaches which has a span of 8m by 6m.
• Hard murum was supplied for a total depth of 0.3m both for rigid
pavement and approaches.
• Total of 36 cum of hard murum was used for this purpose.
• Then there was provision of soling using 80 mm size trap metal in 15
cm. layer including filling voids with Crushed sand/grit, ramming,
watering etc.
9) Provision of Cushioning
• What is Cushion?
Cushion is a layer of earth crust between pipe and road crust which is
provided when there is a gap between existing ground and proposed
road crust.
88 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
In case cushion is between 0 and 600 mm, then pipe should be provided
with encasing.
90 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
91 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
PROJECT NO. 4
Building details
92 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
➢ Departmental details: -
On the floors of building various departments are provided in building;
On ground floor and first floor of new collector building various departments
are provided such as,
Ground Floor First Floor
➢ R.T.I.\ Online R.T.I.
Dept. ➢ Freedom fighter
➢ Setu dept ➢ mukhyamantri shayata
➢ Employment guarantee ➢ divani daave
scheme dept ➢ complaint
➢ B.M.S. ➢ mining dept
➢ Inward \Outward dept ➢ district revenue
➢ Prapatra dept ➢ supply dept
➢ E.P.B.X. dept
➢ Naazar
➢ Abhilekh ghar
93 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
➢ Creche room
➢ Library
➢ Backup room
Likewise on second floor and third floor various departments also provided,
94 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
1. Footing details: -
We observed the isolated footing type for this building.
This footing has a size of,
Size A Size B
Length-1.80M Length-1.80M
Breadth-1.80M Breadth-1.80M
Depth-1.05M Depth-0.45M
2. Column Details: -
We have seen the various shapes of column using in the collector
building such as Circular column, rectangular column, square column.
All kinds of column having the isolated type of footing with the grade
of concrete of M-25.
We observed 7 different sizes of column with their respective height.
95 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
Size of column
3. Beam Details: -
We have seen the beams at various levels in building such as Plinth
beam, Lintel beam, Floor beam.
All kinds of column having the isolated type of footing with the grade of
concrete of M-25.
We observed 7 different sizes of column with their respective height.
4. Staircase details: -
Dog legged staircase is provided in this building.
Open well system staircase is also provided.
96 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
5. Other details: -
A. Waterproofing details: -
97 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
B. Firefighting system: -
In case of fire accident, the inbuilt system in building which
fights against the fire and results the less damage to the building.
Following are the causes for fire accident;
1. Electrical problems
2. Smoking materials
3. Human error
4. Combustible dust
5. Arson
6. Heating equipment
7. Poor housekeeping
8. Mechanical friction
9. Flammable liquids and gases
98 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
99 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
100 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
101 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
102 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
103 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
104 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
Building details: -
After studying the drawing of new administrative building, we get the following
things: -
Departmental details: -
On both the floors of building various departments are provided in building;
On ground floor of new administrative building various departments are provided such
as,
➢ Stamp office.
➢ Tahsil Office.
➢ Lok Adalat.
➢ Meter room
➢ Revenue Office.
➢ S.D\ Tehsildar...
105 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
Likewise on ground floor, various departments also provided on first floor as,
➢ Auditorium
➢ Waiting Lobby
➢ V.C.R.
➢ Green Room
➢ Computer Room
➢ Taluka Agri. Office
➢ Regional Forest Office
➢ VIP Room
➢ Co.Op.Dept.
➢ Sub Register office.
5. Footing
6. Column
7. Beam
8. Staircase, etc.
106 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
6. Footing details: -
We observed the isolated footing type for this building.
This footing has a size of
Size A Size B
Length-1.80M Length-1.80M
Breadth-1.80M Breadth-1.80M
Depth-1.05M Depth-0.45M
7. Column Details: -
We have seen the various shapes of column using in the administrative
building such as Circular column, rectangular column, square column.
All kinds of column having the isolated type of footing with the grade of concrete
of M-25.
We observed 7 different sizes of column with their respective height.
Size of column
8. Beam Details: -
We have seen the beams at various levels in building such as Plinth beam,
Lintel beam, Floor beam.
107 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
All kinds of column having the isolated type of footing with the grade of concrete of
M-25.
9. Staircase details: -
Dog legged staircase is provided in this building.
4 no. of staircase is provided in this building.
Waist slab= 200 mm thick
Landing width =2000 mm wide
Trade=300 mm
Riser= 150 mm
10.Other details: -
C. Waterproofing details: -
Koba brick structure:
Koba brick structure is the type of structure in which laying of half brick is
applied to the whole slab, after applying the brick slab apply the mortar paste.
108 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
109 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
110 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
111 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
112 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
113 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
114 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
115 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
FOOTING DETAILS
116 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
117 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
118 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
COLUMN DETAILS
119 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
120 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
121 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
122 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
123 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
124 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
125 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
126 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
127 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
128 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
Conclusion
During my industrial training, there are many changes from the point of learning
environments and discussion among colleagues. It can directly increase the
dedication and rational attitude toward myself.
However, there are still some weaknesses that can be improved in the future.
Therefore, I conclude that the industrial training program has provided many
benefits to students even if there are minor flaws that are somewhat disfiguring
condition, so that this weakness can be rectified in the future.
All in all, this internship was a fantastic opportunity to gain hands-on experience
and hone my skills on field. I am grateful for all the lessons & experiences I have
gained during my time at PWD, which I can now confidently apply to any future
roles.
129 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
References
130 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
131 | P a g e
INTERNSHIP REPORT ON PUBLIC WORKS DEPARTMENT
132 | P a g e