Professional Documents
Culture Documents
Technology -
• Diaphragm walls are rectangular-section excavations with a complete ground asportation that is made in situ.
• The result is an underground concrete wall.
• They are essentially retention walls, which are constructed for instance at wharfs.
• A rectangular-section tool is generally used to remove the soil, thus creating a rectangular excavation.
• Furthermore, the rectangles making up the wall must be interlocked to ensure structural endurance and water tightness.
• The diaphragm wall panel construction entails three steps: the construction of guide wall, the panel excavation (demolition
– removal - stabilization), and the construction phase (reinforcing cage – casting – curing).
• To build a continuous diaphragm wall the primary panels are firstly constructed and spaced at a distance slightly larger
than the panel width. The secondary panels are built in the empty spaces between the primary ones. T
Diaphragm Sheet Pile Wall -
• The diaphragm wall, bearing piles, and anchor piles would be installed from a dry ground platform, either above high tide
level or in a dewatered excavation.
• The top portion of a diaphragm wall cast is usually inferior concrete, and therefore the wall would be cast higher than
required and cut down to level.
• Construction of the in-situ relieving
slab and cap would be done in a
dewatered excavation.
• The walls generally range in
thickness from 500 - 1,500 mm and
can be excavated to depths of over
50 m.
• Excavation is typically carried out
using rope-suspended mechanical or
hydraulically operated grabs.
• Specific ground conditions or greater
depths may require the use of hydro
mills – hydraulically-operated
reverse circulation trench cutters –
to penetrate hard rock by ‘cutting’
rather than ‘digging’. Hydro mills can
achieve depths of up to 80 m.
Construction Stages -
• A diaphragm wall is constructed using a trench excavated in ground and supported by a mud fluid (typically bentonite or
polymer mud) until the mud is replaced by concrete, after the steel cage installation.
• Walls generally range from 600 to 1500 mm thickness, in wide between 2000 and 3500 mm and can be excavated to depths
of 60m or more.
2. Pre-trenching –
• It is performed to remove shallow obstructions and provide stable support for guide walls.
• This is performed as open excavation backfilled with flow fill/ excavated under self-hardening slurry.
3. Guide Wall Construction –
• Guide walls are two temporary parallel cast-in-place or pre-cast
lightly reinforced concrete beams constructed along the side of the
wall in order to guide the excavation tool and stabilise the top
portion.
• Guide walls maintain the horizontal alignment and wall continuity of
a diaphragm wall while are adopted to
avoid superficial soil collapse
to mark the panels position and
to support the steel cages during the concrete aging.
• This temporary support is important as the slurry levels vary during
construction and the wall tends to be unstable.
• Equally important, guide walls help guide the diaphragm wall grabs
vertically and aid in the positioning of the final structure.
• The dimensions and shape of the guide walls may change
depending on the nature of the surface soil.
• As it happens in bored piles, the bentonite slurry inside the
excavation hole shall always be kept some meters above the height
of the water table.
• In some special cases where the water table is very close to the
surface and the soil has poor mechanical properties, the guide walls may be built on a higher height compared to the ground
plane to preserve the above mentioned height difference.
Guide walls
8. Reinforcing Cage
Placement –
• Once the bottom of the panel is
reached and cleaned, the
reinforcement cage can be
lowered into position.
• The reinforcement cages have a
significant size and weight, as a
general rule, the cage is built by Fixing and placing the reinforcing cage
laying the components (of
adequate length) on the ground
then connecting them together.
• Reinforcement is inserted in the
form of a steel cage but may be
required to lap a few sections in
order to reach the required
length.
10. Using hydro fraise (reverse circulation trench cutter) to form diaphragm wall panel:
• Bored piles of square section can be installed using the Hydrofraise or similar drilling techniques. The bore hole is stabilized
by drilling mud.
• The “Hydro fraise” is a drilling machine powered by three down-the-hole motors, operating with reverse circulation.
• A heavy metal frame, serving as a guide, is fitted at its base with two cutter drums carrying tungsten carbide tipped cutters.
• These rotate in opposite directions and break up the soil. A pump is placed just above the drums and evacuates the loosened
soil, which is carried up to the surface by the drilling mud.
• The mud with cuttings is continuously filtered (desander unit) and then poured back into the trench.
• A heavy crawler crane supports and manipulates the machine. It carries the power pack supplying the hydraulic power,
which is conveyed through hoses to the three down-the-hole motors, two of them driving the cutter drums and the third
driving the pump.
• The hydraulic cutting device is designed to give the cutter drums a high torque at low speed of rotation. The guide frame is
suspended from the cable-operated crane. A hydraulic feed cylinder is used to achieve a constant rate of advance or to
maintain a constant weight on the cutter drum.
The hydrofraise is used for the construction of diaphragm and cut-off walls in difficult conditions: excavation of rock and
hard layers of soil, deep panels and strict tolerances.
Equipments Used -
1. Hydrofraise -
• Excavation of the soil.
• Pumping of the mix soil support slurry from the trench to the slurry
plant.
• Cleaning of the bottom of the excavation.
• Replacement of the support slurry before concreting.
2. Slurry Plant
• Production and storage of the support slurry.
• Pumping of the Support slurry from the slurry plant to the trench.
• Separation of the mix soilsupport slurry created by the hydrofraise.
• Treatment of the waste slurry.
Construction Method -
• The execution of diaphragm walls with hydrofraise is based on the reverse circulation technique.
• The excavation is carried out by milling soil by means of two drums fitted with tungsten carbide cutters, rotating in opposite
directions.
• Particles of soil, suspended in the support fluid, are pumped off the trench by utilizing a suction pump and delivered to the
desanding plant through the pipelines.
• At the plant the particles of soil are removed from the bentonite suspension, which is recycled into the storage tanks
The support slurry is prepared in the slurry plant. Bentonite powder (1) is mixed with water in a high turbulence mixer (2) to
produce the support slurry, which is pumped (3) to the storage tanks (5). •The support slurry is pumped from the storage
tanks to the trench my means of a centrifugal pump (6). •The hydrofraise (8) cuts the soil, mixes it with the support slurry
and pump it back (8) to the plant, where the soil is separated from the slurry with a desanding unit (4). •Waste slurry is
pumped to the waste slurry storage tank (9) and then treated with a filter press (10).
Importance -
• Bentonite is of a great commercial importance possessing innate bleaching properties like fuller's earth; hence, it is also
known as bleaching clay.
• Containing more than 85% clay mineral, montmorillonite, it is high plastic clay.
• There are basically two types of bentonites, namely: • Swelling-type (or sodium bentonite) and • Non-swelling-type (or
calcium bentonite). Sodium bentonite is usually referred to as bentonite, whereas calcium bentonite is called Fuller's earth.
• The commercial importance of bentonite depends more on its physicochemical properties rather than its chemical
composition.
• Excellent plasticity and lubricity, high dry-bonding strength, high shear and compressive strength, low permeability and low
compressibility make bentonite commercially viable.
• Bentonite is valued in foundry sand binding, drilling mud, iron ore palletization and as a waterproofing and sealing agent in
civil engineering works.
• Bentonite slurry is prepared with an objective to achieve maximum hydration of the bentonite, therefore its powder must be
added to the mixing water gradually in order to ensure that all the particles are wetted and do not clump into partially
hydrated balls.
• Bentonite slurry can be prepared either in batches or in a continuous process, depending on the type of equipment used.
• Typically, the bentonite powder is added through a simple venturi-hopper or directly into a high shear mixer. • The mixing
equipment must generate sufficient shear to ensure that all the individual bentonite particles are dispersed in the mixing
water.
• The quantity of bentonite powder to be added to the mixing water depends on the quality of the bentonite and the required
viscosity of the slurry.
• For most applications, concentrations between 4% and 6% by weight are typical.
Functions and Uses of
Bentonite Slurry -
• The steel pipes are installed at both panel fronts before concreting.
• The pipes rest on the excavation bottom and match the circular shape of the panel
fronts.
• The concrete injected takes the shape of the stop end pipes, the latter are filled with
bentonite slurry and the panel has concave fronts.
• Once primary panels have been constructed and the stop end pipes
removed, secondary panels are executed.
• Once secondary panels have been fully excavated, concreting can
start. Concrete fills the semicircular joints and provides a very good
interlock.
Disposable pipes
• Pipes are in PVC; they are fixed to the cage and lowered
to rest on the bottom.
• During concreting, the whole section is filled by concrete,
except for the pipes which remain full of bentonite slurry.
• The result is a panel with two holes.
• After excavating the secondary panels, by using a
dedicated tool the concrete seam separating the pipe
from the secondary panel and the pipes are demolished.
• As a result, a round indentation is created in the primary
panel. When concrete is cast in the secondary panel, it primary secondary primary secondary
fills the recess and creates a joint with the primary panel.
pipes