Professional Documents
Culture Documents
1. EARTHWORKS
1. Earthworks are engineering
works created through the moving of
massive quantities of soil
–
2. Scope excavation,cutting & filling,
leveling & platforming
3. Earth shall be excavated to required level
4. Machineries used excavator, bulldozer,
–
2. DIAPHRAGM WALL
Definition
• Permanent retaining wall structure in substructure construction
• Underground structural elements commonly used for retention system & permanent wall
The construction of diaphragm wall is commenced with a 20m wide working platform
Stability Fluid
Bentonite Slurry
Bentonite Slurry is used as a stability fluid during excavation. It is prepared by mixing
bentonite powder with water in bentonite plant installed on site. Bentonite slurry is frequently
recycled during usage and the properties of the slurry is checked prior to concreting.
Bentonite Supply Pipeline Networks
The excavation is carried out using a suspended mechanical line grab mounted on
heavy crawler crane, to the full required depth.
The level of bentonite is kept as high as possible between the guide wall
Using the grab, excavated materials are loaded on trucks and removed out from site.
When excavation is completed, the bentonite slurry shall be replaced or recycled prior
to placing reinforcement cage and concreting.
Grab machine
Excavation Sequences
Steel Reinforcement (Rebar) Cage is fabricated on site and delivered by crane into the
panel and lowered down into the trench.
Steel cage is placed in segments in the trench and positioned on the top of the guide
Fabrication of Rebar Cages
Rebar cage
CONCRETING
Special concrete mix design using 20% PFA (Pulverized Fuel Ash) + 80% OPC
(Ordinary Portland Cement for Low Permeability & Low Absorption.
Concreting is placed by the tremie method.
Concrete is poured into the hopper and is raised from the bottom of the trench,
displacing the bentonite slurry.
The tremie pipe is kept immersed in the concrete at the bottom of panel to ensure
fresh concrete does not mix with bentonite slurry.
Concreting of diaphragm wall panel
BORED PILING
Definition
Cast in situ pile formed by excavating a shaft of specified size 1,500mmDia & 1,050mmDia
to required depth & casting the excavated shaft with concrete of specified strength after
reinforcement is lowered down.
Type of Auger
After reaching required depth cleaning bucket is used to clean bottom of b/hole
–
Steel Reinforcement Installation
4. Plunge-In Column
Plunge-In Column (PIC), designed exclusively to support the basement slab during
excavation, are installed concurrently with the piling work at the boring platform level
PIC are I beams designed to cater slab weight with max live load of 2.5 kPa in a grid
of 8.5m x 9 m
Bored Piling work will commence from 1.5m below Ground Floor Level to the require bored
pile depth.
Plunge In Columns (350 x 350 Universal Beam) will be installed and embedded 2m into the
bored pile immediately upon the concreting of Bored Piles.
Installation of PIC
Column a vertical structural element that transmit through compression the weight
–
1.Site is trimmed to a general platform of RL +30.50 to facilitate the commencement of bored
pile & diaphragm wall
2.Guide wall for diaphragm wall to constructed along the perimeter of wall with top of guide
wall is approx. 300 mm below ground
3. A perimeter working platform of approx. 20m wide perpendicular from d/wall alignment is
to be allowed for d/wall activities where center portion to be cut down to RL +27.50 with 1:1
slope to facilitate bored piling works
Temporary Openings
Four (4) Temporary Openings will be provided at the Lift Core Wall area for the purpose of:
1. Ventilation
2. Access for construction materials
& machineries
3. Access for removal of excavated soil
4. Construction of lift pit & core wall
by conventional method (bottom up)
Ground Floor slab will be cast once the Plunge In Columns were
completely Installed at the particular Zone
Excavation to 1.5m below the Basement 1 slab will continue after 16 days
casting of the Ground Floor Slab
To monitor Wall.
Diaphragm the effects of Deep Excavation works to Common Utility Tunnel (CUT) &
-
Th e M ethods :
Settlement Marker (inside CUT, Bldg & Adjacent Pavement)
Strain Gauges
Standpipe Piezometer
Inclinometer
Subsequent excavation below the Basement 3 slab level will then proceed after 16 days
casting of the Basement 1 slabs.
Excavation to pilecap level will be carry out after construction of the basement 3 slab.
The Basement 2 slab will construct simultaneously while excavation to the lowest Basement
is in progress.
Construct CBP concurrently with the foundation bored piles from existing ground
level
Cast CBP until RL 12.10 which is approximately 900mm from B4 level
Upon excavation until B4 level, construct 900mm thick capping beam to tie all CBP
Excavation of Lift Pits to the face of the contiguous bored piles will be carry out
concurrently with the removal of excavated earth by hoisting out using cranes and
buckets.
Construction of Lift wall pile caps will then continue.
Construction of Basement 4 columns will be carry out upon the completion of
Basement 4 slabs.
Construction of Lift Wall and the columns from B4 to B3 will proceed and the
temporary opening will be sealed off
Construction of columns from B2 to B1 will then continue.
Similarly, the construction of Lift Wall and the columns from B3 to B2 will proceed
and the temporary opening will be seal off.
Construction of columns from B1 to Ground Floor will continue.
Construction of Lift wall and the columns from B2 to B1 will commence and the temporary
opening will be sealed off.
Construction of Lift Wall and the Columns from B1 to Ground Floor will proceed and finally
temporary opening will be sealed off
3 comments:
1.
Like...........
Reply
2.
like.........
Reply
3.
Reply
Load more...
Newer Post Older Post Home
Subscribe to: Post Comments (Atom)