Professional Documents
Culture Documents
Department” (PWD)
Bachelor of Technology
By
Divyansh Sharma
(19BCE017)
1
CANDIDATE'S DECLARATION
2
ACKNOWLEDGEMENT
3
ABSTRACT
4
acceptance criteria for bitumen-stabilised sand bases for light/medium
traffic to be proposed.
Construction methods for bituminous stabilisation are also described.
Details are given of methods of surface dressing, which is important
both as an initial running surface on new bases and as a maintenance
treatment. Premixed bituminous materials, both as bases and
surfacings, might perhaps be considered as inadmissible for low-cost
roads. Such roads, however, usually require progressive improvement
because of the traffic growth which accompanies development. There
is a growing use of strengthening overlays and the report briefly
discusses premixed materials and their applications.
5
CONTENTS
Topic Page no.
Candidate declaration 2
Approval Certificate 3
Acknowledgement 4
Abstract 5-6
Abbreviations 8
List of Table 9
List of figures 10
6
ABBREVATIONS
7
LIST OF TABLES
8
LIST OF FIGURES
Fig. No Caption Page no.
2.1 Pothole Measurement 13
2.2 Wet Mix 14
2.3 Paver Machine 16
2.4 Base Course 17
2.5 Tendering Process 18
2.6 Measurement of Road 19
2.7 Calculated Reduced Depth 20
2.8 Moisture Content Test 21
2.9 Retaining Wall 22
2.10 Breast Wall 23
2.11 Rubble Masonary 24
3.1 Surveying 25
3.2 Flexible Pavement 26
3.3 Construction Equipment 27
3.4 Dumper 28
3.5 Flow Chart 30
4.1 Drawing 32
4.2 Finishing Work 34
4.3 Walls 35
9
CHAPTER-1 INTRODUCTION
12
WEEK-2
23rd – 29th January (Battal – Mansar Road)-
Calculation
Mean width = 1.24 +
1.26+1.29+1.3+1.3+1.26+1.24+1.25+1.29/9=1.27m
Wet mix required:- 250m x 1.27m x 0.056m x 9 = 160cubic meter
13
RD Length Width Depth
4/0-4/250 250 1.24 0.56
4/250-4/500 250 1.26 0.56
4/750-4/1000 250 1.29 0.56
5/250-5/500 250 1.3 0.56
5/500-5/750 250 1.3 0.56
5/750-5/1000 250 1.26 0.56
6/250-6/500 250 1.24 0.56
6/100-7/250 250 1.25 0.56
7/250-7//500 250 1.29 0.56
Measurement Of Potholes
Table 2.1
14
WEEK-3
30th January – 5th February (Battal – Mansar Road)-
After the laying of base course layer of WBM we started the process
of spreading tuck coat which is used as a binder course. A tuck coat of
bitumen is applied at 6.0 to 7.5 kg per 10 sq.meter area. This quantity
maybe increased approximately 10 to 20 % for non-bituminous base.
After this process preparation and placing of premix is prepared in a
hot mix plant of a required capacity with the desired quality control.
Bitumen or Tar may be heated upto 150 to 180 degree celsius and the
aggregate temperature should not be more than 14 degree Celsius
from the binder temperature all these mixtures can be transported by
the heavy dumpers carried to the location is spread by the mechanical
paver machine at temperature of 120 to 165 degree Celsius.
15
WEEK-4
16
WEEK-5
For the construction of the road, firstly Public Work Department took
the clearance permission from the Forest Department of that area.
The distance of the road from Thial to Chountra Mata is 13km
approximately, till now they had granted the permission for the first 6
kms of road construction. The estimated cost of construction of this
project for first 6 kms is 25.4 cr rupees. After that tendering process
of road construction was started and tender was given to Lone and
Bhatt Co. Pvt. Ltd. with 24.9% blow which is approx. 19.1 crore .
17
WEEK - 6
18
Fig 2.7 Calculated RD
19
WEEK – 6
20
WEEK – 7 to 9
After performing all the neccessary soil tests ,the cutting and filling of
the site is carried when we joined that site most of the cutting filling
was done and rest was carried out. The amount of material from cuts
roughly matches the amount of fill needed to make nearby
embankments to minimize the amount of construction labor.
21
Fig 2.10 Breast Wall
After that the areas prone to the landslide are inspected and we
observed that there are some places where the necessary precautions
can be done to prevent the hazardous disaster due to various
weathering agencies due to all these reason breast walls were
designed for the area which are at the side of hill so that breast walls
can prevent soil erosion that can cause landslide whereas on the other
side reataining walls were also designed for the areas with loosend
soil to prevent erosion of soil which can cause landslide of the roads
22
WEEK – 10
27th March- 6TH April –
In this week the construction of breast wall were started. In this
construction lean concrete of M10 were used at the base. After that
columns are made for the filling of gravels which is rubble masonry.
As per the specifications the slope provided in breast wall above 4m
is 1/3 of height and for the walls below 4m are provided with slope of
1/4th of the height of wall. As the walls located at site were all below
4m we provided the slope of 1/4th of the height of the breast wall.
23
CHAPTER- 3 CONCEPTS
3.1 SURVEY
Civil surveying is an engineering operation that involves
assessing and recording details about an area of land. These
observations can then be used to help plan construction projects.
24
3.2 TRANSPORTATION ENGINEERING
Transportation engineering or transport engineering is the application
of technology and scientific principles to the planning, functional
design, operation and management of facilities for any mode of
transportation in order to provide for the safe, efficient, rapid,
comfortable, convenient, economical, and environmentally
compatible movement of people and goods transport.
25
3.3 Construction Equipment
CONSTRUCTION EQUIPMENT means the equipment, machinery,
structures, scaffolding, materials, tools, supplies and systems owned,
rented or leased by Contractor or its Subcontractors or Sub-
subcontractors for use in accomplishing the Work, but not intended
for incorporation into the Project.
They are also known as heavy machines, heavy trucks, construction equipment,
engineering equipment, heavy vehicles, or heavy hydraulics.
Proper use of appropriate equipment contributes to the Economy, Quality,
Safety, Speed, and Timely completion of the Project. Construction equipment is
an integral part of any construction process. It is not always desirable or
possible for the Contractor to own each and every type of Construction
Equipment required for the Project.
26
Fig 3.4 Dumper
27
3.4 Estimation & Costing
28
3.5 Construction Management
29
CHAPTER-4 LEARNING
During our internship we learned about various things regarding civil
engineering basic thing we learned is how to communicate with
colleagues and how to complete project work within proper time by
the help of construction management.
The various functions and activities of construction management are;
1. Planning: It is usually done in office. "It is an administrative
process which is carried at the topmost level to decide about the
policy or methods of reaching the desired objectives.Before
starting any construction work, the planning on the following
aspects is necessary. The requirement of financial aid, its extent
and the sources from which it can be recovered.
2. Organizing is a process of fixing the responsibilities of
individual members or group of members within the
organization and coordinating their work to achieve a common
goal. The success of a construction project lies in the fact that all
the members employed in the organization at any level of
hierarchy should co-operate with each other to achieve common
objective. This is possible only, if duties and responsibilities of
each member are defined properly
3. Staffing is a process of appointing the required member of
employees (managers, skilled and unskilled workers) within the
organization for fulfilling the responsibilities of construction
work, as laid down by the organization structure.
4. Directing is the process of issuing instructions, guidelines and
broad outlines, related to project for achieving the desired
objectives, from the planning authority to the supervisory.
Quantity of billing :
During our internship we learned how to calculate quantity of bill
of a project with the help of Rate Schedule. Billing is an important
factor in construction. It is the documentary aspect of the work
done, through which payments will be made to the person
30
concerned within the contract and accountable to finish the work.
Incomplete billing will cause losses to the contractor or the client.
Hence, bills are to be excellent and obvious at any stage of the
work.
Bills from the work sites are to be prepared in a standard printed
format. Here the billing engineer roles and responsibilities along
with the job description will be understood.
Engineering Drawings:
31
Technical Terms:
We learned about various technical terms in civil engineering like
WBM & WMM etc and also we learned about various civil
engineering tools.
Road Construction:
As we did our training specially in road construction we learned a lot
about everything in road construction like process procedures test etc .
What we learned are as follow:
Surface Preparation: Preparation is the first step in the Bitumen
Road Construction Steps. It is the cleaning of surfaces from hard
rocks, stones holes, dust, and other materials. The uneven
surface to fill with 12 mm to 40 mm aggregates. If the uneven
surfaces are large coarse aggregates uses for filling. These
fillings to make before the laying of the surface course.
Placing: The placing of bitumen and aggregates are the next step
after application of coatings. The bitumen heats and transports
from plant to the site with the help of trucks.
32
be 10 to 12 tonnes. A pneumatic roller of 15 to 30 tones having
a tire pressure of 7kg per sq.cm use for roads. The wheels of the
roller to keep wet with water at rolling. The number of rolling
depends on the thickness of the layer.
33
Retaining Wall & Breast Wall :
We also learned about problems related to soil erosion which can be
prevented by reataining and breast wall:
BREAST WALL: Breast Wall is defined as the wall built to prevent
the soil on a natural slope embankment from sliding down the slope
from the harsh weather effects, i.e. land sliding, erosion etc. It is on
the downstream side of the road or a building.
34