Indicate reason and items to be bumped off with estimated cost if applicable:
Not specified in the APP and some items are insufficiently allocated but badly needed.
QTY UNIT COST TOTAL
*Repairs & Maintenancepaint brush 4" 2 100.00 200.00
-
*Signages/Tarpaulins Tarpaulin 3*4 ft 1 500.00 500.00
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
LIEZLE R. CABANGAN
BAC Chairman
MARILYN A. GONZALES
BAC Member
MAEJILL C. ARIOLA
BAC Member
Procurement Form 2
Indicate reason and items to be bumped off with estimated cost if applicable:
Not specified in the APP and some items are insufficiently allocated but badly needed.
QTY UNIT COST TOTAL
-
-
*Signages/Tarpaulins Tarpaulin 3*4 ft 1 500.00 500.00
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
LIEZLE R. CABANGAN
BAC Chairman
MARILYN A. GONZALES
BAC Member
MAEJILL C. ARIOLA
BAC Member
Procurement Form 2
Indicate reason and items to be bumped off with estimated cost if applicable:
Not specified in the APP and some items are insufficiently allocated but badly needed.
QTY UNIT COST TOTAL
-
-
*Signages/Tarpaulins Tarpaulin 3*4 ft 1 500.00 500.00
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
LIEZLE R. CABANGAN
BAC Chairman
MARILYN A. GONZALES
BAC Member
MAEJILL C. ARIOLA
BAC Member
Procurement Form 2
Indicate reason and items to be bumped off with estimated cost if applicable:
Not specified in the APP and some items are insufficiently allocated but badly needed.
QTY UNIT COST TOTAL
-
-
*GAD wood 2x3x14 1 385.00 385.00
nail 2 1/2 " 0.25 300.00 75.00
nail 1" 0.25 200.00 50.00
Paint green 1 250.00 250.00
Paint brown 1 210.00 210.00
square bar 5 250.00 1,250.00
welding rod 1 300.00 300.00
primer 2 200.00 400.00
cement 4 250.00 1,000.00
tiles (16x16) 25 81.00 2,025.00
tile cement 2 350.00 700.00
snacks 20 100.00 2,000.00
meals 20 200.00 4,000.00
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
LIEZLE R. CABANGAN
BAC Chairman
MARILYN A. GONZALES
BAC Member
MAEJILL C. ARIOLA
BAC Member
Procurement Form 2
Small Value x
for school operation Procurement (SVP) 4,200.00
Goods and Services
Indicate reason and items to be bumped off with estimated cost if applicable:
Not specified in the APP and some items are insufficiently allocated but badly needed.
QTY UNIT COST TOTAL
-
-
*Semi-Expandable- water dispenser 1 4,200.00 4,200.00
Office Equipment
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
LIEZLE R. CABANGAN
BAC Chairman
MARILYN A. GONZALES
BAC Member
MAEJILL C. ARIOLA
BAC Member
Procurement Form 2
Small Value x
for school operation Procurement (SVP) 8,220.00
Goods and Services
Indicate reason and items to be bumped off with estimated cost if applicable:
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
LIEZLE R. CABANGAN
BAC Chairman
MARILYN A. GONZALES
BAC Member
MAEJILL C. ARIOLA
BAC Member
Procurement Form 2
Small Value x
for school operation Procurement (SVP) 7,894.00
Goods and Services
Indicate reason and items to be bumped off with estimated cost if applicable:
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
LIEZLE R. CABANGAN
BAC Chairman
MARILYN A. GONZALES
BAC Member
MAEJILL C. ARIOLA
BAC Member
Procurement Form 2
x
Supplies for the school
management Small Value
operations Procurement (SVP) 900.00
Indicate reason and items to be bumped off with estimated cost if applicable:
Not specified in the APP and some items are insufficient but badly needed.
QTY UNIT COST TOTAL
*Office Supplies Printer Ink, black (L120) 5 275.00 1,375.00
Printer ink, colored (L120) 2 295.00 590.00
Printer ink, black (L3110) 6 275.00 1,650.00
Printer ink, colored (L3110) 2 295.00 590.00
HDMI 2 450.00 900.00
Repair & replacement of printer 4 550.00 2,200.00
-
-
-
-
-
-
-
-
-
-
LIEZLE R. CABANGAN
BAC Chairman
MARILYN A. GONZALES
BAC Member
MAEJILL C. ARIOLA
BAC Member