Substructure
At least 6000 bricks are needed at this level if each brick costs Shs280 that would cost one around
Shs1.6m.
About 4 trips of lake sand (Shs800,000), 3 trips of river sand (Shs540,000), 4 trips of hardcore
(Shs800,000), 3 trips of aggregate (Shs720,000) and 40 bags of cement (Shs1,120,000).
It is also important to buy the Anti termite, about 2 litres (Shs40,000) and 2 pieces of DPM (Shs160,000).
Foundation
For a proper execution on the foundation, you need to dig in up to about Shs8m on the higher end.
bricks---9000@280=2,520,000sh
Cement ---65bags@28000=1,820,000sh
Rings ---10bundles@4000sh=40000sh
Hoop iron---1roll@40000=40000sh.
Binding wire---1roll@100,000sh=100,000sh
Kalitunsi---25pcs@3500=87500sh
Nails 5"---5kg@5000=25000sh
3"---5kg@5000=25000sh
Roofing
Valleys---6pcs@20,000sh=120,000sh
Ridges ---12pcs@25000=300,000sh
Nails.6"---10kg@5000=50,000sh
5"---25kg@5000=125,500sh
4"---10kg@5000=50,000sh
3"---25kg@5000=125,000sh
Roofing nails---30kg@6000=180,000sh
Rubber washer---5pkts---6000=30,000sh
Timber
Tie beams---70pcs@8500=560,000sh
Ceiling
Timber
4*2---70pcs@7000=490,000sh
3*2---60pcs@5000=300,000sh
EML(8*2)---15bundle@25000=375000sh
Nails2"---10kg@5000=50,000sh
1.5kg---10kg@5000=50,000sh
Cement ---5bags@28000=140,000sh
Sand---1trip elf@140,000=140,000sh
Shutters
metallic windows fully finished with burglars,loovers and locks ---6 of size 5*5ft@400,000=2,400,000sh
FRONT DOOR
size 9*8ft---1@1300,000sh=1300,000sh
Dooors---10@300000=3000,000sh
Internal finishing
Cement ---20bags@28000=700,000sh
Lake sand---200,000sh---200,000sh
Tiles
floors tiles---130SM@28000=3,640,000sh
Grout---30@6000=180,000sh
Strips---10pcs@8000=80,000sh.
Spacer---5pkts@3000=15000sh
Painting
Undercoat paint---5cans@50000=250,000sh
Vinyl paint---3cans@200000=600,000sh
Thinner---10ltrs@6000=60,000sh
Brushes----5@5000=25,000sh
Rollers----3@10000=30,000sh
External finishing
Cement---20Bags@28000=560,000sh
Sand lake---1forward@200000=200,000sh
Under coat---5cans@50000=250,000sh
Electrical installations
Conduits 3.1"---40pcs@3000=120,000sh
Conduits 1"----15pcs@3500=52,500sh
Connectors----10bars@5000=50,000sh
Lamp holders-----15pcs@3000=45,000sh
Cables 1.5mm----150m@3000=450,000sh
Cables 2.5mm----80m@3500=280,000sh
Earthing ----800,000sh
Accessories -------400,000sh
Plumbing
WC complete -----4@350000=1,400,000sh
Soap dish----4@50000=200,000sh
Galley traps----4pcs@15000=60,000sh
Floor traps-----6pcs@10000=60,000sh
TOTAL :51,516,600sh
TOTAL BOQ=64,395,750SH