Professional Documents
Culture Documents
1
Contents
Overview
Background
Southwest Corridor Core Challenges
Rolling Stock
Retained Assets
Operational Readiness and Railway Performance
Corridor Protection
Takeaways, Conclusions & Food for Thought
2
Overview & Background
3
Sydney Metro City & Southwest - Overview
Conversion Activities
i. Overlaying Sydney Metro Assets onto a
Sydney Trains operational railway
ii. Addressing Sydney Trains operational
requirements (living together)
iii. Residual assets activities
iv. Pre-conversion testing requirements
affecting
a. Infrastructure
b. Systems and
c. Operations
v. Post conversion arrangements
ST’s/SM ARTC
7
Southwest Corridor Core Challenges
• Circa 100-year-old corridor of differing aged assets (track, OHW System, drainage , bridges, embankments, retaining
walls, stations, etc.).
• Ballasted track formation along the whole of the alignment also OHW heights and staggers on the Southwest Section
differ to those on Northwest and City Sections (greenfield tunnel versus established brownfield open).
• Parallel Freight Corridor along 50% of the corridor
• Significant areas of dense population (history of corridor breaches).
• Stations (heritage protection, long and curved platforms, singular exits, can’t cater for equipment rooms, etc.).
• Traction system not capable of supplying the headway requirements to meet future projected demands.
• Elements of the line are subjected to flooding events.
• Rolling Stock procured for the Northwest and City Sections required to operate on the Southwest Section with no
modifications.
• Bankstown station currently a through station required to become a “double terminus station” for Sydney Trains and
Sydney Metro Operations.
9
Rolling Stock
• Rolling stock procured for Northwest:
- 6 car length with future expansion to 8 car to be
considered.
- Circa 150mm narrower than the Sydney Trains rolling
stock running on Southwest Corridor (and that which
was running on the Epping to Chatswood Section on
the Northwest Corridor prior to conversion).
• Platform to train interface (DSAPT requirements)
managed through:
- Straight platforms
- Fixed gap fillers mounted on the platform
- PSD fixed gap fillers
Note – the above is relevant to the Northwest and City Sections
12
Retained Assets
• Broken into differing categories (Commercially)
- Track, OHW Structures and OHW.
- Retaining Walls, Embankments and Culverts.
- Drainage.
- Other (Station Structures, Bridges, etc.).
• Condition Assessments and Strengthening (if appropriate)
- Bridges, Station Structures, etc. assessed and retained or renewed
based on remaining asset life.
- Culverts cleaned out and ‘enhanced/renewed’ based on modelling
results.
Sydenham through to Marrickville
- Drainage broken out into two distinct categories (within or outside in flood plain
16
Operational Readiness and Railway
Performance Activities
CBTC Overlay
Equipment
• Balises installed in the track
• Axle counters fitted
• Wi-Fi antenna’s mounted on OHW Structures
• Points & turn-outs fitted, detected but locked out of service.
Note – In order to install these whilst under the operational control of Sydney Trains, it was incumbent upon Sydney
Metro to demonstrate there would be:
• No issues relating to EMC that would adversely affect their systems.
• No issues relating to the physical installations that would adversely impact their maintenance activities.
• No issues that would introduce safety concerns and/or create hazards to their staff or infrastructure
Equipment
• Platform Screen Doors (with integrated Mechanical Gap Fillers and Intrusion Detectors) Functionality
• PSDMGF/ODS interface with Train Functionality
• CBTC & CCS Functionality
Note – Due to Sydney Trains Rolling Stock Doors not aligning with the Sydney Metro Rolling Stock Doors:
- PSD’s and ODS’s cannot be installed prior to the final shutdown.
- MGF testing and meeting legislative requirements with respect to PTI Compliance needs advance testing.
- RAM’s verification necessary in advance of shutdown and transfer of operations.
- Assurance required that MGF’s will not deploy whilst under Sydney Trains Operations
Note – Due to the need for the continued safe and compliant delivery of Sydney Trains services and operations:
- Installation prior to conversion needed to be coordinated with Sydney Trains (particularly Camera’s, Speakers, Help
Points).
- Interim maintenance contracts for lifts required to ensure early introduction of new facilities.
Converting a Legacy Rail Corridor to GoA4 Unattended Train Operation 20
Operational Readiness and Railway Performance
Activities
General Alignment Activities
Equipment
• Fencing (segregation and / or boundary)
• Electronic access system (Sydney Trains requirements & commissioning timing)
• Track changes
• OHW changes
• Traction power changes
Note – A coordinated and agreed methodology of ‘gradual introduction of required changes’ necessary to maintain a
safe and reliable Sydney trains Service until conversion:
- Fencing introduces ‘Signal Sighting and Corridor Access issues’
- Electronic Access Control into the corridor (Sydney Trains assets remain in the corridor and thus requires post
conversion access arrangements)
- Track and OHW changes required planned possessions and ‘Standards Derogations’
- Temporary traction control arrangements to facilitate testing
Converting a Legacy Rail Corridor to GoA4 Unattended Train Operation 21
Corridor Activities &
Protection
22
Corridor Activities & Protection
Initial Approach
• Market Research – Included UK Test Track Activities
• Development of Safety, Operational, and Technical Requirements
• Risks and Hazard Workshops
• Development of Performance Specifications
Market Engagement
• EOI – Included Operational and Performance requirements
Contract Awarded 2023
26
Takeaways, Conclusions & Food for Thought –
Metro Conversions
Sydenham to Bankstown
Acknowledgement should be given to Sydney Metro for the investment entered into, their engineering vision and the
contribution they have, and with knowledge share, will continue to provide to the industry.