Professional Documents
Culture Documents
Galian GWT STP (Klarif Volume Galian STP GWT SMP Sma)
Galian GWT STP (Klarif Volume Galian STP GWT SMP Sma)
Urugan SMP :
1 Lt. Dasar Gedung 1490.93
2 Pengurangan Void Pit Lift 2.28 2.30 5.23
3 Pengurangan Void Pit Lift 2.25 2.30 5.18
4 Pengurangan Void Pit Lift 2.28 2.33 5.29
5 Pengurangan Void Pit Lift 2.38 2.37 5.63
Total 1469.60 1249.16
URUGAN 2498.33
Volume Galian GWT dan STP SMP
0.70 m
No Item P1 (m) P2 (m) P (m) L1 (m) L2 (m) L (m) Tinggi (m) Volume (m3)
Galian STP & GWT :
1 GWT SMP 31.32 27.31 29.31 15.46 11.76 13.61 2.50 963.52 33.92 m3
2 STP SMP 13.40 10.80 12.10 17.29 10.9 14.09 1.98 337.69
Total 1301.21
0.25 m
Item P (m) L (m) h (m) Jumlah Volume (m3)
Galian Sloof & Pile Cap :
1 Sloof TBME-1 43.40 0.60 0.40 10.42
2 Pile Cap PCME-1 1.20 1.20 0.60 3 2.59
3 Pile Cap PCME-1* 1.45 1.25 0.60 1 1.09
Total 14.10
No Item P1 (m) P2 (m) P (m) L1 (m) L2 (m) L (m) Tinggi (m) Volume (m3)
Galian STP & GWT :
1 GWT SMA 16.15 11.50 1.62 300.87
2 STP SMA 15.22 10.70 12.96 16.20 12.87 14.54 1.98 372.98
Total 673.85
0.25 m
Item P (m) L (m) h (m) Jumlah Volume (m3)
Galian Sloof & Pile Cap :
1 Sloof TBME-1 52.28 0.60 0.40 12.55
2 Pile Cap PCME-1 1.20 1.20 0.60 6 5.18
Total 17.73
GALIAN 2006.89
Elv. Elv.
No. Item Pekerjaan P (m) L (m) Gambar Eksisting h (m) Volume
(m) (m)
A Galian STP & GWT SMP 736.23
1 Galian STP SMP 7.25 8.90 - 3.60 - 0.80 2.80 180.67
2 Galian GWT SMP 24.98 6.95 - 4.00 - 0.80 3.20 555.56
m3
m3
m3
m3
m3
m3
m3
Volume Galian GWT dan STP SMP
0.25 m
Item P (m) L (m) h (m) Jumlah Volume (m3)
Galian Sloof & Pile Cap :
1 Sloof TBME-1 43.40 0.60 0.40 10.42
2 Pile Cap PCME-1 1.20 1.20 0.60 3 2.59
3 Pile Cap PCME-1* 1.45 1.25 0.60 1 1.09
Total 14.10
0.25 m
Item P (m) L (m) h (m) Jumlah Volume (m3)
Galian Sloof & Pile Cap :
1 Sloof TBME-1 52.28 0.60 0.40 12.55
2 Pile Cap PCME-1 1.20 1.20 0.60 6 5.18
Total 17.73
GALIAN 2006.89
Klarifikasi Volume Galian STP GWT SMP SMA
0.7 m 33.92 m3
2 Galian SMA
a GWT 16.15 11.50 1.8 334.31 m3
b STP 12.96 14.54 2.5 471.10 m3
Total 2355.24 m3