Professional Documents
Culture Documents
Review
filifg
U. Burger:
Overvoltage Protection for Totally Enclosed
SF 6 Switchgear and CGI Cables 179
J. Urbanek
the data. In special cases we are assisted in this by the
It is proposed that the electrical circuits are described by relevant Standard, e.g. publication 56 of IEC [6],
force, form and quality factors for calculating the inter- As the Standards must be applicable for any given network
ruption response of high-voltage circuit-breakers. These new they are necessarily idealized to a large extent. Conse-
expressions have not been commonly used before in this quently, the Standards do not in fact correspond to a real
connection. A discussion along similar lines about a new electrical network. If we need an electrical network for
arc theory which describes the thermal and dielectric re- investigation or calculation purposes we must attempt to
striking by means of counter-forces and a further form approximate the Standards, even if this means diverging
factor leads to the expression for a vectorial breaker stress. from real network configurations.
This permits the breaking capacity for a short-circuit at the A second important point must be noted here. Special
terminals to be calculated on a general basis according to attention must be paid to the fact that the individual
IEC recommendations. The contribution concludes with a effects are considered according to their order of priority
review of the IEC test requirements, the initial curve of the so that the order of the approximation can be selected.
transient recovery voltage and breaker developments.
Forces
Let us consider the forces as those characteristic values of
the network which we believe will impede the switching
operation. The correctness of our choice is confirmed by
working back. First of all we must consider the rated
voltage of the network. However, as we cannot dehne an
electrical network with this alone let us take the rated
breaking current as the second determining factor. But no
proper physical breaking operation can take place in a
circuit of this nature; we require a further value, e.g. the
frequency of the restriking voltage. We have now deter-
mined the three dimensions, voltage, current and time,
in which the electrical phenomena take place. As is the
case in IEC recommendations we consider only the first
phase to clear of a three-phase system and instead of the
rated voltage we take the peak value of the transient re-
covery voltage « c as a reference value and instead of the
oscillating frequency we take a tangent from the neutral
Introduction point to the transient recovery voltage u' = Uc/t3. For the
sake of simplicity we will restrict ourselves to the two-
]n general, only the rating is known of a breaker in an parameter method [6]. In order to become independent of
electrical circuit. It is also known that the limiting data of the asymmetry of the current we will refer to the gradient
the breaker are higher, and the corresponding data of the of the current at zero transition /„'.
network lower, than the ratings. This is, of course, per-
The forces are therefore: uc, «', /„' (1)
fectly adequate for practical purposes.
However, in many cases it would be useful to know the At the same time these dehne the scalar factors
magnitude of the stresses involved. The question is, how
/o «c Wc
difficult is it for various breakers to interrupt the current = P-VL = Uc, fit = — = 13 (2)
at various points in the network? u u
Methods of answering such questions are dealt with in There is only one Standard circuit (Fig. I a) from which
the following. all circuits clearly dehned by the forces (1) can be derived
by multiplication with the scalar factors (2). This circuit is
referred to as the circuit of the third order after the number
The Electrical N e t w o r k of its variables. All Standard numerical values are given
in line a of the Table.
Let us begin with a very important Statement. There are The forces (1) can also be represented as the components
no two points in the network which are truly identical. of a three-dimensional vector K. All imaginable circuits of
There is therefore an enormous volume of information third order thus fill an octant of a sphere having a volume
available. As always, we can gain knowledge only by of oo3. The position of any given electrical circuit is shown
reducing the volume of information, i.e. by compacting by the defined polar vector K.
The data for all terminal short-circuit loops having the From the scalar factors for current, voltage and time we
same form and quality factors can be calculated by multi- can calculate the multiplication factors for the Standard
plication with the scalar factors: [Xi = /'„' t3, fxu — Uc, values in the Table in the normal fashion: /uc = [Xil[xt![xu\
fit = t3, where /„' = rate of rise of inherent current on /MR = [Xu/VU [XL = [Xu [Xt/fXi.
zero transition.
iic, u c /t3 = peak value and rate of rise of recovery voltage
according to IEC [6] respectively.
The Breaker
\
/ / — s
irc can decay.
%
The Counter-Forces
kVe can develop scalar factors for the breaker in exactly
he same manner as we did for standardizing the electrical
90
80
\
»1
;ircuits. Firstly, let us introduce the expression for the
;ounter-forces:
70
1
ud Po ua
(9)
60
Ii
/
We can now derive scalar factors in similar fashion to (2).
40
(10)
1
E =
U <j 10
multiplying with any function of e. This would have Fig. 3 - Unaffected recovery voltage u of a terminal short-circuit (Fig. 1
with the data according to the Table, line d) in relation to time t. The
:hanged the form but not the content of the further definition of l 3 , td, «c and u 1 is according to two-parameter test according
results. to I E C [6],
We can also imagine that the breaker form factor remains
;onstant and a parameter in the same manner as the cir-
cuit form factors. We have good reason to believe that
this will prove to be of significant material value for the counter-forces (9), e.g. ua = 200 kV, ua/& = 200 kV/[j.s
quenching medium. P . e2
ua •&
500 A/s that we can calculate the stress
Su = 0-5, S u ' = 0 005, Si 4 • 104
Stresses at t h e Breaker
Once we have solved the general problem of the terminal
We can standardize the forces in the circuit and the short circuit on a numerical basis, as will be discussed in
:ounter-forces at the breaker. The ratio of the corres- the following, we can immediately see from Fig. 4 whether
ponding scalar factors would then give us the transforma- this stress is permissible.
tion multiplication factors between the circuit and breaker Introducing the expression for breaker stress considerably
values. improves the calculation of the breaking capacity. As we
We obtain the same factors also if we apply one of the have shown the general problem of the terminal short
two scalar systems to the other system. The relationship circuit has a volume of oo 10 . With the aid of the breaker
between the corresponding forces and counter-forces then stress concept we can reduce this volume to oo3 or oo4 if
Dccurs in the new system. If the form factors are kept the breaker form factor is to be analysed. The problem of
konstant these relationships represent the three variables the terminal short circuit can be solved with a desk top
of the coupled system. In the following we refer to the Computer in two weeks (Fig. 4) but without our concept for
ratio of the forces (1) and the counter-forces (9) as the breaker stress it would take 40000 years to solve with the
breaker stress: same information.
W c u e
e _ c ' _ ' <J c - _ '»' "d '
(11)
&
Ju — > — Oi — — An Example
ud ua P0
We can consider the breaker stress as a polar vector with The complete terminal short-circuit problem is shown
the components voltage stress Su, stress due to rate of rise graphically in Fig. 4 (see also line d in the Table and
5 U ' and current stress Si'. The stress condition is fully Fig. 1 d and 3). The breaking capacity is represented by
defined by quoting these three stress components and the an area in the region of the breaker stresses according to
constant form factors. (11). Stresses within this area are permissible; outside
Describing a circuit by the forces (1), e.g. uc = 100 kV, this area they lead to breaker failure. Approximately 1000
u' = 1 kV/jjis, i' = 20/(xs gives no indication of the stress points were calculated for Fig. 4. Each point was the
imposed on the breaker by the circuit. ft is not until we result of an alternating series of quenching and restriking,
know that this circuit is confronted by a breaker with the of either thermal or dielectric nature, where the faults
were smaller than ±2%. For aesthetic reasons, instead of the morc rapidly the smaller the stress due to the rate of
using Su and Si their logarithms were entered with a rise. This merely indicates that the frequency of the re-
suitable displacement of the neutral point. Figure 4 shows covery voltage has a stronger influence than its amplitude;
three types of stress which characteristically limit the the rate of rise of voltage is proportional to both.
breaking capacity. These ranges are referred to as:
the voltage limit, The Current Limit
the maximum rate of rise, and
In the lower ränge where 5 U < 0-1 the voltage stress re-
the current limit.
gains its importance. We cannot identify any influence by
the stress due to the rate of rise 5 U '. In this ränge the dura-
The Voltage Limit tion of the stress, which is proportional to Su/S u IS SO
If the voltage limit Su is greater than 0-99 it restricts the short that the arc integrates over it. Consequently the
breaking capacity. As the voltage stress increases the stress becomes proportional to the integral over the re-
permissible current stress SV reduces extremely rapidly. covery voltage, i.e. approximately proportional to Su2/Su'.
Where Su = 1 we have SV = 0. This can be immediately The permissible current stress would therefore exceed all
understood if we refer back to the definition of Su (11). limits with reducing voltage stress. However, nozzle
Where Su = 1, i.e. « c = «d, this means that the peak blockage then occurs. This is not considered in our arc
value of the inherent transient recovery voltage uc is theory. We can take it into account by intersecting the
sufficient to break across the arc Channel which has cooled limiting surface at a given critical value for current stress
down in the mean time and which has a dielectric strength [5],
of Wd- If the current Si is greater than zero, the arc Channel Figure 4 shows clearly how the maximum rate of rise
would still be warm at the instant the peak value uc overlaps the current limit. This is of great significance in
occurs. Because of the low density the Channel would practice. The curve of the initial transient recovery voltage
break down at a lower voltage than wa- is characterized by its particularly high rate of rise but low
However, the Channel has more time to cool if the stress peak value. Figure 4 also gives us a clear value for the
due to the rate of voltage rise Ou ' is smaller. It is therefore voltage below which we can ignore such phenomena
understandable that the permissible current stress rises (S u >0-1).
rapidly as soon as the voltage stress drops only slightly
below 1.
Deciphering t h e Stress
The Maximum Rate of Rise Using the stress has made it possible for us to calculate
In the medium ränge where 01 < Su < 0-95 the voltage the whole problem in concrete figures. However, what is
stress plays a very subordinate role. The permissible cur- the Situation for the individual case? We must differentiate
rent stress Si' is inversely proportional to the stress due between two questions. First we have a concrete circuit
to the rate of rise IJU '. Our tests were generally carried out given by the forces (1). In addition to this Fig. 4 shows
in this ränge. We should not be too surprised that, in this the multiplicity of all breakers which just manage to
ränge, the total stress increases as the voltage stress drops, qualify for these requirements.
Conclusions
\
h model. We can now use the theoretical curves for deriving
further information and apply them to other geometries or
\
JLJx X/
X \
Problems. The combination of measurement techniques
h
and theoretical models, as discussed here, has proved
itself in solving many problems in breaker development.
The theory or the discrepancy between truth and the
theoretically described ideal case is tested by measure-
2 4 6 8 10 12 14 16 18 ment. Consequently, the theory can be applied in investi-
200035.1 , / m s gating many problems and questions which could other-
Fig. 3 - Variation of arc radius r with respect to time for various r.m.s. wise not be cleared up or, if so, only at great expense by a
current values / j and / 2 series of tests.
Comparison between experiment (crosses) and theory.
Application in Designing
t h e I n f l o w G e o m e t r y at t h e Drive
current. This permits the narrowest possible nozzle cross The pressure drop in the reservoir of a two-pressure
section to be determined for a given maximum current. breaker and also the pressure rise in the compression
The absolute pressure and pressure drop also determine volume of a puffer type breaker depend largely on the
the velocity at which the conductive arc column can be mass of quenching medium which flows through the
reduced in the region of zero transition, i.e. they influence nozzle geometry. This gas flow is necessary for cooling
the response with respect to thermal restriking. The length the arc, restricting its diameter and quenching it rapidly
of the arc in the high-pressure section is an important after zero transition.
factor for dielectric response. This length also, across The mass flux density in the arc is negligibly small com-
which the pressure has not dropped appreciably from the pared with the cold gas region. Consequently, only the
Stagnation point value, can be derived from the flow cross section of the cold gas flow is effective for the mass
pattern. flux. The arc therefore very strongly influences the mass
The instantaneousflow field determines the instantaneous loss through the nozzle because its diameter, which varies
arc cross section. However, the arc diameter and its with the arc current, reduces the flow cross section of the
Variation with the arc current and geometry have a strong nozzle to a greater or lesser degree. The nozzle cross sec-
influence on the flow of quenching medium. In order to tion is normally designed so large that the arc is well
clear up many questions it is important to know the blasted even at maximum possible current. At these high
Variation of the arc cross section with respect to time for a currents the mass flux through the nozzles is reduced to
given curve of the arc current and the contact movement. very small values. At small currents, however, there is a
Figure 3 shows a comparison between a curve of arc cross large cross section available for the gas flow and large
section with respect to time derived theoretically from the quantities of quenching gas are lost. These relationships
interaction between arc and quenching medium flow and are illustrated in Fig. 4 which shows the mass flux through
values measured on a type ELK breaker. 1 The curve the nozzle system corresponding to Fig. 2 for a given
along the time scale shows the arc radius for two different pressure in the high-pressure volume in relation to the
r.m.s. current values. The Variation of arc radius with arc current. As current increases, the arc reduces the nozzle
respect to time is distorted from the sinusoidal current cross section and the mass flux reduces accordingly. The
curve because the radius depends on the nozzle zone knee in the curve corresponds to that current value at
geometry which alters with the contact travel. The crosses which the arc just fills the nozzle cross section. The mass
in the diagram represent values measured for the arc flux at even higher currents is represented by the gas
cross section of an ELK breaker. The measurements were flow through the hot arc. This is very small compared
carried out for a test case where the phase angle and with the mass flux through the nozzle without an arc. In
amplitude of the current curve and also the velocity of the case of the sinusoidal Variation of the arc current the
curve runs from left to right up to the maximum current
and back to the ordinate within a half wave. The total
1
G. Mauthe, W. Bischofbcrger, K.D. Schmidt, A. Ueber: Type ELK quenching medium loss is derived by adding the instan-
circuit-breakers for metal-enclosed S F e insulated switchgear installations.
Brown Boveri Rev. 61 1974 (4) 152-166.
taneous value of mass flux.
Conclusion
Description
Introduction The modular system of construction used for the series
DLFB - DLF - DLFK is based on three main compo-
Brown Boveri airblast circuit-breakers, and particularly nents:
the DLF ränge, have for years been a byword in their
special field. By the end of 1974, the total number of DLF - double interrupting Chamber with integral operating
breaker groups delivered for voltage ratings from 72-5 to mechanism,
765 kV will be more than 1800. These will include the first - load-bearing insulator column with control rod,
of the DLFK constant-pressure breakers. This success is - base assembly with control unit.
the result of carefully planned, continued development of The Standard base assembly can take the form of an air
receiver which, when arranged vertically, does away with
the supporting steelwork required otherwise.
The breaker can, however, also be built with a connecting
housing. With this configuration it is possible to dispense
with the air tank when the breaking capacity is modest
(DLFB), add on a flange-mounted receiver when the
breaker is uprated (DLF), and then for very high breaking
capacities fit an assembly which keeps the pressure in the
interrupting Chamber constant during the opening process
(DLFK), Fig. 1 a, b and c.
Every model, whether DLFB, DLF or DLFK, for voltage
ratings from 72-5 to 1100 kV and breaking capacities
from 20 to 63 kA, is based on these components. All parts
of the breakers are interchangeable.
20 kA 40kA 50 . . . 6 3 k A
'///'V''/',
200017.1
Fig. 2 - Uprating by increasing the number of interrupting Chambers Inereased Interrupting-Chamber Capacity
from 2 to 4 or from 6 to 8
In the early 'fifties, the breaking capacity of the inter-
rupting Chamber of an airblast circuit-breaker was 500
MVA. Today, the breaking capacity of a DLFK Chamber
is 4500 MVA (Fig. 3).
Principal Applications
Because of their breaking capacity, short opening time
and permissible number of switching cycles, airblast
circuit-breakers of the DLF ränge have for many years
Fig. 3 - The rise in breaking capacity P of the interrupting Chambers of been used particularly in stations at load centres and cri-
Brown Boveri o u t d o o r airblast breakers since 1950
tical points in networks. An advantage of the airblast
breaker in such cases is that it can perform a large number
of Operations at short intervals and without derating,
as required in the event of consecutive faults, for example.
With the aid of suitable compressor plant, the DLF
breaker can also be employed economically in smaller
switching stations so that here, too, the merits of this kind
of breaker can be used to advantage. Airblast breakers
of this ränge prove their Performance every day in many
installations operating under widely varied conditions.
Special Applications
Reactor Breakers
r i i i i i i i i i i i i i i i i i i i
1950 1955 1960 1965 1970 1975 Experience shows that trials in the test bay are not repre-
sentative of conditions in Service because the magnitude
Test Results
1
IEC = International Electrotechnical Commission
ANSI = American National Standards Institute
Fig. 5 - Terminal short-circuit test, cycle CO. Synthetic test with super-
posed voltage on a double interrupting Chamber of a breaker type D L F K
245 nc 4
a: Magnetic-type oscillogram
«T = Voltage in high-current circuit
/'s = Current across breaker
b: CR oscillogram of recovery voltage
200021.1
Tests with Elevated Breaking Capacity per Chamber with 75 % of the rated breaking current, referred to 15 GVA
The breaker DLFK 362 pc 4 also has four interrupting at 245 kV.
Chambers per pole on a Single column (Fig. 6). With a All airblast breakers of the DLF ränge are ideally suited
rated breaking current of 56 kA this gives a capacity per for switching capacitive currents. On the one hand, switch-
Chamber of roughly 4500 MVA, equivalent to a three- ing in sections of capacitor banks, for example, with high
phase rating of 35 GVA. Oscillograms of a corresponding transient currents is quite straightforward, while on the
test have been shown in an earlier article ([1], Fig. 10). other, disconnecting similarly presents no difficulties since
the flow of quenching medium is independent of current
Tests with Elevated Voltage per Chamber and ensures a rapid rise in the dielectric strength of the
With two interrupting Chambers per pole, the 245 kV contact gap, without the need for any assistance. For a
breaker is heavily stressed as regards the specific voltage breaker of this kind which can handle phase Opposition,
per Chamber. interrupting capacitive currents in general presents no
Oscillograms of a DLF 245 nc 2 (150 kV per Chamber) problem because the recovery voltage in the former case
opening under phase Opposition conditions have been attains at least the same value, but in a much shorter
published elsewhere ([4], Fig. 5). time.
As an example of testing this breaker under short-line Interruption of a capacitive current of 400 A with one
fault conditions, Fig. 7 shows an oscillogram on opening Chamber of the DLFK 362 pc 4 is illustrated in Fig. 8.
Mechanical Tests
The question of reliability has always received the closest
attention. Design, development, manufacture and quality
control are especially aimed towards this objective.
Of the mechanical tests, particular mention should be
made of the long-term tests carried out to date. Since the
development programme began, nine breaker poles have
each undergone between 10000 and 15000 CO Operations.
These tests have included two and four-chamber assem-
blies, together with their control cubicles; the compo-
nents used are partly picked out at random from the
production line. The pressure for the tests is varied in
steps between 20 and 35 bar. Two of the nine breaker
poles under long-term test are constant-pressure breakers.
These tests are part of the programme of development and
improvement, and at the same time provide a means of
continuous quality control.
Earthquake tests occupy a special place as regards the
stresses applied to a circuit-breaker. While it is true that
at present there is no test procedure which is accepted
generally and internationally, test methods nevertheless
do exist that are equivalent to, or more severe than,
exposure to an earthquake. The most exacting test of
this kind is the shaking table method, whereby the test
object on the table slowly passes through the frequency
ränge close to its natural frequency.
A problem with the shaking table method is to find a test
facility able to accommodate a test specimen as tall as an
outdoor circuit-breaker. One such facility is the Istituto BROWN BOVERI 161259.1
Sperimentale Modelli e Strutture (ISMES) in Bergamo. Fig. 6 - Pole of a D L F K airblast breaker for 362 kV, / a = 56 kA,
Here, using all the height available, a DLF breaker for /„ = 3150 A
m
•••• • •• •
several breakers, and so far has fully come up to expecta-
tions. The total effect is to reduce the number of com-
a 200024.
1 I Ii M M ii ii ii y y i ii i i i i i i II II
M
lms
"s
" H Ü
VA*
Moreover, laying and Atting is much simpler and faster showed no defects or excessive wear when they were
than with copper pipes. Flexible piping suitable for pri- eventually inspected. The experience gained with earlier
mary pressures from 150 to 200 bar is now obtainable. breaker types regarding maintenance has been applied to
the DLF ränge. This, together with successfully withstood
severe long-term tests, has allowed us to set the interval
Longer M a i n t e n a n c e Intervals between inspections at 10 years or 5000 normal Operations.
Maintenance has been made considerably simpler by the
It is a tradition of Brown Boveri airblast breakers that fact that when the time for an overhaul arrives, initially
the amount of maintenance required is extremely small. the condition of only one interrupting Chamber and one
DCF breakers which had been in trouble-free service for control unit is checked [6]. In most cases the result of this
10 to 15 years without being overhauled, for instance, still inspection, which takes only a short time, is that work on
Fig. 9 - Control units, former (a) and new (b) models, for D'LF airblast
circuit-breakers shown with cover removed
a b
Conclusion
Bibliography
200026.1
It is a well known fact that the probability of an arcing Pressure Rise in t h e Enclosure
fault occurring in an SF 6 insulated installation is very
remote. The insulating capacity of these installations is It is useful to first investigate theoretically the effects of an
unafifected by climatic conditions. SF 6 switchgear operates internal arc with respect to the expected pressure rise in
on the basis of a gas pressure which is above atmospheric the enclosure. The expected pressure rise calculated by
pressure. The gas density is normally monitored by a simplified means is shown in Fig. 1.
density relay. As the dielectric strength is proportional to It can be seen from Fig. 1 that the smaller volumes must
the gas density, constant dielectric strength is ensured be primarily designed with adequate wall thicknesses, for
over the whole monitoring ränge under all temperature mechanical reasons, to prevent bursting of the correspond-
conditions. In normal operation the actual dielectric ing plant component due to the very high pressure rise to
strength is always above the guaranteed insulating level. be expected. With larger volumes the wall thicknesses
If it drops below the insulating level the fact is indicated must be designed from the aspect that the plant compo-
10 ms
200064.1
b
- Consequential damage due to the fault expanding can Other plant components which are not affected must be
occur only in those sections of the plant which must be kept in service as far as possible.
interrupted in any case as a result of the fault. - The switchgear and plant components damaged by an
- If an arc fault occurs in switchgear with a double busbar arc fault must be rapidly and easily exchangeable.
system at least one busbar must always remain under
voltage. The chosen concept ensures that an arc fault is restricted
- In the event of an arc fault in a plant with a single busbar to the first protection stage ( < 100 ms) of the affected
system the busbar repair time must be kept to a minimum. compartment volume for all plant components. Should
the first stage of the short circuit protection system fail
under high short-circuit currents an internal pressure relief
takes place. It is thus impossible for the enclosure to burst.
Fig. 6 - Measured melt-through times (with stabilized arc root) Generally, the first pressure relief provides such a large
a 4 m m thick stainless steel volume that, even with very high short-circuit currents,
b = 8 m m thick aluminium fault durations of up to several seconds are permissible
c - 4 mm thick carbon steel
i = Short-circuit current without the enclosure bursting.
t Melt-through time External effects (danger to personnel, damage to adjacent
40
plant, cables, pressure piping, control leads and auxiliary
equipment as well as buildings) are eliminated.
Melt-through must not take place before the end of the
i [kA)
second protection stage ( > 500 ms). As illustrated in
• 30
Fig. 6 fulfilling this requirement on a general basis
becomes expensive because very thick walls have to be
employed. Our investigations showed, however, that it
20
is difficult to stabilize the arc with cast aluminium and
that without stabilization the electro-magnetic forces
always direct the arc towards the insulator. The root of the
arc in the enclosure is at the solid flange (or directly
adjacent to it) resulting in longer melt-through times.
Provided that these facts are borne in mind, economical
Ol arrangements can be found while complying with the
0 100 200 300 400 500 600 above requirements.
—/[ms]
The investigations confirmed the theoretical considera- immediate measures to be taken to enable operation to
tions discussed under the section dealing with the prin- be continued.
ciples of the Brown Boveri protection concept in typical 2. There are several methods available for accurate fault
field applications. location where this is necessary. Two of the more im-
portant are:
- Measuring the gas decomposition: This takes advantage
Fault Location of the fact that the arc decomposes a part of the gas in
the affected section. The gas decomposition can be de-
The following means are available for fault location: termined by smell or by means of a simple measurement.
1. The displays of the individual components of the nor- - Pressure rise due to the arc is indicated by a pressure
mal protection system are used for roughly determining gauge of the trailing pointer or contact type.
the location of the fault, in similar fashion to conventional Temperature-sensitive colours and other methods can also
installations. In most cases this rough fault location enables provide information about the location of the fault.
Bibliography
A new circuit-breaker for medium breaking capacities has of SF6 engineering, resulted in a reliable and economical
been developed as an extension to the ränge of type ELK type of breaker. The most up-to-date measuring methods
SFe insulated, metal-enclosed switchgear. The new breaker developed in our laboratories, and Computer programmes
operates on the single-pressure pujfer principle and has an used in the field of plasma physics, applied to this breaker
oil-hydraulic drive. Modular principles permit breakers to gave deeper insight into the quenching phenomena and the
be built for up to 765 kV using only afew components. Apply- effect of the design parameters which determine the breakin
ing all experience gained in airblast and l.o.v. circuit-breaker capacity.
engineering, and also the 15 years of experience in the field
2500
2100
2500
4 2 0 . . . 525 kV 525...765kV
Fig. 2 - Range of type E L K S F 8 circuit-breakers for rated voltages of d: Four quenching Chambers per breaker pole
145 to 765 kV e: Six quenching Chambers per breaker pole
a: One quenching Chamber per breaker pole b Width
b: Two quenching Chambers per breaker pole t = Depth
c: Three quenching Chambers per breaker pole
Rated voltage kV 145 170 245 300 362 362 420 525 525 765
40
1
Opening and EL {\ u|
closing current kA 31,5--
Rated voltage kV 145 170 245 300 36-2 362 420 525 525 MB
mm
765
Size III IV
BROWN BOVERI
The arrangement of the breakers with four and six quench- Covers. The contacts are operated by fibre reinforced in-
ing Chambers per phase can be seen in Fig. 2. A breaker sulating rods. In the case of a breaker with a Single quench-
pole comprises two breakers with two or three quenching ing Chamber these are arranged centrally. For breakers
Chambers connected in series and an enclosure according with two and three quenching Chambers per pole these
to the voltage. These are arranged side by side on a com- insulating rods are arranged next to the quenching Cham-
mon frame. Each breaker pole has its own drive, i.e. two bers and the driving force is transmitted through arms in
drives operate in parallel for each phase, and these are the intermediate housings to the driven contacts. A sealed
arranged such that they operate simultaneously. shaft transmits the driving force into the gas Chamber.
The breaker position indicator and the auxiliary switch Control capacitors connected in parallel with the quench-
are rigidly connected with the breaker drive linkage. These, ing Chambers ensure even voltage distribution.
and also the tripping coils, are arranged in the breaker As can be seen from Fig. 4c the quenching units of all
frame with easy access. breakers in the ränge can be assembled from a few basic
components.
Quenching Unit The quenching Chamber operates on the puffer principle
The quenching unit, fixed to the front end of the enclosure of a compression system. The arc is quenched by blasting
by a cylindrical post insulator, comprises one or more in a nozzle made of insulating material, supported by a
quenching Chambers, intermediate housings and end metallic auxiliary nozzle opposite it. An adequately di-
Quenching unit
Live components
Earthed c o m p o n e n t s
Insulators
SF f i
Principle
Closing
- command 'close' arrives at tripping coil of solenoid valve
- solenoid valve 'close' operates
- pressure build up at control piston amplifier valve
- amplifier valve changes over
- pressure drop at control piston of main valve
- main valve connects drive cylinder with high-pressure
reservoir
- pressure applied to large surface area of drive piston
- drive piston moves contacts in closing direction
- vacuum blast of pre-ignition arc in quenching Chamber
- arcing contacts close, pre-ignition arc quenched
- spring for driving auxiliary piston is loaded
- continuous current contacts close
Fig. 5 - Operation of auxiliary piston - breaker is now closed.
Compressed volume AK in relation to the contact travel J
A = Main piston
B Auxiliary piston Opening
a Without auxiliary piston
b - With auxiliary piston - command 'open' arrives at tripping coil of solenoid valve
s x = Contact Separation - solenoid valve 'open' operates
- pressure drop at control piston of amplifier valve
- amplifier valve changes over
- pressure drop at control piston of main valve
The drive is designed for operating two or three quenching - main valve connects operating cylinder with low-
Chambers, i.e. only a single type of drive is used through- pressure reservoir
out the whole breaker ränge, with appropriate settings. - pressure reduced at large surface area of drive piston
In order to ensure reliability of the drive the oil pressure - drive piston moves towards open position
for Controlling the high-pressure pump and breaker lock- - start of compression in quenching Chamber by means of
out is monitored, as well as the gas volume in the hydraulic auxiliary piston
reservoir. - continuous current contacts separate
Under normal circumstances the breaker contacts are - arcing contacts separate
held with füll drive pressure in the open or closed position - auxiliary piston reaches final position
Table II: Densities and pressures of breaker gas content and response levels (*) of density monitor
Signal from Breakers for low switching Breakers for high switching
density monitor capacities capacities
contacts
Density Pressure (abs) Density Pressure (abs)
g/1 bar at 20 °C g/1 bar at 20 °C
- strong blast at arc The slight gas decomposition due to switching high short-
- arc is quenched at a maximum of 20 ms after contacts circuit currents and also the residual moisture due to
separate assembly and overhaul are adsorbed in a static filter in the
- breaker open, end of blast. cover of the service aperture on the side of the unit.
Installation and M a i n t e n a n c e
Quenching and Insulating M e d i u m
The circuit-breaker comprises three units which require
As type ELK breakers operate on the puffer principle and, assembly:
consequently, the quenching gas need not be stored under
- the breaker pole comprising breaker enclosure and
high pressure, the cost of gas supply and monitoring is
correspondingly low. The dielectric strength is based on a quenching unit
minimum gas density of 21-5 g/1 (corresponds to p a bs = - the breaker frame, and
3-5 bar at 20°C). In operation the breaker is filled with - the drive assembly comprising the drive and power
gas at a higher pressure and a density monitor with tem- supply.
perature compensation monitors the gas content [9]. The These three units are assembled in the factory to form a
various density and pressure values are compiled in Table 11 triple-pole breaker group and adjusted and tested. Where
together with the tripping levels of the density monitor. transport facilities permit, the complete breaker group is
Special attention was given to the choice of sealing system transported as a unit to the plant. The breaker is con-
for the compartments. The arrangement chosen, together nected to the other components by means of flanges and
with careful density tests on the breaker before it is plug-in contacts.
delivered, ensure that leakage losses are not more than The following engineering was applied to the circuit-
1 % of the gas content per annum. breakers to keep the cost of maintenance to a minimum:
the SF 6 circuit-breakers type EBK and ECK, in airblast Tests carried out under simulated environment at high
and also in l.o.v. breakers. This equipment includes for and low temperatures, combined with continuous switch-
example, maintenance-free bearing materials, wear and ing, further proved that the permissible gas loss set by
arc resistant contact materials, levers and pivots capable Brown Boveri can be guaranteed at less than i % of the
of withstanding mechanical stresses, and also the me- gas content per annum.
chanically and electrically stressed insulating materials for
the quenching Chambers and drive shafts [7]. As far as the
drive is concerned all control elements were carried over Testing the Current-Carrying Capacity
from the l.o.v. breakers and only the drive cylinder is a
new development [8], The mechanical tests are therefore The current-carrying capacity is examined as a type test
mainly concerned with the interaction of the individual on a complete breaker pole and is a three-part test:
components in the overall breaker system and it was not - peak withstand current test
necessary to carry out investigations on the individual - short-time current test
components. - temperature rise test at rated current.
In designing the drive it was necessary to take into account
The tests were carried out and evaluated according to
the fact that the arc exerts certain reactive forces on the
the recommendations of IEC Technical Committee 17C.
drive. Depending on the magnitude and phase displace-
All data given in Table I for ELK breakers are guaranteed.
ment of the short-circuit current at the instant of contact
Separation, certain reactive forces are exerted on the drive Tests carried out up to the limit of current-carrying capa-
due to the pressure increase resulting from the arc. These city showed that the design has adequate margins of
phenomena were simulated in Computer programmes [10]. safety.
The necessary data for this was supplied by a series of
tests carried out with special test equipment (Fig. 8).
Investigations have confirmed that a single model of Proving the Switching Capacity
drive unit can cover all requirements for the complete As always, h.v. circuit-breakers must be subjected to
ränge of ELK breakers. The necessary setting data for the extremely comprehensive development tests, right up to
drives for breakers with two and three quenching Cham- type tests which confirm the required switching capacity.
bers per pole and for the three-pole drive for breakers Any method which reduces the complexity of development
with a single quenching Chamber were derived from tests. tests is very welcome. Those methods which are suitable
An interruption time of two cycles is obtained in both for this purpose are given in Table III.
cases. Until now, during the development of a new breaker, we
Both breakers and drives fulfil the set requirements with have relied mainly on basic investigations, known test
respect to mechanical reliability with a large margin of methods [11] and experience gained in previous develop-
safety. Even after 10 000 switching cycles, with one breaker ments. Today the circuit-breaker designer has new methods
carrying out 2000 short-circuit interruptions, the mech- at his disposal, primarily new calculation methods and
anical components were found to be functioning perfectly optical investigation equipment, which were employed
and the settings and travel characteristics had not altered. throughout the development of the ELK breakers to
An oscillogram of a close/open cycle is shown in Fig. 7. support the methods usually applied.
302 kV • \
\V/ ^•
L
216kV
;' ... : -
MIHI
Fig. 10 - Oscillograms of an autoreclosure in a synthetic test circuit with Recommended Measured
voltage injection. Test on the complete pole of a 170 kV S F 6 puffer type (IEC)
circuit-breaker type E L K with one quenching Chamber per pole for a
Breaking current 40 kA 40-2 kA
breaking current of 40 kA
170 kV
a: Magnetic oscillogram Voltage ( r . m . s . ) — — x 1-5 147 kV 153 kV
b,c Cathode ray oscillograms of transient recovery voltage after
Voltage (peak) « c
yj 290 kV 302 kV
the second Interruption
Voltage in the heavy current circuit Time coordinate ?•> 290 [is 268 (xs
Short-circuit current
to ! C o m m a n d s for test circuit-breaker and auxiliary circuit-
breakers
Instant of contact Separation in the test circuit-breaker
Transient recovery voltage across the breaker
a b
Calculation processes The methods described here were used for deriving ex-
- which describe the switching behaviour of circuit- perimentally the parameters which determine the breaking
breakers [12, 13] permit the switching capacity to be capacity, such as nozzle cross section, nozzle shape, blast
derived mathematically and hint at possible means of pressure and blast flow rate, contact velocity, etc.
improvement, Part of these investigations were carried out on a model
of the puffer type breaker (Fig. 8). The contact and di-
- which permit the gas flow in the contact zone to be
mensions of this model correspond to the natural size of
determined [10] do away with unnecessary testing because
a 170 kV puffer type breaker with one quenching Cham-
geometrical arrangements which are obviously out of the
ber.
question can be eliminated.
From the outset of development the relevant international
specifications such as IEC and ANSI were applied through-
out. The result of these efforts is the new puffer-type
Optical means of measuring breaker type ELK.
- are the most suitable for the present level of engineering Of this ränge of breaker the following are subjected to the
for providing complete knowledge of the phenomena greatest stress:
occurring in the contact zones of circuit-breakers,
- 170 kV breakers with one quenching Chamber per pole
- can be applied to any type of breaker,
for interrupting 40 kA (this breaker is shown being
- provide comprehensive information about the arc and
tested in Fig. 9),
the flow of quenching medium in the quenching Chamber
- 245 kV breakers with two quenching Chambers per
of a circuit-breaker without affecting the quenching pro-
pole for interrupting 50 kA,
cess,
- 420 kV breakers with three quenching Chambers per
- permit Computer programmes and Computer processes
pole for interrupting 50 kA.
to be checked and supply new data for calculation.
Type testing these breakers has proved the guaranteed
It is now possible to calculate and measure both the breaking capacity for the whole ränge. This applies not
arc and the flow of quenching medium. This progress in only for terminal faults, but generally for all other switch-
the field of breaker physics does not permit a purely ing conditions according to IEC. Voltage distribution
mathematical development of a circuit-breaker but con- over the series-connected quenching Chambers of a pole
siderably reduces the development period. is also taken into account.
Certain selected type tests are described in the following. Out-of-phase switching imposes the greatest voltage stress
on the 170 kV breaker with only one quenching Chamber
Proving the breaking capacity under terminal fault con- per pole. It was proved in various test series that one
ditions involves a large number of tests because the re- quenching Chamber can safely cope with 450 kV (peak)
quirements also stipulate tests at 10, 30 and 60% of the and can thus easily cover the switching conditions.
rated breaking current. Because of the exceptionally high Capacitive currents can be interrupted with the ELK
breaking capacity per quenching Chamber, these tests have breaker without restriking or reignition. This has been
to be carried out almost exclusively in synthetic test cir- proved by appropriate tests with currents up to 400 A.
cuits [14]. The oscillograms of an autoreclosure cycle are An overvoltage factor of 2 was not exceeded during inter-
shown in Fig. 10 and the contacts after ten interruptions rupting magnetizing currents in transformers running
at 40 kA are shown in Fig. 11. Short-circuit currents of under no load.
over 50 kA were applied in the tests to determine the The short-circuit making capacity with füll preignition,
absolute limit of the breaker. i.e. with virtually symmetrical short-circuit current is
Coping with short-line faults is a particular problem for tested by the triggering wire method [7]. The making tests
every breaker and requires particular attention during with fully asymmetrical short-circuit current are carried
development. It is generally known today that a short- out and proved with the CO and O-CO switching cycles.
line fault at 90 % of the rated breaking current represents Figure 13 illuminates the progress made in breaker devel-
a critical stress for SF 6 breakers. This point was investi- opment with the example of a dififerential pressure breaker
gated particularly thoroughly. The tests were carried out type ECK and the new puffer system breaker type ELK.
with a simulated line for synthetic short-line fault tests The breaking capacity of a quenching Chamber has been
[14]. The oscillograms of a representative test are shown almost doubled in the last three years [6, 7], It is shown
in Fig. 12. that today it is easily possible to interrupt 7500 MVA,
V
capacity of 9000 to 10000 MVA.
4000 y
Insulation, Design and Voltage Tests
There are various factors which can affect the dielectric
2000
strength of SF e breakers in operation:
- surface roughness of electrodes due to deposits
- pollution of insulators as a result of switching Operations
1962 1964 1966 1968 1970 1972 1974
- moisture
Fig. 13 - Development of breaking capacity P of a quenching Chamber.
These problems were investigated in a long series of tests Rate of rise of recovery voltage > 1000 V/[i.s
and results are compiled in a report [15], The solutions to a Differential pressure breaker type E C K
b = Puffer type breaker type ELK
these problems are now known. This applies for example
to the insulating materials developed by Brown Boveri
specially for application in metal-enclosed switchgear and
which have proved themselves over many years of Opera-
tion under extreme test conditions. Mention should also
be made of the fact that the füll dielectric strength could
be proved at a breaker after 10 interruptions with a short-
circuit current of 40 kA without any chemical Alters being
used in these tests.
The main objective in developing the ELK breaker was to Type tests have confirmed that the design of the new
find the most economical arrangement for various sizes breaker satisfies even the latest requirements in respect of
of breaker, i.e. the smallest dimensions with respect to insulation coordination. Figure 14 shows a test rig for
insulation distance and enclosure diameter, taking into determining the data for designing the dielectric of type
account the required insulation coordination between ELK circuit-breakers with three quenching Chambers per
break and earth. pole.
that the cross section and thus also the conductivity and current increases, this charging power is compensated
current carrying capacity increases with voltage. more and more by the inductive losses until the ideal
The usual cross sections of cables today are less than operating condition is reached where the natural power
500 mm 2 . An upper limit of about 1500 mm 2 is given by curve ( P n a t ) intersects the zero line. At this point there
manufacturing and cable laying restrictions, regardless of are zero reactive losses. If the current is further increased
the rated voltage. The loading capacity of cables reduces the inductive reactive losses increase rapidly.
with rise in rated voltage because their thermal resistance The curves b in Fig. 2 represent the reactive loss charac-
and dielectric losses increase with the thickness of insu- teristics of CGI cables where represents a single-phase
lating material. CGI cable without the sheath current, b 2 represents a
In the case of CGI cables, which comprise solid conduc- single-phase CGI cable with the füll sheath current and
tors and cable sheaths, design aspects predetermine the the curve between these two, i.e. b 3 applies to a three-
minimum wall thicknesses so that the result is relatively phase CGI cable. The surge impedance load (SIL) of
large conductor cross sections which decrease with rated CGI cables is 3 to 4 times greater than that of overhead
voltage. In the case of high voltages therefore, the CGI lines. Consequently the transmission properties of a CGI
cable is predestined for transmitting very high currents cable correspond to those of three or four parallel over-
and has considerably better properties than the conven- head lines.
tional cable. The limiting value to which a CGI cable can be conti-
Where long transmission distances are involved the ränge nuously loaded without additional cooling depends not
of practical applications of a transmission medium de- only on its dimensions but also to a large extent on the
pends Iargely on the amount of its reactive losses [4], ambient conditions, i.e. primarily on the depth to which
The reactive loss curves for various transmission media at it is buried and the thermal properties of the soil.
420 kV are shown in Fig. 2 for comparison. The origin of Conventional cables (curve c in Fig. 2) represent a high
the curves at I = 0 corresponds to the capacitive charging capacitive loading over the whole ränge of Operations.
power of the corresponding system under no load. As Although the characteristic curve is basically similar to
that of overhead lines and CGI cables the surge impe- tween the conductor and the cable sheath and appropriate
dance load is always considerably higher than the thermal measures are taken to prevent wear due to friction.
limit. Consequently, only the initial ränge, with virtually There are no short circuit forces to be considered between
constant, high capacitive reactive power, is of practical conductor and cable sheath in single-phase CGI cables
interest. Compensating the reactive power would be a because the individual forces are mutually compensating
costly proposition. in this cylindrical, symmetrica! arrangement.
In the case of three-phase CGI cables each conductor is
supported by two insulators arranged in the shape of
Design Features a vee (Fig. 4) mounted on a ring which permits movement
to take place relative to the cable sheath. This arrangement
Operational and economics aspects are the factors which has the considerable advantage that there is no solid
decide whether single-phase or three-phase CGI cables insulating material between the three conductors, thus
will be used. Over short transmission distances the single- preventing any creepage paths from forming. The axes of
phase version is more favourable because the potheads the two supports are in line with the supports of the other
with the outdoor bushings or the individual phase junc- conductors so that in the event of a short circuit the forces
tions to the transformer and switching stations are simpler occurring are only tensile or compressive. This arrange-
and less expensive to produce. Where longer distances are
involved, and particularly where the cables are laid under-
ground, the three-phase CGI cable becomes more eco-
nomical because the space occupied is considerably smal-
ler and thus the high proportion of the costs for burying
the cables is considerably reduced. Fig. 5 - Compressed-gas insulated cable with bulkhead insulator and
ball joint
Single and three-phase CGI cables are produced as rigid
sections of about 12 m long comprising cable sheath,
aluminium conductor and support insulators preassembled
in the factory, tested and fitted with gas and dust proof
seals ready for transport. The units are welded together
(conductor and cable sheath) on site and precautions are
taken to prevent ingress of dust or other pollution during
this process.
Insulation
Because of the large number of support insulators re-
quired between the conductor and the cable sheath they
must be easy to produce and must have ideal properties in
respect of the electrical, thermal and mechanical require-
ments. In the case of a single-phase CGI cable these con-
ditions are best met with a three-legged arrangement as
shown in Fig. 3. The conductor can slide in an aluminium
ring to facilitate the difference in thermal expansion be-
BROWN BOVERI 163506.1
Changing Direction
Directional changes of up to 5° are permissible between
adjacent tube sections when they are installed on site.
Consequently, where the 12 m long sections are installed
the minimum radius for a change of direction is 140 m.
Shorter tube sections permit smaller bend radii to be
achieved. Ball-type swivel joints are available for sudden
changes in direction of up to 90° (Fig. 5). Where space is
restricted and complex cable runs are involved in densely
built-up areas, this arrangement of infinitely variable
changes in direction has a considerable advantage over
Standard high-voltage cables.
Corrosion Protection
Fig. 7 - Curves of field strength between the electrodes ( E a n d to earth
( E 2 ) for a three-phase C G I cable The aluminium sheaths of single-phase CGI cables are
fitted with a corrosion protection which may take the
[p.u.] form of a glass fibre bandage with several layers of tar/
3
£ epoxy resin coating before they are buried.
\ 1 / The steel casings of the three-phase CGI cables are fitted
\\ \7( f t ^/ with a 3-5 mm thick plastic coating which has been proved
on oil and gas pipelines.
A specially developed paint coating has proved itself
adequate for above-ground installation of CGI cable.
\\ ii
\\ ii
\ i
Field D i s t r i b u t i o n and Dielectric Stresses
ii in CGI Cables
ii
ii In contrast to the ideal even distribution of stresses in the
—if— ii dielectric (SF 6 ) in an homogenous field the field strength
*lV3-. distribution in a symmetrical cylindrical field (as is the
* The lower value applies for cable sheaths of non-conducting materials (and also approximately for stainless steel and aluminium) and the higher
value for magnetizable steels.
/
q max = — (3) 1,2 / / X \
/ //'/
v. n7 cm / ' /
\
where Ü in kV 1,0 /
\
/
v in m/s /
0,8
Figure 3 shows the corresponding maxima for the specific / / /
voltage stress in relation to the line-to-line voltage for
three different velocities and for the critical instant of
0,6
// /
/
— Q
Fig. 5 - Pressure curve \ p in relation to the displaced quantity Q and
velocities v1 and v 2
f
Cres
10 = Contact drive section (8)
11 = D a m p i n g unit Lres
Conclusion
Bibliography
U. Burger
still requires an effective overvoltage protection system
Totally enclosed SFf) switchgear is being used on an ever and the question arises as to which is the most favourable
wider scale. Although totally enclosed lightning arresters location for it. Protection must be provided primarily for
are also available it is often desirable to provide protection the most expensive object, i.e. the transformer. In an
by means of conventional lightning arresters at the junction SF 6 plant it is connected through the overhead line by a
between the overhead line and enclosure. The extent to section of CGI cable. In the totally enclosed SF 6 insulated
which protection of the equipment, especially the trans- lightning arresters available today the conductor is in an
former, is provided is discussed here. insulating tube filled with either nitrogen or air and this
tube is enclosed in an SF 6 filled housing. However, a con-
ventional lightning arrester at the entrance to the plant at
the junction with the overhead line involves less expen-
diture. The question then arises as to whether an SF 6
insulated, totally enclosed lightning arrester or a conven-
tional arrester is to be provided for protecting the plant,
particularly the transformer. The degree of protection
The Problem provided by the second, simpler arrangement in respect of
the transformer is investigated in the following. A Com-
Rising power consumption in agglomeration areas and puter programme [1] was made available for the relevant
shortage of space will increase the use of SF 6 switchgear calculations.
over the next few years. Although it is theoretically pos-
sible to provide the link between power stations and
distribution centres with materials available today in the
form of cables (conventional or compressed gas insulated Basic Considerations
using SF e ) the overhead line will always remain an eco-
nomical means of transporting electrical energy. However, Plant Layout
the overhead grid is subject to atmospheric faults. Inten- A switchgear plant generally has a complex configuration.
sive lightning research over the last twenty years has pro- It would be beyond the scope of this contribution to
vided us with plenty of information and also a better investigate all combinations of feeders, busbars and con-
knowledge of lightning discharges. As investigations have nections to the transformers. The most unfavourable case
shown, the more important lightning data can be gained in respect of stresses due to overvoltages is surely the
by Statistical methods. The results indicate that in spite simple arrangement shown in Fig. 1 on which this investi-
of all protection measures which it would be possible to gation is based. A long overhead line is connected to a
apply to an overhead line the probability of a lightning transformer by means of an SF 6 CGI cable. This case can
stroke or a flashover between phases cannot be entirely also occur in a very complex plant where various feeders
eliminated. The expensive equipment in the various plants to and from the busbar are disconnected.
The same surge impedance is assumed for both the over-
head line and the lead to the lightning arrester. The values
chosen are given in Table I.
Fig. 1 - Layout of plant under investigation
= Line impedance
D = Distance between junction of overhead line and cable and
the nearest tower
Table I
RE = Earth resistance of tower
Zx, t2 = Line impedance and length of connection to arrester Surge Length
Z 3 ) /3 = Line impedance and length of C G I cable or length of totally
enclosed plant between junction 1 and transformer T
impedance
T = Transformer
1 = Junction between overhead line and enclosure or arrester Overhead line Z x = 350 Q o o , D = 250 m
connection point
2 = Arrester Arrester connecting line Z 2 = 350 Q 0 to 20 m
CGI cable Z 3 = 75 Q Oto 100(500) m
Transformer
From the consideration that the maximum voltage at the
transformer occurs during the first 10 JAS during the very
rapid phenomena occurring here, the equivalent circuit
Np
i
the following). Curve A shows the voltage gradient for
N.
the IEC recommendation for arresters, whose maximum
is 1200 kV/fxs.
V
The highest values for gradients are to be expected with
restrikes or multiple strokes. At the origin of the over- m
voltage the former have virtually the same gradient as the y/y)
collapse of the air gap in a time of less than 0-05 jxs.
With follow up strokes the maximum current gradient can
m
be in the region of 80 kA/fxs. The manner in which the
very steep waves are damped is dealt with in the conclusion
to this contribution. V//.
In order to further refine the assumptions a second con-
sideration is made where the steepness of the overvoltage
wave is held constant above a given value. The assumption
that the tail of the wave is horizontal can be justified for 200 300 400 500 600 700[kV]800
100
the short phenomena considered here. •u 200041.1
Fig. 5 - Transformer voltage UT in relation to length of C G I cable / 3 Fig. 6 - Transformer voltage UT in relation to the rate of rise s of the
Arrester direct at the junction between line and cable (/ 2 = 0) see Fig. 1 unrestricted, linearly rising wave
Curve Parameters: Rate of rise of wave rising without restriction Arrester direct at the junction between line and cable (/ 2 = 0)
Dotted line: See text.
l3 — Length of C G I cable
CT = Transformer capacitances
/ ,
[p.u.] | Arrester direct at junction between line and
° cable (/ 2 = 0), length of C G I cable l 3 = 100 m.
3.2 \ Rate of rise of unrestricted linearly rising cur-
\
/' \ rent: 3 p.u./[xs
/
\ /
/
1 = Voltage at transformer
/ I 2 = Voltage at arrester
2,8
/
U / // /
/
/
/
2,4 /
f
/
/
'1
I h h
/ /
/ /
/ /
/ /2 / 2 i / 2
2,0
' f
/ /
/ / / '''
/
•
/
/
/
1,6 / / /
/ ' J /
/ // // / /
/
// // //
1,2
// '//,
/ /
0,8
/ /
/
j
M / OnF
/ 2nF
/ /
/
' /
/ lOnF
0,4 /
from the initial curve a capacitance at the end of the line This may be possible if the overvoltage peak is of short
causes only a displacement of the gradient with respect to duration so that the capacitor is not fully charged. As the
time with an overvoltage surge rising linearly. The nor- oscillogram shows the wave tends briefly towards a drop
mally expected effect of a reduction in the overvoltage in voltage at the arrester. It is very difficult to obtain a
with a larger capacitance can therefore not occur here. clear picture of this complex phenomenon.
[p.u./(xs]
/ 1,5
/
/
/ 1,5
/
/
/
6
/
/ / O
f
20 40 60 80 100 [m]
1
0 200 400 600 800 [m] 1000
Fig. 10 - Theoretical overvoltage at transformer UT in relation to the Fig. 11 - Transformer voltage UT in relation to length of CGI cable L3
surge wave arriving Us with protection by an ideal arrester direct at the with a stroke of lightning direct at the first tower from the plant (D =
junction between line and cable 250 m, Fig. 1)
Arrester direct at the junction between line and cable.
Parameters of lightning stroke:
- form 1/100 [as
- current strength such that a voltage peak of 1-5, 3 and 6 p.u. occurs
at the tower earthing resistor
F o r 1 and 2 see text.
Fig. 12 - Diagram for assessing the protection ränge of a conventional The procedure for the practical application of the curves shown on the
arrester at the input of an S F 6 installation (distance l 2 = 5 m) left of the diagram is as follows:
Um = Operating voltage of network &> = Choose abscissa scale according to a given earthing factor (e.g.
Ce = Earthing factor c e = 0-8)
a = Holding levels Nt ® = Draw Ordinate at the corresponding abscissa value for the line-to-
b = Rate of rise of arriving wave [p.u./|xs] or voltage drop [p.u.] at line supply voltage (e.g. Um = 420 kV)
the tower earth with a close-up lightning stroke (conversion ® = Determine intersection of 2 with the holding voltage (e.g. Nt =
according to Fig. 3) 1300 kV)
/3 Length of CGI cable ® = Determine the length of CGI cable protected (e.g. C G I cable of
up to 50 m protected without special measures)
Table II
Conditions:
Earthing factor c e = 0-816
Lightning current peak = 100 kA
* Parameter b in Fig. 12 (right-hand side)