You are on page 1of 7

Setting plant capacity

P. L. McCarthy*
The optimum plant capacity for a new mine is usually based on empirical studies or ‘rules of
thumb’, subject to confirmation by detailed scheduling of the proposed mining operation.
Historically the mining industry has a record of poor returns on investment and a high rate of
project failure using these methods, with underperformance in grade being a common
experience. Periods of high mineral prices tend to obscure this underlying problem. The
assumption that ‘economies of scale’ will result from increasing throughput rates needs to be
balanced by an awareness of the adverse effects of increasing the rate beyond a level that is
supportable by the resource. For each scale of operation considered, it is a reality that for any
intended head grade, at the associated intended cutoff grade, the actual head grade achieved
will fall as the mining rate increases. This effect is known to people at operations but is not
generally recognised in current ore reserve estimation methodology. Once recognised, this
dependence of head grade on mining rate can be quantified and used to establish the
economically optimum mining and processing rate for a new project. A simple analysis is
proposed, which may be extended to detailed spreadsheet modelling for financial optimisation.
Keywords: Head grade, Mill expansion, Mine optimisation, Plant capacity, Processing rate, Production rate

This paper is part of a special issue on Metallurgical Plant Design and Operating Strategies

Introduction either the ore tonnage or head grade, or both, cannot be


sustained.
A design rate of mining and processing is selected in The physical limit to the rate at which any orebody can
every mine feasibility study, although any attempt to be mined is dictated by the possible rate of development,
optimise that rate is rarely documented. To maximise available face length (in a pit) or available stopes
return on investment, it has long been recognised that (underground), grade control turnaround, and so on.
both the capital investment per unit of output and the There is also an economically optimum rate, which is
operating cost per unit of output should be minimised. lower than the physical limit of mine production, beyond
In general, both of these cost measures decrease as the which the negative influences of a high rate of mining
scale of the project increases, so the initial temptation is begin to outweigh the incremental cost advantages.
to ‘push the orebody to the limit’. It is also clear that mining slowly is more predictable,
However, the technical and commercial risk both while attempting to mine quickly leads to greater
increase as the scale of the project increases. Hoover1 production volatility and a less certain outcome. As more
said ‘the lower the production rate, the lower the capital is invested in the larger operation, it has a higher
required investment, the longer the income stream and commercial risk.
the lower the risk to the investor’. While this was well An empirical study by Taylor4 further refined in
before the advent of discounted cash flow (DCF) Taylor5 provided a surprisingly simple relationship
analysis, the point made by Hoover remains a good one. between mine life (hence mining rate) and ore reserve
A study reported by Tatman2 compared the final tonnage for open pit porphyry copper mines. McSpadden
feasibility study production rate with the average and Schaap6 extended this work to other types of ore
sustained production rate from 60 steeply dipping deposit and both surface and underground mines.
tabular deposits. Tatman found that 35% of the mines These studies were based on what mines were doing at
did not achieve their planned production rate, and was the time but there was no claim made that the resulting
able to derive an empirical formula relating the risk of mining rates were optimal. However, Smith7 observed
failure to the geometry of the deposit and the rate of that ‘the production rate from Taylor’s Law appears to
mining. Tatman’s conclusions are consistent with the provide a reasonable starting point for a project
author’s observations for underground mines3 that in evaluation’. Smith7 presented a number of other
general there is a limiting rate of mining advance commercial ‘rules of thumb’.
(typically y60 vertical metres per year) beyond which The empirical studies are very useful in setting guides
to production rates based on industry practice, but offer
no fundamental principles that can be applied. In most
Level 19, 114 William Street, Melbourne, Vic. 3000, Australia feasibility studies, there is an implicit attempt to
*Corresponding author, email pmccarthy@amcconsultants.com.au maximise production within ‘safe’ limits. This may not

ß2010 Australasian Institute of Mining and Metallurgy


Published by Maney on behalf of the Institute and The AusIMM
Received 15 April 2002; accepted 1 September 2010 Mineral Processing and Extractive
184 DOI 10.1179/037195510X12816242170979 Metallurgy (Trans. Inst. Min. Metall. C) 2010 VOL 119 NO 4
McCarthy Setting plant capacity

be the optimum strategy. In particular, the negative physical influences on the mining process discussed
impact on head grade of a high mining rate is well above. There may be an assumption by metallurgical
known in operations but is ignored in the literature on and process engineers that the mine planners have ways
mine optimisation. of optimising the rate, or alternatively that they can
This paper presents the first steps in developing a deliver whatever rate is needed to meet economic
rational basis for optimising the production rate that criteria. Neither assumption is true.
recognises, in particular, the relationship between The track record of mine feasibility studies is poor. The
mining rate and head grade. 35% failure rate (to achieve production targets) observed
by Tatman2 may be compared with the observation that
Orebody size and mining rate only 50% of underground base metal mines and mills
reach design throughput by year 3 and 25% never reach
Let us consider orebodies of increasing size, excluding
design throughput.8 In an earlier study of 35 Australian
flat tabular orebodies, which are a special case. Usually,
gold mines,9 68% of mines failed to deliver the planned
as the orebody gets bigger:
head grade, while a review of nearly 50 North American
(i) the available tonnes per vertical metre increases
projects showed that only 10% achieved their commercial
(ii) for a pit, the stripping ratio to a particular
aims with 38% failing within about one year.10
depth decreases
(iii) for an underground mine, the development effi-
ciency (in tonnes per metre) (t m21) increases Process of optimisation
(iv) possible stope sizes get bigger (to a geotechnical
Ideally, a feasibility study would result in an optimised
limit)
design for the mine and processing plant. In reality,
(v) lower cost and more productive mining meth-
most studies are constrained by time, budget and data to
ods become possible
achieve a minimum economic hurdle, without really
(vi) the average capital investment per tonne of
determining how much better the project could be with
eventual production decreases
further study. The gross variables under the designer’s
(vii) the physical limit of mine production increases
control are the cutoff grade, production rate, mining
(viii) the economically optimum mining rate increases.
method and process design. Of these, the mining method
For any particular orebody may choose any mining rate
and process design can be selected using well established
up to the physical limit of mine production. Experience
criteria based on experience, field data and test work.
and analysis suggest that as we increace the chosen
mining rate: The sensitivity of project value (however defined) to
(i) the required total capital investment increases the key parameters of production rate and cutoff grade
(ii) the required working capital, including prestrip- is illustrated in Fig. 1.11 Various combinations of these
ping or advance development, increases two parameters give a three-dimensional ‘value surface’
(iii) the fixed component of operating cost is spread which has one or more zones of maximum value. For
over more tonnes each combination, it is necessary to design and schedule
(iv) step capacity limits are reached, requiring the mine, estimate costs and evaluate the financial result.
further capital investment A discreet (although perhaps daunting) set of combina-
(v) head grade to the mill decreases, for reasons tions is sufficient to estimate the shape of the entire
discussed below surface and to identify the optimum.
(vi) control of the mining process begins to deterio- The objectives of optimisation must be aligned with
rate after some point the corporate objectives of the owner. Some stated
(vii) the physical limit of production from the corporate objectives, such as maximising annual ounces
orebody is approached of gold production or maximising mine life, cannot be
(viii) potentially negative social and environmental optimised. Clearly, increasingly large subeconomic
impacts increase projects will satisfy the former objective while decreas-
(ix) the rate of waste production and disposal increases. ingly large subeconomic projects will satisfy the latter.
In the author’s experience mining and processing rates For short life projects, increasing the mining rate
are set in the following ways: increases the risk that most of the production will be
(i) to satisfy economic criteria (e.g. return on delivered into a trough in the product price. Sensitivity
investment), often with inadequate regard to analysis based on a range of price scenarios will identify
what the orebody will sustain the rate that yields an acceptable risk.
(ii) to match existing installed mill capacity (e.g. There is also the problem of capital allocation
when a pit is converted to an underground between competing projects. If there is no restriction
mine) on the available capital, then the corporate value is
(iii) using ‘rules of thumb’ such as the equivalent maximised by maximising the net present value (NPV)
vertical advance rate limit, or Taylor’s rule of every available viable project and carrying all of them
(iv) by detailed ‘paper’ or computer scheduling of through to production. In the real world, where
mine production to establish the physical limit, available capital is restricted, the corporation must
then designing at the physical limit or with some select projects for investment using some ranking
‘margin of comfort’ technique. Economic theory says that projects should
(v) to meet corporate goals such as ounces per year be ranked using the present value ratio (PVR), which is
of gold production. the ratio of NPV to initial capital investment. For
Experience with feasibility studies and a survey of the simplicity, the capital investment is usually taken to be
literature have not given an example of a quantitative the total of negative cash flows before achieving positive
approach that optimises production rate based on the cash flows.

Mineral Processing and Extractive Metallurgy (Trans. Inst. Min. Metall. C) 2010 VOL 119 NO 4 185
McCarthy Setting plant capacity

1 Finding and climbing the hill of value11

If the perceived risks are similar, projects with higher the practical implications of high mining rates. The
PVRs are selected before those with lower PVRs. A practical issues usually become important well before
project with a high NPV but a low PVR may require the NPV maximum value is reached.
more capital than the corporation (or the investment For each size of operation considered, it is a reality
community) is able or willing to risk, or if developed it that for any intended head grade, at the associated
may displace alternatives which would have provided a intended cut-off grade, the actual head grade achieved
better aggregate return on investment. will fall as the mining rate increases.
From the above, the mining rate should be optimised Once recognised, this dependence of grade on mining
to maximise the project NPV at the corporation’s agreed rate has a profound effect on mine planning. Figure 3
discount rate, provided that this leaves it with a PVR shows the relationship between mining rate and head
that will make it an attractive investment. Arguably, the grade for the Kambalda underground nickel mines in
mining rate should be changed (and possibly reduced) to Western Australia, based on 37 years of production
improve the PVR, even at the expense of NPV, if this history at an average mining rate of 1?1 million tonnes
will allow the project to proceed in competition with per annum (Mtpa). This example is particularly inter-
others. This observation emphasises the importance of esting because production rates were reduced and head
right sizing the operation rather than pushing through- grades significantly improved after ownership of the
put into the limiting range. mines was disaggregated, with production continuing to
be delivered into a shared treatment facility. The charts
Head grade and mining rate for the individual Kambalda mines show a similar
relationship. The head grade improvement was due
The grade–tonnage curve is an essential tool in mine mainly to slower and more selective mining and not to
planning, allowing the designer to choose a small, high changing the cutoff grade. If life of mine plans are
grade option or a large, low grade option, or any option developed for a new mine using this relationship for
in between these limits (Fig. 2). For each option there is a grade, instead of a ‘base case’ head grade assumption,
set of corresponding cut-off grades used in planning and the optimum mining rate turns out to be considerably
operations. The size referred to here is the tonnage of ore less than what is physically possible in the orebody with
that can ultimately be extracted from the resource. the available equipment.
Different mining and processing rates can be applied In mining terms, the production rate can be expressed
to each size option, each having a different NPV. Smith7 as the ‘effective vertical advance rate’, or the relationship
describes the NPV maximum value as a ‘failure point’, between actual mining rate and the ‘tonnes per vertical
noting that it is an upper economic limit for the possible metre’ available in the deposit. It turns out that
range of production rates rather than an optimum rate. underground mines designed for advance rates of 40–
Smith’s paper deals with economic criteria and not with 50 vertical metres per year are most often successful,
whereas those attempting 60 vertical metres or more per
year are most likely to fail.
The failures are due to overcapitalisation of plant and
inadequate advanced development, coupled with an
inability to maintain the intended grade at an excessive
production rate. The grade problem is as much due to
human nature as it is to technology; if people are set
unrealistic goals then ‘waste plus ore equals more ore’.

Production variability and its


implications
The variability of production, head grade, recovery,
2 Grade tonnage curve throughput or output can be measured hourly, daily,

186 Mineral Processing and Extractive Metallurgy (Trans. Inst. Min. Metall. C) 2010 VOL 119 NO 4
McCarthy Setting plant capacity

3 Head grade and mining rate history: Kambalda nickel mines

monthly, etc. The more variable this measure, the less production, and the value of that option can be
use is being made of the installed capacity and hence of estimated.
the capital invested and of the fixed component of What is needed is an optimisation procedure that is
operating cost. One of the key symptoms of a system reasonably rigorous and transparent and that identifies
that has been pushed beyond its stable capacity is an any factors of conservatism built into the mine and
increase in production variability. process plant.
A mining project designed for a 1?0 Mtpa rate with
5% variability needs an installed capacity of 1?05 Mtpa.
If a decision to increase the mining rate by 10% to
Simplified optimisation model
1?1 Mtpa leads to an increase in variability to 15%, then We will consider the objective to maximise the annual
the installed capacity must be increased to 1?27 Mtpa, surplus of revenue over costs. This ignores
an increase of 20%. If the capacity is only increased by the time value of money, but offers useful insights into
10%, the increased variability will lead to a slight the importance of the grade–rate relationship. We will
reduction in metal output. assume that a preliminary mining rate somewhere near
the physical limit for the resource has been chosen, a
corresponding cutoff grade has already been selected,
Temptation of tonnage and therefore the total tonnes available over mine life
In general industry practice, the tonnage capacity of the can be estimated.
process plant sets the rate. If the plant has been First consider revenue. The most important aspect of
constructed with surplus capacity or expanded to that this model, and the key to right sizing our mine, is to
point, then great pressure is put on the mine to fill the establish that, for any given cutoff grade, the head grade
mill, often with scant regard for the effect on the quality declines as we increase the mining rate. This is because
of the material delivered. The author once reviewed a we push progressively harder to win tonnes within the
mine where the stope designs included discrete zones of confines of our orebody.
hard, abrasive waste rock. Upon suggesting that a We can describe this effect by the equation
smaller, more selective stope design would be advanta-
geous, he was told, ‘we looked at that but we couldn’t G~g{ht (1)
get the scheduled tonnes’. The mill throughput was later where G is the realised head grade (in % metal), g is the
reduced and the stopes redesigned, for a substantial grade (in % metal) that could be achieved with slow and
improvement in mine NPV. selective mining (as t approaches zero), h is a constant,
Both the owners and designers of process plants seem to unique for each orebody, illustrated by the slope of the
pride themselves on building plants that substantially line in Fig. 3, and t is the mining rate in tonnes per
exceed ‘nameplate capacity’. This excess capacity is soon annum.
converted into a demand for the mine, with the con-
We can calculate the annual revenue D from
sequences already noted. The existence of this excess
capacity implies that the design engineers are not D~(vt)(g{ht) (2)
particularly competent, or they are overly conservative.
Having specified a particular design throughput, the owner where D is the annual revenue in dollars and v is the
has been obliged to pay for something greater, increasing realised value of the product in dollars per tonne of
the capital investment and reducing the return on assets. metal in mill feed.
There may be some second guessing happening here. We will consider both the annual operating cost
The plant designers do not really believe the optimisa- (including sustaining capital) and the annualised capital
tion and mine scheduling work carried out by the mining cost, which we obtain by amortising total project capital
engineers, and expect that they will actually deliver more over the mine life. The annual operating cost P can be
ore than the design. Excess capacity may also be useful modelled as a typical ‘fixed and variable’ cost of the form
in responding to variations in resource grade or product P~azbt (3)
price. If that is the reason for building in excess capacity,
then the specifications should say so, along with the where a and b are constants.
circumstances under which the excess capacity will be The project capital cost C is also of the ‘fixed and
utilised. The owner has paid for an option to expand variable’ form when related to tonnes per annum of

Mineral Processing and Extractive Metallurgy (Trans. Inst. Min. Metall. C) 2010 VOL 119 NO 4 187
McCarthy Setting plant capacity

installed capacity, hence (i) assuming that the exploration drilling is repre-
sentative, at a mining rate of zero (i.e. with
C~czdt (4) infinite selectivity) the head grade would be
where c and d are constants. close to the average grade of the above cut-off
This is a simplification, as real capital costs increase as drill intercepts composited to minimum mining
a step function in relation to capacity, but the series of width
steps may be approximated in this way. (ii) using the most selective practical mining
If R is the total ore (in tonnes) available over the mine life, method the resulting head grade can be
then the amortised capital cost per tonne C/R is given by estimated from the dilution history of similar
operations. Such selective methods might
C=R~c=Rz(dt)=R (5) include the use of a 1?0 m wide bucket on a
60 t excavator in an open pit, or hand held cut
and the annualised capital cost A is
and fill underground mining. In either case
A~(ct=R)z(dt2 )=R (6) intensive grade control would be assumed and a
vertical advance rate of y30 m/year might be
We seek the mining rate t that maximises the annual surplus expected
of revenue minus annual costs. (iii) using a conventional approach to planning with
The annual surplus~D{P{A a vertical advance rate of y50 m/year, the head
 grade at the chosen cut-off grade can be
~ðvtÞðg{htÞ{ðazbtÞ{ðc=RÞt{ dt2 =R (7) estimated
(iv) an upper limiting case occurs in an open pit
This will be a maximum when when the rate is limited by the largest equipment
t~(vg{b{c=R)=2(vhzd=R) (8) that can operate within the pit. In an under-
ground mine, the limit might occur using
sublevel open stoping with a highly regularised
stope shape and unlimited advanced develop-
Example 1 ment. In either case a vertical advance rate
If R510 Mt, v5$800/t, g512%, h5261028, a5$6M, approaching 100 m/year would apply. The
b5$54/t, c5$5M and d5$7?50/t, then the optimum rate geometric dilution would be substantial and
is t51?24 Mtpa with a head grade of 9?5%. Changing h grade control would be ineffective.
to 0 (i.e. ignoring the grade–rate effect) allows t to run Using the above point estimates, a curve can be fitted to
away to a very large and meaningless number. give a grade–tonnage relationship, or to estimate the
This result is a simplification, but similar calculations value of h, for any selected cutoff grade.
can be put into spreadsheet form with any desired level An example is provided by the history of one high
of detail and used to optimise NPV. It is clear that grade gold deposit. Highly selective mining in the
understanding the grade–rate relationship (i.e. the likely nineteenth century gave a head grade of 90 g t21 Au,
value of h) is the key to optimising the mining and whereas modern hand held cut and fill methods gave a
treatment rate. head grade of 30 g t21 Au. This fell to 15–20 g t21 Au
using mechanised cut and fill and would have fallen
further, to an estimated 10 g t21 Au, if sublevel
Estimating grade–rate relationship benching had been attempted. The cutoff grade was
It is possible to say that h cannot exceed a value of g/t, about the same for each period; only the rate of mining
because that is the value obtained when the marginal changed, with an associated impact on dilution.
tonne of material added to t is pure waste. Because the significance of the grade–rate relationship at
As a first approach to estimating the grade–rate the limiting rate has not been previously considered in the
relationship, it is possible to estimate the head grade that literature, there are no published estimates of the value of
would result from applying the selected cut-off grade at h, which is unique for each orebody and depends on the
specific mining rates as follows: grade and physical size of the orebody. However, if

4 Head grade and mining rate history: Kambalda nickel mines

188 Mineral Processing and Extractive Metallurgy (Trans. Inst. Min. Metall. C) 2010 VOL 119 NO 4
McCarthy Setting plant capacity

Table 1 Values of k for selected Australian mines

Name Period Minerals Method* k R2 Comment

Osborne 1997–2005 Cu/Au UG 2.10 0.536


Mt Lyell 1934–74 Cu/Ag/Au Mainly OC 1.21 0.358
Peak 1993–2008 Pb/Ag/Zn/Cu/Au UG 1.12 0.610
Mt Lyell 1900–33 Cu/Ag/Au UG and OC 0.94 0.526 Early years of mining
Mount Morgan 1933–81 Cu/Ag/Au OC 0.52 0.214
Broken Hill 1900–2008 Pb/Ag/Zn UG 0.51 0.400 Multiple mines on one orebody
Argyle 1979–2008 Diamonds OC 0.48 0.192
Rum Jungle 1954–70 U/Cu OC 0.48 0.342
McArthur River 1995–2008 Pb/Ag/Zn UG 0.41 0.458
Kambalda 1967–2004 Ni UG 0.36 0.597
Century 2000–08 Pb/Ag/Zn OC 0.35 0.563
Mary Kathleen 1959–82 U OC 0.34 0.146
CSA 1968–2007 Pb/Ag/Zn/Cu UG 0.29 0.122
Olympic Dam 1988–2008 Cu/U/Ag/Au UG 0.28 0.811
Cannington 1997–2008 Pb/Ag/Zn UG 0.28 0.648
Rosebery 1937–80 Pb/Ag/Zn/Cu/Au UG 0.28 0.705 Milled multiple mines after 1980
Ranger 1982–2008 U OC 0.27 0.611
Woodcutters 1986–99 Pb/Ag/Zn Mainly UG 0.26 0.218
Mt Lyell 1975–2008 Cu/Ag/Au UG 0.21 0.170 Non-selective caving since 1995
Moonta 1890–1923 Cu UG and OC 0.21 0.162
Woodlawn 1979–89 Pb/Ag/Zn/Cu/Au OC 0.13 0.113
Mt Isa Copper 1943–2008 Cu UG 0.11 0.151
Mt Isa Lead 1931–2005 Pb/Ag/Zn UG 0.10 0.271
*UG: underground; OC: open cast.

historical production data are analysed whereby the grade Example 3


is expressed as a percentage of the weighted mean historical A planned underground gold mine is based on an ore
grade, and the annual production is expressed as a reserve of 18 Mt at 5 g t21 Au. The orebody extends
percentage of the average annual historical production, over 600 vertical metres. Adopting an equivalent vertical
then a dimensionless constant k can be defined such that advance rate of 50 m/year gives a mine life of 12 years
k~{DG(%)=Dt(%) (9) and a production rate of 1?5 Mtpa. It is assumed that
the competent person preparing the ore reserve estimate
The value of k is illustrated by the slope of the line in allowed for dilution at a mining rate of 1?5 Mtpa. A
Fig. 4. Also, the value of k can be calculated as 0?263 for value of k50?5 is inferred from similar deposits. Using
the values of h, g and t in example 1. the approach in example 1, the predicted head grades
Historical values of k for selected Australian mines are can be listed in Table 2.
given in Table 1, with corresponding R2 values of the best This information can be used in financial modelling to
fit lines. These results are based on historical production further optimise the production rate.
data compiled by Mudd.12 The derived k values cluster
around a mode of 0?3 and 70% of them lie between 0?2 and Conclusions
0?5. These k values should be used with caution because
they incorporate the influences of changes in cutoff grade, The optimum plant capacity should be based on
planned dilution, unplanned dilution and in some cases appropriate studies, which will identify the maximum
mining technology, as well as the effects of changes in return on investment over a range of sensitivity
orebody characteristics over time. Nevertheless, they scenarios. While unit capital and operating costs are
reflect valid choices of operating points for these orebodies reduced as the mining and processing rate is increased,
and it is better to use these values than to assume that the other negative influences become important. The influ-
mining rate has no effect on head grade. ence of the mining rate on head grade is a key
consideration.
Example 2 Once the design capacity is set, including any
A mine is operating at a rate of 1 Mtpa at a head grade intended overcapacity, the plant should be constructed
of 2%Cu. An expansion to 1?5 Mtpa is proposed and a to conform to the design. Any subsequent decision to
value of k50?3 is inferred from similar deposits. The exploit excess capacity should take into account the
new head grade can be calculated from ability of the mine to deliver feed of the required
quality.
G2 ~G1 ½1{kðt2 {t1 Þ=t1  To reduce the incidence in underperformance of mines
relative to their feasibility studies, the plant throughput
G2 ~2|½1{0:3|ð1:5{1:0Þ=1 (10)
should not be increased beyond a point where the
G~1:7%Cu diminishing head grade becomes more significant than
any reduction in direct costs and amortisation.

Table 2 Head grades at different production rates Acknowledgement


Rate, Mtpa 0.5 1.0 1.5 2.0 2.5 This paper has been reproduced with the kind permis-
Grade, g t21 6.7 5.8 5.0 4.2 3.3
sion of the Australasian Institute for Mining and

Mineral Processing and Extractive Metallurgy (Trans. Inst. Min. Metall. C) 2010 VOL 119 NO 4 189
McCarthy Setting plant capacity

Metallurgy from Metallurgical Plant Design and 7. L. D. Smith: ‘A critical examination of the methods and factors
affecting the selection of an optimum production rate’, CIM Bull.,
Operations Strategies (MetPlant) 2002, 15–16 April
1997, 90, 48–54.
2002, Sydney, Australia. 8. D. J. Ward and P. L. McCarthy: ‘Start-up performance of new base
metal projects’, in ‘Adding value to the Carpentaria Mineral
Province’, Aust. J. Min. Conf., 1999 (unpublished).
References 9. B. B. Burmeister: ‘From resource to reality: a critical review of the
achievements of new Australian gold mining projects during the
1. H. C. Hoover: ‘Principles of mining’, 153–160; 1909, New York,
period January 1983 to September 1987’; 1988, Sydney, Macquarie
McGraw-Hill.
University.
2. C. R. Tatman: ‘Production rate selection for steeply dipping
10. D. Harquail: ‘Investing in junior mining companies’, Proc. 6th
tabular deposits’, Min. Eng., Oct. 2001, 62–64.
Mineral Economics Symp. CIL, Montreal, PQ, Canada, January
3. P. L. McCarthy: ‘Economics of narrow vein mining’, in ‘Narrow 1991, CIM.
vein mining’, 89–97; 1993, Bendigo, Vic., AusIMM. 11. A. Hall and B. Hall: ‘Doing the right things right – identifying and
4. H. K. Taylor: ‘Mine valuation and feasibility studies’, in ‘Mineral implementing the mine plan that delivers the corporate goals’,
industry costs’, (ed. J. R. Hoskins and W. R. Green), 1–17; 1978, Proc. 1st Int. Mine Management Conf., Melbourne, Vic.,
Spokane, WA, Northwest Mining Association. Australia, October 2006, AusIMM, 119–128.
5. H. K. Taylor: ‘Rates of working mines – a simple rule of thumb’, 12. G. M. Mudd: ‘The sustainability of mining in Australia: key
Trans. Inst. Min. Metall., 1986, 95, 203–204. production trends and their environmental implications for the
6. G. M. McSpadden and W. Schaap: ‘Technical note – a test and future’, Research Report no. RR5, Department of Civil
comment on Taylor’s rule of mine life’, Proc. Australas. Inst. Min. Engineering, Monash University and Mineral Policy Institute,
Metall., 1984, 289, 217–223. Clayton, Vic., Australia, 2009.

190 Mineral Processing and Extractive Metallurgy (Trans. Inst. Min. Metall. C) 2010 VOL 119 NO 4

You might also like