PENDING COMPLAINTS
1 CC 1 11.11.12 Written SLB Ruslan Hasanov Delay of spare parts delivery (Resato units) Alesger Guliyev OPS Elvira Aksyanova 01.10.13 open
2 CC2 31.07.13 Written HALLIBURTONGregory Avereyn Halliburton XR tool damage Elvira Aksyanova OPS Elvira Aksyanova, Aynur Babayeva, Zaur Dadashev
open
C LO S E D COMPLAINTS
3 CC3 29.06.2013 Written BP Dmitriy Bobrov Left supplied by KTB to BP has been broken after second time usage Elvira Aksyanova OPS Elvira Aksyanova, Aynur Babayeva, Zaur
30.08.2013
Dadashev
close
4 CC4 27.08.2013 Written HALLIBURTONMammad Huseynov Low quality spare parts Aynur Babayeva OPS Aynur Babayeva, Elvira Aksyanova 19.09.2013 close
Alasgar
We cant wait for ages, please let me know if you can get these parts at your earliest, otherwise we have to think other way to resolve issue.
Thanks
According to inspection report number: 071/12 these parts in HPU type: HPU-W-30-1/400-1/P/I/CB/CR/sep (indoor) should be replaced:
• Muffler
• Seals of pumps 160-30 & 160-400
• Check valve of pumps 160-30 &160-400
• Check valve
• Brass connection
• PRV
• Switcher of water inlet part.
Parts painted over yellow are non-standard and it will take time for Holland engineers to find them in their stock.
KTB-BD-005-F001 12.02.2013
If you have more questions please don’t hesitate to contact us.
We cant wait for ages, please let me know if you can get these parts at your earliest, otherwise we have to think other way to resolve issue.
Thanks
According to inspection report number: 071/12 these parts in HPU type: HPU-W-30-1/400-1/P/I/CB/CR/sep (indoor) should be replaced:
• Muffler
• Seals of pumps 160-30 & 160-400
• Check valve of pumps 160-30 &160-400
• Check valve
• Brass connection
• PRV
• Switcher of water inlet part.
Parts painted over yellow are non-standard and it will take time for Holland engineers to find them in their stock.
Best regards,
Alesker Guliyev
Sales-engineer assistant
KTB-BD-005-F001 12.02.2013
According to meeting held on 08.05.2013 / 11.00. a.m. and
attached MOM there has been held Negotiations regarding stock of
Elvira
Resato unit/spare parts for all SLB segments : will it partly on SLB
2 Aksyanova/Aynur 01.11.13 open
cost or fully on KTB stock. KTB already ordered stock for Fuad
Babayeva
Pashayev. List of spares with quote had been sent to Ivan Yakovlev
and Ruslan Hasanov, waiting confirm from them
3
4
5
KTB-BD-005-F001 12.02.2013
CC 1
e.
KTB-BD-005-F001 12.02.2013
e.
Comments
KTB-BD-005-F001 12.02.2013
< BACK TO OVERVIEW
KTB-BD-005-F001 12.02.2013
Full content of Complaint
From: Agalar Mahmudov [mailto:AMahmudov@slb.com]
Sent:
From: Wednesday, 12 September,
Gregory Avereyn 2012 11:36
[mailto:Gregory.Avereyn@halliburton.com]
Sent: Thursday, July 25, 2013 11:16 PM
To: KTB
Cc: Jamila Alibayova; Murad Azizov; 'Zaur Dadashov'
Subject: RE: HDBS repair
Elvira, Zaur,
Gregory AVEREYN
Service coordinator
Mobile: +994 55 5052022
VOIP: 884450011
Switchboard: +994 12 4907000
HALLIBURTON Eurasia Limited
Drill Bits & Services
Salyan Highway,16 km
Lokbatan Settlement,
Actions to be taken:
nyway as said, our procedure was not followed up at all as the tool should have been scrapped at evaluation. Will
roup to see if we can take the risk to use it again or not
ne, I believe I would have done it better myself… I tried to insert a brand new travelling blocks and it’s stay stuck in all
looks the machining has been done by hand grinding after the welding and not properly on a mill… I’m not talking
on…
the repair are not too big. If not I will look for another supplier or I will have simply to scrap this tool… FYI, this tool
Aynur,
Irina,
Do you know the ETA of materials you’ve ordered for WA platform in order to plan a repair? Could you please speed up the
Regards
____________________________________________
Dmitry Bobrov
Maintenance Supervisor
BP Exploration (Caspian Sea) Ltd.
Baku, Azerbaijan
West Azeri Platform
ACG Project
Email: bobrovda@bp.com
Tel: +994 (0) 124979000 Ex 854103
Mob: +994 (050) 3632039
BP Exploration (Caspian Sea) LTD.
Registered Office: Chertsey Road, Sunbury, Middx TW167BP, UK.
Representative Office, Azerbaijan, 2 Neftchiler, Villa Petrolia, Baku, AZ 1003 Azerbaijan, Tax ID No 9900070211
Actions to be taken:
1 Additional visit to WA for lift breakdown
2
3
4
5
CC 3
ause it’s completely broken. At the moment lift is isolated and we can’t use it. That was after second time they came to the
? Could you please speed up the delivery? This activity needs to be added to the plan then.
Tax ID No 9900070211
651421D6.pdf
CC 3
s
Full content of Complaint
Please be informed, that we have problems with our certain vendors about quality of their service. We repeatedly ask our v
and items. For instance, in the last order to KTB, as seen from the correspondence below we requested the vendor to learn
pitifully, the supplied parts by KTB were again of low quality, and as we are in urgency and short of time amidst intense mix
vendors to heed the quality issue when they get the parts in local market and to meet the requirements we put forward. We
Thanks&Regards,
Mammad Huseynov
Mechanic
Advanced Fluids Facility, Baroid.
Halliburton Eurasia Ltd.
Baku, Azerbaijan.
Phone (Cell): +994 50 565 39 09
Email:Mammad.Huseynov@halliburton.com
Actions to be taken:
1 Oil filer Dinaldson to be replaced with requested model "Fleetguard" LF670
2
3
4
5
CC 4
service. We repeatedly ask our vendors to procure quality goods, but unfortunately they keep delivering low quality parts
we requested the vendor to learn about the problem at the spot and they were explicitly briefed on every detail. After that,
d short of time amidst intense mixing and loading activities we were forced to accept them. We request you to direct the
requirements we put forward. We appreciate your help and thank you for your understanding and support.