AL-RASHID TOWER

Site MV ELECTRICAL ROOM


Site Test Report Power Transformer-
NAMEPLATE DETAILS

RATING POWER
MAKE
TYPE Dry PRIMARY 13.8KV

% IMPEDENCE SECONDARY
RATED
60Hz VECTOR GROUP Dyn11
FREQUENCY
SERIAL NO. NUMBER OF PHASES 3-PH

1. MECHANICAL CHECK AND VISUAL INSPECTION.

Sr. DESCRIPTION DONE REMARKS


1 Inspect for physical damage/defects (cracks, chips, etc., of the cast resin)  OK
2 Check nameplate for correctness.  OK
3 Check tightness of all bolts (torque wrench method).  OK
4 Check that all groundings are securely connected , Including star point neutral.  OK
5 Perform all specific checks per manufacturer instructions.  OK

2. ELECTRICAL TESTS.

Sr. DESCRIPTION DONE REMARKS


1 Insulation resistance and Polarization Index (PI) test.  OK
2 Turns ratio all (taps) test  OK
3 Vector relationship Verification  OK
4 Winding resistance measurement (all taps).  OK

Testing Engineer Contractor Consultant

Name: Name: Name:


Sign. Sign. Sign.

Date: Date: Date:


1
AL-RASHID TOWER

Site MV ELECTRICAL ROOM


Site Test Report Power Transformer-
3. INSULATION RESISTANCE:

3.1 Insulation Resistance

IR value IR value
Applied points between Applied voltage PI Remarks
60 sec. (Ω) 600 sec. (Ω)
Prim to Earth 5kv OK

Prim to Sec 5kv OK

Sec to Earth 1kv OK

4. WINDING RESISTANCE MEASUREMENT:

4.1. Primary Winding:

Measured Measured Measured


Tap no. On site temperature On site temperature On site temperature Remarks

U-V(mΩ) V-W(mΩ) W-U(mΩ)


OK
OK
OK
OK
OK

Testing Engineer Contractor Consultant

Name: Name: Name:


Sign. Sign. Sign.

Date: Date: Date:


2
AL-RASHID TOWER

Site MV ELECTRICAL ROOM


Site Test Report Power Transformer-
Secondary Winding:

Measured Measured Measured


Tap no. On site temperature On site temperature On site temperature Remarks
u-v(mΩ) v-w(mΩ) w-u(mΩ)
OK
Tap no. u-n(mΩ) v-n(mΩ) w-n(mΩ)
OK

5. TURNS RATIO TEST:

Voltage Test Actual Measured of % I exc


Tap Position TAP
H/X Voltage(V) Ratio Ratio Error (mA)

Nominal

Nominal

Nominal

Nominal

Nominal

6. VECTOR GROUP TEST:

The vector group of the transformer Dyn11 is verified.

Testing Engineer Contractor Consultant

Name: Name: Name:


Sign. Sign. Sign.

Date: Date: Date: