You are on page 1of 42

BOQ TILL DPC DHA 20A/15J

Description No L B H Qty LumpSum

Excavation 1 58.66 38.79 7.5 17065.66 110,000/-


1:2:4 & 1:4:8 Concrete Estimated Quantity
S# DESCRIPTION no L B H QTY
1 Lean 1:4:8 1 45 39 0.25 438.75
RCC Raft upto
Plinth beam (1:2:4)
WF-1 1.00 17.00 3.25 0.75 41.44
1.00 12.00 3.25 0.75 29.25
2 1.00 13.00 3.25 0.75 31.69
1.00 20.50 3.25 0.75 49.97
1.00 29.00 3.25 0.75 70.69
1.00 12.00 3.25 0.75 29.25
252.28
WF-2 1.00 12.00 3.25 0.75 29.25
1.00 41.75 3.25 0.75 101.77
1.00 16.00 3.25 0.75 39.00
2.00 9.00 3.25 0.75 43.88
3 0.75 85.31
1.00 35.00 3.25
1.00 28.75 3.25 0.75 70.08
1.00 13.00 3.25 0.75 31.69
400.97
WF-3 7.00 2.50 2.50 0.75 32.81
4
F-1 1.00 5.00 5.00 1 25.00

F-2 1.00 15.00 3.00 1 45.00


5 C-1 16.00 5.00 5 400.00
C-2 3.00 10.00 10 300.00
G-Col. 2 11 11 242.00

Plinth Beam Rft 1.00 209.00 0.75 1 156.75


1.00 33.00 0.75 1 24.75
1.00 32.00 0.75 1 24.00
1.00 38.00 0.75 1 28.50
6 4.00 18.00 0.75 1 54.00
1.00 28.00 0.75 1 21.00
3.00 14.00 0.75 1 31.50
6

340.50

Total Quatity of 1:2:4 Ratio of Concrete 2038.56 Cement 1:2:4 =


Total Quatity of 1:4:8 Ratio of Concrete 438.75 Cement 1:4:8 =

BRICKS Estimated Quantity


DESCRIPTION no L B H QTY
766.13
1 Brick Mesonery @ Foundation
1.00
1.00
340.50
340.50
0.75
1.13
3
0.5 191.53
Total 957.66

177.00 0.33 11.5 671.72


2 Brick Mesonery @ Boundery Wall 1.00
Total 671.72

No. Of
FootingsNo. Of Bars Dia.
S# DESCRIPTION L Rft Unit Wt.
/Beams/
Columns

Footing Steel
A
WF-1 Straight Bars 1 10 #3 103.5 1035 0.17
Distribution Bars 1 180 #4 5 900 0.302
WF-2 Straight Bars 1 7 #3 164.5 1151.5 0.17
Distribution Bars 1 251 #4 4 1004 0.302
WF-3 Straight Bars 1 5.00 #3 17.50 87.5 0.170
Distribution Bars 1 31.00 #3 3.25 100.75 0.170

F-1 Straight Bars 1 10.00 #4 5.00 50 0.302


B Distribution Bars 1 10.00 #4 6.50 65 0.302

F-2 Straight Bars 1 7.00 #3 9.00 63 0.170

Distribution Bars 1 18.00 #4 7.50 135 0.302


Gate Columns Str. Bars 2 8.00 #4 8.00 64 0.302
Gate Columns Rings 2 15.00 #3 5.00 75 0.170
Total 'A'
Steel For Pedestal Columns
C1 16 4.00 #4 5.00 320 0.302
Ties 16 9.00 #3 2.25 324 0.170

C
C2 3 8.00 #6 10.00 240 0.680
Ties 3 31.00 #3 10.00 930 0.170
C Gate Columns 2 8.00 #4 11.00 176 0.302
Ties 2 20.00 #3 4.75 190 0.170
Total 'B'
Plinth Beam Steel
Straight Bars 1 4.00 #4 340.50 1362 0.302
Rings 1 171.00 #3 2.25 384.75 0.170
D Total 'C'
Description Item Unit Rate Quantity Total Price
Till Dpc Sand 1 33000 2 66000
Crush 1 69000 1 69000
Cement 1 1025 500 512500
Steel 1 262 2133 558846
Pouring Lean 1 440 15000
Step Footing 1 686.06 30000
Beam & Pedestel Col. 1 1352.50 20000
Brick Mesonery 1 28 3250 91000
Total 1362346
360bags Sand 900Cft Crush 450Cft
30 Bags Sand 210Cft Crush 110Cft

Cft
Cft Bricks Quantity
Cft 14.00 13407.1875

Cft Bricks Quantity


Cft 14 9404.01

Quantity Unit

Weights Steel Kg/Rft


#3 0.17
175.95 Kg. #4 0.302
271.8 Kg. #5 0.472
195.755 Kg. #6 0.68
303.208 Kg. #8 1.209
14.875 Kg.
17.1275 Kg. #3 738.06 KG
15.1 Kg. #4 1230.952 KG
19.63 Kg. #5
10.71 Kg. #6 163.2 KG
40.77 Kg. #8
19.328 Kg. Total
12.75 Kg. 2132.21
1084.254 Kg.

96.64 Kg.
55.08 Kg.
163.2 Kg.
158.1 Kg.
53.152 Kg.
32.3 Kg.
558.472 Kg.

411.324
65.4075 Kg.
476.7315 Kg.
3139.382
675.675

Total Price

1191.75
2035.5
3227.25

90363
Estimate for MAC 3
S# DESCRIPTION no L B H QTY
1 Lean 1:4:8 1 45 39 0.25 438.75

RCC Raft upto


Plinth beam (1:2:4)
WF-1 1.00 17.00 3.25 0.75 41.44
1.00 12.00 3.25 0.75 29.25
2 1.00 13.00 3.25 0.75 31.69
1.00 20.50 3.25 0.75 49.97
1.00 29.00 3.25 0.75 70.69
1.00 12.00 3.25 0.75 29.25
252.28
WF-2 1.00 12.00 3.25 0.75 29.25
1.00 41.75 3.25 0.75 101.77
1.00 16.00 3.25 0.75 39.00
2.00 9.00 3.25 0.75 43.88
3 0.75 85.31
1.00 35.00 3.25
1.00 28.75 3.25 0.75 70.08
1.00 13.00 3.25 0.75 31.69
400.97
4 WF-3 7.00 2.50 2.50 0.75 32.81

F-1 1.00 5.00 5.00 1 25.00

F-2 1.00 15.00 3.00 1 45.00


5 C-1 16.00 5.00 5 400.00
C-2 3.00 10.00 10 300.00
G-Col. 2 11 11 242

Plinth Beam Rft 1.00 209.00 0.75 1 156.75


1.00 33.00 0.75 1 24.75
1.00 32.00 0.75 1 24.00
1.00 38.00 0.75 1 28.50
6 4.00 18.00 0.75 54.00
1
1.00 28.00 0.75 1 21.00
3.00 14.00 0.75 1 31.50
340.50

Total Quatity of 1:2:4 Ratio of Concrete 1096.56


Total Quatity of 1:4:8 Ratio of Concrete 438.75

7
Estimate For Fish Feed Mill
S# DESCRIPTION no L B
Brick Mesonery @ Foundation
1.00 340.50 0.75
1
1.00 340.50 1.13

Brick Mesonery @ Boundery Wall 1.00 177.00 0.33

Plastering

Paint
4

Sliding Door(10'x12.5')
Ventilator(9'x2')
ESTERNAL DEVELOPMENT
Plinth Protection&Pathways
Excavation
For Plinth
For Kerb Stone
5
6 P.C.C 1:4:8
B For plinth Masonery

For Kerb Stone


1
Brick masonery For Plinth
For plinth

P.C.C 1:4:8 For Plinth&Pathways


2 For Plinth

For Pathways

P.C.C 1:2:4 For Plinth&Pathways(3" Thickness)


3
For Plinth

For Pathways

4 Kerb Stone 1.00 300.00

6
H QTY Unit

3 766.13 Cft
0.5 191.53 Cft Bricks/Cft Total Bricks
Total 957.66 Cft 14.00 13407.1875

11.5 671.72 Cft 14 9404.01


Cft
Cft
Cft
Cft
Cft
Cft
Cft
Total 671.72 Cft

Sft
Sft
Sft
Sft
Sft
Sft
Sft
Total 0.00 Sft

Sft
Sft
Sft
Sft
Sft
Sft
Sft
Total 0.00 Sft
0.00 Sft
0.00 Sft

Cft
Cft
Cft
Total 0.00 Cft

Cft
Cft
Cft
Total 0.00 Cft

Cft 127
Cft
Total 0.00 Cft

Cft
Cft
Cft
Total 0.00 Cft

Sft
Sft
Sft
Total 0.00 Sft
300.00 Rft.
1524
1200
2724
336
3060
Estimate For Fish Feed Mill(Steel Reinforcement)
No. Of
DESCRIPTION Footings/Beams/ No. Of Bars Dia. L Rft
S# Columns
Footing Steel
A
WF-1 Straight Bars 1 10 #3 103.5 1035
Distribution Bars 1 180 #4 5 900
WF-2 Straight Bars 1 7 #3 164.5 1151.5
Distribution Bars 1 251 #4 4 1004
WF-3 Straight Bars 1 5.00 #3 17.50 87.5
Distribution Bars 1 31.00 #3 3.25 100.75
F-1 Straight Bars 1 10.00 #4 5.00 50
B Distribution Bars 1 10.00 #4 6.50 65
F-2 Straight Bars 1 7.00 #3 9.00 63
Distribution Bars 1 18.00 #4 7.50 135
Gate Columns Str. Bars 2 8.00 #4 8.00 64
Gate Columns Rings 2 15.00 #3 5.00 75

Steel For Pedestal Columns


C1 16 4.00 #4 5.00 320
Ties 16 9.00 #3 2.25 324
C2 3 8.00 #6 10.00 240
Ties 3 31.00 #3 10.00 930
C Gate Columns 2 8.00 #4 11.00 176
Ties 2 20.00 #3 4.75 190

Plinth Beam Steel


Straight Bars 1 4.00 #4 340.50 1362
Rings 1 171.00 #3 2.25 384.75

Columns in Super Str.


C1 8 8.00 #5 36.50 2336
Ties 8 96.00 #3 4.50 3456
C3 4 8.00 #5 36.50 1168
4 4.00 #4 36.50 584
Ties 4 96.00 #3 5.00 1920
E
Roof Beam Steel For Storey
1
Short Diretion
B1(NO. 4)
Bottom&Top Steel 4 8.00 #5 20.00 640
Curtailment Bars 4 2.00 #5 6.00 48
Torsion Steel 4 10.00 #5 18.00 720
Ties 4 50.00 #3 6.50 1300
B3(NO. 8)
Bottom&Top Steel 8 10.00 #5 20.00 1600
Ties 8 38.00 #3 6.50 1976
F
Longer Diretion
B2(NO. 4)
Bottom&Top Steel 4 7.00 #4 55.50 1554
Torsion Steel 4 3.00 #4 53.42 641.04
4 7.00 #5 54.42 1523.76
Ties 4 116.00 #3 6.50 3016

Slab Reinforcement
G
Main Bars 1 104.00 #5 18.25 1898
Distribution Bars 1 28.00 #5 54.42 1523.76

Storey 2&3
Longer Diretion
B6(NO. 2)
Bottom&Top Steel 4 6.00 #4 55.75 1338
Negative Steel on Top 4 2.00 #4 18.00 144
Ties 4 145.00 #3 6.50 3770
Shorter Direction
B6(NO. 2)
Bottom&Top Steel 4 6.00 #4 23.25 558
Negative Steel on Top 4 2.00 #4 8.00 64
H
Ties 4 62.00 #3 6.50 1612

Storey 4
Longer Diretion
B7(NO. 2)
Bottom Steel 2 4.00 #5 56.42 451.36
Top Steel 2 2.00 #4 55.75 223
Curtailment Bars 2 2.00 #5 17.00 68
Ties 2 93.00 #3 5.50 1023
Shorter Diretion
B7(NO. 2)
Bottom Steel 2 4.00 #5 23.25 186
Top Steel 2 2.00 #4 23.25 93
Curtailment Bars 2 2.00 #5 7.00 28
Ties 2 40.00 #3 5.50 440

Trusses

A1(Bottom Cord)(2"x2"x.25") 6 24
Top Cord(2"x2"x.25") 6 25.76
A2(1.5"X1.5"X.1793") 6 25.984

Purlins 8 56
S.G.I 22 SWG SHEET 1 56 26
2 26 2

Wind Ties(1"x3/16") 10 56

Ridge 1 56
Base plate(8"x8"x0.5") 12 0.67 0.67
Unit Wt. Quantity Unit

Weights Steel Kg/Rft


#3 0.17
0.17 175.95 Kg. #4 0.302
0.302 271.8 Kg. #5 0.472
0.17 195.755 Kg. #6 0.68
0.302 303.208 Kg. #8 1.209
0.170 14.875 Kg.
0.170 17.1275 Kg.
0.302 15.1 Kg.
0.302 19.63 Kg.
0.170 10.71 Kg.
0.302 40.77 Kg.
0.302 19.328 Kg.
0.170 12.75 Kg.
Total 'A' 1084.254 Kg.

0.302 96.64 Kg.


0.170 55.08 Kg.
0.680 163.2 Kg.
0.170 158.1 Kg.
0.302 53.152 Kg.
0.170 32.3 Kg.
Total 'B' 558.472 Kg.

0.302 411.324
0.170 65.4075 Kg.
Total 'C' 476.7315 Kg.
Kg.
Kg.

Kg.
Kg.
Kg.
Kg.

0.473 1104.928 Kg.


0.170 587.52 Kg.
0.473 552.464 Kg.
0.302 176.368 Kg.
0.170 326.4 Kg.
Total 'D' 2747.68 Kg.

0.473 302.72 Kg.


0.473 22.704 Kg.
0.473 340.56 Kg.
0.170 221 Kg.

0.473 756.8 Kg.


0.170 335.92 Kg.

0.302 469.308 Kg.


0.302 193.5941 Kg.
0.473 720.7385
0.170 512.72 Kg.
Total 'E' 3876.065 Kg.

0.473 897.754 Kg.


0.473 720.7385 Kg.
Total'F' 1618.492 Kg.

0.302 404.076 Kg.


0.302 43.488 Kg.
0.170 640.9 Kg.

0.302 168.516 Kg.


0.302 19.328 Kg.
0.170 274.04 Kg.
Total 'G' 1550.348 Kg.

0.473 213.4933 Kg.


0.302 67.346 Kg.
0.473 32.164 Kg.
0.170 173.91 Kg.

0.473 87.978 Kg.


0.302 28.086 Kg.
0.473 13.244 Kg.
0.170 74.8 Kg.
Total 'H' 691.0213 Kg.

Grand
Sum 12126.33 Kg.
'A,B,C,D,E
,F,G&H'

Kg.
3.402781 222.3233
3.402781 238.627 Kg.
1.83035 129.4732 Kg.
total A 590.4234 Kg.
448 Rft.
1456 Sft.
104 Sft.
total 1560 Sft.
0.638 162.1053 Kg.
total B 162.1053 Kg.
56 Rft.
20.4 49.85967 Kg.
total C 49.85967 Kg.
Total A,B,C 802.3883 Kg.
Estimate for MAC 3
S# DESCRIPTION no L B H QTY
RCC Column upto
G.F.Slab(1:1.5:3)
C1 1.00 3.00 1.25 11.5 43.13
1
C2 4.00 2.25 1.50 11.5 155.25
C3 1.00 2.00 1.50 11.5 34.50
C4 1.00 2.00 1.50 11.5 34.50
C5 1.00 2.50 1.25 11.5 35.94
2 C6 2.00 2.25 1.25 11.5 64.69
C7 1.00 2.00 1.25 11.5 28.75
C8 1.00 2.50 1.25 11.5 35.94
C9 1.00 2.00 1.25 11.5 28.75
3 S.W 1 2.00 7.50 1.00 11.5 172.50
SW 2.00 5.00 1.00 11.5 115.00
Retaining wall 1.00 247.00 0.75 11.5 2130.38
Deduction of -280.31
columns (1.00) 32.50 0.75 11.5
Total 2599.00
PCC 1:4:8 Under
Floor 1.00 78.50 43.50 0.25 853.69
Total 853.69
GF Roof Beams
G.F 1 1.00 80.00 1.00 1.5 120.00
4 G.F 2 1.00 80.00 1.00 1.5 120.00
G.F 3 1.00 80.00 1.00 1.5 120.00
G.F 4 1.00 119.25 0.75 1 89.44
G.F 5 1.00 112.75 0.75 1 84.56
G.F 6 1.00 22.50 0.75 1 16.88
G.F 7 1.00 43.50 1.00 1.5 65.25
G.F 8 1.00 90.00 1.00 1.5 135.00
G.F 9 1.00 43.50 1.00 1.5 65.25
G.F 10 1.00 43.50 1.00 1.5 65.25

5
Total 881.63
GF Roof Slab 1800.00
Concrete 1.00 80.00 45.00 0.5
Total 1800.00

6
6

7
4 80 1.5 1 480
5 45 1.5 1 337.5
2 45 0.75 3 202.5

1020
2620 17.6 100 461.12
Estimate For Fish Feed Mill
S# DESCRIPTION no L B H QTY Unit
Excavation
4.00 51.25 1.50 1 307.50 Cft
1
6.00 55.00 1.50 1 495.00 Cft
Total 802.50 Cft
Brick masonery in super
structure
Storey 1 4.00 51.25 0.75 12.5 1921.88 Cft
3 2.00 55.00 0.75 12.5 1031.25 Cft
Ventilator (20.00) 9.00 0.75 2 -270.00 Cft
Door (3.00) 10.00 0.75 12.5 -281.25 Cft
Storey 2&3 4.00 51.25 0.75 6.5 999.38 Cft
2.00 20.00 0.75 6.5 195.00 Cft
Storey 4 2.00 51.25 0.75 7 538.13 Cft
2.00 20.00 0.75 7 210.00 Cft
Total 4344.38 Cft
Plastering
Storey 1 6.00 51.25 15 4612.50 Sft
2.00 55.00 15 1650.00 Sft
Ventilator (20.00) 9.00 2 -360.00 Sft
Door (3.00) 10.00 12.5 -375.00 Sft
Slab 2.00 51.25 18.5 1896.25 Sft
Storey 2,3&4 2.00 51.25 27 2767.50 Sft
2.00 20.00 27 1080.00 Sft
Total 11271.25 Sft
Paint
Storey 1 6.00 51.25 15 4612.50 Sft
4 2.00 55.00 15 1650.00 Sft
Ventilator (20.00) 9.00 2 -360.00 Sft
Door (3.00) 10.00 12.5 -375.00 Sft
Slab 2.00 51.25 18.5 1896.25 Sft
Storey 2,3&4 2.00 51.25 27 2767.50 Sft
2.00 20.00 27 1080.00 Sft
Total 11271.25 Sft
Sliding Door(10'x12.5') 3.00 10.00 12.50 375.00 Sft
Ventilator(9'x2') 20.00 9.00 2.00 360.00 Sft
ESTERNAL
DEVELOPMENT
Plinth
Protection&Pathways
Excavation
For Plinth 2.00 57.25 1.00 1 114.50 Cft
2.00 61.00 1.00 1 122.00 Cft
For Kerb Stone 1.00 300.00 1.00 0.75 225.00 Cft
5 Total 461.50 Cft
6 P.C.C 1:4:8
B For plinth Masonery 2.00 57.25 1.00 0.25 28.63 Cft
2.00 61.00 1.00 0.25 30.50 Cft
For Kerb Stone 1.00 300.00 1.00 0.25 75.00 Cft
Total 134.13 Cft
1 Brick masonery For
Plinth
For plinth 2.00 57.25 0.75 2 229.00 Cft
2.00 61.00 0.75 2 244.00 Cft
Total 473.00 Cft
P.C.C 1:4:8 For
Plinth&Pathways
2 171.75 Cft
For Plinth 2.00 57.25 3.00 0.5
2.00 55.00 3.00 0.5 165.00 Cft
For Pathways 1.00 170.00 12.00 0.5 1020.00 Cft
Total 1356.75 Cft
P.C.C 1:2:4 For
Plinth&Pathways(3"
3 Thickness)
For Plinth 2.00 57.25 3.00 343.50 Sft
2.00 55.00 3.00 330.00 Sft
For Pathways 1.00 170.00 12.00 2040.00 Sft
Total 2713.50 Sft
4 Kerb Stone 1.00 300.00 300.00 Rft.

6
127 1524
1200
2724

336
3060
NATIONAL AGRICULTURAL RESEARCH CENTRE
(Directorate of Works and Estate Management)

Estimate
Construction of Fisheries Feed Mill at NARC
A) CIVIL WORKS
S# DESCRIPTION QTY UNIT RATE AMOUNT
1 Excavation in foundation trenches in
all kind of soil dry or wet or boulders
and back filling the excavated stuff in
6” layers inside foundation or
depressions and under floor or where
ever required within site of work
including breaking of clods leveling.
dressing compacting complete in all
respect.
7000.00 Cft. 10.00 70000.00
2 Providing and laying P.C.C 1:4:8 in
foundation or where required with ¾”
thick down graded margalla crushed
stone aggregates and Lawrencepur
sand including machine mixing,
placing, compacting, curing complete
as per drawings, specifications and as
directed by the Engineer Incharge.

680.00 Cft. 150.00 102000.00


3

Providing and laying machine mixed


RCC 1:2:4 having minimum 28 days
cube crushing strength of 3000 psi
including Steel formwork and its
removal, having straight unbroken
joints and compacting, leveling,
rodding/ Vibration and curing, etc.
complete as per design and drawings
and structural specifications but
excluding the cost of steel
reinforcement:
a Footings 1587.00 Cft. 300.00 476100.00
b Colums up to plinth 195.00 Cft. 350.00 68250.00
c Plinth beams 1098.00 Cft. 350.00 384300.00
d Columns in Super Structure 1102.00 Cft. 350.00 385700.00
e Roof and Bracing Beams 1990.00 Cft. 350.00 696500.00
f Low Roof Slab 1282.00 Cft. 300.00 384600.00
4 P/ fixing mild steel reinforcement
having minimum yield strength of
60,000 PSI including cost of
straightening, cleaning, bending,
binding, wastage, steel chairs, placing
in position at any height and floor and
16 SWG binding wire, complete as
per drawings, specifications and as per
directions of the Engineer Incharge.

22000.00 Kg 110.00 2420000.00


5 Providing & laying first class
Machine made brick masonry of
approved quality in Super Structure
laid and jointed with cement sand
mortar1:4, masonry to be laid in
courses true to line, level and plumb,
protected and properly cured.All work
to be completed as per drawings and
specifications, including providing
and fixing specified anchorage with
concrete members and GI ties every
4th course @ 3' c/c as shown on
drawings and as directed by the
engineer:

4560.00 Cft. 300.00 1368000.00


Providing & applying 1/2" thick
plaster of 1:4 cement sand mortar on
Internal surface at any floor or any
height using fine Lawrencepur sand
including all bends corners, recess
including scaffolding and providing
8” wide wire mesh of 17 SWG
3/4”x3/4” size fixed with G.I. staples
on masonry/ concrete joints. All
plaster to be finished smooth with
steel trowel in true level, line and
plumb and properly cured complete in
all respect.

11700.00 Sft. 35.00 409500.00


Providing & applying paint of
approved shade and quality on all
plaster surface and any height
including jambs etc completed in all
aspects.
11700.00 Sft. 15.00 175500.00
7
Providing & filling local sand under
floors or where required in layers not
exceeding 4” thickness, including
consolidation, watering, leveling and
dressing etc. complete as per
instructions of the Engineer. 6650.00 Cft. 35.00 232750.00
8 Providing and laying PCC 1:4:8 under
floor or where required with approved
quality ¾” thick down graded
margalla crushed stone aggregates and
Lawrencepur sand including machine
mixing, placing, levelling,
compacting, curing and side stops as
per drawings, specifications and as
directed by the Engineer.
990.00 Cft. 140.00 138600.00
9 P/laying 4" thick PCC 1:2:4 in panels
with 1-1/2"x1/2" marble dividing strip
not less then 16 sft i/c finishing curing
levelling complete in all respect.
2950.00 Sft. 100.00 295000.00
10 Providing and fixing MS
Gate(10'x12.5')
375.00 Sft. 1200.00 450000.00
11 Providing and fixing MS
Ventilator(9'x2') 360.00 Sft. 400.00 144000.00
12 Providing, cutting, welding and fixing
of M. S Angle,base plate,wind Ties
for Truss i/c enemal paint etc
complete.
875.00 Kg 150.00 131250.00
13 Providing, cutting, welding and fixing
Purlins of MS Tube(3"x1.5"x18
SWG) 448.00 Rft 110.00 49280.00
providing and fixing G.I corrugated
sheet 22 SWG inclding over lap,J
bolts with bitumenious washers etc
complete.
1560.00 Sft. 90.00 140400.00
14 providing and fixing S.G.I sheet
Ridge 22 SWG etc complete. 56.00 Rft 250.00 14000.00

Total 'A' 8535730.00


B External Development

Plinth Protection and Pathways


Excavation in foundation trenches in
all kind of soil dry or wet or boulders
and back filling the excavated stuff in
6” layers inside foundation or
depressions and under floor or where
ever required within site of work
including breaking of clods leveling.
dressing compacting complete in all
respect.
490.00 Cft. 10.00 4900.00
Providing and laying P.C.C 1:4:8 in
foundation or where required with ¾”
thick down graded margalla crushed
stone aggregates and Lawrencepur
sand including machine mixing,
placing, compacting, curing complete
as per drawings, specifications and as
directed by the Engineer Incharge.
165.00 Cft. 150.00 24750.00
Providing & laying first class brick
masonry of approved quality in Plinth
laid and jointed with cement sand
mortar1:4, masonry to be laid in
courses true to line, level and plumb,
protected and properly cured.All work
to be completed as per drawings and
specifications, including providing
and fixing specified anchorage with
concrete members as shown on
drawings and as directed by the
engineer:

481.00 Cft. 180.00 86580.00


Providing and laying PCC 1:4:8 under
floor or where required with approved
quality ¾” thick down graded
margalla crushed stone aggregates and
Lawrencepur sand including machine
mixing, placing, levelling,
compacting, curing and side stops as
per drawings, specifications and as
directed by the Engineer.
1398.00 Cft. 150.00 209700.00
P/laying 4" thick PCC 1:2:4 in panels
with 1-1/2"x1/2" marble dividing strip
i/c finishing curing levelling complete
in all respect.
2850.00 Sft. 100.00 285000.00
Providing and laying Kerb stone of
1.5'x1.5'x.5' size thick PCC 1:2:4 Pre-
cast Kerb stone including the cost of
fixing with 1:2 cement sand mortar at
joints and making proper shape and
grove completed in all aspects.
300.00 No. 200.00 60000.00

Total 'B' 670930.00


TOTAL 'A,B' (Civil Works) 9,206,660.00
Estimate For Fish Feed Mill
S# DESCRIPTION no L B H QTY Unit
Excavation
1 24.00 7.00 7.00 5 5880.00 Cft
Total 5880.00 Cft
PCC 1:4:8
24.00 7.00 7.00 0.33 388.08 Cft
2 Under Plinth 4.00 51.25 1.50 0.33 101.48 Cft
6.00 55.00 1.50 0.33 163.35 Cft
Total 652.91 Cft
RCC 1:2:4
3 24.00 6.00 6.00 1.75 1512.00 Cft
Total 1512.00 Cft
Column upto Plinth
Level
4 C1 12.00 1.25 1.25 4.5 84.38 Cft
C2 12.00 1.25 1.50 4.5 101.25 Cft
Total 185.63 Cft
Plinth Beam
4.00 51.25 1.00 2 410.00 Cft
5
6.00 53.00 1.000 2 636.00 Cft
Total 1046.00 Cft
Columns in Super
Str.
Storey 1
6 225.00 Cft
C1 12.00 1.25 1.25 15
C2 12.00 1.25 1.50 15 225.00 Cft
Total 450.00 Cft
Roof Beams
B1(12"X24") 4.00 17.00 1.00 2 136.00 Cft
B2(12"X24") 4.00 51.25 1.00 2 410.00 Cft
7
B3(12"X24") 8.00 17.00 1.00 2 272.00 Cft
B4(12"X24") 2.00 20.00 1.00 2 80.00 Cft
Total 898.00 Cft
Low Roof Slab 1232.50 Cft
8 Concrete 2.00 58.00 21.25 0.5
Total 1232.50 Cft
Storey 2to4
Column in Super Str.

C2 12.00 1.25 1.50 27 607.50 Cft


Total 607.50 Cft
9
9
Bracing Beam
B6,5(12"X24")
Longer Side B6 4 52 1 2 416 Cft
Shorter Side B5 4 19 1 2 152 Cft
Total 568 Cft
Bracing Beam
B6,5(12"X24")
Longer Side B6 2 52 1 2 208 Cft
Shorter Side B5 6 19 1 2 228 Cft
Total 436 Cft
Estimate For Fish Feed Mill
S# DESCRIPTION no L B H QTY Unit
Excavation
1 24.00 6.50 6.50 6 6084.00 Cft
Total 6084.00 Cft
PCC 1:4:8
24.00 6.50 6.50 0.33 334.62 Cft
2 Under Plinth 2.00 55.25 1.50 0.33 54.70 Cft
4.00 48.00 1.50 0.33 95.04 Cft
Total 484.36 Cft
RCC 1:2:4
3 24.00 6.00 6.00 1.75 1512.00 Cft
Total 1512.00 Cft
Column upto Plinth
Level
4 C1 12.00 1.25 1.25 4.17 78.19 Cft
C2 12.00 1.25 1.50 4.17 93.82 Cft
Total 172.01 Cft
Plinth Beam
2.00 55.25 1.00 2 221.00 Cft
5
4.00 48.00 1.000 2 384.00 Cft
Total 605.00 Cft
Columns in Super
Str.
Storey 1
6 195.00 Cft
C1 12.00 1.25 1.25 13
C2 12.00 1.25 1.50 13 195.00 Cft
Total 390.00 Cft
Roof Beams
B1(12"X24") 2.00 55.25 1.00 1.58 174.59 Cft
7
B2(12"X24") 4.00 48.00 1.00 1.58 303.36 Cft
Total 477.95 Cft
Low Roof Slab 1134.00 Cft
Concrete 2.00 56.00 20.25 0.5
8
2.00 18.75 2.00 0.5 37.50
Total 1134.00 Cft
Storey 2to4
Column in Super Str.

C2 12.00 1.25 1.50 27 607.50 Cft


Total 607.50 Cft
9
Bracing Beam
B6,5(12"X24")
9

Longer Side B6 4 52 1 2 416 Cft


Shorter Side B5 4 19 1 2 152 Cft
Total 568 Cft
Bracing Beam
B6,5(12"X24")
Longer Side B6 2 52 1 2 208 Cft
Shorter Side B5 6 19 1 2 228 Cft
Total 436 Cft
60840

62966.47
4290.96

317520 34327.7

15575.18 1541943

55044

163350

148200

152944

317520

1278384

1492891
Estimate For Fish Feed Mill
S# DESCRIPTION no L B H QTY Unit
Excavation
1 24.00 8.00 8.00 5 7680.00 Cft
Total 7680.00 Cft
PCC 1:4:8
In Footings 24.00 7.50 7.50 0.33 445.50 Cft
2 Under Plinth 4.00 51.25 1.50 0.33 101.48 Cft
6.00 55.00 1.50 0.33 163.35 Cft
Total 710.33 Cft
RCC 1:2:4
3 24.00 7.00 7.00 1.75 2058.00 Cft
Total 2058.00 Cft
Column upto Plinth
Level
C1 12.00 1.25 1.25 3.5 65.63 Cft
4
C2 8.00 1.25 1.50 3.5 52.50 Cft
C3 4.00 1.25 1.50 3.5 26.25 Cft
Total 144.38 Cft
Plinth Beam
4.00 51.25 1.00 2.5 512.50 Cft
5
6.00 53.00 1.000 2.5 795.00 Cft
Total 1307.50 Cft
Local Sand Filling
1.00 55.00 51.25 1.66 4679.13 Cft
Total 4679.13 Cft
PCC 1:4:8 Under
Floor 1.00 55.00 51.25 0.33 930.19 Cft
Total 930.19 Cft
PCC 1:2:4 For
Flooring 3" Thick 1.00 55.00 51.25
2818.75 Sft
Total 2818.75 Sft
Columns in Super
Str.
Storey 1
6 C1 12.00 1.25 1.25 15 225.00 Cft
C2 8.00 1.25 1.50 15 150.00 Cft
C3 4.00 1.25 1.50 15 75.00 Cft
Total 450.00 Cft
Roof Beams
B1(12"X30") 4.00 17.00 1.00 2 136.00 Cft
B2(12"X30") 4.00 51.25 1.00 2 410.00 Cft
7
7
B3(12"X30") 8.00 17.00 1.00 2 272.00 Cft
B5(12"X30") 2.00 20.00 1.00 2 80.00 Cft
Total 898.00 Cft
Low Roof Slab 1232.50 Cft
8 Concrete 2.00 58.00 21.25 0.5
Total 1232.50 Cft
Storey 2to4
Column in Super Str.

C1 8.00 1.25 1.25 27 337.50 Cft


C2 4.00 1.25 1.50 27 202.50 Cft
9 Total 540.00 Cft
Bracing Beam
B6(12"X30")
Longer Side 4 52 1 2.5 520 Cft
Shorter Side 4 19 1 2.5 190 Cft
Total 710 Cft
Bracing Beam
B7(12"X24")
Longer Side 2 52 1 2 208 Cft
Shorter Side 2 19 1 2 76 Cft
Total 284 Cft
93582.5

120924.4

214506.9
Estimate for MAC 3
Description No L H Qty Unit
Plastering
Storey 1
Celing 2.00 50.00 18 1800.00 Sft
Beams 8.00 50.00 1.5 600.00 Sft
4.00 55.25 1.5 331.50 Sft
Walls 2.00 48.50 14.5 1406.50 Sft
2.00 55.75 14.5 1616.75 Sft
2.00 22.50 14.5 652.50 Sft
2.00 24.00 14.5 696.00 Sft
2.00 30.00 14.5 870.00 Sft
Col 8.00 5.50 14.5 638.00 Sft
Col 16.00 1.25 14.5 290.00 Sft
Shade 2.00 54.00 2.5 270.00 Sft
2.00 55.25 2.5 276.25 Sft
Under ventilater 2.00 50.00 0.75 75.00 Sft
Gate Offsets 1.00 39.00 1 39.00 Sft
3.00 27.00 1 81.00 Sft
2.00 16.50 1 33.00 Sft
2.00 17.50 1 35.00 Sft
1.00 19.00 1 19.00 Sft
Ventilator (12.00) 8.50 2 -204.00 Sft
Door (3.00) 9.00 9 -243.00 Sft
(4.00) 2.50 7 -70.00 Sft
(4.00) 3.50 7 -98.00 Sft
(1.00) 5.00 7 -35.00 Sft
(1.00) 15.00 12 -180.00 Sft
Storey 2,3&4 6.00 50.00 5 1500.00 Sft
2.00 18.75 5 187.50 Sft
4.00 18.75 7 525.00 Sft
Under Truss gap 2.00 50.00 1 100.00 Sft
2.00 18.75 1 37.50 Sft
Beams 6.00 50.00 5 1500.00 Sft
6.00 21.25 5 637.50 Sft
4.00 18.75 6 450.00 Sft
2.00 50.00 1 100.00 Sft
6.00 50.00 1 300.00 Sft
Col 12.00 2.75 21 693.00 Sft
Plinth 2.00 56.00 0.5 56.00 Sft
1.00 55.25 0.5 27.63 Sft
Total 15013.63 Sft
50.75
22.5
18.25

66

33

336

You might also like