You are on page 1of 4

Project Name Type of : The Project for Construction of BEPS-23 School, Child Fund Myanmar

Project Project : Construction of One Storeyed R.C.C Building


Location : BEPS-23 School, Hlaing Thar Yar Township, Yangon Region
Name of Work : One Storeyed R.C.C Building (60'x 30')
Summary
Price Amount
No Description Specif Unit Quantity
icatio (Kyats) (Kyats)
0 Direct temporary work
0-1 Site Clearing & Leveling (70'-0"x40'-0") clearing work and leveling Sqft 2,800.00 500 1400000

0-2 Staking works for preparation (70'-0" x40'-0" ) staking work Sqft 2,800.00 193 500000
0-3 Scaffolding Work Bamboo scaffloding Sqft 2,200.00 326 716305
Subtotal 2616305

1 Earth work
Manual
1-1 Excavation soil work Sud 41.69 16062 669630
Incl. Transport and stockpile
1-2 Hardcore filling with sand grouting Sub-grade with compaction Sud 6.03 29743 347097
1-3 Soil filling under ground floor Excavated soil Sud 11.67 36250 423045
1-4 Sand Filling work (depth=3'=6") ~ 50'-0"x50' -0" x3'-6" (Rough sand filling) Sud 131.25 10186 1336976
1-5 Sand Filling (thick =1'-10") Imported sand Sud 26.22 10186 267070
Subtotal 3043818
2 Concrete works
Pouring of blinding concrete including with
(1:3:6) lean concrete for footing retaining wall, 405069 1122563
transportion, placing and consoliding
2-1 GF slab base, Stair & Ramp base cement concrete Sud 5.24
1:3:6 cement concrete (Rivershingle)
Pouring of blinding concrete including with
(1:2:4) cement concrete for Footing, Column, 255177 1768380
trasportion, placing and consoliding
2-2 Plinth beam and Ramp Sud 6.93
cemnet concrete
with slump test(1:2:4) (Rivershingle)
Pouring of blinding concrete including with
(1:2:4) cement concrete for Ground floor (4" 255177 1515754
trasportion, placing and consoliding
2-3 thick) cemnet concrete motar finish Sud 5.94
with slump test(1:2:4) (Rivershingle)
Pouring of blinding concrete including with
(1:2:4) cement concrete for Long column & 255177 1229955
trasportion, placing and consoliding
2-4 roof beam cemnet concrete Sud 4.82
with slump test(1:2:4) (Rivershingle)
Pouring of blinding concrete including with
(1:2:4) cement concrete for window sill, lintel 255177 1150852
trasportion, placing and consoliding
2-5 beam and sunshade cemnet concrete Sud 4.51
(1:2:4) cement concrete (Rivershingle)

To make Test Pieces for Concrete 3889 175000


compressive strength test with curing for
Test Pieces and tools(mold etc) / Three (3)
9pieces/lot( Footing, Short Column, Plinth
2.6 samples shall be tested no. 45
beam, Long Column and Roof beam)
at seven (7) days, three (3) samples shall be
tested at seven (14) days and other three (3)
samples shall be tested at twenty eight (28)
days for compressive strength
Project Name Type of : The Project for Construction of BEPS-23 School, Child Fund Myanmar
Project Project : Construction of One Storeyed R.C.C Building
Location : BEPS-23 School, Hlaing Thar Yar Township, Yangon Region
Name of Work : One Storeyed R.C.C Building (60'x 30')
Summary
Subtotal 6062504
3 Rebar works
Foundation (footing, short column and Plinth
3-1 Placing of Rebar including fabrication & ton 1.56 1536334 2396681
beam) 16mm, 10mm & 8mm erection
Superstructure (long column & roof beam)
3-2 Placing of Rebar including fabrication & ton 1.77 1536334 2719312
16mm,10mm & 8mm erection
Window sill, lintel beam & sunshade (10mm
3-3 Placing of Rebar including fabrication & ton 0.20 1536334 307267
& 6.5mm) erection
3-7 Transportation cost for Test pieces of Re-bar All kind of Re-bar, 1m-3nos .(16mm & no. 6.00 3000 18400
10mm)
Subtotal 5441660
4 Formworks
Foundation (footing, short column and plinth
4-1 Formwork include material (2 times) Sqft 1,253.18 1550 1943477
beam and ramp)
4-2 Superstructure (long column & roof beam) Formwork include material (2 times) Sqft 1,634.51 1550 2534858

4-3 Window sill, lintel beam & sunshade Formwork include material (2 times) Sqft 75.43 1550 116980
Subtotal 4595315
Price Amount
No Description Specifi Unit Quantity
cation (Kyats (Kyats)
5 Masonry work
Brick under ground beam and other/(1:3) 288254 3035318
5.1 Retaining Wall (9" thick), Stair & Ramp Sud 10.53
cement motar
Brick wall (4.5" thk;) for External/ internal t=4.5", class room partation with (1:3) 2150.5 3945915
5-2 Sqft 1,834.88
wall cement motor at every 4th course
Subtotal 6981233
6 Finishing work
Plastering work for (external wall, internal 403 1839456
6.1 t= 3/4", (1:3) cement motor finish Sqft 4561.10
wall, stairs and ramp)
MD - 3 no. 196 115783
6.2 Door and Window Chowket (5"x2") Pyinkado W - 10 no. Rft 590.45
LV - 3 no.
MD - 3 no. 196 71711
Coal tarring & X-met work - (Door and
6.3 W - 10 no. Rft 365.70
window Chowkets)
LV - 3 no.
Teak panelled Door fully pannel leaves & 4085 906839
MD - 3 no.(4'-0"x7'-0")
window fully 5mm thk, glass and funligth
6.4 Sqft 222.00
fully 5mm thk glass accessories fixing work
W - 10 no.(1'-6"x4'-0")
(thk: 1.5") and etc.
6.5 Concrete Block fixing work (0'- 9"x 0'-9") concrete block Sqft 51.65 1162 60000
shera board (6mm)thk:,Hollow (38mmx 839.5 217600
38mmx 1.2mm) @4'c/c,
6.6 Ceiling work (38mmx20mmx1.2mm)@2'c/c, c- channel Sqft 2,592.00
frame, 12mm thread rod & 2'x2' manhole ,
2'x2' ventilation & etc accessories fixing
work
Stainless Steel (2" dia pipe, 1"dia pipe & etc) 702 33164
6.7 Wheel Chair Hand Rail (3'-0"ht) Rft 47.25
accessories fixing work - Wheel chair hand
rail
6.8 Installation of Donation of Sign Board Decorative stainless steel Sht 1.00 96476 96476
(4"x2"~ 100mmx48mmx5mm thk;) U-beam 1137 2878654
Rafter (MS)@10'C/C , (C-
75mm38mmx15mmx2mm) Lip Channel
6.9 Steel Structure for roofing Purlin @ 2'-6" C/C , 50mmx50mmx2mm Sqft 2,531.28
angle purlin cleat, (6"x6"x8mm) thk: Gusset
plate welded to Main Rafter and 2-16mm Ø ,
Anchor bolts and etc accessories fixing work

0.42mm thick 4-angle color roofing sheet , 604 1528544


6.10 Roofing sheet Sqft 2,531.28
Accessories workand etc
0.42mm color metal sheet ridging (112.5 Rft) 1800 571093
and
6.11 Ridging work and Gutter work 6" width metal plain sheet gutter (194.67Rft) Rft 317.17
and 3" downtake pipe with accessories
Putty work / Wall, column, beam ceiling, installation work & etc
Surface preparation before painting with 274 2008063
6.12 Sqft 7,317.66
stair,sunshade putty (2- coats)
Painting work / Wall, column, beam ceiling, 365 2572000
6.13 Plastics Emulsion paint (OE)- (3 coats) Sqft 7,317.66
stair,sunshade
Surface preparation before 132 120249
6.14 Painting work / For all wood work Sqft 914.70
Surface preparation before Enamel 154 300551
6.15 Painting work / For all iron work Sqft 1,302.65
painting (2-coats)
Teaching white board (8'-0"x4'-0")- 3 with white board frame and etc. 50000 150000
6.16 sheets 3.00
sheets accessories installation work
Subtotal 13470183
Subtotal 43,111,018
Transportation 2.5 % 1,077,775
Charge
Supervision Charge 2.5 % 1,077,775

Commercial Tax 5 % 2263328.4

Grand Total base on real price at site 47,529,896.40


Price Amount
No Description Specification Unit Quantity
(Kyats) (Kyats)
Please fill in here if you have any additional items

1
2
3

Remarks

1 Indirect cost of the contractor such as Transportation, Site supervision,


2 General administration and other expenses should be included in the unit price.
3 The bidders are expected to check the quantities by items during site visit.
4 Any descripancies between this BOQ and actual site requirement should be reported before submitting the bid.
5 Bid submitted without site visit may be at the risk of bidders.
6 All unit price to be fill in this form is in Myanmar (Kyats).
7 If bidder want to add other items, bidder can add them as necessary.