Professional Documents
Culture Documents
2 Airwasher 1
2.1 2 Bend PVC Eliminator mm (2550x2250) 840 840
2.2 Inspection Window with mountings (1155x2410) Nos 1 9000 9000
2.3 Prefilters (500x500) Nos 20 1500 30000
2.4 Prefilters (500x250) Nos 5 900 4500
2.5 Left Panel (1160x2410) Nos 1 12000 12000
2.6 Canvas (1270x1270) Nos 1 10000 10000
2.7 Damper (1270x1270x150) Nos 1 14000 14000
2.8 Canvas Connected Duct Piece (1270x1270) Nos 1 14000 14000
2.9 Connecting Duct Piece (1270x1270) Nos 1 14000 14000
120000
3 Airwasher 2
3.1 2 Bend PVC Eliminator mm (4200x1800) 1120 1120
3.2 Prefilter (600x600) Nos 18 1800 32400
3.3 Prefilter (600x350) Nos 3 1050 3150
3.4 Outer Base Sheet mm (4200x2600x250) 18" 23300 23300
100000
4 Airwasher 3
4.1 2 Bend PVC Eliminator mm (3150x2000) 930 930
4.2 Support Channel (3150) Nos 4 4000 16000
4.3 Damper (1270x1270x150) Nos 1 14000 14000
4.4 Roof Support (2170) Nos 2 2500 5000
4.5 Outer Base Sheet mm (3150x2900x250) 18" 15600 15600
4.6 Prefilter (500x500) Nos 24 1500 36000
100000
5 Airwasher 4
5.1 Prefilter (620x600) Nos 18 1950 35100
5.2 Prefilter (620x300) Nos 3 1100 3300
5.3 Outer Base Sheet mm (2250x2610x250) 18" 9000 9000
5.4 2 Bend PVC Eliminator mm (2250x1950) 700 700
100000
6 Airwasher 5
6.1 Prefilter (600x510) Nos 24 1500 36000
10000
7 Airwasher 6
7.1 2 Bend PVC Eliminator mm (2350x5050) 1680 1680
7.2 Prefilter (500x500) Nos 40 1500 60000
7.3 Prefilter (500x250) Nos 10 900 9000
60000
8 Airwasher 7
8.1 Prefilter (600x570) Nos 32 1700 54400
8.2 Honey Pad mm (5000x2300) 5500 5500
50000
9 Airwasher 10
9.1 Prefilter (610x610) Nos 12 1800 21600
9.2 Prefilter (610x305) Nos 3 900 2700
10000
LIST OF EXCLUSIONS
Kindly note that the
All masonry work/civil works such as supports for the condensing units, cutting away and making good of walls/ floors/ slabs and making & closing of
1
trenches etc.
2 Electrical work except control panel
3 Electric power and water for the erection and commissioning of system.
4 Warranty on consumable items such as belts, filters, Cellulose paper pads, canvas etc.
5 Water and electricity supply connections up to equipments.
6 Lockable storage space for safe custody of material and working space for our workers.
7 Any other items not specifically mentioned in our offer but require completing the work.
8 Scaffolding and crane.
9 Any under deck or over deck insulation, thermal or acoustic insulations works for false ceiling or walls etc.
10 Any kind of false ceiling works, boxing work, wooden framework/carpentry work.