Professional Documents
Culture Documents
SUBCONTRACTOR:
Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 PHYSICAL CHECKS
a. Check all electrical components (equipment such
as conduits, wires, trunking, switches, socket,
outlets etc.) connected to final circuits for the
protection and damage
b. Check the installation of the DBs.
c. Check internal wiring for strong connection
identification, labelling etc.
d. Check that all metallic components are
earthed/bonded.
2 POLARITY CHECK
a. Check that all single pole switches are installed in
the live conductor.
3 CONTINUITY OF PROTECTIVE CONDUCTORS
a. For all final circuits check continuity of the
protective conductor from the furthest point to the
main earth terminal of the DB by a DC ohm meter.
b. Repeat (3a.) above for all ring final circuit
conductors.
c. Tabulate the readings.
4 INSULATION RESISTANCE TEST
a. This test is preferably carried out before the light
fittings or current using equipment are installed.
THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH
CONTRACT SPECIFICATIONS.
SUBCONTRACTOR:
Checked
ITEM POINTS TO BE CHECKED by REMARKS
Cont’d
b. Measure insulation resistance between phase,
neutral and earth by a 500V meggar.
c. Repeat (4b.) above for all circuits and tabulate.
THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH
CONTRACT SPECIFICATIONS.