Professional Documents
Culture Documents
INSTITUTE OF ENGINEERING
THAPATHALI CAMPUS
SUBMITTED BY:
Sapan Pokharel THA075BCE115
Subodh Subedi THA075BCE125
Tejendra Bist THA075BCE138
Vivek Pokharel THA075BCE142
Yuken Shrestha THA075BCE143
Yukesh Chaulagain THA075BCE144
April 2023
COPYRIGHT
The authors of this report have granted permission for its free availability for inspection
by the Department of Civil Engineering, ThapathaliCampus Library. Additionally, the
authors have agreed that the Head of the Department where the report was completed
may authorize by the professors whosupervised the work, or in their absence, extensive
copying of this report for scholarly purposes. Proper recognition must be given to the
authors of the report or to the Department of Civil Engineering, Thapathali Campus in
any use of this report. It is strictly prohibited to copy or publish this report for financial
gain without written approval from both the Department of Civil Engineering,
Thapathali Campus and the authors of the report.
If you wish to request permission to copy or use any material from this report, either in
whole or in part, please direct your request to:
Head of Department
Dr. Indra Narayan Yadav, PhD
Department of Civil Engineering
Thapathali Campus
Institute of Engineering
Kathmandu, Nepal
TRIBHUVAN UNIVERSITY
INSTITUTE OF ENGINEERING
THAPATHALICAMPUS
DEPARTMENT OF CIVIL ENGINEERING
CERTIFICATE
This is to certify that this project work entitled Design of RC T-Girger Bridge" has
been examined and declared successful for the fulfilment of academic requirement
towards the completion of Bachelor Degree in Civil Engineering.
iii
ABSTRACT
This report covers the analysis and design of the RC T-Girder Bridge, as well as the
design of its components The data obtained from LRBSU has been verified through
field observation, and a combination of structural, hydraulic, and geotechnical
processes have been used to analyze the data. The bridge's components have been
designed by the relevant IS and IRC codes of practice considering IRC Class A and
Class 70R vehicles. The effective width method has been used for the analysis of the
cantilever and restrained slab respectively. The analysis of the T-beam has been done
using Courbon's method and Influence Line Diagram. The laminated pad elastomeric
bearing has been chosen and designed as per the IRC code. Furthermore, the bridge
includes two identical abutments and a hammerhead pier dividing the bridge into two
equal spans which have been specifically designed to withstand both basic and seismic
load combinations. Open footing has been provided for both the abutment and pier. The
outcomes have been displayed through drawings.
iv
SALIENT FEATURES
Location
Geographical Information
• Latitude: 27o31’47.54’’ N
• Longitude: 85o05’57.98’’ E
• Classification of Road : DRCN
• Type of the Road Surface: Earthern
• Terrain/ Geology: Hilly
Information on Structure
v
Design Data
vi
TABLE OF CONTENTS
COPYRIGHT .................................................................................................................. i
CERTIFICATE ..............................................................................................................ii
ACKNOWLEDGEMENT ........................................................................................... iii
ABSTRACT.................................................................................................................. iv
SALIENT FEATURES .................................................................................................. v
LIST OF FIGURES ...................................................................................................... ix
NOTATION .................................................................................................................xii
1 Introduction ............................................................................................................ 1
1.1 Background ..................................................................................................... 1
1.2 Title of Project ................................................................................................. 2
1.3 Objectives ........................................................................................................ 2
1.3.1 General Objective .................................................................................... 2
1.3.2 Specific Objectives .................................................................................. 2
1.4 Assumptions and limitations ........................................................................... 3
2 Methodology ........................................................................................................... 4
2.1 Acquisition of Data ......................................................................................... 4
2.2 Structural Planning and Preliminary Design ................................................... 5
2.3 Idealization and Analysis of Bridge Structure ................................................ 5
2.4 Design, Detailing and Drawings ..................................................................... 6
2.5 Project Flow Chart .......................................................................................... 7
3 Acquisition of Data ................................................................................................. 8
3.1 Topographic Study and Engineering Study .................................................... 8
3.1.1 Location Details of Bridge Site................................................................ 8
3.1.2 Topography .............................................................................................. 8
3.1.3 Engineering Survey Data ......................................................................... 9
3.2 Geological and Geotechnical data ................................................................. 10
3.2.1 Bore hole log .......................................................................................... 11
3.2.2 Safety against shear failure: ................................................................... 13
3.2.3 Settlement criteria .................................................................................. 14
3.3 Hydrological Study Data and Hydraulic Design ........................................... 15
3.3.1 Catchment Characteristics ..................................................................... 15
vii
3.3.2 Hypsometric Data of Catchment ............................................................ 17
3.3.3 Rainfall Analysis .................................................................................... 18
3.3.4 Design Flood .......................................................................................... 25
3.3.5 Hydraulic Deign ..................................................................................... 30
3.4 Traffic Study Data ......................................................................................... 36
3.5 Design Data . .................................................................................................. 36
4 Preliminary Design ............................................................................................... 37
4.1 Selection of Materials: .................................................................................. 37
4.2 Material Properties: ....................................................................................... 37
4.3 Preliminary Sizing of Superstructure Components: ...................................... 38
5 Analysis and Design of Bridge ............................................................................. 43
5.1 Analysis and Design of Superstructure ......................................................... 43
5.1.1 Analysis and Design of Deck Slab......................................................... 44
5.1.2 Analysis and Design of Longitudinal Girders ....................................... 60
5.1.3 Analysis and Design of Cross-Girders ................................................... 88
5.2 Analysis and Design of Bearing .................................................................. 106
5.2.1 Selection of Bearing and Design Method ............................................ 106
5.2.2 Design of Elastomeric Bearing ............................................................ 106
5.3 Analysis and Design of Seismic Arrester .................................................... 119
5.4 Analysis and Design of Sub-Structure ........................................................ 122
5.4.1 Analysis and Design of Abutments...................................................... 122
5.4.2 Analysis and Design of Pier ................................................................. 141
6 REFERENCES . .................................................................................................. 163
7 CODES AND STANDARDS ............................................................................ 164
ANNEX A . ................................................................................................................. 165
ANNEX B . ................................................................................................................. 203
viii
LIST OF FIGURES
Figure 3-10: Stage-Discharge Relationship Curve for River at Bridge Site ............... 32
Figure 5-3: Vehicle wheel arrangement for Shear force design in Class-A................ 46
Figure 5-5: Vehicle wheel arrangement for Shear force in Class 70-R wheel ............ 48
Figure 5-7: Vehicle wheel arrangement for Shear force in 70-R Bogie...................... 50
Figure 5-9: Vehicle wheel arrangement for Shear force in 70-R Track...................... 52
Figure 5-15: ILD for BM at 10.39m and Positioning of Class A load ........................ 64
ix
Figure 5-16: ILD for BM at quarter span and Positioning of Class A load ............... 65
Figure 5-17: ILD for SF at support and Positioning of Class A load ......................... 65
Figure 5-18: ILD for SF quarter span and Positioning of Class A load ..................... 66
Figure 5-20: ILD for BM at 11.21m from support and positioning of 70R Wheeled load
...................................................................................................................................... 67
Figure 5-21: ILD for BM at quarter span and positioning of 70 Wheeled load ......... 67
Figure 5-22: ILD for SF at support span and positioning of 70R Wheeled load ........ 68
Figure 5-23: ILD for SF at quarter span and positioning of 70R Wheeled load ........ 68
Figure 5-25: ILD for BM at mid-span and positioning of 70R Tracked load ............. 70
Figure 5-26: ILD for BM at quarter span and positioning of 70R Tracked load ........ 70
Figure 5-27: ILD for SF at support and Positioning of 70R Tracked load ................. 71
Figure 5-28: ILD for SF at quarter span and Positioning of 70RTracked load.......... 71
x
Figure 5-41: End Cross Girder Loaded With Dead Load for Bearing Replacement Case
...................................................................................................................................... 99
Figure 5-42: End Cross Girder Loaded With Dead Load ......................................... 100
Figure 5-43: Vertical Reaction on a bearing due to braking load ............................ 108
xi
NOTATIONS
xiii
1 Introduction
RC T-girder bridges are a common type of bridge structure that are widely used in
modern transportation infrastructure. These bridges are known for their exceptional
strength and durability, making them ideal for carrying heavy loads.
The use of reinforced concrete in the construction of T-girder bridges allows for a
high degree of customization, as the material can be easily molded to create complex
shapes and forms. Additionally, the inherent durability of reinforced concrete ensures
that these bridges can withstand years of heavy use without significant maintenance or
repair.
1.1 Background
The design and construction of bridges have been essential for the development of
modern transportation infrastructure. The use of bridges has allowed people and
goods to travel more easily and efficiently, enabling economic growth and societal
advancement.
The development of T-girder bridges, specifically, can be traced back to the mid-20th
century, with the advent of new technologies and construction techniques. The T-
girder configuration was initially designed to address the shortcomings of previous
bridge designs, such as the use of bulky steel trusses or concrete arches.
1
The use of reinforced concrete in T-girder bridges also allowed for greater
customization and flexibility in design. Engineers could create bridges with varying
spans, widths, and deck heights, providing greater versatility in meeting the needs of
different transportation infrastructure projects.
In recent years, there has also been a growing focus on incorporating construction
practices in bridge design, including the use of recycled materials and energy-efficient
construction techniques.
1.3 Objectives
The overall goal of this project is to design T-Beam bridge as part of a bachelor's degree
in Civil Engineering final year project work mandated by the Institute of Engineering's
syllabus.
In addition to the above-mentioned goals, this project's specific goals are listed below.
• To acquire sufficient topographical, hydrological, and geotechnical
information from secondary sources.
2
1.4 Assumptions and limitations
This project will have following assumptions and limitations:
• The strength and durability test for the material to be used will not be carried
out, rather it is assumed to be the same as given in relevant IS code.
3
2 Methodology
Primary data collection involved on-site observation and interviewing local people to
understand their needs and bridge requirements. Additionally, the span, alignment,
and depth of foundation for the bridge were measured and arranged, and a
topographic survey of the bridge site was conducted.
a) Desk Study
Desk study was conducted, which involved a comprehensive literature review, past
report analysis, and the study of design codes, topography, catchment area, road and
river characteristics, and data provided by LRBSU.
b) Hydrological Analysis
Hydrological analysis was performed, utilizing data provided by LRBSU and the
Department of Hydrology and Meteorology. The following important parameters/data
are collected by hydrological analysis.
• Maximum discharge
• Design discharge
• Linear waterway
• Scour depth
c) Geotechnical Study:
LRBSU provided all the data in the form of a soil test report. It included Dynamic
Cone Penetration Test (DCPT), sieve analysis, direct shear test, water content test,
and other investigations. Borehole log was available for both the banks of the river.
These were used to calculate safe bearing capacity of the soil, scour depth, etc.
4
2.2 Structural Planning and Preliminary Design
During the structural planning and preliminary design phase, we carefully considered
factors such as waterway requirements and geological conditions of the river-bed.
Based on our evaluation, we opted for a T-girder bridge with two spans, supported by
two abutments and an intermediate pier.
The idealization and analysis of the bridge structure was a crucial stage in the design
process. Initially, we idealized the loads, structural components, and support
conditions. This involved developing an accurate and detailed model of the bridge,
incorporating the materials, dimensions, and other relevant factors.
5
Influence line diagram helped us determine the longitudinal placement of the live load
to obtain the maximum response. Effective width method was used to analyze the
cantilever slab and the restrained slab. Courbon's method and Influence Line Diagram
was utilized to determine the transverse distribution of load to the main girder.
Overall, the idealization and analysis of the bridge structure was a complex and
detailed process that required extensive knowledge of structural engineering
principles and relevant design codes. Our team carefully evaluated each component to
ensure the safety and effectiveness of the final design.
The limit state design method has been used in the design of structural components for
bridges. The following codes were used:
• IRC 6-2017
• IRC SP 105-2015
• IRC 112-2020
• IRC SP 114-2018
AutoCAD has been used to create plan, sectional and detailed drawings of various
bridge components on a standard scale.
6
2.5 Project Flow Chart
7
3 Acquisition of Data
Topographic map of the bridge site was provided by LRBSU. We conducted cross
section and longitudinal section levelling of the river at proposed bridge axis for
verification.
The bridge site over Rapati Khola Bridge is located in Bhimphedi Rular Municipality,
Makwanpur district. The geographical co-ordinates of the proposed bridge site are:
Latitude = 27°31’47.54’’N
Departure = 85°05'57.98"E
3.1.2 Topography
The bridge site lies in the flood plain of the river with fairly level topography. The river
seems to carry large boulder during monsoon, so a large number of boulders were
deposited on the site. River is meandering at 300m U/S of the site and straight at D/S.
8
3.1.3 Engineering Survey Data
X-SECTION
855
854
853
852
851
850
849
848
847
846
40 30 20 10 0 10 20 30 40 50
RL 853.822 852.804 851.886 849.322 849.062 849.254 851.075 851.292 851.841 852.815
9
L-PROFILE
853
852
851
850
849
848
847
846
845
0+030 0+015 0+000 0+015 0+030 0+045 0+060
RL 847.779 848.346 849.062 849.917 850.739 851.571 852.323
We were provided soil test report conducted by Agni Boring and Soil Test Pvt Ltd.
Borehole log and laboratory test data and their analysis were provided by LRBSU.
10
3.2.1 Bore hole log
11
Using these N values, allowable safe bearing capacity is calculated. For safety in
bearing, two criteria must be fulfilled.
12
3.2.2 Safety against shear failure:
Teng relation for shear failure gives bearing capacity for different width of footing
and the depth of soil:
Depth (m)
Width of
footing B(m)
2 3 4.5 6 7.5
N 34 34 35 36 38
13
13.50 123.53 143.65 183.76 227.53 289.51
For rivers with gravel bed, the maximum permissible settlement is 40mm. For that
following equation is used: -
qa = 720 (N-3) ( (B+1) / 2B )2 Kd R’w
Where qa = Net allowable bearing pressure in psf for 1 inch settlement and B in ft.
Kd = (1+ D/B)
Since this formula gives qa for 1 inch (25mm) settlement, Qa = qa x 40/25
Depth (m)
Width of footing
B (m)
2 3 4.5 6 7.5
14
13 26.34 28.10 31.72 35.52 40.65
It can be seen that allowable pressure is lower in settlement criteria. Therefore, 40mm
settlement criteria is used to calculate bearing capacity of the soil.
The hydrological data of the catchment area is in the form of annual precipitation data
acquired from DHM provided by MLRBP. Hypsometric data of the catchment has
been deduced from Google Earth Pro and Global Mapper. The design was performed
by synthesizing the provided data by MLRBP in the early stage of the design. The
field observation was done after certain period of time and was checked with the
synthesized data and was corrected.
The bridge site in Rapati Khola is located at Latitude of 27031'47.54"N and Longitude
of 85005'57.98"E. The outlet elevation of the river at which bridge is situated is about
849.062m (from Google Earth Pro) and the elevation of headwater (Highest Point) is
about 2055.392m. The catchment area up to bridge site estimated by GIS is about
56.152 sq.km and main channel length is about 7.996 km. The perimeter of the
catchment is 36.64km. The stream slope of the river given by GIS is 8.09%. The field
observed slope is 5.03% and the time of concentration found with the help of Kirpich
equation is 39.45 minutes.
15
Figure 3-4: Catchment of Rapati Khola at proposed bridge site from
Google Earth Pro
16
Figure 3-6: LSAT Image of the catchment
The data presented below have been abstracted from Google Earth Pro and GIS.
17
Catchment area under different land use
Barren 10.932
Snow capped 0
Settlement 1.310
Chisapanigadi rain gauge station lies inside the catchment whereas Daman, Rajaiya
and Daman lies outside of the catchment. The data were acquired from the MLRBP
for all the stations. The data obtained from Raijaiya and Lele were less than 25 years
while the data for Daman and Chisapanigadi was for more than 25years.
18
Area
Index Percent
SN Name of the Station
No. Weightage
(sq.km.)
3 925 Rajaiya 0 0
4 1075 Lele 0 0
19
Calculation of Design Rainfall (100 years return period)
Weibull Method
Chisapanigadi and Daman were used for rainfall analysis. Plot of extreme rainfall and
return period was made and extreme rainfall values were taken from the best fit curve.
Chisapanigadi:
Extreme
Extreme Probability Return
Rainfall in Rank
Station Year Rainfall (P)= Period,
decending (m)
(mm) (X) m/(N+1) T=1/P
order
20
1999 262.10 131.00 18 0.58 1.72
Chisapanigadi
500
450
400 y = 99.107ln(x) + 63.585
Extreme Rainfall (mm)
350
300
250
200
150
100
50
0
1 10 100
Return Period,T
21
Daman:
Extreme
Extreme Return
Rainfall in Rank Probability,
Station Year Rainfall Period,
decending (m) P= m/(N+1)
(mm) T=1/P
order
22
2003 129.00 76.00 22 0.71 1.41
Daman
400
350 y = 93.804ln(x) + 36.203
Extreme Rainfall, mm
300
250
200
150
100
50
0
1 10 100
Return Period, T
23
Gumbel Method:
Chisapa- 469.80
157.22 85.549
nigadi 0
3.65
0.5362 1.1124 4.6
32
433.22
Daman 124.88 84.403
0
Chisapa
2.1462 0.207 0.3978 2.6184 2.6872 486.631
nigadi
24
Using Mononob’s method, calculating rainfall intensity:
2
𝑅100 24 3
I= ∗ (𝐷)
24
2
511.015 24 3
= ∗ (0.659)
24
= 233.941mm/hr
Thus, the design rainfall intensity is 233.941mm/hr.
The guidelines provided in cl.3.2 Nepal Bridge Standards, NBS-2067, for all
permanent bridges, flood having return period of 100 years has been used as design
flood for the bridge. The design life for the permanent bridge must be 50 years as
provided in the NBS-2067.
1
R = 1 − (1 − )n
T
1 50
R = 1 − (1 − 100) = 39.49%
WECS/DHM (1990)
Total catchment area of the river section at a proposed bridge site = 56.152 sq.km
Catchment area below 3000m elevation at a proposed bridge site (A) = 56.152 sq.km
Return Period (T) = 100 years
Q100 = 14.639 × (A + 1)0.7342
= 14.639 × (56.152 + 1)0.7342
= 285.446 cumecs
DHM (2004)
25
PCJ (1996)
In determining the floods of Rapati Khola, this method has been used for the average
value of hourly rainfall intensity at two representative stations, which are located near
the basin area and have comparatively good series of rainfall data. Using this method,
the maximum rainfall design discharge Qp for the required exceedance probability ‘p’
has been computed using the equation,
Qp = 16.67 × ap × op × ∅ × F × k f
Maximum Hourly
Station Name Average
Intensity in mm/min, ahr
Chisapanigadi 3.899
3.853
mm/min
Daman 3.807
= 3.482 mm/min
Kf = 0.9962
Qp = 16.67 × ap × op × ∅ × F × k f
26
= 531.103 cumecs
𝐐 = 𝐊 × 𝐀𝐛
Where, K and b are constants depending upon return periods
For 100 years return period,
K= 21.5181 b = 0.7281
Q = 21.5181 × 56.5120.7281 = 406.011 cumecs
Dicken’s Method
3⁄
Q = CD × A 4
A = 56.152 km2
CD = 11.37 (taken as for northern India)
3⁄
Q = CD × A 4
3⁄
= 11.37 × 56.152 4
= 233.229 cumecs
1185
Where, C = 2.342 × log(0.6T) × log ( )+4
𝑝
a+6 0+6
p= × 100 = × 100 = 10.685%
A+a 56.152
Where, a = snow covered area = 0
A + a = catchment area in sq. km = 56.152
T = return period in years = 100 years
1185
C = 2.342 × log(0.6 × 100) × log (10.685) + 4 = 11.753
3⁄
Q = 11.753 × 56.152 4 = 241.086 cumecs
The method is used for the Maharastra State of India, but still used in Nepal due to
similarity.
27
124 × A 124 × 56.152
Qp = = = 853.506 cumecs
√A + 10.4 √56.152 + 10.4
Fuller’s Method
0.8
𝐴 0.3
𝑄 = 1.03 × 𝐴 (1
× + (0.8 × log10 𝑇)) × (1 + (2 × ( ) ))
2.59
0.8
56.152 0.3
Q = 1.03 × 56.152 × (1 + (0.8 × log10 100)) × (1 + (2 × ( ) ))
2.59
= 405.373 cumecs
Rational Method
Since the catchment is big, this method is only used for comparison.
Area in sq.km Value of Weighted Average
S.N Type of land
coverage A C CA C
28
I = 233.941 mm/hr
A = 56.152 sq.km
C×I×A 0.407 × 233.941 × 56.152
Q= = = 1473.224 cumecs
3.6 3.6
Among ten methods used above, only seven methods of discharge calculations have
been considered based on suitability with the catchment.
Among seven methods, three methods produced nearest values were used. The
average of these three methods has been used as design discharge.
29
376.282+ 405.373 + 406.011
Design Discharge (Qd) = ≈ 395 m3 /s
3
Hence, Design discharge (Qd) = 395 m3 /s
Hydraulic
Depth RL Area Perimeter Velocity Discharge
Mean
(m) (m) (m2) (m) (m/s) (m3/s)
(m)
30
Estimation of stage from raking curve method and stage-discharge relationship:
Discharge
Depth(G) Y=logQ X=log(G-a) X2 X2 XY
(Q)
Now with the help of discharge-stage relationship i.e. Q =Cr × (𝐺 − 𝑎)β , the stage at
given design discharge is calculated as:
N(ΣXY) − (ΣX)(ΣY)
β= = 2.237
N(ΣX 2 ) − (ΣX)2
ΣY − (β × (ΣX))
b= = 1.97
N
Cr = eb = 7.208
Q = Cr × (𝐺 − 𝑎)β
31
4
3.5
3
HFL 2.5
2
y = -1E-06x2 + 0.0037x + 0.5459
1.5
1
0.5
0
0 200 400 600 800 1000 1200 1400 1600 1800
Discharge
(c) As per the clause 106.5.1.6, IRC 05: 2015, in a hilly terrain, the minimum waterway
under the bridge should be kept same as the linear waterway at HFL. The linear
waterway at HFL (851.062m) has been found to be 34.086m from AutoCAD.
So, Linear Waterway = 34.086m
32
3.3.5.3 Check for afflux
3.3.5.4 Freeboard
Mean particle size obtained from Geotechnical Report provided by the MLRBP,
i.e., d50 = 22mm
Lacey's Silt factor, f = 1.76√dmm = 1.76 × √22 = 8.255
The data provided in geotechnical report hasn’t provided d90 material. So, the value is
being calculated through the references from empirical calculations.
d90 = 1.88×d60 =1.88×30=56.4mm
33
Lacey-Inglish Formula
1 1
q2 3 ( 12.046 )2 3
Scour Depth, dsm = 1.34 ( ) = 1.34 × ( ) = 3.484m
f 8.255
This method is not suitable for the bed material particle mean size greater than
4mm.Lacey-Inglish formula is satisfactory to estimate mean scour depth for
meandering alluvial rivers with loose non-cohesive sandy materials, the results from
this method is not satisfactory for rivers transporting sediments and for gravel-bed
rivers. So, this method is not appropriate for the given site.
Kellerhal's Formula
q0.8 (12.046)0.8
Scour Depth, D = 0.47 = 0.47 × = 2.121m
(d90 )0.12 (56.4)0.12
Correction:
W 0.61
Corrected scour depth, dcorr = D × ( )
P
where,
W = linear waterway calculated from Kellerhal's method
= 3.26 × √410.603
= 66.058m
P = Linear waterway provided = 44m
66.058 0.61
dcorr = 2.121× ( ) = 3.176m
44
Kothyari Formula
34
dse b 0.67 D −0.6
= 0.88 × ( ) ×( ) × α−0.3
D d d
2 0.67 2 −0.6
= 0.88 × ( ) ×( ) × 0.932−0.3 = 0.759
22 22
∴ dse = 0.759 × 2 = 1.518m
Dse = maximum scour depth below HFL = dse + D = 1.518 + 2 = 3.518m
. The river bed of proposed site is composed with gravels and for such rivers,
Kelleharl’s formula and Kothyari formula (2007) can be used to estimate scour depth.
Kothyari formula involves more assumptions than Kellerhal’s formula. So, for such
reasons, Kellerhal’s scour depth relation has been employed to determine scour depth
as the parameters used in Kellerhal’s formula are known.
Hence, maximum scour depth below HFL = 3.176m
Maximum scour depth for abutment = 1.27 × d = 1.27 × 2.215= 4.03m
Maximum scour depth for pier = 2 × d = 2 × 2.215 = 6.352m
2 HFL 851.062 m
4 Afflux 0.827m
5 Freeboard 2.0 m
35
3.4 Traffic Study Data
No specific study on traffic. The bridge planned on project site has been planned as
according to Nepal Road Standard 2071. It has been designed with clear carriage way
of 7.5 width and 1.75m footpath on both sides.
36
4 Preliminary Design
The materials below are selected as per the requirements needed on the construction of
the bridge. The selection is based on the construction practice, literature review,
supervisor’s consult and available materials on the market. Following materials are
selected for design:
A: Concrete (Should be Design as clause 6.4.2 and Clause 18.5, IRC 112 and values
obtained by standards mentioned in IS 516:1959 from sample tests.)
37
4.3 Preliminary Sizing of Superstructure Components:
a. Carriage width:
Carriageway of 7.5m is taken. (Traffic>100 vehicle pcd so 3.75m per lane for DRCN
NRRS 2071 Table 6.1)
b. Wearing coat:
Asphalt concrete wearing coat thickness of 50mm at edge and 3% camber and 2.5%
camber at second lane from both edges resulting of crown thickness of 150mm
(cl.1309 of standard specification of road and bridge works)
d. Drainage Spout:
Drainage spout is placed @5000mm c/c spacing throughout span but kept at
2000mm from the edge of span at both sides before Kerb.
38
e. Kerb:
f. Slab deck:
g. Main girder:
The thickness of the web is not be less than 250mm. So, we provide width of web is
300mm.
The bulb is provided as width of 700mm and height of 200mm and tapered to web
section within height of 150mm.
Number of girders provided is 3.
Depth of main girder is 1650mm.
Center to center spacing distance shall not be less than 1/20 of span which is 1.1m
generally.
39
The spacing provided be:
Total deck width−cantilever slab width×2 11−2.25×2
= = = 3.25m
no.of girder−1 3−1
h. Cross girder
Minimum width of cross girder should not less than be minimum web thickness of
main girder. So we adopt the web width of 300mm.
Number of cross girder is 4. 2 intermediate cross girders and 2 end cross girders are
provided.
The center to center spacing between two consecutive cross girders is 7300mm.
Depth of both intermediate and cross girder practiced be:
0.75×depth of main girder = 1238mm (JD victor)
We adopt the depth of cross girder as 1240mm.
i. Expansion joint:
j. Bearing size
k. Abutments:
• Total height of abutment = Max scour depth + free board +grip length+ depth
of main girder + thickness of bearing &pedestal
= 4.762 + 2 +2 + 1.65 +0.5 (values are preliminary
and need further to change)
=10.912 ~ 11.3m
• Material Selection:
40
Since height be greater than 5m, choose RCC abutment. From below height
data, RCC is preferred. So, we choose M20 Concrete and Fe 500D rebar.
• Seating width:
Minimum seating width = 305+2.5L + 10H (cl.219.9, IRC 6)
= 305 + 2.5×22 + 10×11.3
= 473mm
From cl.910.8, IRC 78-2014
Seating width = Bearing width + minimum projection of cap + width of
expansion join + 150mm
= 300 + 75 + 40 + 150 = 565mm
Adopt 750mm seating width. (Taking projection for future jacking condition
while repairing bearing parts)
• Dirt wall:
Height of dirt wall = depth of girder + bearing thickness - approach slab
= 1650 +500 – 300
= 1850 mm
Thickness of dirt wall > 200mm (cl.710.6.4, IRC 78-2014, Clause 710.6.4)
>Height of dirt wall / 7 = 264.285 mm
Adopt the thickness of dirt wall be 300mm.
l. Footing:
41
The thickness must be greater than 200mm (cl. 710.8.2, IRC 78). Adopt thickness of
500mm.
Length of abutment = c/c distance between girders + width of bearing + 2×clearance
= 6.5 + 0.3 + 2×0.5
= 7.8m
Adopt length of abutment as width of deck slab i.e. 11000mm.
m. Approach slab:
n. Pier
Type of pier:
RCC single column hammer head pier.
42
5 Analysis and Design of Bridge
Main Girder: It is primary load bearing member of the bridge, spaced at regular
intervals along the length of the bridge. A and C are exterior main girders and B is the
intermediate main girder. 3 main girders are spaced @ 3.25m.
Deck Slab: It is a concrete slab that integrated on top of the T-girders to provide for a
driving surface and footpath. Restrained Slab (3.25 x 7.3) is provided between the
girders and beyond that Cantilever Slab (2.25 x 22) is provided.
Design Loads
There are 6 restrained slabs per span. Each slab is supported on girders on each side- at
7.3m c/c by cross girders and 3.25 m c/c by main girders.
Slab has been designed for IRC Class A and 70R loadings.
General Terms in LL Analysis:
Effective Span length, lo = 3.17 m
Width of the slab, b = 7.15 m
Track length perpendicular to traffic direction = W
Track length along traffic direction= B
Effective width of dispersion of a wheel= bef
Effective length of dispersion of a wheel, lef = W+ 2* (0.22 + 0.1)
Distance of the center of gravity of the concentrated load from the nearer support = a
Continuity Factor, C.F. = 0.80
44
The BM is maximum at center of span when CG of load acts at center and SF is
maximum at supports when loads are arranged in such a way that dispersed contact
width of its outmost wheel up to the bottom of wearing course just touched the support
edge.
IRC Class A:
𝑏 7.15
= = 2.29 so, α = 2.60 (IRC: 112 Annex B 3.2)
𝑙 3.17
3.25
a= = 1.63 m
2
b1 = 0.250 + 2 * 0.1 = 0.45 m
𝑎 1.63
bef = α ∗ a (1 − 𝑙 ) + 𝑏1 = 2.60 ∗ 1.63 (1 − 3.17) + 0.45 = 2.51 m
𝑜
2.51
(Since, 1.2 > , there is an overlap.)
2
lef = 0.5 + 2 * (0.22 + 0.1) = 1.14 m
45
2.51 2.51
Net width of dispersion, B = + 1.2 + = 3.71 m
2 2
Net length of dispersion, L = 1.14 m
4.5 4.5
Impact Factor Fraction = = = 0.49 (IRC:6 2017 Clause 208.2)
6+𝑙 6+3.17
Now,
𝑇𝑜𝑡𝑎𝑙 𝐿𝑜𝑎𝑑∗𝐼𝐹∗𝐶𝑜𝑛𝑡𝑖𝑛𝑢𝑡𝑖𝑦 𝐹𝑎𝑐𝑡𝑜𝑟 114∗1.49∗0.8
Intensity of load, ω = = = 32.15 kN/m2
𝐿∗𝐵 3.71∗1.14
ωL 𝑙 ω𝐿2
Bending Moment due to Class A = ∗ − = 23.82 kNm
2 2 8
Figure 5-3: Vehicle wheel arrangement for Shear force design in Class-A
1.14 0.3
a= + = 0.72 m
2 2
𝑎 0.72
bef = α ∗ a (1 − 𝑙 ) + 𝑏1 = 2.60 ∗ 0.72 (1 − 3.17) + 0.45 = 1.90 m
𝑜
Now,
𝑇𝑜𝑡𝑎𝑙 𝐿𝑜𝑎𝑑∗𝐼𝐹 114∗1.49∗0.8
Intensity of load, ω = = = 32.29 kN/m2
𝐿∗𝐵 3.71∗1.14
46
48.06∗1.14∗(3.17−0.57)
SF due to Class A = = 36.01 kN
3.17
Thus,
Ultimate BM due to Class A = 1.5 * BMLL + BMDL = 46.18 kNm
Ultimate SF due to Class A = 1.5 * SFLL + SFDL = 70.49 kN
𝑏 7.15
= = 2.29 so, α = 2.60 (IRC: 112 Annex B 3.2)
𝑙 3.17
3.25
a= = 1.63 m
2
b1 = 0.250 + 2 * 0.1 = 0.385 m
𝑎 1.63
bef = α ∗ a (1 − 𝑙 ) + 𝑏1 = 2.60 ∗ 1.63 (1 − 3.17) + 0.385 = 2.44 m
𝑜
47
2.44
(Since, 1.370 > , there is an overlap.)
2
lef = 0.86 + 2 * (0.22 + 0.1) = 1.5 m
2.44 2.44
Net width of dispersion, B = + + 1.37 = 3.81 m
2 2
Net length of dispersion, L = 1.50 m
Impact Factor Fraction = 0.25 (IRC:6 2017 Clause 208.3)
Now,
𝑇𝑜𝑡𝑎𝑙 𝐿𝑜𝑎𝑑∗𝐼𝐹∗𝐶𝑜𝑛𝑡𝑖𝑛𝑢𝑡𝑖𝑦 𝐹𝑎𝑐𝑡𝑜𝑟 170∗1.49∗0.8
Intensity of load, ω = = = 29.71 kN/m2
𝐿∗𝐵 3.81∗1.50
ωL 𝑙 ω𝐿2
Bending Moment due to Class 70R W = ∗ − = 26.97 kNm
2 2 8
Figure 5-5: Vehicle wheel arrangement for Shear force in Class 70-R wheel
1.5 0.3
a= + = 0.90 m
2 2
𝑎 0.90
bef = α ∗ a (1 − ) + 𝑏1 = 2.60 ∗ 0.90 (1 − 3.17) + 0.385 = 2.06 m
𝑙𝑜
𝑏 7.15
= = 2.29 so, α = 2.60 (IRC: 112 Annex B 3.2)
𝑙 3.17
3.25
a= = 1.63 m
2
b1 = 0.220 + 2 * 0.1 = 0.42 m
𝑎 1.63
bef = α ∗ a (1 − ) + 𝑏1 = 2.60 ∗ 1.63 (1 − 3.17) + 0.42 = 2.48 m
𝑙𝑜
49
2.48
(Since, 1.22 > , there is an overlap.)
2
lef = 0.86 + 2 * (0.22 + 0.1) = 1.5 m
2.48 2.48
Net width of dispersion, B = + + 1.22 = 3.70 m
2 2
Net length of dispersion, L = 1.5 m
Impact Factor Fraction = 0.25 (IRC:6 2017 Clause 208.3)
Now,
𝑇𝑜𝑡𝑎𝑙 𝐿𝑜𝑎𝑑∗𝐼𝐹∗𝐶𝑜𝑛𝑡𝑖𝑛𝑢𝑡𝑖𝑦 𝐹𝑎𝑐𝑡𝑜𝑟 200∗1.49∗0.8
Intensity of load, ω = = = 36.04 kN/m2
𝐿∗𝐵 3.70∗1.5
ωL 𝑙 ω𝐿2
Bending Moment due to Class 70R Bogie = ∗ − = 32.71 kNm
2 2 8
Figure 5-7: Vehicle wheel arrangement for Shear force in 70-R Bogie
1.5 0.3
a= + = 0.9 m
2 2
𝑎 0.9
bef = α ∗ a (1 − 𝑙 ) + 𝑏1 = 2.60 ∗ 0.9 (1 − 3.17) + 0.42 = 2.10 m
𝑜
𝑏 7.15
= 3.17 = 2.29 so, α = 2.60 (IRC: 112 Annex B 3.2)
𝑙
3.25
a= = 1.63 m
2
51
b1 = 4.57 + 2 * 0.1 = 4.77 m
𝑎 1.63
bef = α ∗ a (1 − 𝑙 ) + 𝑏1 = 2.60 ∗ 1.63 (1 − 3.17) + 4.77 = 6.83 m
𝑜
Figure 5-9: Vehicle wheel arrangement for Shear force in 70-R Track
1.48 0.3
a= + = 0.89 m
2 2
𝑎 0.89
bef = α ∗ a (1 − 𝑙 ) + 𝑏1 = 2.60 ∗ 0.89 (1 − 3.17) + 4.77= 6.43 m
𝑜
Thus,
Ultimate BM due to Class 70R T = 1.5 * BMLL + BMDL = 57.15 kNm
Ultimate SF due to Class 70R T = 1.5 * SFLL + SFDL = 94.66 kN
A 46.18 70.49
Mlim = 0.166 * fk * b * d2
𝑀𝑙𝑖𝑚
Depth required, dreq =√
0.166𝑓𝑘 𝑏
53
59.51∗106
=√
0.166∗30∗1000
Longitudinal Reinforcement:
𝑑 𝑑 𝑀
Depth of neutral axis, x = − √( )2 − (SP: 105 Clause 6.2)
0.832 0.832 0.1347fk𝑏
= 34.330 mm
MEd = 0.87fyAst (d - 0.41597x)
Or, 59.51*106 = 0.87 * 500 *Ast *(174 – 0.41597 * 34.330)
59.51∗106
i.e, Ast = = 856.54 mm2
0.87∗500∗159.720
𝑓𝑐𝑡𝑚 2.5
Ast,min = 0.26* btd = 0.26 * ∗ 1000 ∗ 174 = 192.18 mm2
𝑓𝑦𝑘 575
113.1∗1000
Ast,provided = = 1130.97 mm2
100
Distribution Reinforcement:
200
= 1+ √170 = 2.08
𝐴𝑠𝑡
ρ1 = = 0.0065 ≤ 0.02
𝑏𝑑
54
then,
VRd.c = [0.12𝑘(80ρ. 𝑓𝑐𝑘 )0.33 ]𝑏𝑑
= [0.12 ∗ 2 ∗ (80 ∗ 0.0065 ∗ 30)0.33 ]1000 ∗ 174
= 103.39 kN > 102.82 kN
Since VRd.c > VEd, slab is safe in shear.
Cantilever overhang takes flexural loads from load effects induced by loads, self-
weight, dead loads due to kerb & railing post and live loads. There are two cantilever
slabs on either side of main girder, width of 2.25 m each.
The moment resulting from dead loads, including the self-weight of the slab, kerb,
railing (made of GI pipe), and RC post, has been computed for a cantilever slab per
55
unit width. The calculation was done with respect to the fixed end of the cantilever
slab, which is located at the face of the main girder.
Load Factored
Description Measurement PSF
(kN) Load (kN)
Total 26.89
56
Factored Bending Moment due to DL = 30.59 kNm
Factored Shear Force due to DL = 26.88 kN
The minimum clearance for IRC Class A loading is 150 mm i.e, a wheel of Class A
rests in cantilever slab. Any of IRC Class 70R loads doesn’t rest on cantilever slab with
minimum clearance of 1.2m.
57
Now,
𝑇𝑜𝑡𝑎𝑙 𝐿𝑜𝑎𝑑∗𝐼𝐹 57∗1.161
Intensity of load, ω = = = 89.634 kN/m2
𝐿∗𝐵 0.69∗1.07
ω𝑙 2 89.634∗(0.2+0.535)2
Bending Moment due to Class A = = = 24.21 kNm
2 2
Shear Force due to Class A = ω ∗ l = 89.634 * 0.735 = 65.88 kN
Pedestrian Load:
Pedestrian 8.1 6
58
Check for depth:
Mlim= 0.166fkbd2
𝑀𝑙𝑖𝑚
Depth required, dreq =√
0.166𝑓𝑘 𝑏
62.90∗106
=√
0.166∗30∗1000
Longitudinal Reinforcement:
𝑑 𝑑 𝑀
Depth of neutral axis, x = − √( )2 − (SP: 105 Clause 6.2)
0.832 0.832 0.1347fk𝑏
= 40.71 mm
MEd = 0.87 * fy * Ast * (d - 0.41597x)
Or, 62.90 * 106 = 0.87 * 500 *Ast *(172 – 0.41597 * 40.71)
62.90∗106
i.e, Ast = = 909.02 mm2
0.87∗500∗155.07
𝑓𝑐𝑡𝑚 2.5
Ast,min = 0.26 * b td = 0.26* ∗ 1000 ∗ 172194.43 mm2
𝑓𝑦𝑘 575
Distribution Reinforcement:
Area of distribution Reinforcement = 0.2*Ast = 223.40 mm2
Rebar diameter, Φ = 10 mm & Cross Section Area of rebar = 78.54 mm2
Spacing required = 1000*78.54/Ast = 352 mm
Provide Φ10 @350 mm c/c.
78.54∗1000
Ast,provided = = 341.48 mm2
350
59
Check for Shear:
200
k = 1+ √ ≤ 2.0
𝑑
200
= 1+ √ = 2.08
172
𝐴𝑠𝑡
ρ1 = = 0.0065 ≤ 0.02
𝑏𝑑
VRd.c = [0.12𝑘(80ρ. 𝑓𝑐𝑘 )0.33 ]𝑏𝑑
= [0.12 ∗ 2 ∗ (80 ∗ 0.0065 ∗ 30)0.33 ]1000 ∗ 172
= 102.17 kN > 98.76 kN
Since VRd.c > VEd, slab is safe in shear.
There are three longitudinal T-girders with bottom bulb spaced 3.25m apart c/c. Here,
edge girder and intermediate girder designs were finalized independently.
60
5.1.2.1 Load Analysis of main girder
Below, the weight per unit length of the longitudinal girder, fillet, deck slab, and
wearing course is determined. The dead load is presumed to be a uniformly
distributed load (UDL) all along the main girder.
Volume
Sp. Partial
per Load,
S.N. Particulars Description Weight, FOS,
meter, kN/m
kN/m3 ϒ
m3/m
Deck Slab /
2 Flange portion 3.25 * 0.22 0.715 25 1.35 24.13
of girder
Web portion of
0.30 *
3 girder excluding 0.309 25 1.35 10.42
(1.43-0.25-0.15)
bulb
61
1
2 * 2 * 0.30 *
4 Fillet 0.045 25 1.35 1.52
0.15
0.70 * 0.25 +
0.15
5 Bottom Bulb * 0.25 25 1.35 8.44
2
(0.70+0.30)
In this case, the self-weight of cross girders acts at the center of the main girder as a
concentrated load.
3.25 3.25
Load of cross girder at intermediate main girder = 1.03 * 0.30 * ( + +) * 25 *
2 2
1.35 = 33.89kN
Bending Moment at any point ‘x’ distance away from support due to dead load is
given by:
M = (R * x -57.03 * x2 - 33.89 * x - If(x>22/3, 33.89 * (x - 22/3), 0) … … …(i)
Shear force at any point ‘x’ distance away from support due to dead load is given by:
SF = (R - 57.03 * x - 33.89 - If(x>22/3, 33.89, 0) … … …(ii)
Bending Moment:
4.5
Impact Factor Fraction = 6 + 22 = 0.161
0.5
𝑊1 ∗ (1.75 + 0.15 + 2
) + 𝑊1 ∗ (2.15 + 1.8) + 𝑊1 ∗ (3.95 + 1.2 + 0.5) + 𝑊1 × (5.6 + 1.8)
x̅ =
4𝑊1
= 4.8m
Sum of square distance of girders from the central axis of the bridge axis,
Eccentricity of live load with respect to the axis of the bridge, e = -0.70
Let distance of the girder from the central axis of the bridge axis be dx.
End Girder A
63
dx = -3.25
ΣW ΣI × dx × e
RA = × [1+ ]
n Σdx2 ∗ I
= 0.88W
Similarly,
At x = 10.39m
Figure 5-16: ILD for BM at quarter span and Positioning of Class A load
Shear Force:
At Support
Putting x=0 in eq. ii;
Factored SF due to dead load = 661.21kN
At quarter span
65
Putting x=5.5 in eq. ii;
Factored SF due to dead load = 347.98kN
Figure 5-18: ILD for SF quarter span and Positioning of Class A load
Bending Moment
15.5
Impact Factor Fraction =
100
Impact Factor = 1.155
66
RA = 0.51W
RB = 0.33W
RC = 0.16W
Figure 5-20: ILD for BM at 11.21m from support and positioning of 70R
Wheeled load
At Quarter Span
Figure 5-21: ILD for BM at quarter span and positioning of 70 Wheeled load
67
Moment due to LL = 2327.25kNm
Ultimate bending moment = 4838.09kNm
Shear Force
At Support
Figure 5-22: ILD for SF at support span and positioning of 70R Wheeled load
SF due to LL = 709.41kN
Ultimate SF = 1290.15kN
At Quarter Span
Figure 5-23: ILD for SF at quarter span and positioning of 70R Wheeled load
SF due to LL = 479.41kN
Ultimate SF = 772.43kN
68
70R-Tracked Vehicle:
RA = 0.51W
RB = 0.33W
RC = 0.16W
Bending Moment
At the mid-span
69
Figure 5-25: ILD for BM at mid-span and positioning of 70R Tracked load
At quarter span
Figure 5-26: ILD for BM at quarter span and positioning of 70R Tracked load
Shear Force
70
At Support
Figure 5-27: ILD for SF at support and Positioning of 70R Tracked load
SF due to LL = 627.30kN
At quarter span
Figure 5-28: ILD for SF at quarter span and Positioning of 70RTracked load
SF due to LL = 741.36kN
71
5.1.2.1.2 End Girder
Below, the weight per unit length of the longitudinal girder, fillet, deck slab, railing
post, footway, G.I. pipe, and wearing course is determined. The dead load is
presumed to be a uniformly distributed load (UDL) all along the main girder.
Parti-
Volume Sp.
S.N al Load,
Particulars Description per m, Weight
. FOS, kNm
m3/m , kN/m3
ϒ
0.10*(7.5-
1 Wearing Coat 0.213 22 1.75 8.181
3.25)/2*1
72
(12*(1.1*0.2*0.2))
2 Railing post 0.024 25 1.35 0.81
/22
3*1*4.37*9.81/10
3 GI pipe 1.35 0.174
00
0.22*(3.25/2+0.3/
4 Deck Slab 0.391 25 1.35 13.17
2)
(11-3.25*2-
5 Cantilever Slab 0.3)/2*(0.22+0.15) 0.389 25 1.35 13.11
/2
Web portion of
0.30 * (1.43-0.25-
7 girder excluding 0.309 25 1.35 10.42
0.15)
bulb
1
8 Fillet 2 * 2 * 0.30 * 0.15 0.045 25 1.35 1.519
Fillet under
9 0.002 25 1.35 0.06
cantilever slab
0.15
0.70 * 0.25 + 2
10 Bottom Bulb 0.25 25 1.35 8.438
* (0.70+0.30)
In this case, the self-weight of cross girders acts at the center of the main girder as a
concentrated load.
3.25
Load of cross girder at intermediate main girder = 1.03 * 0.30 * * 25 * 1.35 =
2
16.947kN
73
Figure 5-30: Dead Load on End Main Girder
(69.25∗22+16.95∗4)
Reaction at supports due to dead load(R) = = 763.87kN
2
Bending Moment at any point ‘x’ distance away from support due to dead load is
given by:
M = (R * x -69.25 * x2 - 16.95 * x - If(x>22/3, 16.95 * (x - 22/3), 0) … … …(i)
Shear force at any point ‘x’ distance away from support due to dead load is given by:
SF = (R - 69.25 * x - 16.95 - If(x>22/3, 16.95, 0) … … …(ii)
They are calculated in a similar way as intermediate girder and are summarized in the
following table:
74
75
76
5.1.2.2 Design of Main Girder
Flange depth
235.25mm
77
Design of longitudinal reinforcement
i) At mid span
β1 = 0.80952
β2 = 0.41597
Assume xu < Df
MuR,xu = Df = 12960.47 > 7137.1 => Singly reiforced
𝑑 𝑑 𝑀𝐸𝑑
Neutral axis depth, xu = − √( )2 − = 140.43 < Df
2∗𝛽2 2∗𝛽2 𝛽1∗𝛽2∗𝑏∗𝑓𝑐𝑑
(Assumption is right)
Required area of steel, Ast = 11381.33
Take Φ32mm TMT bar = 32.00
No. of Bars = 14.15
Provided number of bars = 15.00
Ast,provided = 12063.72
At support
Design shear, VEd = 1290.15kN < 0.5*bw* d * v * fcd = 1633.935kN
Incase of direct support with flexible bearing and predominantly UDL,
Net shear force, VNS = Shear force at d’ distance from the center of the support
=1205.431kN
Shear stress, τu = 1205.431/(300*1500) * 1000 = 2.68MPa
78
Design value of the shear force which can be sustained by the yielding shear
reinforcement:
VRd.c = (0.12 K * (80 * ρ1 * fck) * 0.33 + 0.15 * σcp) * bw * d’
200
K=1+√ = 1.37 < 2
300
Reinforce
At 0 L/8 L/4 3L/8 L/2
-ment
Diameter of
32 32 32 32 32
Reinforcement
bar, mm
Longitudinal
bar, mm2
Legs 2 2 2 2 2
Shear
Spacing
146.8 218.4 298.4 480.6 954.8
required, mm
Spacing
100 200 200 300 300
provided, mm
Surface reinforcement
80
5.1.2.2.2 Design of Exterior Main Girder
Flange depth
81
Longitudinal and shear reinforcement are calculated as intermediate girder and are
checked for maximum and minimum reinforcement. They are summarized in
following table:
Reinforce
At 0 L/8 L/4 3L/8 L/2
-ment
Diameter of bar,
32 32 32 32 32
mm
Reinforcement
Longintudinal
mm2
Legs 2 2 2 2 2
Shear
Spacing required,
146.8 180.3 280.3 449.0 954.8
mm
Spacing provided,
100 150 200 200 200
mm
Minimum shear reinforcement spacing for 2-legged 10 dia bar stirrups is 663.62mm.
In order to verify that the structure and structural elements perform adequately during
service life. The serviceability limit states shall have to be satisfied. The serviceability
limit states are:
- Stress level
- Crack width
- Deflection
82
5.1.2.3.1 Stress level
The section is design such that maximum compressive stress on flange in 0.36fck <
0.46fck. Hence serviceability limit state of stress level is satisfied in order to keep the
longitudinal cracks, micro cracks or creep within acceptable limits.
For frequent, rare and quasi-permanent load combination, partial factor of safety is 1.0
and 1.2 for dead load and surfacing respectively.
Uniformly distributed load = 1.0 * 45.233 + 1.2 * 4.675 = 50.843kN/m
Concentrated load = 12.553kN
Reaction, R = 584.379kN
Maximum Bending moment
= (R * 11 - 50.843 * 112 / 2- 12.553 * 11 - 12.553 * (11 - 22/3)
= 3306.140kN
Area of reinforcement provided = 12867.96mm2
d’ = 1500mm
Clear cover, c = 40mm
Total depth, h = 1650mm
Es = 200 kN/mm2
Ecm = 31 N/mm2
Modular ratio, αe = Es / Ecm = 6.452
Neutral axis depth:
bf * df *(x – df / 2) + 300 * (x – 230.35)2 / 2 = αe * Ast * (d’ – x)
Solving above equation; x = 270.321mm
Ac,eff = MIN(2.5 * (h - d); (h - x) / 3; h / 2)*300 = 112500mm2
ρp,eff = As / Ac,eff = 0.034
Stress in the tension reinforcement assuming a cracked section, σsc = 182.284N/m
kt = 0.5
fct,eff = 2.5
83
𝐬𝐜−𝐤𝐭∗𝐟 𝐜𝐭.𝐞𝐟𝐟/𝛒𝐩,𝐞𝐟𝐟∗(𝟏+𝛂𝐞∗𝛒𝐩,𝐞𝐟𝐟)
εsm - εcm = = 0.00068896 ≥ 0.6 * σsc / Es =
𝐄𝐬
0.000546852
Diameter of bar, ∅ = 32
Sr,max = 3.4c + 0.425 * k1 * k2 * ∅ / ρp,eff = 294.533
Thus, Wk = Sr,max * εsm-εcm = 0.20292 < 0.3 ( For moderate condition of exposure)
Hence, the serviceability limit state of crack width is satisfied for end girder.
Shrinkage Deflection
84
From Table 6.7,
For ho = 397.900mm, kh = 0.726
Age of the concrete in days at the beginning of drying shrinkage, ts = 28 days
(End of curing)
= 0.991
85
RHo = 100%
Factor to allow for the effect of concrete strength on the notional creep coefficient,
β(fcm) = 18.78/fcm1/2 = 2.969
Factor to allow for the effect of concrete age at loading on the notional creep
coefficient,
= 0.488
Coefficient to describe the development of creep with time after loading,
= 0.993
Cross sectional area, Ac = 1206633.75mm2
Total perimeter, P = 9295mm
Exposed perimeter, u = P – 220 – 185 - 2825 = 6065mm
ho = 2 * Ac / u = 397.900mm
Coefficient depending on the relative humidity (RH in percent) and the notional
member size (ho in mm),
βH = 1.5 [1 + (0.012 * RH)18] * ho + 250]
= 848.036 ≤ 1500 (for fcm ≤ 45MPA)
Factor to allow for the effect of relative humidity on the notional creep coefficient
= 1.558
фo = фRH * β(fcm). β(to) = 2.259
⸫Creep coefficient, ф(t,to) = фo * βc(t,to) = 2.244
87
W a mm b δ
26.379 2020 19980 0.391
39.569 5980 16020 2.872
39.569 7500 14500 3.376
56.056 9630 12370 5.411
56.056 11000 11000 5.535
56.056 14050 7950 4.955
56.056 15420 6580 4.374
26.914
Total deflection due to live load in frequent combination = 26.914 < 27.5mm
Hence, the serviceability limit state of crack width is satisfied for main girder.
i) End Cross Girders: Girders 1 and 4 are two end girders in figure above. Depth of
these girders has been reduced to 1.24m.
ii) Intermediate Cross Girders: Girders 2 and 3 are two intermediate girders in figure
above. Depth of these girders has been reduced to 1.24m.
88
5.1.3.1 Analysis and design of intermediate cross girder
Load of
Slab at Total
end L B H V weight no P.S.F weight
TOTAL 15.376
slab at
mid 3.25 0.22 0.715 17.875 1 1.35 24.131
TOTAL 38.35
89
Figure 5-35:Dead load intermediate Cross Girder
VMax = 56.146kN
MMax = 54.057kN-m
Since, girder is fixed, the negative moment at the end of support must be noted. If
continuous analysis of the intermediate cross girder is done, the maximum moment at
the end of support is 34.63kN-m.
90
Bending moment and shear force due to Live loads:
Wheel axle load of 114kN is kept as possible near to the edge of the cross girder
satisfying the minimum gaping between the edge of the wheel and kerb. The intensity
of a wheel is 285 kN/m and the distribution of the wheel for intermediate cross girder
is 28.256kN due to half wheel load. For full wheel load, the reaction is 56.512kN.
For Class A, the truck is kept at both lanes. So, the reaction at the supports of cross
girder is as given figure.
91
b) IRC Class 70R Track loading
Wheel axle load of 700kN is kept as possible near to the edge of the cross girder
satisfying the minimum gaping between the edge of the wheel and kerb. The intensity
of a wheel is 76.586 kN/m and the distribution of the wheel for intermediate cross girder
is 147.611 due to half wheel load. The For full wheel load, the reaction is 295.226kN.
Since one wheel of the axle doesn’t lie completely on the cross girder, the load obtained
at that wheel is (488/840) × 295.226 = 171.512 kN
For Class 70-R track, the truck is kept at one lane. So, the reaction at the supports of
cross girder is as given figure.
92
c) IRC Class 70R Wheel loading
Wheel axle load of 170kN is kept as possible near to the edge of the cross girder
satisfying the minimum gaping between the edge of the wheel and kerb. The intensity
of a wheel is 447.368 kN/m and the distribution of the wheel for intermediate cross
girder is 83.893 due to half wheel load. The For full wheel load, the reaction is 167.787.
Since one wheel of the axle doesn’t lie completely on the cross girder, the load obtained
at that wheel is (620/860) × 167.787 = 120.962 kN
For Class 70-R wheel, the truck is kept at one lane. So, the reaction at the supports of
cross girder is as given figure.
Bending moment:
MMax = 330.473-kNm
Shear force:
93
VMax =167.787 × 1.162 × 1.5 = 292.453kN
Analysis Summary:
Effective width of flange for T-beam: (Equation 7.6.1.2 from IRC 112-2020)
𝑏𝑒𝑓𝑓,𝑖 = ∑ 𝑏𝑒𝑓𝑓,𝑖 + 𝑏𝑤 ≤ 𝑏
Flange Depth:
0.35 × 0.22 +0.3 × 0.37
Average thickness of both part = = 0.289m
0.35 + 0.3
94
Actual Section Equivalent Section
Df = 289 mm
d' = 54 mm, clear cover= 40mm and diameter of bar be ∅25𝑚𝑚
deff = 1240 - d' = 1240 - 54 = 1186 mm
Xu, lim = 0.62d = 0.62 × 1186 = 735.32 mm
Assume N.A lies in flange region
For M30,
2
0.2216
𝑥 = 1.202 × 𝑑𝑒𝑓𝑓 − √1.445 × 𝑑𝑒𝑓𝑓 − 𝑀×
𝑏
0.2216
𝑥 = 1.202 × 1186 − √1.445 × 11862 − 599.628 × 106 ×
1600
𝑥 = 29.333𝑚𝑚 < 𝐷𝑓
So, assumption of N.A lying in flange is satisfied.
Now, Finding Mu,lim for M30 concrete we have,
Mu,lim = 4.996 × b × 𝑑 2
=4.996 × 1600 × 11862
= 11243.765kN-m >MMax ,
So, the section has been designed as a singly reinforced section.
Reinforcement design
IRC112-2020)
95
Ast > (Ast )min
(Ast )max = 0.025 ×𝑏𝑤 ×𝑑 = 0.025 × 300 × 1186 = 8895mm2 (cl. 16.5.1.1 IRC112-2020)
(Ast )max >Ast
Take reinforcement of ɸ28 mm.
Ast 1174.356
Number of Bars required = = = 1.9
Aϕ 282
π× 4
Here, depth of girder at support is greater than 750 mm, so side face reinforcement is
required.
Ast =0.1% of bd
0.1
Ast = × 300 × 1186 = 355.8 mm2
100
Provide ɸ 10 mm bars.
Ast 355.8
Number of Bars required = = = 4.53
Aϕ 102
π× 4
Allowable shear force without shear reinforcement: IRC 112-2020 clause 10.3.2
The design shear resistance of the member without shear reinforcement VRd.c is given
by:
VRd.c = [0.12×K× (80×ρ1 ×fck) 0.33 + 0.15σcp] bwd ×d
VRd.c min = (vmin + 0.15×σcp) ×bw×d
200
K =1+√ ≤2
𝑑
200
=1+√1186
=1.41 ≤2
Vmin = 0.031×K3/2 ×fck1/2
Vmin = 0.031×1.413/2 ×301/2
Vmin = 0.285
σcp = 0
96
𝐴𝑠𝑙
p1= ≤ 0.02- Reinforcement ratio for longitudinal reinforcement
𝑑×𝑏𝑤
= 0.005
VRd.c min = (0.285) ×300×1186
=101.287
∴ VRd.c = [0.12×1.41× (80×0.005 ×30) 0.33] 300×1186
=138.48 kN ≥ VRd.c min
VEd =The design shear force at a cross-section resulting from external loading
=543.262 kN
∴Since VEd> VRd.c, shear reinforcement design is required
Maximum Allowable Shear Force (for maximum shear force take 𝜃= 450)
𝑐𝑑 𝑓
VRd.max = 𝛼𝑐𝑤 × 𝑏𝑤 × 𝑧 × 𝑣1 × 𝑐𝑜𝑡𝜃+𝑡𝑎𝑛𝜃 (cl. 10.3.3.2, Eq10.8 IRC: 112-2011)
Here,
VRD,max =The design value of maximum shear force
𝛼𝑐𝑤 =1 for σcp=0 (RCC)
Lever Arm (z) = 0.9d =1067.4mm
𝑓
𝑐𝑘
v1 = 0.6 × (1 − 310 ) is the strength reduction factor = 0.542
fcd = 13.4
θ=450
Now,
13.4
∴VRd.max = `1 × 300 × 1067.4 × 0.542 × 2
= 1150.746 kN
And,
VRds = VNS = VED + Vccd + Vtd = VED = 543.262 kN
Here,
For uniform cross section: Vccd=Vtd=0
VRds =the design value of the shear force
VNS =Net Design Shear Force = Algebraic sum of VED, Vccd and Vtd
Vccd =Design value of the shear component of the force in the compression area, in the case
of an inclined compression chord
Vtd =Design value of the shear component of the force in the tensile reinforcement, in
the case of an inclined tensile chord
97
∴Since, VRds < VRd,max, the section is safe
Design of Shear Reinforcement IRC 112:2020 Cl 10.3.3.1.-4
By equating VNS and, VRd, max we get
2×𝑉𝐸𝑑
sin−1(𝛼 )
𝑐𝑤 ×𝑏𝑤 ×𝑧×𝑣1 ×𝑓𝑐𝑑
∴ θ =
2
0
=13.025
∴As per the code 21.80≤θ≤450
Adopt θ=21.80
𝐴𝑠𝑤
∴VRds=VNS=VEd= × 𝑧 × 𝑓𝑦𝑤𝑑 × 𝑐𝑜𝑡𝜃
𝑆
𝐴
`𝑆 = 𝑉𝑠𝑤 × 𝑧 × 𝑓𝑦𝑤𝑑 × 𝑐𝑜𝑡𝜃
𝐸𝑑
500
fywd= 1.15 = 434.78 N/mm2
98
5.1.3.2 Analysis of end cross girder
Figure 5-41: End Cross Girder Loaded With Dead Load for Bearing Replacement
Case
99
Dead Load:
Bending moment and shear force due to Dead Loads:
Total
At girder L B H V weight no P.S.F weight
web 3.25 0.3 1.24 1.206 26.544 1 1.35 35.834
WC 3.25 0.3 0.1 0.097 2.437 1 1.75 4.265
fillet 3.25 0.3 0.15 0.146 3.656 1 1.35 4.935
TOTAL 13.857
At mid of
slab
portion 1.625 0.22 0.357 8.937 1 1.35 12.065
WC 1.625 0.1 0.162 4.062 1 1.75 7.109
TOTAL 19.175
Bending moment:
MMax = 35.174kN-m
Shear force:
VMax = 38.097kN
Live Load:
same as intermediate girder
CLASS
CLASS A 70RT CLASS 70RW
DESIGN SF (kN) 197.000 487.117 292.453
DESIGN
MOMENT(kNm) 278.263 545.571 330.472
100
Analysis Summary
CLASS CLASS CLASS
A 70RT 70RW
SF (kN) 197.000 487.117 292.453
Live Load
BM kNm) 278.263 545.571 330.472
Since, shear from Bearing Replacement case (or lifting case) have been found more
than that of combined effect of dead load and live loads and moment obtained from
combined effect of dead load and live loads is more. So, no any case governs the
response on its own. We design on basis of maximum values from both cases.
So,
Design Bending moment at mid = 580.745kN-m
Design Bending moment at support = 372.510kN-m
Design shear force = 687.712kN
Effective width of flange for T-beam: (Equation 7.6.1.2 from IRC 112-2020)
𝑏𝑒𝑓𝑓,𝑖 = ∑ 𝑏𝑒𝑓𝑓,𝑖 + 𝑏𝑤 ≤ 𝑏
101
Flange Depth:
0.35 × 0.22 +0.3 × 0.37
Average thickness of both part = = 0.289m
0.35 + 0.3
2
0.2216
𝑥 = 1.202 × 𝑑𝑒𝑓𝑓 − √1.445 × 𝑑𝑒𝑓𝑓 − 𝑀×
𝑏
0.2216
𝑥 = 1.202 × 1186 − √1.445 × 11862 − 580.745 × 106 ×
950
𝑥 = 48.232𝑚𝑚 < 𝐷𝑓
So, assumption of N.A lying in flange is satisfied.
Now, Finding Mu,lim for M30 concrete we have,
Mu,lim = 4.996 × b × 𝑑 2
=4.996 × 950 × 11862
= 6675.985kN-m >MMax ,
So, the section has been designed as a singly reinforced section.
102
Ast = 1145.043 mm2
𝑓𝑐𝑡𝑚 2.5
(Ast )min = 0.26 × ×𝑏𝑤 ×𝑑 = 0.26 × 500 × 300 × 1186 = 462.654mm2 (cl. 16.5.1.1
𝑓𝑦𝑘
IRC112-2020)
Ast > (Ast )min
(Ast )max = 0.025 ×𝑏𝑤 ×𝑑 = 0.025 × 300 × 1186 = 8895mm2 (cl. 16.5.1.1 IRC112-2020)
(Ast )max >Ast
Take reinforcement of ɸ28 mm.
Ast 1145.043
Number of Bars required = = = 1.85
Aϕ 282
π× 4
IRC112-2020)
Ast > (Ast )min
(Ast )max = 0.025 ×𝑏𝑤 ×𝑑 = 0.025 × 300 × 1186 = 8895mm2 (cl. 16.5.1.1 IRC112-2020)
(Ast )max >Ast
Take reinforcement of ɸ25 mm.
Ast 732.751
Number of Bars required = = = 1.49
Aϕ 252
π× 4
Here, depth of girder at support is greater than 750 mm, so side face reinforcement is
required.
Ast =0.1% of bd
103
0.1
Ast = × 300 × 1186 = 355.8 mm2
100
Provide ɸ 10 mm bars.
Ast 355.8
Number of Bars required = = = 4.53
Aϕ 102
π× 4
Allowable shear force without shear reinforcement: IRC 112-2020 clause 10.3.2
The design shear resistance of the member without shear reinforcement VRd.c is given
by:
VRd.c = [0.12×K× (80×ρ1 ×fck) 0.33 + 0.15σcp] bwd ×d
VRd.c min = (vmin + 0.15×σcp) ×bw×d
200
K =1+√ ≤2
𝑑
200
=1+√1186
=1.41 ≤2
Vmin = 0.031×K3/2 ×fck1/2
Vmin = 0.031×1.413/2 ×301/2
Vmin = 0.285
σcp = 0
𝐴
p1= 𝑑×𝑏𝑠𝑙 ≤ 0.02- Reinforcement ratio for longitudinal reinforcement
𝑤
= 0.005
VRd.c min = (0.285) ×300×1186
=101.287
∴ VRd.c = [0.12×1.41× (80×0.005 ×30) 0.33] 300×1186
=138.48 kN ≥ VRd.c min
VEd =The design shear force at a cross-section resulting from external loading
=687.712kN
∴Since VEd> VRd.c, shear reinforcement design is required
Maximum Allowable Shear Force (for maximum shear force take 𝜃= 450)
𝑐𝑑 𝑓
VRd.max = 𝛼𝑐𝑤 × 𝑏𝑤 × 𝑧 × 𝑣1 × 𝑐𝑜𝑡𝜃+𝑡𝑎𝑛𝜃 (cl. 10.3.3.2, Eq10.8 IRC: 112-2011)
104
Here,
VRD,max =The design value of maximum shear force
𝛼𝑐𝑤 =1 for σcp=0 (RCC)
Lever Arm (z) = 0.9d =1067.4mm
𝑓
𝑐𝑘
v1 = 0.6 × (1 − 310 ) is the strength reduction factor = 0.542
fcd = 13.4
θ=450
Now,
13.4
∴VRd.max = `1 × 300 × 1067.4 × 0.542 ×
2
= 1150.746 kN
And,
VRds=VNS=VED + Vccd + Vtd = VED =687.712kN
Here,
For uniform cross section: Vccd=Vtd=0
VRds =the design value of the shear force
VNS =Net Design Shear Force = Algebraic sum of VED, Vccd and Vtd
Vccd =Design value of the shear component of the force in the compression area, in the case
of an inclined compression chord
Vtd =Design value of the shear component of the force in the tensile reinforcement, in
the case of an inclined tensile chord
∴Since, VRds < VRd,max, the section is safe
Design of Shear Reinforcement IRC 112:2020 Cl 10.3.3.1.-4
By equating VNS and, VRd, max we get
2×𝑉𝐸𝑑
sin−1(𝛼 )
𝑐𝑤 ×𝑏𝑤 ×𝑧×𝑣1 ×𝑓𝑐𝑑
∴ θ =
2
0
=18.12
105
500
fywd= 1.15 = 434.78 N/mm2
The span length of this bridge is 22m and bridge is RCC T-beam. Since, the
superstructure dead load is itself more with relative to other bridges such as truss
bridges. So, the bearings selected must be higher resistible to higher concentrated load
given by superstructure. The choice of bearing is also followed by considering the
functional requirement of bearing, overall cost, ease of installation, durability,
maintenance, construction facility available. Followed by such consideration we select
steel laminated elastomeric pad bearing. The bearing has been designed by limit state
design method as per IRC: 83(Part II)-2018 Standard specification and code of
practices for road bridges, section IX.
For the design, loads has been assessed and then for the critical load combinations of the
calculated loads, bearings has been designed.
106
Calculation of Loads on bearing
8. Main
girder:
a. Web
portion
excluding
bulb 22 0.3 1.03 6.8 25 169.95 3 509.85
b. Bulb
portion 22 0.25 5.5 25 137.5 3 412.5
9. Cross
girder 2.95 0.3 1.02 0.90 25 22.57 8 180.54
Total 3332.995
107
4644.743
= = 774.124kN
6
Minimum possible dead load from superstructure (without considering wearing
course) on a bearing
4644.743-635.25
= = 668.248kN
6
Class A load
Braking load = 0.2 × (2 × 27 + 2 × 114 + 4 × 68) = 110.8kN
Class 70-R Track load
Braking load = 0.2 × 700 = 140kN
Take Braking load = Maximum of above two cases = 140kN
140
Horizontal braking effort on each main girder = = 46.67kN
3
Braking load acts at 1.2 m above wearing course (cl. 211.3 IRC-06: 2017).
Point of application of braking load = 1.65 + 0.1 + 1.2 = 2.95m
46.67 × 2.95
Vertical reaction on a bearing due to braking load = = 6.258kN
22
d) Wind Load
108
From Table 12, IRC 06: 2017,
For plain terrain and basic wind 33.0 m/s,
VZ = 27.8 m/s
PZ = 463.7 N/m2
From NBC 104,
Basic wind speed = 47 m/s
Then,
47
VZ = × 27.8 = 39.59 m/s
33
47
PZ = 463.7 × ( )2 = 940.6 N/m2
33
Gust factor, G = 2 for span up to 150 m (cl. 209.3.3, IRC 06: 2017)
For single beam (cl. 209.3.3, IRC 06: 2017)
CD = 1.3 for B/D ≥ 6
For Combined effect of multiple beams CD, Combined = 1.5 × 1.3 = 1.95 (cl.209.3.3, IRC
06: 2017)
Transverse area of bridge, A= 36.3 m2
FTW = 940.6 × 36.3 × 2 × 1.95 = 133.161kN
133.161
FTW per bearing = = 22.193kN
6
Wind Load in Longitudinal direction of Bridge,
FLW = 0.25 × FTW (cl. 209.3.4, IRC 06: 2017)
= 0.25 × 133.161
= 33.29kN
33.29
FLW per bearing = = 5.549kN
6
Wind load in Vertical direction of bridge;
Plan area = 22.48 × 11 = 247.28 m2
FV
W = P Z × A × G × CL
348.887
FV
W per bearing= = 58.148kN
6
109
Taking Live load consideration as per cl.209.3.6 IRC 6:2017, use VZ as 36m/s we
calculate wind load in transverse and longitudinal direction similar as for VZ = 47m/s.
In this case combination of wind load from superstructure and live load structure must
be used.
As for taking wind load for superstructure for VZ = 36m/s
FTW = 78.124kN
78.124
FTW per bearing = = 13.021kN
6
FLW = 19.531kN
19.531
FLW per bearing = = 3.255kN
6
For live load, use CD be 1.2 and area be total length of live load structure multiplied
by height 3m and following process as similar as cl.209.3.3. IRC 6:2017.
FTW = 90.054kN
90.054
FTW per bearing = = 15.01kN
6
FLW = 22.513kN
22.513
FLW per bearing = = 3.752kN
6
Now from combination we get;
FTW = 168.178kN
168.178
FTW per bearing = = 28.03kN
6
FLW = 42.044kN
42.044
FLW per bearing = = 7.007kN
6
From above cases, the case of VZ = 36m/s analyzing in both dead and live load of
superstructure and live load structure respectively governs the analysis of wind load.
So, we prefer the following as respective wind load.
FTW = 168.178kN
168.178
FTW per bearing = = 28.03kN
6
FLW = 42.044kN
42.044
FLW per bearing = = 7.007kN
6
110
e) Seismic Load
111
627.511
FV
S, per bearing = = 104.592kN
6
Basic Combination
Seismic
LL as WL as
Description of Combination
Load leading leading
Horizontal Load
P.S. P.S. P.S.
Load Load Load
F F F
Wind Load 7.01 0.9 6.31 1.5 10.51 - -
Seismic Load 149.99 - - - - 1.5 224.98
Braking Load 46.67 1.5 70.00 1.15 53.67 0.2 9.33
113
Load due to
temperature 12.08 0.9 10.87 0.9 10.87 0.5 6.04
variation
TOTAL 87.18 75.06 2.20 240.35
Among three combinations of load, vertical load has been found maximum for Basic
Combination where carriageway load acts as leading load. For horizontal load we
consider Basic combination for maximum response whereas we do not design bearing
for seismic load. To resist seismic loads, certain devices like dampers and seismic
arresters are used.
VMin = 668.248N (Dead load without wearing course)
VMax = 1414.832kN
HMax = 87.18kN
From Table B1 (Annexure B) of IRC 83: 2018 (Part II), laminated bearing with
following dimensions is chosen:
Length, b = 500.0 mm
Width, a = 300.0 mm
Thickness of steel plate, hs = 4.0 mm
Thickness of middle elastomer layer, hi = 12.0 mm
Thickness of elastomer layer at top and bottom, he = 6.0 mm
Number of steel plate = 4
Number of middle elastomer layer = 3
Total thickness of elastomer layer, h = 3 × 12 + 2 × 6 = 48.0 mm
⸫ Total height of bearing, h0 = 3 × 12 + 4 × 4 + 2 × 6 = 64.0 mm
Provide 6.0 mm gap on either side of elastomer.
So,
Effective length, b’ = (500 – 2 × 6) = 488.0 mm
Effective width, a’ = (300 – 2 × 6) = 288.0 mm
Effective area of bearing, A1 = 488 × 288 = 140544 mm2
114
Figure 5-44:Plan of a Bearing
b 500
i) = = 1.67 < 2 (OK)
a 300
a 300
ii) = = 60 > h = 48 mm (OK)
5 5
a 300
iii) = = 30 < h = 48 mm (OK)
10 10
A1
iv) Shape factor, S = (cl. 5.1.3.1 IRC 83:2018 (Part II)
lP × te
Where, lP = 2 × (a’ + b’) = 2 × (288 + 488) = 1552 mm
2 × 1.4 × h e + 3 × hi 2 × 1.4 × 6+ 3 × 12
te = = = 10.56 mm
total number of layers 5
115
140544
S= = 8.575 > 6 & < 12 (OK)
1552 × 10.56
A1
Allowable bearing pressure = 0.25 × fCK × √ = 0.25 × 30 × 2 = 15 N/mm2
A2
a. Maximum design strain (cl. 5.1.3, IRC 83: 2018 (part II))
εu,k
εt,d = KL (εc,d + εq,d + εα,d ) ≤ εu,d =
γm
Where, KL = 1, is type loading factor
εc,d = Strain due to compressive design load (cl. 5.1.3.2, IRC 83:2018 (Part II))
εq,d = Strain due to shear (cl. 5.1.3.3, IRC 83:2018 (Part II))
εα,d = Strain due to angular rotation (cl.5.1.3.4, IRC 83:2018 (Part II))
εu,k = 7 (Note 1 of Clause 5.1.3) and γm = 1
εu,k 7
εu,d = = = 7.0
γm 1
• Strain due to Compressive design load
1.5 × FZ, d
εc,d =
G × Ar × S
Where, FZ, d = Maximum vertical load = 1414.832kN
G = Shear modulus of elasticity of elastomer, generally taken as 1.0 N/mm2
S = Shape factor
Ar = Reduced effective plan area due to the loading effects given by,
Vx, d Vy, d
Ar = A1 × (1 - - ' )
a' b
116
Maximum horizontal load in the direction of a
Vx, d = ×h
G × A1
87.18 × 1000
= × 52
1 × 140544
= 32.256 mm
Similarly, Vy, d = 0
32.256
Ar = 140544 × (1 - - 0) = 124803.072 mm2
288
1.5 × 1414.832 × 1000
εc,d = = 1.98 mm
1 × 124803.072× 8.575
• Strain due to shear
2 2
Vxy, d √Vx, d + Vy, d Vx, d 32.256
εq,d = = = = = 0.672 mm < 1 (OK)
Tq Tq Tq 48
• Strain due to angular rotation
𝑎′2 ∗ ∝𝑎,𝑑 + 𝑏′2 ∗ ∝𝑏,𝑑
εα,d = ∗ 𝑡𝑖
2 ∗ ∑ 𝑡𝑖3
Where, ∝b,d = 0 as there is no rotation along longitudinal axis
∝a, d = ∝DL LL
d + ∝d
83:2018(part II))
400 × 4369.164 × 106 × 22000 × 10-3 400 × 3428.104 × 106 × 22000 × 10-3
= +
0.5 × 5000 × √30 × 3.32 × 1011 5000 × √30 × 3.32 × 1011
= 0.008456 + 0.003318
=0.0118
So,
2882 × 0.0118 + 4882 × 0
εα,d = × 12 = 1.05
2 × (3 × 123 + 2 × 63 )
Now,
εt,d = KL (εc,d + εq,d + εα,d )
= 1 × (1.98 + 0.672 + 1.05)
= 3.702 < εu,d = 7 (ok)
b. Reinforcing plate thickness (cl. 5.1.3.5, IRC 83: 2018 (part II))
117
Kp × FZ, d × (t1 + t2 ) × Kh × γm
ts =
Ar × fy
Where, Kp = Stress correction factor = 1.3
t1 and t2 are the thickness of elastomer layer on either side of the plate
fy = yield stress of the steel = 250.0 N/mm2
Kh = factor for induced tensile stresses in reinforcing plate whose value is given as,
Without holes: Kh = 1
So, for elastomer without holes
1.3 × 1414.832 × 1000 × (12 + 12) × 1 × 1
ts =
124803.072 × 250
= 1.415 mm < 4.0 mm (OK)
= 1.48 mm
Now,
𝛼 ′ × ∝a, d + b' × ∝b, d 288 × 0.0118 + 388 × 0
∑ VZ, d - = 1.45 -
Kr, d 3
= 1.48- 1.132
= 0.348 > 0.0 (ok)
118
ii.Buckling stability
As our bridge is in seismic region V so as per IRC code seismic stopper for the
transverse seismic movement must be designed.
Total seismic load along the transverse direction (from bearing design)
119
= 941.327kN
Load per stopper= 0.25 × 941.327 = 235.332kN
The width of stopper available at the edge after providing 20mm for rubber pad
= 400 – 20
=380mm.
Length provided = 600mm
Height of stopper =750mm
So, provide 600 × 380 × 700 mm.
120
Figure 5-48:Reinforcement of Seismic Arrester
121
5.4 Analysis and Design of Sub-Structure
Since, the total height of abutment= maximum scour depth for abutment foundation
below HFL + grip length + free board + depth of main girder + thickness of bearing
=4.89 + 2 + 2 + 1.65 + 0.064
= 10.6m (11m is adopted)
Since, this height is greater than 6m. So, concrete type of abutment is preferred over
masonry type abutment.
122
Figure 5-51:Elevation of Abutment
a. Material Selection
Grade of Concrete: M30
Bars for all RC works: TMT500D
b. Geometry of Abutment
• Seating Width
Minimum seating width = 305 + 2.5 L + 10 H (IRC-6: Clause 219.9)
= (305 + 2.5 × 22 + 10 × 11) mm
= 470 mm
• Seating width > Bearing width + Projection of cap + width of Expansion joint + 150
mm (IRC-78-2000: Clause 710.8)
= 300 + 30 + 40 + 150 = 520 mm
Width of expansion joint > 22 × 103 × 1.1 × 10-5 × 45 = 10.89 mm (From
temperature criteria)
123
(It has been assumed that 45oC is the maximum change in temperature in our
bridge site)
Adopt expansion joint as 40mm.
Adopt seating width=750
124
5.4.1.2 Abutment Stem
Load Calculation:
𝜙=45o
125
i = 00, δ = 2/3 × 450 = 30o but must be less than 22.5o. So, adopt δ = 22.50
α = 00, ϒsoil = 22.5kN/m3, H=9.8 m
k = 0.1598
So, Pa = ½ × 0.1598 × 22.5 × 9.82 = 172.655kN/m.
Horizontal component = 172.655× cos (22.5) =159.513 kN/m
Vertical component= 172.655 × sin (22.5) = 61.043kN/m
Load due to dynamic earth pressure: (IRC 6: Cl. 214)
According to Monobe’s theory
𝜙=45o
i=00 δ=2/3 × 450 = 30o but must be less than 22.5o. So, adopt δ=22.50
α=00, ϒsoil = 22.5kN/m3, H=9.8 m
∝h
Ψ = tan-1 ( ) =9.13° and 11.56°
1±∝v
Z
×I Sa
∝h = 2 × =0.18
R g
2
∝v = 3 × ∝ℎ = 0.12
So, k = 0.3019
So, Pa = ½ × 0.3019 × 22.5 × 9.82= 326.18kN/m.
Dynamic increment=326.18-172.656=153.524kN/m
Horizontal component= 153.52 × cos (22.5) =141.84kN/m
Vertical component= 153.52 × sin (22.5) =58.75kN/m
Surcharge Load: (IRC 6: Cl. 214.1.1.3)
1.2 m earth fill from earth surface has been taken as surcharge-load.
Psur = Ka × ϒsoil × h × w = 0.1598 × 22.5 × 9.8 × 1.2 =43.577kN/m
Horizontal component = 43.577 × cos (22.5) = 40.259kN/m
Vertical component= 43.577 × sin (22.5) = 16.676kN/m
And for dynamic case,
Psur = Ka × ϒsoil × h × w = 0.3019 × 22.5 × 9.8 × 1.2 = 79.882kN/m
126
Dyamic increment of surcharge=79.8827-42.2831=37.5996 kN/m
Horizontal component= 37.599 × cos (22.5) = 34.73 kN/m
Vertical component= 37.599 × sin (22.5) = kN/m
Response of abutment at center of Abutment stem is taken for basic and seismic
combination of loads have been calculated. And using IRC-6-2017, ANNEX-B
corresponding load factor for each case is found.
From load combination table (Annex A)
Maximum axial-load = 734.15kN
Maximum bending moment=1771.95kNm
Here, Pu < 0.1fcdAc
734.15 < 0.1 × 13.4 × 715 × 1200 × 10-3
734.15 < 1149.72 (ok)
So, it has been treated as a flexure member. (Cantilever Slab)
Check Depth
1771.95 × 106
dreq = √ = 595.544 mm < 1112.5 mm (ok)
4.996× 1000
Design of Reinforcement
0.2216
X =1.2 × 𝑑 − √(1.44 𝑑 × 𝑑 − 𝑀 × 𝑏
0.2216
=1.2 × 1112.5 − √(1.44 × 1112.5 × 1112.5 − 1771.95 × 106 × 1000
=689.75mm
Xlim=0.62×dprovided = 0.62 × 1112.5 = 689.75𝑚𝑚
𝑑2
Mmax = 4.996 × 103 × 106
1112.52
= 4.996 × 103 × 106
127
=6183.3306 N-mm
and,
𝑀
Ast =
0.87×𝑓𝑦 ×(𝑑−0.41597×𝑋𝑢 )
1771.95×106
=
0.87×500×(1112.5−0.42×155.866)
=3888.144mm2
𝑎×1000
Spacing required= (𝜙 = 25𝑚𝑚)
𝐴𝑠𝑡
490.873× 103
=
3888.055
=126.251mm
0.26×𝑓𝑐𝑡𝑚
Min. Ast =
𝑓𝑦𝑚
0.26×2.5×103 ×1112.5
=
500
=1446.25mm2
Max. Ast =0.025bd
=0.025 × 1000 × 1112.5
=27812.5mm2
Spacing provided=125mm
𝑎×1000
Ast provided=
𝑠𝑝𝑎𝑐𝑖𝑛𝑔 𝑝𝑟𝑜𝑣𝑖𝑑𝑒𝑑
490.873×1000
=
125
=3926.9908mm2
𝑎×1000
Spacing= (𝜙 = 20𝑚𝑚)
𝐴
𝜋∗202 ×1000
=
4×1446.25
=217.223mm2
Spacing to be provided=200mm
3. Horizontal reinforcement:
128
Either AS = 0.1% Of AC or 25% of main vertical bar
=0.001× 103 × 1112.5
=1112.5 mm2
𝑎×𝑏
Spacing = (𝜙 = 20𝑚𝑚)
𝐴𝑠
𝜋×202 ×103
= 4×1112.5
=282.39mm
Spacing to be provided = 250mm
200
=1+ √
1112.5
=1.423
𝐴𝑠𝑙
𝜌1 = ≤2
𝑏𝑤 𝑑
3926.99
=
1000×1112.5
=0.0035≤ 2
𝑁
𝑓𝑐𝑘 = 30 𝑚𝑚2
𝜎𝑐𝑝 = 0
So,
Minimum Shear(v) = 383.44 kN/m> 315𝑘𝑁/𝑚
So, no shear reinforcement is required.
=157.03 N/mm2
129
K t = 0.5
fcm = fck + 10 = 40
Fct,eff = 2.50
Ecm = 31000N/mm2
𝐴𝑠
𝜌1,𝑒𝑓𝑓 = 𝐴
𝑐,𝑒𝑓𝑓
=0.018
𝐸
𝛼𝑒 = 𝐸 𝑠 = 6.451
𝑐𝑚
𝜎𝑠𝑐 − 𝐾𝑡 1 𝜎𝑠𝑐
𝜀𝑠𝑚 − 𝜀𝑐𝑚 = ( (1 + 𝛼𝑒 𝜌𝑝.𝑒𝑓𝑓 )) ≥ 0.6
𝜌𝜌.𝑒𝑓𝑓 𝐸𝑠 𝐸
=0.000397≥ 0.0004
C=50mm
0.425𝑘1 𝑘2 𝜙
Sr,max =3.4c+
𝜌𝜌,𝑒𝑓𝑓
=406.743 mm
Crack width= Sr,max (𝜀𝑠𝑐 − 𝜀𝑐𝑚 )
= 0.1916 mm< 0.3 𝑚𝑚 (ok)
130
5.4.1.3 Dirt wall
Loads on dirt wall are mainly surcharge load, earth static and dynamic load and
seismic load due to weight of dirt wall. The point of action of surcharge and earth
(static and dynamic) lies below the dirt wall i.e., on the stem of abutment. So, only
horizontal component of such forces is important for dirt wall. Dirt wall has been
designed as a cantilever slab of unit width. Earth pressure coefficient for dynamic
condition is k = 0.27
Its detailing has been carried out according to the IRC 112-2011(Cl. 16.3).
The design parameters from the load combination table can be obtained as:
Axial 63.905 kN
Shear 90.704 kN
Moment 161.289 kNm
=225.60 N-mm
𝑀
Ast =
0.87×𝑓𝑦 ×(𝑑−0.42×𝑋𝑢 )
=2086.49mm2
𝑎×1000
Spacing required = (𝜙 = 25𝑚𝑚)
𝐴𝑠𝑡
490.873×103
=
2086.49
=235.46mm
0.26×𝑓𝑐𝑡𝑚
Min. Ast =
𝑓𝑦𝑚
0.26×2.5×103 ×212.5
=
500
=276.25mm2
131
Max. Ast = 0.025bd
=0.025 × 1000 × 212.5
=5312.5mm2
Spacing provided = 200mm
𝑎×1000
Ast provided =
𝑠𝑝𝑎𝑐𝑖𝑛𝑔 𝑝𝑟𝑜𝑣𝑖𝑑𝑒𝑑
490.873×1000
=
200
=2454.369mm2
200
K=1 + √
𝑑
200
=1+ √
212.5
=1.9701
𝐴𝑠𝑙
𝜌1 = ≤2
𝑏𝑤 𝑑
2454
=
1000×212.5
=0.01154≤ 2
𝑓𝑐𝑘 = 30𝑁/𝑚𝑚2
𝜎𝑐𝑝 = 0
So,
Minimum Shear(v)=150.4 kN/m > 91𝑘𝑁/𝑚
So no shear reinforcement is required.
132
5.4.1.4 Abutment cap
Longitudinal reinforcement
Adopt 16mm diameter bar @200mm c/c
Transverse reinforcement
Adopt 16mm diameter bar@150mm c/c
The bearing capacity of soil is good even at the shallow depth. For such condition,
spread footing can be used for the foundation of abutment.
The analysis of structural strength for the design of the foundation is checked as per
IRC6:2017 Table B.4. The combinations were analyzed and the maximum heel soil
pressure was obtained from seismic combination 0.3H + V. The maximum toe pressure
was obtained from basic combination-1 at carriageway load as leading load.
The design values are taken from load combination table at ANNEX A. The design
value taken form the combination table are-
For toe,
Moment = 909.970 kNm/m
Axial load = 1758.15 kN/m
Eccentricity = 0.518 m
For heel,
Moment = 58.964 kNm/m
Axial load = 1837.549 kN/m
133
Eccentricity = -0.032 m
From given load analysis combination the maximum soil pressure obtained as:
𝑃𝑢 6×𝑒
𝜎𝑡𝑜𝑒 = 𝐹 × (1 + 𝐹 ) and,
𝑤𝑖𝑑𝑡ℎ 𝑤𝑖𝑑𝑡ℎ
𝑃𝑢 6×𝑒
𝜎ℎ𝑒𝑒𝑙 = × (1 − )
𝐹𝑤𝑖𝑑𝑡ℎ 𝐹𝑤𝑖𝑑𝑡ℎ
Maximum Stress,σtoe =331.473 kN/m^2
Minimum Stress,σheel =251.296 kN/m^2
4.7
= 251.296 + ( × (331.473 − 251.296))
7.5
= 301.54 kN/m2
=42.109kNm/m
Total Moment at section 1-1= 1314.707kNm/m
3.5
= 251.296 + ( × (331.473 − 251.296))
7.5
= 288.711 kN/m2
134
Rectangular portion = 𝜎𝑥 × ((𝐹𝑤𝑖𝑑𝑡ℎ − 𝜎𝑥 + 𝑒)2 × 0.5) = 1447.983𝑘𝑁𝑚/𝑚
1
Triangular portion = 0.5 × (𝜎𝑡𝑜𝑒 − 𝜎𝑥 ) × ((𝐹𝑤𝑖𝑑𝑡ℎ − 𝜎𝑥 + 𝑒)2 × 3)
=71.864kNm/m
Total Moment at section 2-2= 1219.847kNm/m
Design of footing
1314.706×106
Depth required, dreq=√ = 512.983𝑚𝑚
4.996×1000
𝑑 𝑑 𝑀
Depth of neutral axis, x = − √( )2 − (SP: 105 Clause 6.2)
0.832 0.832 0.1347fk𝑏
= 113.843 mm
MEd = 0.87fyAst (d - 0.41597x)
1314.706∗106
i.e, Ast = = 2841.47 mm2
0.87∗500∗1063.64
Spacing of reinforcement:
𝑎×1000
Spacing required = (𝜙 = 28𝑚𝑚)
𝐴𝑠𝑡
615.752×103
= 2841.47
= 216.70 mm
Spacing to be provided at toe section is 200mm
615.752×1000
Area of steel provided =
𝑠𝑝𝑎𝑐𝑖𝑛𝑔 𝑝𝑟𝑜𝑣𝑖𝑑𝑒𝑑
135
615.752×1000
= 200
= 3078.761 mm2
0.26×𝑓𝑐𝑡𝑚
Min. Ast =
𝑓𝑦𝑚
0.26×2.5×103 ×1112.5
=
500
=1446.25mm2
Max. Ast =0.025bd
=0.025 × 1000 × 1112.5
=27812.5mm2
Spacing provided = 200 mm
Bending moment and shear force will be higher in basic combination of load. So, it
will govern the design of footing.
2.6 1 2
i. M1-1 = 395.82 × 2.6 × + 2 × 2.6 × 62.45 × × 2.6=1478.59kNm
2 3
5.2 1 1 5.2
ii. M2-2 = 242.1 × 5.2 × + 2 × 5.2 × 124.9 × × 5.2-1166.1 × =804.22kNm
2 3 2
429.74+458.27
iii. SF3-3 = × 1.188=527.48kN
2
242.1+333.08 1166.1
iv. SF4-4 = × 3.788 - × 3.788=239.93kN
2 5.2
2 1 2
v. M2m from right edge = 410 × 2 × 2 + 2 × 2 × 48.04 × × 2 = 884.05kNm
3
Design of Footing:
Check Depth
1478.59 × 106
dreq = √ = 544.89 mm < 1412.5 mm (ok)
0.133 × 30 × 1000
136
Design of Reinforcement
𝑓𝑦 𝐴𝑠𝑡
Mmax = 0.87fyAst d (1 – )
𝑓𝑐𝑘 𝑏𝑑
500 𝑥 𝐴𝑠𝑡
1478.59 × 106 = 0.87 × 500 × Ast × 1412.5 × (1 – )
25∗1000∗1412.5
On Solving,
Ast = 2494.52 mm2
Astmin = 0.12% 𝑜𝑓 1000 × 1500 = 1800 mm2 < Ast
1000
Spacing of bar, S = 2494.52 = 196.78 mm
𝜋 ×12.52
𝑓𝑦 𝐴𝑠𝑡
Mmax = 0.87fyAst d (1 – )
𝑓𝑐𝑘 𝑏𝑑
500 𝑥 𝐴𝑠𝑡
804.22 × 106 = 0.87 × 500 × Ast × 1412.5 × (1 – )
25 𝑥 1000 𝑥 1412.5
On Solving,
Ast = 1334.05 mm2
Astmin = 0.12% 𝑜𝑓 1000 × 1500 = 1800 mm2 > Ast (Provide Minimum)
1000
Spacing of bar, S = 1800 = 272.71 mm
𝜋 ×12.52
𝑓𝑦 𝐴𝑠𝑡
Mmax = 0.87fyAst d (1 – )
𝑓𝑐𝑘 𝑏𝑑
500 × Ast
884.05 × 106 = 0.87 × 500 × Ast × 1412.5 × (1 – )
25 × 1000 × 1412.5
On Solving,
Ast = 1470.13 mm2
Ast,min = 0.12% 𝑜𝑓 1000 × 1500 = 1800 mm2 > Ast
Thus, minimum reinforcement is provided.
137
1000
Spacing of bar, S = 1800 = 272.71 mm
π ×12.52
i. At section 3-3
Maximum Spacing:
Provide 8mm dia 2-legged vertical stirrups at 300mm c/c.
138
Check development length of bar beyond face of abutment
Maximum crack width of the foundation has been calculated as per IS 456. Bottom
corners of foundation slab are expected to have maximum crack width. Calculation of
crack width is based on Annex F.
Since the section is cracked, all the relations and equations for cracked section can be
applied.
Design crack width is given as: (Annex F)
3acr εm
Wcr = 2(acr -Cmin )
1+
h-x
Minimum clear cover (Cmin) = 75 mm
Diameter of bar (db) = 25 mm
Depth of NA (x) = 182.5 mm
139
Effective Depth (d) = 1412.5 mm
Total Depth (h) = 1500 mm
b = 1000 mm
Then,
𝑎𝑐𝑟 = √(75 + 12.5)2 + (75 + 12.5)2 = 123.74 𝑚𝑚
And,
b × (h-x) × (a-x)
εm =ε1 -
3 × Es × As × (d-x)
where,
M (d-x) 1478.59 × 106 (1412.5-182.5)
ε1 = x
× = 182.5
×
Es × As × (d- 3) (h-x) 200000 × 3775.95 × (1412.5- 3 ) (1500-182.5)
ε1 =0.00111
So,
b × (h-x) × (a-x) 1000 × (1500-182.5) × (1500-182.5)
εm =ε1 - = 0.00111-
3 × Es × As × (d-x) 3 × 200000 × 3775.95 × (1412.5-182.5)
εm =0.000487
3acr εm 3 × 123.74 × 0.000487
Wcr = 2(acr -Cmin )
= 2(123.74-75)
=0.168 mm
1+ 1+
h-x 1500-182.5
Hence, the crack width has been found within the limit.
140
5.4.2 Analysis and Design of Pier
For the design of pier, following data has been obtained from hydrological and
geotechnical investigation report.
Allowable bearing capacity of soil = 370 kN/m2
Bridge span =22m
Size of bearing = 500x300x64mm
Carriageway width = 7.5m
c/c distance between outermost girders = 6.5 m
Size of expansion joint provided = 40mm
Depth of girder (main) = 1.48m
Velocity of water current = 8.3 m/s
Type of foundation = Open foundation
RL of bottom of pier = 842.962 m
Depth of pier = 10.10 m
RL of HFL = 851.062 m
Material
Concrete: M30
Rebar: TMT500D
Type of pier – RCC single column hammer head pier
Preliminary sizing:
Length of pier cap = c/c spacing of main girder + bearing length + 2 * clearance
= 6.5 + .5 + 2*.5 = 8.0m
Minimum Width of pier cap= 2 * projection beyond bearing + c/c distance + width
= 2*0.5+ 0.7 + 0.3 = 2m
Assume diameter of stem = 2.0m and
Projections = 150mm
141
Width, B = 2 +2* 0.15 = 2.3 m
Thickness of pier cap:
Adopt 1500mm at the face of pier stem and 750mm at the end.
Axial Load on pier = (DL + LL) from super structure + DL of pier cap
DL from superstructure = 3288.773 kN
LL from superstructure = 870.382 kN
DL of pier cap = CSA * Width * 25 = 567.094 kN
Pedestal weight = 11.250 kN
Therefore, design axial load Pu = 6526.180 kN Let Ag be the sectional area required then,
Pu = 0.67 fy Asc + 0.4 fck Ac Assume 1% steel reinforcement then 6373.086 x
Load Analysis
(For Class A) 114kN load of rear axle of 1st trailer unit = 865.88kN
(Class 70R Wheeled) 170kN load of rear axle of 2nd trailer unit = 870.38kN
Maximum moment from three girders due to live load in longitudinal direction is
when load is considered on only one span and following axle load is on first bearing:
(For Class A) 114kN load of front axle of 1st trailer unit = 718.47 * 0.4 = 287.39kNm
143
(Class 70R Wheeled) 120kN load of front axle of 1st trailer unit = 709.41 * 0.4 =
283.76kNm
(Class 70R Tracked) it’s end at the midspan = 627.30 * 0.4 = 250.92kNm
Maximum moment from three girders due to live load in transverse direction is when
(d) Load due to braking effect (As per IRC 6 clause 211.2)
144
Case-I
Wind velocity is 36 m/s
Pz = 551.841 N/m2
Wind load = Pz * A * Cd * G
Transverse = Wind load on Superstructure + Wind load on vehicle
= (551.841 * 36.3 * 2 * 1.95 + 551.841 * 66 * 2 * 1.2)/1000 kN
= 165.536 kN
Case-II
Wind velocity is 47 m/s
Pz = 940.6 N/m2
Transverse = Wind load on Superstructure
= 940.6 * 36.3 * 2 * 1.95/1000 kN
= 133.161 kN
Hence, transverse wind load from case-I is maximum.
Longitudinal Load = 0.25 * Transverse load
= 41.384 kN
Vertical Wind load = 940.6 * 242 * 0.75 * 2/1000 = 341.438 kN
Self-weight = 1253.766 kN
146
Design of Pier Cap
Pier cap has been designed as cantilever beam and detailed as per IRC-112
+1.35DLp
= 2644.511 kN
147
Design Shear force (For seismic combination)
Take diameter of bar ∅32 and clear cover 40mm, then effective depth
d = 1500 – 40 – 16 -10 = 1434 mm
β1 = 0.80952
β2 =0.41597
xlim = (ecu/(ecu+eyd))*d = 0.617 d
Mur, lim= β1 fcd b xlim x (d – β2 xlim)
= 0.80952 x 0.67 x fck/1.5 x b xlim (d – 0.41597 xlim)
= 0.166 fck bd2
So, dreq = √ (5994.88 x 106 /(0.166 x 30 x 2300)) = 723 mm < 1500 mm
Hence, depth provided is sufficient.
Design of reinforcement
Depth of neutral axis,
X = 1.202 d – √ (1.45 d2 - Me x 0.2216/b)
= 173.144 mm (sp 105 p. 44)
As = Me/ (0.87fy (d-0.41597xu))
= 10118.622 mm2
148
From IRC 112 16.5.1.1
(𝐴𝑠𝑡)min = 0.26fctm/𝑓𝑦k x bd= 4347.664mm2
And, (𝐴𝑠𝑡)max = 0.04𝑏𝐷 = 0.04𝑥2300𝑥1500 = 138000 𝑚𝑚2
Spacing = 2300 x (π x 322/4) / 10118.622 = 182.808
Provide Φ32 bars @ 170mm c/c
Ast provided = 10880.999 mm2
Here (𝐴𝑠𝑡)m𝑖𝑛 < 𝐴𝑠𝑡 provided < (𝐴𝑠𝑡)𝑚𝑎𝑥
So, designed section is ok.
Shear Reinforcement
149
Angle of inclination of compression face, β = 14.74°
Lever arm, z = 1.43m
Design moment, Mu = 5994.88 kNm
Vccd = Mu/z*tan β = 1100.14 kN
Vtd = 0
VNS = VEd – Vccd – Vtd = 1544.37 kN
With 10mm diameter 6 legged stirrups,
Area of shear reinforcement, Asw = 471.24mm2
fywd = fyk/γm = 434.78 N/mm2
VRd.s = VNS
So, required spacing (s) = Asw z fywd cotθ/ VNS = 428.08 mm
Shear reinforcement ratio, ρw = Asw/(s.bw)
ρw.min = 0.0789%
So,
0.0789 < (Asw/s*2300)*100
=> s < 259.771mm
150
Check for Serviceability
Forces
Load Lever Design Force)
Load (kN)
Factor arm Pu Moment
DLss DLss 995.13 1.00 2.36 995.126 2352.478
DLwc DLwc 102.85 1.20 2.36 123.420 291.765
Cap DLcap 97.03 1.00 1.45 97.031 140.404
Total 1215.577 2784.647
M = 2784.647
As =10880.999 mm2
clear cover = 40 mm
total depth, h = 1500 mm
Es = 200 GPa
Ecm = 31 GPa
modular ratio = 6.452
neutral axis depth, x= 383.960 mm
Ac,eff =165000 mm2
ρp,eff = 0.066
σsc = 195.954
kt = 0.500
fct,eff = 2.5
εsm-εcm = 0.001
c = 40 mm
∅ = 32 mm
Sr,max = 8.492
Thus, Wk = 0.185mm < 0.2mm
Hence, serviceability limit state is verified.
The longitudinal reinforcement of the pier stem is designed as a column using SP 16.
151
Height of pier stem, l0 = 8600 mm
Diameter of the pier stem, D = 2000 mm
Gross CSA concrete, Ac = п/4 * D2 =3141592.654 mm2
Minimum diameter of longitudinal reinforcement, ф min = 12 mm
Take longitudinal bar diameter = 32.000 mm
Clear cover = 75.000
Effective cover, d' = 75+ 32 = 91.000 mm
For an idealized column with an elastomeric bearing at one end and fixed at the other
end:
Effective length of the column, le = 1.3 * l0 = 1.3 * 8600 = 11180 mm (from table
11.1, IRC-112)
Slenderness ratio, λ = le / D = 5.590 < 12 (⸫ Stem is a short column)
𝑙0 𝐷
Min. eccentricity be designed with, e min = + = 83.867mm
500 30
Calculated eccentricity, e = 10015.991 > e min
0.05D = 100.000 mm < e
So, the pier stem is subjected to combined axial load and uniaxial bending.
d' / D = 0.046 ≅ 0.05
The design moment and axial load are taken from load combination table provided in
ANNEX A.
From chart 59 of SP 16,
𝑴𝒖𝒓 𝑷𝒖 𝒑
Combinations Pu Muy Mux Mur
𝐟𝐜𝐤 𝐝𝟑 𝐟𝐜𝐤 𝐝𝟐 𝐟𝐜𝐤
Load
Combination:
Basic, Live 8413.1 4420.3 8386.2 9479.8 0.039 0.070 0.02
Load as
leading
Load
Combination:
7791.5 2970.2 4274.0 5204.7 0.022 0.065 0.01
Basic, Wind
as leading
152
Load
Combination:
Seismic, 7237.7 18015.5 7437.5 19490.3 0.081 0.060 0.06
longitudinal
max
Load
Combination:
Seismic, 7237.7 5916.8 20202.0 21050.7 0.088 0.060 0.07
transverse
max
Load
Combination:
8059.2 5916.8 7437.5 9503.9 0.040 0.067 0.02
Seismic, vert
max
Max p/fck 0.07
Transverse reinforcement:
153
200 200
K=1+√ = 1 + √2000 = 1.33 ≤ 2
𝑑
Asl
ρ1 = п = 0.02048 ≤ 0.02
∗d^2
4
⸫ ρ1 = 0.02
Longitudinal force due to loading, NEd = 7237.74 kN
The cross-sectional area of concrete, Ac = 3141592.65 mm2
Concrete compressive stress at the centroid axis due to axial loading,
σcp = NEd/Ac = 2.304 <0.2*fcd = 2.68
vmin = 0.031 * K3/2 * fck1/2 = 0.26
The design shear resistance of the member without shear reinforcement
VRd.c = (0.12 K* (80*ρ1*fck) * 0.33 + 0.15 * σcp) * п * d2 / 4 = 2385.28 kN
Subjected to minimum of VRd.c = (vmin + 0.15 σcp) п/4 * d2 = 1574.39 kN
Since V Rd.c ≥ V Ed, transverse reinforcement is only provided to hold the longitudinal
reinforcement in place and avoid its buckling.
So, minimum reinforcement is provided as per IRC 112, clause 16.2.3
Maximum spacing, S max = min (12*ф long. min; D; 200 mm)
= min (12 * 32; 2000; 200)
= 200 mm
Minimum diameter of hoops, ф min = max (8mm; ф longitudinal / 4)
= max (8; 32/4)
= 8mm
Provide 10mm diameter 4-legged stirrups
Area of shear reinforcement (ASW) = 314.159 mm2
ρw.min = 0.072*√(fck)/fy = 0.000789
So, max spacing = ASW/(bw* ρw.min) = 199.158 mm
Thus, provide 10ф @ 180 mm c/c.
Thus, as per IRC 112, CL 17.2.1.1.3 confinement of the compression zone is provided
154
Take the diameter of the hoop, d = 20 mm
Confined concrete core’s diameter measured up to the hoop centerline = 2000 – 2 * 75
+ 20
= 1870 mm
As per IRC 112, clause 17.2.1.3, spacing of hoops or ties in the longitudinal direction,
SL ≤ 5 * diameter of the smallest longitudinal bar = 160 mm
SL ≤ 1/5 * 1866 mm = 373.2 mm
Take SL = 110 mm
Diameter of the hoop bar, Dsp = 2000 – 2*75 + 2*20 = 1890 mm
Area of the hoop bar, Asp = п/4 * 162 = 314.16 mm2
4𝐴𝑠𝑝
Volumetric ratio, ρw = = 0.006044
𝑆𝐿∗𝐷𝑠𝑝
𝜌𝑤∗𝑓𝑦𝑑
Required quantity of confining reinforcement, ωwd = = 0.1961
𝑓𝑐𝑑
Confined (core) concrete area of the section within the outside diameter of the hoop,
Acc = 2805520.78 mm2
⸫ ωwd.c ≥ 0.180
ωwd ≥ ωwd.c. Hence, OK. provide 20 ф hoop bar at spacing 110 mm c/c.
Since normalized axial force, ηk ≤ 0.24. As per IRC 112, clause 17.2.1.4 the design
length Lh of
potential plastic hinges is estimated as the larger of the following two values:
depth of the pier section within the plane of bending (perpendicular to the axis of
rotation of the hinge) i.e. diameter of pier stem.
distance from the point of maximum design moment to the point where the design
moment is 80 percent of the value of the maximum moment.
Let x be the distance from the stem base where the moment is 80 percent of the value
of the
155
maximum moment. Then, the moment for seismic load combination in the transverse
direction at
that point is calculated below:
14 14
√(∑ 𝐻𝑥𝑖 ∗ 𝑍 + 𝑀𝑢𝑦𝐿𝐿)2 + (∑ 𝐻𝑦𝑖 ∗ 𝑍 + 𝑀𝑢𝑥𝐿𝐿)2 = 0.8 ∗ 𝑀𝑢𝑟
𝑖=1 𝑖=1
Material
Concrete -M30
Rebar grade – Fe500D
Soil properties
Preliminary dimension
Length, L = 10 m
Breadth, B = 10 m
Area, A = 100 m2
Depth, Df = 2 m
Self-weight = 10 * 10 * 1.6 *25 = 4000kN
Analysis of footing
157
Load combination table summary
Design Parameters
Depth, Df = 2 m
Clear cover = 75 mm
Diameter of rebar = 32 mm
Area of single rebar = 804.248 mm2
Effective depth, dy = 1909 mm
Effective depth, dx = 1877 mm
Effective depth, d = 1893 mm
158
For Mux –
160
Spacing provided = 130 mm
Ast provided along longitudinal direction = 61865.209 mm2
VEd = 14040.130 kN
Average pressure, Wavg = 140.401 kN/m2
e
β = 1 + 0.6 π(D+4d) = 1.342
Ast,along longitudinal
% steel in longitudinal direction, ρl = = 0.00324
dy∗L
Ast,along transverse
% steel in transverse direction, ρt = = 0.00330
dx ∗ L
𝟐𝟎𝟎
k=1+√ = 1.325
𝐝
a = 2d = 3786 mm
vmin = 0.031 * k3/2 * fck1/2 = 0.259 N/mm2
161
1
2d 2d
vRd = (0.12k (80ρ1 fck )3 ) ≥ vmin ∗ = 0.316 N/mm2
a a
𝟐𝟎𝟎
k=1+√ = 1.325
𝐝
a = d = 1893 mm
1
2d 2d
vRd = (0.12k (80ρ1 fck )3 ) ≥ vmin ∗ = 0.632 N/mm2
a a
At face of column
vRd max= 0.134 * fck * (1 – fck /310) = 3.631 N/mm2 > vEd, Ok
Hence, the footing is safe in shear.
162
6 REFERENCES
1. Raju, N. K. Design of Bridges (Fourth ed.). New Delhi: Oxford & IBH
Publishing Co Pvt. Ltd.
5. Agni Boring and Soil Test Pvt. Ltd. Geotechnical Report on Soil Investigation
work for Rapati Khola (Golphing Beshi and Aapchour) RCC Bridge of
Bhimphedi Rural Municipality, LRBSU
6. New Planet Engineering Services Pvt. Ltd., Kathmandu. Detail Project Report
(DPR) Preparation of Rapati Khola RCC Bridge of Bhimphedi Rural
Municipality, LRBSU
163
7 CODES AND STANDARDS
1. ‘IRC: 5-2015 Standard Specification and Code of Practices for Road Bridges,
Section-I General Features of Design’, Indian Road Congress, 2015
2. ‘IRC: 6-2017 Standard Specification and Code of Practices for Road Bridges,
Section-II Loads and Stresses’, Indian Road Congress, 2017
3. ‘IRC: 78-2014 Standard Specification and Code of Practices for Road Bridges,
Section-VII –Foundation and Substructure’, Indian Road Congress, 2000
4. ‘IRC: 83-1987 Standard Specification and Code of Practices for Road Bridges,
Section IX- Bearings- Part II: Elastomeric bearings’, Indian Road Congress,
1996
5. ‘IRC: 83-2018 Standard Specification and Code of Practices for Road Bridges,
Section-IX - Bearings- Part II: Elastomeric bearings’, Indian Road Congress,
2018
6. ‘IRC: 112-2020 Code of Practices for Concrete Road Bridges’, Indian Road
Congress, 2020
7. ‘IRC SP 105: Explanatory Handbook to IRC:112-2011: Code of Practice for
Concrete Roads Bridges’, Indian Road Congress, 2015
8. ‘SP 16-1980: Design Aids for Reinforced Concrete to IS: 456-1978’, Bureau of
Indian Standards, 1980
9. ‘IS 1893: Criteria for Earthquake Resistant Design of Structures’, Bureau of
Indian Standards, 1986
164
ANNEX A
165
Analysis of Abutment Stem
166
Seismic Condition - H+0.3V
Load Force Lever Frorce Moment
SN Description Factor Vertical Horizontal arm Axial Shear Resisting Overturning
Dirtwall
1 Weight 1 13.875 0.45 13.88 6.24
2 Stem Weight 1 214.500 0.00 214.50 0.00
Abutment
3 Cap Weight 1.35 30.000 0.15 40.50 6.08
4 DLas 1 19.432 0.45 19.43 8.74
5 DLss 1.35 132.980 0.30 179.52 53.86
6 DLwc 1.75 16.500 0.30 28.88 8.66
7 LLss 0.2 69.730 0.30 13.95 4.18
8 FHbr 0.2 18.182 8.20 3.64 29.82
9 Fvbr 0.2 2.438 0.30 0.49 0.15
10 Fvwl 0 10.926 0.30 0.00 0.00
11 FLwl 0 1.065 11.40 0.00 0.00
12 Fcst 0.5 0.988 8.20 0.49 4.05
13 Fep(v) 1 61.043 0.60 61.04 36.63
14 Fep(H) 1 159.513 3.23 159.51 515.87
15 Fsur(v) 0.2 16.181 0.45 3.24 1.46
16 Fsur(H) 0.2 39.064 4.90 7.81 38.28
17 Seismic Loads - Horizontal
Dirtwall
17a Weight 1.5 2.498 8.88 3.75 33.25
17b Stem Weight 1.5 38.610 7.55 57.92 437.26
Abutment
17c Cap Weight 1.5 5.400 3.58 8.10 28.96
17d Fep(H) 1.5 3.498 4.90 5.25 25.71
17e Fsur(H) 1.5 23.936 6.47 35.90 232.23
Seismic
Loads -
18 Vertical
Dirtwall
18a Weight 1.5 0.500 0.45 0.75 0.34
18b Stem Weight 1.5 7.722 0.00 11.58 0.00
Abutment
18c Cap Weight 1.5 1.080 0.15 1.62 0.24
18d Live Load 1.5 0.502 0.30 0.75 0.23
18e Fep(v) 1.5 17.626 0.60 26.44 15.86
18f Fsur(v) 1.5 4.317 0.45 6.47 2.91
Sum 623.04 282.37 72.18 1418.81
167
Seismic Condition - 0.3H+V
Load Force Lever Frorce Moment
SN Description Factor Vertical Horizontal arm Axial Shear Resisting Overturning
1 Dirtwall Weight 1 13.875 0.45 13.88 6.24
2 Stem Weight 1 214.500 0.00 214.50 0.00
Abutment Cap
3 Weight 1.35 30.000 0.15 40.50 6.08
4 DLas 1 19.432 0.45 19.43 8.74
5 DLss 1.35 132.980 0.30 179.52 53.86
6 DLwc 1.75 16.500 0.30 28.88 8.66
7 LLss 0.2 69.730 0.30 13.95 4.18
8 FHbr 0.2 18.182 8.20 3.64 29.82
9 Fvbr 0.2 2.438 0.30 0.49 0.15
v
10 F wl 0 10.926 0.30 0.00 0.00
L
11 F wl 0 1.065 11.40 0.00 0.00
12 Fcst 0.5 0.988 8.20 0.49 4.05
13 Fep(v) 1 61.043 0.60 61.04 36.63
14 Fep(H) 1 159.513 3.23 159.51 515.87
15 Fsur(v) 0.2 16.181 0.45 3.24 1.46
16 Fsur(H) 0.2 39.064 4.90 7.81 38.28
17 Seismic Loads - Horizontal
17a Dirtwall Weight 1.5 0.749 8.88 1.12 9.97
17b Stem Weight 1.5 11.583 7.55 17.37 131.18
Abutment Cap
17c Weight 1.5 1.620 3.58 2.43 8.69
17d Fep(H) 1.5 1.049 4.90 1.57 7.71
17e Fsur(H) 1.5 7.181 6.47 10.77 69.67
Seismic Loads -
18 Vertical
18a Dirtwall Weight 1.5 1.665 0.45 2.50 1.12
18b Stem Weight 1.5 25.740 0.00 38.61 0.00
Abutment Cap
18c Weight 1.5 3.600 0.15 5.40 0.81
18d Live Load 1.5 1.674 0.30 2.51 0.75
18e Fep(v) 1.5 58.754 0.60 88.13 52.88
18f Fsur(v) 1.5 14.389 0.45 21.58 9.71
Sum 734.15 204.73 116.79 889.73
168
Combination (1) - Wind Load
Forces Lever Load Factored Forces Factored Moments
SN Description
Vertical Horizontal Arm Factor Axial Shear Resisting Overturning
Dirtwall
1 Weight 13.875 0.20 1 13.875
2 Stem Weight 214.500 0.65 1 214.500
Abutment Cap
3 Weight 30.000 0.80 1.35 40.500 32.400
Footing
4 Weight 225.000 0.00 1 225.000 0.000
5 DLas 19.432 0.20 1 19.432 3.886
6 DLss 132.980 0.95 1.35 179.523 170.546
7 DLwc 16.500 0.95 1.75 28.875 27.431
8 LLss 69.730 0.95 1.15 80.189 76.180
9 FHbr 18.182 9.40 1.15 20.909 196.545
10 Fvbr 2.438 0.95 1.15 2.804 2.664
11 Fvwl 10.926 0.95 1.5 16.390 15.570
12 FLwl 1.065 12.60 1.5 1.598 20.135
13 Fcst 0.988 9.40 0.9 0.889 8.360
14 Fep(v) 61.043 0.05 1 61.043 3.052
15 Fep(H) 159.513 5.32 1.5 239.270 1271.959
16 Backfill Weight 837.900 1.85 1 837.900 1550.115
17 Fsur(v) 16.181 0.20 1.2 19.417 3.883
18 Fsur(H) 39.064 11.90 1.2 46.877 557.841
Sum 1739.447 309.544 1550.115 2390.453
169
Analysis for design of footing
170
Seismic Combination 0.3H+V
171
Abutment
20c Cap Weight 3.600 0.80 1.5 5.400 4.320
Footing
20d Weight 27.000 0.00 1.5 40.500 0.000
20e Live Load 1.674 0.95 1.5 2.510 2.385
20f Fep(v) 58.754 0.05 1.5 88.131 4.407
20g Fsur(v) 14.389 0.20 1.5 21.583 4.317
Sum 1837.549 222.955 1550.115 1491.151
172
Combination (1) - Carriageway Load
173
Stability Check
174
Wind Load as Leading
Forces Lever Load Factored Forces Factored Moments
SN Description
Vertical Horizontal Arm Factor Axial Shear Resisting Overturning
Dirtwall
1 Weight 13.875 3.550 0.9 12.488 44.331
2 Stem Weight 214.500 3.100 0.9 193.050 598.455
Abutment Cap
3 Weight 30.000 2.950 0.9 27.000 79.650
Footing
4 Weight 225.000 3.750 0.9 202.500 759.375
5 DLas 19.432 3.550 0.9 17.489 62.085
6 DLss 132.980 2.800 0.9 119.682 335.109
7 DLwc 16.500 2.800 1 16.500 46.200
8 LLss 69.730 2.800 0 0.000 0.000
9 FHbr 18.182 9.400 0 0.000 0.000
10 Fvbr 2.438 2.800 0 0.000 0.000
v
11 F wl 10.926 2.800 0 0.000 0.000
12 FLwl 1.065 11.800 1.5 1.598 18.856
13 Fcst 0.988 9.400 1.1 1.087 10.218
14 Fep(v) 61.043 3.700 1 61.043 225.859
15 Fep(H) 159.513 5.316 1.5 239.270 1271.959
Backfill
16 Weight 837.900 5.600 1 837.900 4692.240
17 Fsur(v) 16.181 3.550 0 0.000 0.000
18 Fsur(H) 39.064 11.900 1.2 46.877 557.841
Sum 1487.651 288.832 6843.303 1858.874
175
Seismic Combination H+0.3V
Factored Factored
Forces Lever Load
SN Description Forces Moments
Arm Factor
Vertical Horizontal Axial Shear Resisting Overturning
Dirtwall
1 Weight 13.875 3.550 0.9 12.488 44.331
2 Stem Weight 214.500 3.100 0.9 193.050 598.455
Abutment
3 Cap Weight 30.000 2.950 0.9 27.000 79.650
Footing
4 Weight 225.000 3.750 0.9 202.500 759.375
5 DLas 19.432 3.550 0.9 17.489 62.085
6 DLss 132.980 2.800 0.9 119.682 335.109
7 DLwc 16.500 2.800 1 16.500 46.200
8 LLss 69.730 2.800 0 0.000 0.000
9 FHbr 18.182 9.400 0.2 3.636 34.182
10 Fvbr 2.438 2.800 0 0.000 0.000
v
11 F wl 10.926 2.800 0 0.000 0.000
12 FLwl 1.065 11.800 0 0.000 0.000
13 Fcst 0.988 9.400 0.5 0.494 4.645
14 Fep(v) 61.043 3.700 1 61.043 225.859
15 Fep(H) 159.513 5.316 1 159.513 847.972
Backfill
16 Weight 837.900 5.600 1 837.900 4692.240
17 Fsur(v) 16.181 3.550 0 0.000 0.000
18 Fsur(H) 39.064 6.100 0 0.000 0.000
19 Seismic Loads - Horizontal
Dirtwall
19a Weight 2.498 10.075 1.5 3.746 37.743
19b Stem Weight 38.610 4.775 1.5 57.915 276.544
Abutment
19c Cap Weight 5.400 8.750 1.5 8.100 70.875
Footing
19d Weight 40.500 0.600 1.5 60.750 36.450
19e Fep(H) 3.498 6.100 1.5 5.247 32.004
19f Fsur(H) 23.936 7.668 1.5 35.905 275.316
20 Seismic Loads - Vertical
Dirtwall
20a Weight 0.500 3.550 1.5 0.749 2.660
20b Stem Weight 7.722 3.100 1.5 11.583 35.907
Abutment
20c Cap Weight 1.080 2.950 1.5 1.620 4.779
Footing
20d Weight 27.000 3.750 1.5 40.500 151.875
20e Live Load 0.502 2.800 1.5 0.753 2.109
20f Fep(v) 17.626 3.700 1.5 26.439 97.826
20g Fsur(v) 4.317 3.550 1.5 6.475 22.986
176
Sum 1501.603 335.306 6886.650 1615.731
H+0.3V combination
Factored Factored
Forces Lever Load
SN Description Forces Moments
Arm Factor
Vertical Horizontal Axial Shear Resisting Overturning
Dirtwall
1 Weight 13.875 3.550 0.9 12.488 44.331
2 Stem Weight 214.500 3.100 0.9 193.050 598.455
Abutment
3 Cap Weight 30.000 2.950 0.9 27.000 79.650
Footing
4 Weight 225.000 3.750 0.9 202.500 759.375
5 DLas 19.432 3.550 0.9 17.489 62.085
6 DLss 132.980 2.800 0.9 119.682 335.109
7 DLwc 16.500 2.800 1 16.500 46.200
8 LLss 69.730 2.800 0 0.000 0.000
9 FHbr 18.182 9.400 0.2 3.636 34.182
10 Fvbr 2.438 2.800 0 0.000 0.000
11 Fvwl 10.926 2.800 0 0.000 0.000
12 FLwl 1.065 11.800 0 0.000 0.000
13 Fcst 0.988 9.400 0.5 0.494 4.645
14 Fep(v) 61.043 3.700 1 61.043 225.859
15 Fep(H) 159.513 5.316 1 159.513 847.972
Backfill
16 Weight 837.900 5.600 1 837.900 4692.240
17 Fsur(v) 16.181 3.550 0 0.000 0.000
18 Fsur(H) 39.064 6.100 0 0.000 0.000
177
Seismic Combination 0.3H+V
Factored Factored
Forces Lever Load
SN Description Forces Moments
Arm Factor
Vertical Horizontal Axial Shear Resisting Overturning
Dirtwall
1 Weight 13.875 3.550 0.9 12.488 44.331
2 Stem Weight 214.500 3.100 0.9 193.050 598.455
Abutment
3 Cap Weight 30.000 2.950 0.9 27.000 79.650
Footing
4 Weight 225.000 3.750 0.9 202.500 759.375
5 DLas 19.432 3.550 0.9 17.489 62.085
6 DLss 132.980 2.800 0.9 119.682 335.109
7 DLwc 16.500 2.800 1 16.500 46.200
8 LLss 69.730 2.800 0 0.000 0.000
9 FHbr 18.182 9.400 0.2 3.636 34.182
10 Fvbr 2.438 2.800 0 0.000 0.000
11 Fvwl 10.926 2.800 0 0.000 0.000
L
12 F wl 1.065 11.800 0 0.000 0.000
13 Fcst 0.988 9.400 0.5 0.494 4.645
14 Fep(v) 61.043 3.700 1 61.043 225.859
15 Fep(H) 159.513 5.316 1 159.513 847.972
Backfill
16 Weight 837.900 5.600 1 837.900 4692.240
17 Fsur(v) 16.181 3.550 0 0.000 0.000
18 Fsur(H) 39.064 6.100 0 0.000 0.000
19 Seismic Loads - Horizontal
Dirtwall
19a Weight 0.749 10.075 1.5 1.124 11.323
19b Stem Weight 11.583 4.775 1.5 17.375 82.963
Abutment
19c Cap Weight 1.620 8.750 1.5 2.430 21.263
Footing
19d Weight 12.150 0.600 1.5 18.225 10.935
19e Fep(H) 1.049 6.100 1.5 1.574 9.601
19f Fsur(H) 7.181 7.668 1.5 10.771 82.595
20 Seismic Loads - Vertical
Dirtwall
20a Weight 1.665 3.550 1.5 2.498 8.866
20b Stem Weight 25.740 3.100 1.5 38.610 119.691
Abutment
20c Cap Weight 3.600 2.950 1.5 5.400 15.930
Footing
20d Weight 27.000 3.750 1.5 40.500 151.875
20e Live Load 1.674 2.800 1.5 2.510 7.029
20f Fep(v) 58.754 3.700 1.5 88.131 326.085
20g Fsur(v) 14.389 3.550 1.5 21.583 76.620
Sum 1534.158 215.142 6987.791 1105.479
Factor of safety for:
178
total restoring moment 6987.781
Overturning = = = 6.32 >1.5 (OK)
Total overturning moment 1105.479
Resisting Force tanφ × V
Sliding = = = 7.31 >1.25 (OK)
Horizontal Force H
Footing
ΣM 909.870 kNm/m
Pu 1758.150 kN/m
e 0.518 m
179
Maximum Stress,σtoe 331.473 kN/m2
Minimum Stress,σheel 137.367 kN/m2
ΣM 840.338 kNm/m
Pu 1739.447 kN/m
e 0.483 m
Maximum Stress,σtoe 321.562 kN/m2
Minimum Stress,σheel 142.290 kN/m2
180
Abutment
3 Cap Weight 30.000 0.80 1.35 40.500 32.400
Footing
4 Weight 225.000 0.00 1 225.000 0.000
5 DLas 19.432 0.20 1 19.432 3.886
6 DLss 132.980 0.95 1.35 179.523 170.546
7 DLwc 16.500 0.95 1.75 28.875 27.431
8 LLss 69.730 0.95 0.2 13.946 13.249
9 FHbr 18.182 9.40 0.2 3.636 34.182
10 Fvbr 2.438 0.95 0.2 0.488 0.463
11 Fvwl 10.926 0.95 0 0.000 0.000
12 FLwl 1.065 12.60 0 0.000 0.000
13 Fcst 0.988 9.40 0.5 0.494 4.645
14 Fep(v) 61.043 0.05 1 61.043 3.052
15 Fep(H) 159.513 5.32 1 159.513 847.972
Backfill
16 Weight 837.900 1.85 1 837.900 1550.115
17 Fsur(v) 16.181 0.20 0.2 3.236 0.647
18 Fsur(H) 39.064 11.90 0.2 7.813 92.973
19 Seismic Loads - Horizontal
Dirtwall
19a Weight 2.498 10.08 1.5 3.746 37.743
19b Stem Weight 38.610 4.78 1.5 57.915 276.544
Abutment
19c Cap Weight 5.400 8.75 1.5 8.100 70.875
Footing
19d Weight 40.500 0.60 1.5 60.750 36.450
19e Fep(H) 3.498 6.10 1.5 5.247 32.004
19f Fsur(H) 23.936 7.67 1.5 35.905 275.316
Seismic Loads
20 - Vertical
Dirtwall
20a Weight 0.500 0.20 1.5 0.749 0.150
20b Stem Weight 7.722 0.65 1.5 11.583 7.529
Abutment
20c Cap Weight 1.080 0.80 1.5 1.620 1.296
Footing
20d Weight 27.000 0.00 1.5 40.500 0.000
20e Live Load 0.502 0.95 1.5 0.753 0.715
20f Fep(v) 17.626 0.05 1.5 26.439 1.322
20g Fsur(v) 4.317 0.20 1.5 6.475 1.295
Sum 1726.437 343.119 1550.115 1972.687
181
ΣM 422.572 kNm/m
Pu 1726.437 kN/m
e 0.245 m
Maximum Stress,σtoe 275.266 kN/m2
Minimum Stress,σheel 185.117 kN/m2
ΣM 530.622 kNm/m
Pu 1660.813 kN/m
e 0.319 m
Maximum Stress,σtoe 278.041 kN/m2
Minimum Stress,σheel 164.842 kN/m2
182
Combination (2) - Carriageway Load
Forces Lever Load Factored Forces Factored Moments
SN Description
Vertical Horizontal Arm Factor Axial Shear Resisting Overturning
1 Dirtwall Weight 13.875 0.20 1 13.875 2.775
2 Stem Weight 214.500 0.65 1 214.500 139.452
Abutment Cap
3 Weight 30.000 0.80 1 30.000 24.000
4 Footing Weight 225.000 0.00 1 225.000 0.000
5 DLas 19.432 0.20 1 19.432 3.886
6 DLss 132.980 0.95 1 132.980 126.331
7 DLwc 16.500 0.95 1 16.500 15.675
8 LLss 69.730 0.95 1 69.730 66.243
9 FHbr 18.182 9.40 1 18.182 170.909
10 Fvbr 2.438 0.95 1 2.438 2.316
11 Fvwl 10.926 0.95 1.3 14.204 13.494
12 FLwl 1.065 12.60 1.3 1.385 17.450
13 Fcst 0.988 9.40 0.8 0.791 7.431
14 Fep(v) 61.043 0.05 0.85 51.887 2.594
15 Fep(H) 159.513 5.32 1.3 207.367 1102.364
16 Backfill Weight 837.900 1.85 1 837.900 1550.115
17 Fsur(v) 16.181 0.20 1 16.181 3.236
18 Fsur(H) 39.064 11.90 1 39.064 464.867
Sum 1644.626 266.789 1550.115 2020.798
ΣM 470.683 kNm/m
Pu 1644.626 kN/m
e 0.286 m
Maximum Stress,σtoe 269.490 kN/m2
Minimum Stress,σheel 169.077 kN/m2
0.3H + V Combination
183
9 FHbr 18.182 9.40 0.2 3.636 34.182
10 Fvbr 2.438 0.95 0.2 0.488 0.463
v
11 F wl 10.926 0.95 0 0.000 0.000
12 FLwl 1.065 12.60 0 0.000 0.000
13 Fcst 0.988 9.40 0.5 0.494 4.645
14 Fep(v) 61.043 0.05 1 61.043 3.052
15 Fep(H) 159.513 5.32 1 159.513 847.972
16 Backfill Weight 837.900 1.85 1 837.900 1550.115
17 Fsur(v) 16.181 0.20 0.2 3.236 0.647
18 Fsur(H) 39.064 11.90 0.2 7.813 92.973
19 Seismic Loads - Horizontal
19a Dirtwall Weight 0.749 10.08 1.5 1.124 11.323
19b Stem Weight 11.583 4.78 1.5 17.375 82.963
Abutment Cap
19c Weight 1.620 8.75 1.5 2.430 21.263
19d Footing Weight 12.150 0.60 1.5 18.225 10.935
19e Fep(H) 1.049 6.10 1.5 1.574 9.601
19f Fsur(H) 7.181 7.67 1.5 10.771 82.595
Seismic Loads -
20 Vertical
20a Dirtwall Weight 1.665 0.20 1.5 2.498 0.500
20b Stem Weight 25.740 0.65 1.5 38.610 25.097
Abutment Cap
20c Weight 3.600 0.80 1.5 5.400 4.320
20d Footing Weight 27.000 0.00 1.5 40.500 0.000
20e Live Load 1.674 0.95 1.5 2.510 2.385
20f Fep(v) 58.754 0.05 1.5 88.131 4.407
20g Fsur(v) 14.389 0.20 1.5 21.583 4.317
Sum 1837.549 222.955 1550.115 1491.151
ΣM -58.964 kNm/m
Pu 1837.549 kN/m
e -0.032 m
Maximum Stress,σtoe 238.717 kN/m2
Minimum Stress,σheel 251.296 kN/m2
184
Load Combination Tables for Pier Stem
i)Basic Combination
185
Load Combination: Basic, Wind as leading
Eccentricity
Load Lever Design Force (kN or kN-m)
Load (kN) (m)
Factor arm
ey ex Pu Hx Hy Muy Mux
DLss 3288.77 1.35 0.00 0.00 - 4439.84
DLwc 363.00 1.75 0.00 0.00 - 635.25
T
F wc 317.08 1.00 1.00 317.08 317.08
FLwc 42.01 1.00 1.00 42.01 42.01
T
F w 165.54 1.50 0.90 248.30 223.47
186
ii)Seismic Combination
187
Load Combination: Seismic, transverse max
Eccentricity
Load Lever Design Force (kN or kN-m)
Load (kN) (m)
Factor arm
ey ex Pu Hx Hy Muy Mux
DLss 3288.77 1.35 0.00 0.00 - 4439.84
DLwc 363.00 1.75 0.00 0.00 - 635.25
FTwc 317.08 1.00 5.57 317.08 1765.85
FLwc 42.01 1.00 5.57 42.01 233.93
FVs 189.56 1.50 0.00 0.00 - 284.34
FVs sub 45.14 1.50 0.00 0.00 - 67.70
FLs 266.39 1.50 10.60 399.59 4235.61
FLs sub 67.70 1.50 9.35 101.56 949.54
FTs 947.80 1.50 10.60 1421.70 15070.03
FTs sub 225.68 1.50 9.35 338.52 3165.13
Fbuoy -61.64 1.00 0.00 0.00 - -61.64
FHbr 208.00 0.20 10.60 41.60 440.96
FVbr 27.89 0.20 0.00 0.00 - 5.58
Wpier 1253.77 1.35 0.00 0.00 - 1692.58
Total without Live Load 7063.66 584.75 2077.30 5860.04 20001.01
LL,Pu 870.38 0.20 174.08
LL,Ml 709.41 0.20 0.40 56.75
LL,Mt 870.38 0.20 1.16 201.06
Total with Live Load 7237.74 584.75 2077.30 5916.79 20202.07
Resultant 2158.04 21050.70
188
Load Combination: Seismic, vertical max
Eccentricity
Load Lever Design Force (kN or kN-m)
Load (kN) (m)
Factor arm
ey ex Pu Hx Hy Muy Mux
DLss 3288.77 1.35 - 4439.84
DLwc 363.00 1.75 - 635.25
FTwc 317.08 1.00 5.57 317.08 1765.85
FLwc 42.01 1.00 5.57 42.01 233.93
FVs 631.87 1.50 - 947.80
189
Design axial force (Pu) = 8059.17 kN
190
Analysis of footing
Load combination tables
Combination i
Load Combination 1, carriageway load
191
Combination ii
Load Combination 2, carriageway load
192
Combination iii
Load Combination 1 wind
193
Combination iv
Load Combination 2 Wind
194
Combination v
Load Combination: Seismic, longitudinal max
195
Combination vi
Load Combination: Seismic, transverse max
196
Combination vii
Load Combination: Seismic, Vertical max
197
Load combination table for Bearing Check
𝑩.𝑫𝟑
Section modulus, Z = 𝟔 = 166.67 m3
Area = B.D = 100 m2
𝐏 𝑴
Base pressure on foundation, W = 𝐀 ± 𝐙𝒖𝒙
Combination i
Combination I (DL = LL + Water Current + Braking + Buoyancy)
198
Combination ii
Combination II = Combination I + Wind
199
Combination iii
Combination II = Combination I + Seismic
Ecce
ntricity Lever Design Force (kN or kN-m)
Load (kN) (m) arm
ey ex Pu Hx Hy Muy Mux
DLss 3288.77 0.00 0.00 - 3288.77
DLwc 363.00 0.00 0.00 - 363.00
FTwc 317.08 7.57 317.08 2400.33
L
F wc 42.01 7.57 42.01 317.98
V
F s 631.87 0.00 0.00 - 631.87
FVs sub 150.45 0.00 0.00 - 150.45
FLs 887.97 12.60 887.97 11188.40
FLs sub 225.68 11.35 225.68 2561.44
T
F s 947.80 12.60 947.80 11942.29
FTs sub 225.68 11.35 225.68 2561.44
Fbuoy -61.64 0.00 0.00 - -61.64
FHbr 208.00 12.60 208.00 2620.80
V
F br 27.89 0.00 0.00 - 27.89
Wpier 1253.77 0.00 0.00 - 1253.77
Wfooting 5000.00 - 5000.00
Total without Live Load 10654.11 1363.65 1490.56 16688.63 16904.07
LL,Pu 870.38 870.38
LL,Ml 709.41 0.40 283.76
LL,Mt 870.38 1.16 1005.29
Total with Live Load 11524.49 1363.65 1490.56 16972.40 17909.36
200
Combination iv
Combination III wind
201
Combination v
Combination III + seismic
Ecce
ntricity Design Force (kN or kN-m)
Lever
Load (kN) (m) arm
ey ex Pu Hx Hy Muy Mux
DLss 3288.77 0.00 0.00 - 3288.77
DLwc 363.00 0.00 0.00 - 363.00
FTwc 42.01 7.57 42.01 317.98
FLwc 165.54 7.57 165.54 1253.11
FVs 631.87 0.00 0.00 - 631.87
FVs sub 150.45 0.00 0.00 - 150.45
FLs 887.97 12.60 887.97 11188.40
L
F s sub 225.68 11.35 225.68 2561.44
T
F s 947.80 12.60 947.80 11942.29
FTs sub 225.68 11.35 225.68 2561.44
Fbuoy 870.38 0.00 0.00 - 870.38
Wpier 0.00 0.00 0.00 - 0.00
Wfooting 5000.00 - 5000.00
Total 10304.47 1279.18 1215.48 15002.95 14821.71
Allowable bearing pressure = 350 kN/m2 > Absolute max Wmax = 222.701 kN/m2 (OK)
202
ANNEX B
203
44800
SUBMITTED BY:
TRIBHUVAN UNIVERSITY PROJECT TITLE: Sapan Pokharel (075BCE115) SCALE: 1:200
SHEET TITLE:
INSTITUTE OF ENGINEERING DESIGN OF RC T-GIRDER Subodh Subedi (075BCE125) PROJECT SUPERVISOR:
Tejendra Bist (075BCE138)
DEPARTMENT OF CIVIL ENGINEERING BRIDGE Er. Biswa Kumar Balla GENERAL ARRANGEMENT
Vivek Pokharel (075BCE142)
THAPATHALI CAMPUS Yuken Shrestha(075BCE143) DRAWING DWG NO. 1
Yukesh Chaulagain (075BCE144)
22200
2250
℄ Longitudinal
Girder 1 7000
2950
3250
11000
℄ Bridge
3250
℄ Longitudinal
2250
Girder 3
℄ Bearing
℄ Cross Girder
℄ Cross Girder
℄ Bearing
PLAN OF MAIN AND CROSS GIRDER
SUBMITTED BY:
TRIBHUVAN UNIVERSITY PROJECT TITLE: Sapan Pokharel (075BCE115) SCALE: 1:100
SHEET TITLE:
INSTITUTE OF ENGINEERING DESIGN OF RC T-GIRDER Subodh Subedi (075BCE125) PROJECT SUPERVISOR:
Tejendra Bist (075BCE138)
DEPARTMENT OF CIVIL ENGINEERING BRIDGE Er. Biswa Kumar Balla SLAB PLAN
Vivek Pokharel (075BCE142)
THAPATHALI CAMPUS Yuken Shrestha(075BCE143) DWG NO. 2.1
Yukesh Chaulagain (075BCE144)
8NOSΦ10mm
Φ10@250mm c/c
Φ8@100mm c/c I II
8NOSΦ8mm
4Φ16mm
Φ10@250mm c/c
1100
Φ10@200mm c/c Φ12@100mm c/c
Φ10@200mm c/c
Φ12@100mm c/c
150 225
125
225
I II
220
220
150
Φ12@100mm c/c
Φ10@200mm c/c
Φ10@200mm c/c
2100
2250
INTERIOR SLAB
CANTILEVER DETAILING
DETAILING
SUBMITTED BY:
TRIBHUVAN UNIVERSITY PROJECT TITLE: Sapan Pokharel (075BCE115) SCALE: 1:20
SHEET TITLE:
INSTITUTE OF ENGINEERING DESIGN OF RC T-GIRDER Subodh Subedi (075BCE125) PROJECT SUPERVISOR:
Tejendra Bist (075BCE138)
DEPARTMENT OF CIVIL ENGINEERING BRIDGE Er. Biswa Kumar Balla REINFORCEMENT DETAILING
Vivek Pokharel (075BCE142)
THAPATHALI CAMPUS Yuken Shrestha(075BCE143) OF SLAB DWG NO. 2.2
Yukesh Chaulagain (075BCE144)
Φ12@100mm c/c Φ10@200mm c/c
Φ12@100mm c/c
Φ10@200mm c/c
150
300
150
Φ12@100mm c/c Φ12@100mm c/c
Φ10@200mm c/c Φ10@200mm c/c
150
200
250
700
SUBMITTED BY:
TRIBHUVAN UNIVERSITY PROJECT TITLE: Sapan Pokharel (075BCE115) SCALE: 1:30
SHEET TITLE:
INSTITUTE OF ENGINEERING DESIGN OF RC T-GIRDER Subodh Subedi (075BCE125) PROJECT SUPERVISOR:
Tejendra Bist (075BCE138)
DEPARTMENT OF CIVIL ENGINEERING BRIDGE Er. Biswa Kumar Balla REINFORCEMENT DETAILING
Vivek Pokharel (075BCE142)
THAPATHALI CAMPUS Yuken Shrestha(075BCE143) OF GIRDER DWG NO. 3.1
Yukesh Chaulagain (075BCE144)
22940
5Nos.Φ10 side bar @ 200 c/c
Φ8 vertical stirrups @130 c/c
Φ8 vertical stirrups @150 c/c
Φ8 vertical stirrups @200 c/c Φ8 vertical stirrups @300 c/c
22940
5Nos.Φ10 side bar @ 200 c/c
Φ8 vertical stirrups @100 c/c
Φ8 vertical stirrups @130 c/c Φ8 vertical stirrups @250 c/c
Φ8 vertical stirrups @150 c/c
SUBMITTED BY:
TRIBHUVAN UNIVERSITY PROJECT TITLE: Sapan Pokharel (075BCE115) SCALE: 1:50
SHEET TITLE:
INSTITUTE OF ENGINEERING DESIGN OF RC T-GIRDER Subodh Subedi (075BCE125) PROJECT SUPERVISOR:
Tejendra Bist (075BCE138)
DEPARTMENT OF CIVIL ENGINEERING BRIDGE Er. Biswa Kumar Balla REINFORCEMENT DETAILING
Vivek Pokharel (075BCE142)
THAPATHALI CAMPUS Yuken Shrestha(075BCE143) OF GIRDER DWG NO. 3.2
Yukesh Chaulagain (075BCE144)
2Nos.Φ32mm 2Nos.Φ32mm 2Nos.Φ32mm
Φ10mm vertical stirrup @ 300mm c/c Φ10mm vertical stirrup @ 300mm c/c Φ10mm vertical stirrup @ 200mm c/c
Φ10mm side bar @ 200mm c/c Φ10mm side bar @ 200mm c/c Φ10mm side bar @ 200mm c/c
Φ10mm detailing bar @100mm c/c Φ10mm detailing bar @100mm c/c
Φ10mm detailing bar @100mm c/c
14Nos.Φ 32mm longitudinal bars 12Nos.Φ32mm longitudinal bars 10Nos.Φ32mm longitudinal bars
2Nos.Φ32mm 2Nos.Φ32mm
Φ10mm vertical stirrup @ 150mm c/c Φ10mm vertical stirrup @ 100mm c/c
Φ10mm side bar @ 200mm c/c Φ10mm side bar @ 200mm c/c
Φ10mm detailing bar @100mm c/c Φ10mm detailing bar @100mm c/c
AT L/8 AT 0
Φ10mm side bar @ 200mm c/c Φ10mm side bar @ 200mm c/c Φ10mm side bar @ 200mm c/c
Φ10mm detailing bar @100mm c/c Φ10mm detailing bar @100mm c/c Φ10mm detailing bar @100mm c/c
Φ10mm diameter side bar @ 200mm c/c Φ10mm diameter side bar @ 200mm c/c
Φ10mm diameter detailing bar @100mm c/c Φ10mm diameter detailing bar @100mm c/c
AT L/8 AT 0
SUBMITTED BY:
TRIBHUVAN UNIVERSITY PROJECT TITLE: Sapan Pokharel (075BCE115) SCALE: 1:50
SHEET TITLE:
INSTITUTE OF ENGINEERING DESIGN OF RC T-GIRDER Subodh Subedi (075BCE125) PROJECT SUPERVISOR:
Tejendra Bist (075BCE138)
DEPARTMENT OF CIVIL ENGINEERING BRIDGE Er. Biswa Kumar Balla REINFORCEMENT DETAILING
Vivek Pokharel (075BCE142)
THAPATHALI CAMPUS Yuken Shrestha(075BCE143) OF GIRDER DWG NO. 3.5
Yukesh Chaulagain (075BCE144)
2Nos. Φ25mm bars 2Nos. Φ25mm bars
4Nos. Φ10mm side bar @230mm c/c 4Nos. Φ10mm side bar @230mm c/c
SUBMITTED BY:
TRIBHUVAN UNIVERSITY PROJECT TITLE: Sapan Pokharel (075BCE115) SCALE: 1:20
SHEET TITLE:
INSTITUTE OF ENGINEERING DESIGN OF RC T-GIRDER Subodh Subedi (075BCE125) PROJECT SUPERVISOR:
Tejendra Bist (075BCE138)
DEPARTMENT OF CIVIL ENGINEERING BRIDGE Er. Biswa Kumar Balla REINFORCEMENT DETAILING
Vivek Pokharel (075BCE142)
THAPATHALI CAMPUS Yuken Shrestha(075BCE143) OF GIRDER DWG NO. 3.6
Yukesh Chaulagain (075BCE144)
300
25Ø
25Ø @300mm
@200mm c/c
c/c
16Ø
16Ø
@150mm @200mm
c/c
c/c
20Ø 1200
@200mm
c/c 20Ø
@250mm c/c 6500
11000
A
Abutment Plan
28Ø @180mm
16Ø @250mm c/c 16Ø @200mm c/c
c/c
1 1
Φ10@180
2 2
Φ20@120 UPTO 2000mm 2000
FROM STEM BASE
4000 2000 4000 4000 2000 4000
Φ20@130 Φ20@130 Φ20@130 Φ20@130
SUBMITTED BY:
TRIBHUVAN UNIVERSITY PROJECT TITLE: Sapan Pokharel (075BCE115) SCALE: 1:40
SHEET TITLE:
INSTITUTE OF ENGINEERING DESIGN OF RC T-GIRDER Subodh Subedi (075BCE125) PROJECT SUPERVISOR:
Tejendra Bist (075BCE138)
DEPARTMENT OF CIVIL ENGINEERING BRIDGE Er. Biswa Kumar Balla REINFORCEMENT DETAILING
Vivek Pokharel (075BCE142)
THAPATHALI CAMPUS Yuken Shrestha(075BCE143) OF PIER DWG NO. 5.1
Yukesh Chaulagain (075BCE144)
Φ2000
Φ2000
Φ10Links@180mm c/c
80 NOS. Φ32
SUBMITTED BY:
TRIBHUVAN UNIVERSITY PROJECT TITLE: Sapan Pokharel (075BCE115) SCALE: 1:30
SHEET TITLE:
INSTITUTE OF ENGINEERING DESIGN OF RC T-GIRDER Subodh Subedi (075BCE125) PROJECT SUPERVISOR:
Tejendra Bist (075BCE138)
DEPARTMENT OF CIVIL ENGINEERING BRIDGE Er. Biswa Kumar Balla REINFORCEMENT DETAILING
Vivek Pokharel (075BCE142)
THAPATHALI CAMPUS Yuken Shrestha(075BCE143) OF PIER DWG NO. 5.2
Yukesh Chaulagain (075BCE144)